ER26-3515-000 · 2026-09-03 · Solar Energy Industries Association
Comments of the Solar Energy Industries Association in response to PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket Nos.
ER26-3515-000
COMMENTS OF THE SOLAR ENERGY INDUSTRIES ASSOCIATION
Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (Commission),1 the Solar Energy Industries Association (SEIA) submits these comments in response to PJM Interconnection, L.L.C.’s (PJM) filing to establish Interim Resource Adequacy Service (IRAS).2 IRAS is a new transmission service that will be implemented solely during periods when there are insufficient resources to reliably meet demand in real time operations.3 When triggered, IRAS will enable PJM to prioritize load reduction in zones where New Large Loads that have not brought their own new capacity or have their capacity needs met through the Reliability Backstop Procurement (RBP).4 New Large Loads may avoid IRAS by bringing new capacity to the system through the Bring Your Own New Capacity (BYONC) construct.5 BYONC would allow New Large Loads that bring new capacity to the PJM Region to remove themselves—in whole or in part—from IRAS.6
SEIA does not take a position on the new transmission service created by PJM’s IRAS proposal. These comments address the program that would allow New Large Loads to avoid IRAS—the BYONC construct. As the trade association representing both utility-scale and
1 18 C.F.R. § 385.213 (2026).2 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service & a Large Load Registry, Docket No. ER26-3515 (Aug. 13, 2026) (IRAS Filing).3 IRAS Filing at 1.4 IRAS Filing at 1-2.5 IRAS Filing at 2.6 IRAS Filing at 50.
PDF page 2
2
distribution-scale solar and storage developers in PJM, SEIA submits these comments to provide recommendations to the Commission and PJM that would allow Surplus and Distributed Energy Resources (DERs) to provide more capacity to the PJM system through a BYONC.
I. Comments: To make BYONC more effective, PJM must remove market barriers for
Surplus and Distributed Energy Resources.
Under BYONC, the “new” capacity brought to the system “may be supported by
generation, storage, or demand-side resources that meet certain gating criteria.”7 That gating criteria would allow surplus resources and DERs to be part of a BYONC.8 SEIA supports PJM’s proposal to allow surplus resources and DERs to qualify for BYONC. In a recent presentation to the PJM Load Analysis Subcommittee, Charles River Associates stated that behind the meter and co-located resources, like Surplus Resources and DERs, will play a critical near- and medium- term role in meeting new demand from data centers, especially as structural supply gaps in PJM widen.9
Structural supply gaps cannot be remedied by pricing signals. A strong willingness to pay by a developer cannot resolve the significant backlogs facing turbine manufacturers.10 More money cannot build transmission faster in the face of significant transformer backlogs.11 PJM itself publicly acknowledged in a January 2026 stakeholder meeting that significant new capacity
7 IRAS Filing at 53.8 IRAS Filing at 53-54 (“Thus, for generation and storage resources, PJM proposes that the BYONC must be supported by:… (3) the incremental capacity created by the utilization of Surplus Interconnection Service. … Because capacity may also be supplied by demand-side resources, PJM proposes that BYONC may be supported by Planned Demand Resource or Planned Distributed Energy Resources (“DER”) Capacity Aggregation Resources”).9 Charles River Associates, Review of Data Center Forecast Methodology, at 20 (Aug. 26, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2026/20260826/20260826-item-04-- charles-river-associates-review-of-data-center-forecast-methodology.pdf (CRA Load Analysis).10 Umed Paliwal, Amol Phadke, Existing power plants sharing grid access with new resources can lower costs and double PJM’s generation capacity, at 11 (2025), https://surplusinterconnection.s3.us-east-1.amazonaws.com/PJM.pdf (Repower PJM).11 American Society of Civil Engineers, Infrastructure Report Card, Energy, at 76 (2025), https://infrastructurereportcard.org/wp-content/uploads/2025/03/Energy.pdf.
