ER26-3515-000 · 2026-09-03 · Dominion Energy Services, Inc.

Comments of Dominion Energy Services, Inc. o/b/o its affiliate, Virginia Electric and Power Company d/b/a Dominion Energy Virginia re PJM Interconnection,…

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
)
)
)
ER26-3515-000

COMMENTS OF DOMINION ENERGY SERVICES, INC.

Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),1 Dominion Energy Services, Inc. on behalf of its affiliate, Virginia Electric and Power Company d/b/a Dominion Energy Virginia (“Dominion Energy Virginia”), hereby submits the following comments in the above captioned proceeding regarding PJM Interconnection, L.L.C.’s (“PJM”) proposal to establish a new supplemental capacity product, the Interim Resource Adequacy Service (“IRAS”), and related new obligations deemed necessary to support it.2

Dominion Energy Virginia, a subsidiary of Dominion Energy, Inc., is a public service corporation organized under the laws of the Commonwealth of Virginia and a public utility subject to regulation by the Commission and does business in the Commonwealth of Virginia and in the State of North Carolina. It is a regulated, vertically integrated public utility engaged in the generation, transmission, distribution, and sale of electric energy. Dominion Energy Virginia furnishes electric service to approximately 2.8 million retail customers in its approximately 30,000 square miles of certificated service territory covering parts of Virginia and North Carolina. To provide that service, Dominion Energy Virginia owns and operates a diverse fleet of nuclear, oil,

1 18 C.F.R. §§ 385.211 (2026).
2 PJM Interconnection, L.L.C., Docket No. ER26-3515-000 (August 13, 2026) (“PJM Filing”). Dominion Energy Services, Inc. filed a “doc-less” intervention in this proceeding on August 25, 2026.

PDF page 2

2

biomass, pumped storage, hydro, coal, solar, wind and natural gas-fired electric generating capacity of approximately 21,000 megawatts. Dominion Energy Virginia owns 6,800 miles of electric transmission lines in Virginia, North Carolina and West Virginia, which is operated by PJM. Dominion Energy Virginia joined PJM effective May 1, 2005, after obtaining prior approval from the Commission, the Virginia State Corporation Commission, and the North Carolina Utilities Commission.3

I. Introduction
The PJM Filing proposes reforms to the PJM Open Access Transmission Tariff (“Tariff”)
and the Reliability Assurance Agreement Among Load-Serving Entities in the PJM Region
(“RAA”) to establish IRAS, a load reduction service associated with PJM’s capacity market, that will be in effect when the capacity market clears short of the PJM Reliability Requirement.4  New Large Loads added to the system without matching new capacity will be required to provide IRAS, i.e., be interruptible at PJM’s direction, during the Delivery Year.  To establish IRAS, PJM proposes several other related changes as part of the framework.

First, PJM proposes to clarify that Load Serving Entities (“LSE”) interconnecting New
Large Loads in a Delivery Year must bring new capacity in an amount that equals or exceeds the New Large Loads’ peak load as of the commencement of that Delivery Year.  To the extent that they do not fully cover the peak load, the difference will be considered IRAS eligible and subject

3 PJM Interconnection, L.L.C., 109 FERC ¶ 61,012 (2004), on reh’g in part, 110 FERC ¶ 61,234 (2005); Ex Parte: In the matter concerning the application of Virginia Electric and Power Company d/b/a Dominion Virginia Power for approval of a plan to transfer functional and operational control of certain transmission facilities to a regional transmission entity, V.S.C.C. Case No. PUE-2000-00551, Order Granting Approval (Nov. 10, 2004); In the Matter of Application of Virginia Electric and Power Company, d/b/a Dominion North Carolina Power, for Authority to Transfer Functional Control of Transmission Assets to PJM Interconnection, LLC, N.C.U.C. Docket No. E-22, Sub 418, Order Approving Transfer Subject to Conditions (Apr. 19, 2005).
4 Capitalized terms not otherwise defined herein have the meaning as defined in the Tariff, Amended and Restated Operating Agreement of PJM Interconnection, L.L.C., and the RAA.

