Comments of Dominion Energy Services, Inc. o/b/o its affiliate, Virginia Electric and Power Company d/b/a Dominion Energy Virginia re PJM Interconnection,…
Text extracted from the eLibrary original (SHA-256 fdbd4cac5c88907a…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-3515
Topics in the text: Registry access · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) ) ) ER26-3515-000 COMMENTS OF DOMINION ENERGY SERVICES, INC.Read this passage Filed comments: Reliability and curtailment
I. Introduction
printed heading · Topic match: Registry access
E-22, Sub 418, Order Approving Transfer Subject to Conditions (Apr. 19, 2005). 4 Capitalized terms not otherwise defined herein have the meaning as defined in the Tariff, Amended and Restated Operating Agreement of PJM Interconnection, L.L.C., and the RAA. 3 to reduction requests during Emergencies…Read this passage Filed comments: Registry access
II. Comments
printed heading · Topic match: Reliability and curtailment
Some of the current resource adequacy shortfall in PJM can be attributed to the lack of incentives for LSEs to procure new capacity outside the BRA and LSEs relying solely on the BRA to procure needed new capacity.10 PJM’s proposed amendment to the RAA to clarify LSE obligations is a needed first…Read this passage Filed comments: Reliability and curtailment
III. Conclusion
printed heading
Conclusion Dominion Energy Virginia respectively requests that the Commission issue an order granting PJM’s proposed Tariff revisions subject to clarification of the issues discussed above or subject to a compliance requirement for PJM to submit amended Tariff language reframing the obligations…Read this passage
ATTACHMENT A
printed heading
ATTACHMENT A Sample Redlines to Proposed Tariff Attachment DD-4, Section VII 9Read this passage
VII. REQUIREMENTS FOR ASSOCIATING BRING YOUR OWN NEW
printed heading · Topic match: Registry access
By April 15, the Office of the Interconnection shall update the Large Load Registry to reflect any verified arrangements associations between New Large Loads and BYONC. (c) For BYONC associated with an arrangement between a New Large Load and BYONC to be effective for the 2029/2030 Delivery Year,…Read this passage Filed comments: Registry access
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026), I have served a copy of the foregoing to all parties on the official service list in these proceedings. /s/ Wesley Walker Wesley Walker…Read this passage