PDF page 3
3
additions are unlikely to come online before 2032 due to, among other factors, transmission constraints.12 If PJM is going to overcome these supply gaps, then it must use what is available. Surplus and distributed resources are the available resources in the near term. Adding battery storage to existing wind and solar sites through surplus interconnection could add 13.57 GW of capacity to PJM.13 This amount of capacity would increase even more if storage were to be added to thermal plants as well.14 Capacity from surplus resources can be deployed within 12- 18 months, as opposed to the 5-7 year timeline associated with traditional generation.15 Across the PJM region, over 2 GW of distributed energy capacity could be available within just a few months.16 Several states across the PJM region have already, or are in the process of, implementing programs that would encourage the development of even more distribution- connected resources.17 But this potential for new capacity can only be unlocked with the right market rules in place. PJM must take further action to put those rules in place.
12 See Devin Leith-Yessian, Government-Proposed “Backstop” Auction to Test PJM Stakeholder Process, RTO INSIDER (Jan. 26, 2026), https://www.rtoinsider.com/124178-government-proposed-backstop-auction-test-pjm- stakeholder-process/. (“Even with a backstop auction, [David] Mills [PJM board chair and interim CEO] said there are significant barriers to getting new resources built, including transmission upgrades, financing, tariffs, siting, permitting and supply chain constraints. Significant new capacity is unlikely to be available until 2032.”).13 Repower PJM at 32.14 Repower PJM at 12.15 Repower PJM at 34.16 Sunrun, Renew Homes, Tesla, Capacity as a Solution Framework, https://www.vppcapacity.com/, calculated using the Capacity Explorer Tool.17 About the Legislation: Clean and Reliable Grid Affordability Act (CRGA), Ill. Power Agency, https://ipa.illinois.gov/crga.html; N.J. Exec. Order No. 2, § 3 (Jan. 20, 2026), https://www.nj.gov/infobank/eo/057sherrill/pdf/EO-2.pdf. Maryland Energy Storage Program, Order Initiating Workgroup to Develop a Maryland Energy Storage Program, Order No. 90823, Case No. 9715 (Md. P.S.C. Oct. 2, 2023), http://psc.maryland.gov/wp-content/uploads/Order-initiating-Maryland-Energy-Storage-Program- Workgroup.pdf. Maryland Energy Storage Program, Order on Investor-Owned Utility Energy Storage Plan Proposals in Compliance with the Next Generation Energy Act, Order No. 92281, Case No. 9715 (Md. P.S.C. Apr. 8, 2026), https://psc.maryland.gov/wp-content/uploads/2026/04/ORDER_1.pdf
PDF page 4
4
A. Surplus Resources: Barriers to BYONC Participation and Solutions
As explained by SEIA, Advanced Energy United, and Google in the Reliability Backstop Procurement (RBP) filing, in Docket No. ER26-3380, existing PJM rules limit the ability for Surplus Resources to add capacity to the PJM system.18 Currently, PJM only grants capacity interconnection rights (CIRs) and capacity accreditation to surplus resources that merge with the existing facility as a single hybrid resource,19 a developer seeking capacity value through surplus interconnection must elect hybrid treatment—which potentially requires unwinding existing financial arrangements. The alternative—interconnecting independently as a co-located resource—preserves independent financing but limits the surplus resource to energy-only market participation, forfeiting capacity value entirely. Because hybrid treatment requires combined market participation as a single resource,20 it does not allow for component-level settlement, and capacity performance penalty risk cannot be isolated from the host resource. Lenders to the existing facility will rarely consent to the addition of a surplus resource under these conditions, because it exposes the existing project to performance liability arising from a resource it does not own or control. This effectively renders the surplus interconnection pathway commercially unavailable for many projects.