PDF page 3

3

to reduction requests during Emergencies prior to Pre-Emergency Load Management Response.5 Second, PJM plans to establish a Large Load Registry to track Large Loads currently on the system and New Large Loads that will interconnect in the future.  The registry will inform load forecasts and provide information needed to implement IRAS from an eligibility and operational standpoint.6  Third, PJM defines Bring Your Own New Capacity (“BYONC”) to establish the category of new capacity that is required to cover New Large Loads’ peak load and avoid designation as IRAS for a Delivery Year.7  Fourth, PJM proposes to exclude IRAS eligible load from the VRR Curve used in the Base Residual Auctions (“BRA”) and Incremental Auctions (“IA”).  By doing so, capacity auction clearing prices will not be influenced by LSE’s that fail to bring sufficient new capacity online to cover New Large Loads.8  Finally, PJM proposes a compensation mechanism for IRAS Large Loads that PJM curtails during a Delivery Year due to system conditions.  PJM requires Electric Distributors to implement the compensation scheme but will defer to the states and their Relevant Electric Retail Regulatory Authorities (“RERRAs”) to the extent they establish specific retail rates addressing the proposed compensation.9 Dominion Energy Virginia generally supports the proposed framework for IRAS.

However, PJM’s approach for implementation as presented in the transmittal letter and the Tariff amendments raises concerns that it will not accommodate all business models and state regulatory frameworks within the PJM Region.  The following comments highlight where PJM’s proposal should be further clarified, either through the Commission’s order or a requirement for PJM to submit a compliance filing.

5 PJM Filing at p. 21.
6 Id. at p. 22.
7 Id. at p. 23.
8 Id. at pp. 23-24.
9 Id. at pp. 27-28.

PDF page 4

4

II. Comments
PJM correctly recognizes that LSEs should have an affirmative obligation to procure new
capacity to cover any new Large Loads they seek to interconnect and serve during a Delivery Year. LSEs are the wholesale entities serving retail customers, and the costs and obligations for Large Loads, which are retail customers, should flow through the LSEs.  Some of the current resource adequacy shortfall in PJM can be attributed to the lack of incentives for LSEs to procure new capacity outside the BRA and LSEs relying solely on the BRA to procure needed new capacity.10 PJM’s proposed amendment to the RAA to clarify LSE obligations is a needed first step toward reestablishing resource adequacy obligations.

Much of PJM’s proposed framework, however, moves needlessly from federal wholesale
jurisdiction into retail jurisdiction and is likely to cause confusion and potential legal challenges. Instead of establishing IRAS obligations with the LSE, the wholesale jurisdictional entity, PJM focuses its proposal from the perspective of Large Loads, the retail customer. For example, PJM chooses to call new capacity eligible to cover New Large Loads, “Bring Your Own New Capacity,” a term that suggests that the only way for New Large Loads to avoid IRAS is to enter their own arrangements for new capacity.  In describing the BYONC concept, PJM states “to the extent a New Large Load does not want to provide IRAS, it needs to contract with new capacity that meets

10 See PJM, Considerations to Better Align Default Service Programs with PJM Capacity Market, February 2026, at pp. 1 and 11, available at https://www.pjm.com/-/media/DotCom/library/reports-notices/special- reports/2026/20260218-considerations-for-default-service-programs-to-better-align-with-pjm-wholesale- markets.pdf, (“Currently, none of PJM’s seven restructured state procure capacity outside of the capacity market.” And “Currently, these [restructured] states rely heavily, if not exclusively, on PJM’s capacity market to fulfill their resource adequacy needs. The capacity market, also known as the Base Residual Auction, was initially intended to be a truly residual market for states to procure for additional unfilled capacity needs, not to serve as the primary market to satisfy such needs.”) See also, PJM, Prefiled Statement of Manu Asthana o/b/o PJM Interconnection, L.L.C. under AD25-7, Docket No. AD25-7-000, at p. 6 (“Load serving entities in some regions appear to be primarily relying on the spot capacity market rather than using bilateral contracting first, and using the capacity market as a secondary, residual market. This is exacerbating the affordability challenges referenced above.”)

PDF page 5

5

the BYONC gating criteria.”11 Proposed Tariff Attachment DD-4 Section VII, titled “Bring Your Own New Capacity Arrangements with New Large Loads”, is written to only consider “arrangements” that represent a contractual agreement between a New Large Load and a “resource owner.”  The section places only a reporting obligation on the LSE suggesting that they are not associated with any BYONC designated to cover the New Large Loads they will serve during the Delivery Year.12

This myopic view fails to consider that the regulatory framework for retail electric service can differ between states and also between LSEs operating within those states.  In Virginia, for example, Vertically Integrated Utilities (“VIU”) like Dominion Energy Virginia have an obligation to interconnect and serve new customers, including Large Loads, and utilize integrated resource planning to identify the appropriate build out of new capacity to address resource adequacy needs. The costs for Dominion Energy Virginia to serve Large Loads are allocated through retail rates designed to ensure that Large Load customers pay their fair share.  There is not an obligation for Large Loads seeking to interconnect in Dominion Energy Virginia’s franchised territory to either build or contract for new capacity.  In the IRAS framework, Dominion Energy Virginia as LSE will be the entity arranging for new capacity to cover New Large Load expected to interconnect during the Delivery Year.  New Large Loads “bringing their own new capacity” should not be the only means to avoid IRAS, as conveyed by the Tariff.