In the RBP proceeding, SEIA and Advanced Energy United each make recommendations
on how to resolve these concerns and make the surplus interconnection pathway commercially
18 See Solar Energy Industries Association, Comments, Docket No. ER26-3380-000, at 9-12 (filed Aug. 21, 2026); Google LLC, Comments, Docket No. ER26-3380-000, at 10-11 (filed Aug. 21, 2026); Advanced Energy United, Comments, Docket No. ER26-3380-000, at 11-15 (filed Aug. 21, 2026).19 See PJM Tariff, Part VIII, Subpart E, § 414 (Surplus Interconnection Service); see also Hybrid Resources Market Model Selection—Problem Statement, PJM Interconnection, L.L.C. (Aug. 2026) (“Hybrid PS/IC”), available at: https://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-1--- hybrid-resources-market-model-selection---problem-statement.pdf (recognizing that under current rules, the only pathway for surplus resources to obtain capacity value is to become a hybrid resource with the existing project).20 See Hybrid PS/IC (discussing issues relating to hybrid resource combined market participation as a single market unit in PJM’s energy, capacity, and ancillary services markets).
PDF page 5
5
viable.21 To address these barriers and unlock the significant capacity potential of surplus resources, SEIA recommends three reforms. First, PJM should enable surplus resources to obtain independently recognized and bankable capacity positions—distinct from the host resource— without requiring the wholesale restructuring of existing commercial arrangements. This could be achieved through several mechanisms, including: (i) split UCAP settlement between component accounts; or (ii) CIR transfer mechanisms between co-located resources.22 Whichever mechanism is adopted, the objective should be to provide each component of a surplus arrangement with independent settlement, revenue allocation, and penalty isolation necessary to support separate financing.
Second, PJM should establish clear protections ensuring that a default or performance issue arising from the surplus resource cannot create cross-default risk or otherwise interfere with the existing resource’s interconnection agreement or operations. This protection is essential to obtaining lender consent: Absent an explicit structural separation of liability, lenders to the existing facility will not approve the addition of a surplus resource that could jeopardize the project’s existing financing and operational arrangements.
Third, SEIA encourages PJM to evaluate whether additional resources or process
modifications can be devoted to surplus interconnection studies to reduce the time from application to completion, particularly for projects that could deliver capacity within the RBP’s timeframe. The Commission’s acceptance of PJM’s Docket No. ER25-778-000 reforms removed
21 Solar Energy Industries Association, Comments, Docket No. ER26-3380-000, at 9-12 (filed Aug. 21, 2026); Advanced Energy United, Comments, Docket No. ER26-3380-000, at 11-15 (filed Aug. 21, 2026).22 Under PJM’s current framework, a surplus interconnection arrangement results in a revised or amended Generation Interconnection Agreement for the existing facility, rather than a separate, standalone GIA for the surplus resource. See PJM Tariff, Part VIII, Subpart E, § 414(B)(2) (providing that a “revised Interconnection Service Agreement or Generation Interconnection Agreement will be prepared and issued to the owner of the existing or planned Generating Facility”). This structure means the surplus resource’s market participation, obligations, and potential liabilities are housed within the existing project’s agreement, creating the cross-default risk discussed above.
PDF page 6
6
the prior automatic disqualifications that blocked surplus requests. Developers now need PJM to complete the studies on time so they can bring resources online in time for the RBP.23 Together, these reforms—addressing commercial structure, lender protections, and study timelines for surplus interconnection—would enable surplus interconnection to serve as a meaningful near- term pathway for delivering additional accredited capacity to the PJM system, potentially unlocking gigawatts of storage and other resources that are positioned to connect quickly at existing points of interconnection.
SEIA again urges PJM to adopt those recommendations so that New Large Loads can
actually use surplus resources as new capacity under the BYONC construct.