It is likely that PJM chose its IRAS approach to align the design with the Ratepayer Protection Pledge13 and to accommodate the regulatory framework in restructured states where

11 PJM Filing at p. 23 (emphasis added).
12 Proposed Tariff Attachment DD-4, Section VII (a).
13 Ratepayer Protection Pledge, The White House (March 4, 2026)(available at https://perma.cc/N8PH-K82T).

PDF page 6

6

utilities do not own or build new capacity.14  However, by framing the pathway for avoiding IRAS based solely on the New Large Load bringing their own new capacity, PJM’s proposal will

assuredly cause confusion in states with VIUs or other utilities that self-supply their capacity requirements.  It also creates a disconnect between the resource adequacy obligation PJM seeks to place on LSEs in the RAA and the language in the proposed Tariff amendments that place the obligation solely on New Large Loads.

If the Commission approves the PJM Filing, it should make clear in its order that IRAS
and BYONC provisions also accommodate Vertically Integrated Utilities and other self-supply entities that plan generation build out to meet customer load growth in their territories.  As PJM states, there is a need for “regulatory certainty,” but as presented the PJM proposal does not provide that certainty absent additional clarifications and potentially revised Tariff language.15  Tariff amendments would not require any significant change to the proposal itself but would involve reframing the obligations from the standpoint of the LSE serving the New Large Load.

Attachment A to this filing provides example edits to PJM’s proposed Tariff Attachment DD-4, Section VII to accomplish this adjusted approach.  Additional conforming edits would be required throughout the Tariff and the RAA.

14 It should be noted that the PJM Board of Managers took a broader, more appropriate view of the BYONC concept when it issued its letter initiating the Critical Issue Fast Path process that resulted in this filing. See Board Decisional Letter on Critical Issue Fast Path - Large Load Additions, PJM Board of Managers at p. 3 (“Create incentives for Load Serving Entities (LSEs), large loads and/or states to bring new capacity resources to offset their load additions consistent with cost causation principles”)(January 16, 2026)(available at https://www.pjm.com/- /media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp- process-large-load-additions.pdf). The Board also recognized the federal/state jurisdictional issue raised in these comments.  See Id. (“The Board is mindful of the jurisdictional limits of PJM’s authority, which apply to PJM’s relationship with LSEs rather than individual retail customers.”)
15 PJM Filing at p.8.

PDF page 7

7

III. Conclusion
Dominion Energy Virginia respectively requests that the Commission issue an order granting PJM’s proposed Tariff revisions subject to clarification of the issues discussed above or subject to a compliance requirement for PJM to submit amended Tariff language reframing the obligations from the standpoint of the LSE serving New Large Load.

Respectfully submitted,
/s/ Wesley Walker

Wesley Walker
Managing Counsel
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VA 23219
(804)-819-2345
wesley.walker@dominionenergy.com
/s/ James G. Davis

James G. Davis
Regulatory and Market Policy Senior Strategic
Advisor
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VA 23219
(804)-819-2718
james.g.davis@dominionenergy.com
On behalf of Dominion Energy Services, Inc

PDF page 8

8

ATTACHMENT A
Sample Redlines to Proposed Tariff Attachment DD-4, Section VII

PDF page 9

9

VII. REQUIREMENTS FOR ASSOCIATING BRING YOUR OWN NEW
CAPACITY ARRANGEMENTS WITH NEW LARGE LOADS

(a) For any BYONC to be in an arrangement associated with a New Large Load, the Load Serving Entity serving the New Large Load or the applicable Electric Distributor shall report the BYONC associated with the New Large Load in accordance with the PJM Manuals.

(i)   If the BYONC is owned or affiliated with the Load Serving Entity serving the New Large Load, the Load Serving Entity must certify to the Office of Interconnection, in accordance with the PJM Manuals, attesting that the BYONC will follow the requirements of Tariff, Attachment DD-4, section VIII. the Load Serving Entity serving the New Large Load or the applicable Electric Distributor shall report the BYONC in an arrangement with the New Large Load, in accordance with the PJM Manuals. The Office of the Interconnection may also accept information to the extent interconnection customers, Large Loads, Transmission Owners, or other entities voluntarily report any BYONC that may be in an arrangement with a New Large Load; and

(ii)  If the BYONC is not owned by or affiliated with the Load Serving Entity serving the New Large Load, the resource owner or entity with contractual authority over the BYONC to enter into a BYONC arrangement must certify to the Office of Interconnection, in accordance with the PJM Manuals, attesting to the arrangement that the BYONC will be associated with the New Large Load and that the BYONC will follow the requirements of Tariff, Attachment DD-4, section VIII.

(b)   For BYONC associated with an arrangement between a New Large Load and BYONC to be effective for the 2027/2028 and 2028/2029 Delivery Years, for any associated BYONC arrangement to be considered, the requirements of Tariff, Attachment DD-4, section VII(a) must be met by April 1 for the first Delivery Year such arrangement association is to result in a reduction in the New Large Load’s Eligible New Large Load Amount. By April 15, the Office of the Interconnection shall update the Large Load Registry to reflect any verified arrangements associations between New Large Loads and BYONC.

(c)   For BYONC associated with an arrangement between a New Large Load and BYONC to be effective for the 2029/2030 Delivery Year, for any associated BYONC arrangement to be considered, the requirements of Tariff, Attachment DD-4, section VII(a) must be reported to the Office of the Interconnection no later than by 50 days prior to the commencement of the 2029/2030 Base Residual Auction or by 30 days prior to the posting of the planning parameters for the Incremental Auctions arrangement for the 2029/2030 Delivery Year. The Office of the Interconnection shall update the Large Load Registry to reflect any verified arrangements associations between New Large Loads and BYONC after the relevant RPM Auction.

(d)   For BYONC associated with an arrangement between a New Large Load and

PDF page 10

10

BYONC to be effective for the 2030/2031 Delivery Year and subsequent Delivery Years, the requirements of Tariff, Attachment DD-4, section VII(a) must be reported to the Office of the Interconnection no later than by 30 days prior to the posting of the planning parameters for the relevant RPM Auction for the initial Delivery Year the BYONC enters into an arrangement with the New Large Load. The Office of the Interconnection shall update the Large Load Registry to reflect any verified arrangements associations between New Large Loads and BYONC after the relevant RPM Auction.

(e)   BYONC that is in an arrangement associated with a New Large Load must remain in such arrangement associated with that New Large Load unless and until the New Large Load is permanently out-of-service.

(f)     A physical resource may support multiple BYONC, each of which may be in an arrangement associated with different New Large Loads, as long as no BYONC is in an arrangement associated with more than one New Large Load.

(g) A Load Serving Entity may associate New Large Load may enter into an arrangement with discrete BYONC supported by different physical resources.

(h)   A Load Serving Entity may associate New Large Load may enter into an arrangement with BYONC in excess of its current Eligible Large Load Amount, e.g., to allow for expected growth in the New Large Load, and the full megawatt quantity of such BYONC shall be offered in the first RPM Auction for which the New Large Load is included in the Variable Resource Requirement Curve,.

(i)  For any generation or storage resource, the Accredited UCAP of any BYONC shall be the Accredited UCAP for the RPM Auction in which the BYONC cleared for the initial Delivery Year the BYONC is in an arrangement with the New Large Load.

(ii)  For Demand Resources or DER Capacity Aggregation Resources, the Accredited UCAP shall be the Accredited UCAP for the RPM Auction in which the BYONC cleared for the initial Delivery Year the BYONC is in an arrangement with the New Large Load and must be demonstrated each year for a 10-year period using the Demand Response or DER Capacity Aggregation Resources installed capacity for the first Delivery Year after the BYONC is in an arrangement with the New Large Load. For Demand Resources or DER Capacity Aggregation Resources that are also the actual New Large Load, there is no demonstration required for the initial Delivery Year only to not be an Eligible New Large Load.

PDF page 11

11

CERTIFICATE OF SERVICE
I hereby certify that in accordance with Rule 2010 of the Commission’s
Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026), I have served a copy of the foregoing to all parties on the official service list in these proceedings.

/s/ Wesley Walker
Wesley Walker

September 3, 2026