B. Distributed Energy Resources: Barriers to BYONC Participation and
Solutions
In Order No. 2222, the Commission set out to remove the barriers to distributed energy resource aggregations participation in wholesale markets.24 Despite the Commission issuing the rulemaking in September 2020, implementation of Order No. 2222 is still ongoing. For PJM, DER Capacity Aggregation Resources cannot participate in the capacity auction until the 2028/2029 Base Residual Auction.25
PJM will allow DER Aggregations to support a BYONC.26 The BYONC construct is a
program designed to help address the capacity shortfalls that begin in the 2027/2028 Delivery
23 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,083 at PP 30, 33–34 (accepting revisions that expand availability of surplus interconnection service and noting that PJM’s proposal “should expand the use of surplus interconnection service and allow additional capacity resources to connect to the PJM system”); see also Clean Energy Associations Surplus Comments at 3 & n.10.24 Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission Organizations and Independent System Operators, Order No. 2222, 172 FERC ¶ 61,247 (2020), order on reh'g, Order No. 2222-A, 174 FERC ¶ 61,197 (2021).25 PJM Interconnection, L.L.C., 187 FERC ¶ 61,180, P 1 (2024) (“PJM states that the proposed revisions would allow Planned DER Capacity Aggregation Resources to participate in the PJM capacity market beginning with the 2028/2029 Base Residual Auction (BRA).”).26 IRAS Filing at 54.
PDF page 7
7
Year.27 But to participate in a BYONC, the resource must be a Capacity Resource that is committed in the capacity auction.28 With capacity market access delayed until the 2028/2029 delivery year,29 DERs will not be available to participate in a BYONC until a year after the BYONC construct begins. And even then, a DER participating in a BYONC must then face the additional burden of demonstrating the Accredited UCAP requirement each year in the 10-year BYONC period,30 a requirement that is not imposed on other resources participating in a BYONC.
Even after DERs can participate in the capacity market, and in a BYONC, other structural limitations impede the ability of New Large Loads to leverage DERs in a BYONC. Several of these limitations are actively being litigated in a paper hearing before the Commission.31 These comments are not intended to relitigate PJM’s Order No. 2222 compliance filing. However, given the significant changes in the markets since the Commission initially accepted PJM’s initial Order No. 2222 compliance filing, the increasing supply chain and transmission constraints facing the PJM region, and the growing interest in DER programs in the region, it would be wise for PJM to reevaluate how it can unlock new, and readily available, capacity quickly. These comments should serve as guidance to PJM on ways to improve DER access to the wholesale markets so that more resources can quickly be made available to New Large Loads.
27 IRAS Filing at 6.28 IRAS Filing at 55; proposed Tariff, Attachment DD-4, section VIII(a).29 See PJM Interconnection, L.L.C., 187 FERC ¶ 61,180, P 1 (2024); see also Charles River Associates, Grid Under Pressure, at 19 (Feb. 2026), https://media.crai.com/wp-content/uploads/2026/02/17103809/Grid-under-pressure- CRA-Energy-Report.pdf.30 Proposed Tariff, Attachment DD-4, section VI(b)(ii).31 See Voltus, Inc., and Mission:data v. PJM Interconnection, L.L.C., 196 FERC ¶ 61,074 (2026).
PDF page 8
8
II. CONCLUSION
The IRAS proposal is another necessary response to PJM’s growing resource adequacy issues. But there is much to do to ensure the program is successful. These comments do not propose an alternative to what PJM filed. These are recommendations that will allow New Large Loads to leverage what is already on the grid, or what can be added quickly, so that PJM can unlock the full potential of its proposal. Accordingly, SEIA requests that the Commission and PJM consider the market refinements identified in these comments.
Melissa Alfano
Senior Director of Energy Markets and Counsel
Solar Energy Industries Association
1425 K St NW Ste. 1000
Washington, DC 20005
(202) 566-2873
malfano@seia.org
PDF page 9
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing to be served upon each person designated on the official service list compiled by the Secretary in the captioned proceeding. Dated at Washington, D.C. this 3rd day of September, 2026.
/s/ Melissa Alfano