ER26-3515-000 · 2026-09-03 · NRG Business Marketing LLCNRG Energy, Inc., Aspen Gen Funding, LLC and 15 others
Comments and Limited Protest of NRG Business Marketing LLC, et. al. re the Interim Resource Adequacy Service proposed by PJM Interconnection, L.L.C
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
COMMENTS AND LIMITED PROTEST OF THE NRG COMPANIES
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedures,1 the NRG Companies2 (“NRG”) respectfully submit these comments and limited protest in response to PJM Interconnection, L.L.C.’s (“PJM”) August 13, 2026, filing proposing to establish interim resource adequacy service (“IRAS”) and a large load registry to address system reliability (“PJM IRAS Filing” or “IRAS Filing”). In general, NRG supports PJM’s efforts to provide certainty and clarity to market participants and New Large Loads3 that do not bring new supply into the PJM market. NRG also supports PJM’s efforts to articulate rules pertaining to the curtailment of New Large Loads that
1 18 C.F.R. § 385.211 (2026).2 The NRG Companies include the following subsidiaries of NRG Energy, Inc. (“NRG”): NRG Business Marketing LLC, Aspen Gen Funding, LLC, Direct Energy Business, LLC, Doswell, LLC, Energy Plus Holdings LLC, Enerwise Global Technologies, LLC d/b/a CPower, Green Mountain Energy Company, Helix Ironwood, LLC, Independence Energy Group LLC, LSP University Park, LLC, Midwest Generation LLC, NRG Curtailment Solutions, Inc., Reliant Energy Northeast LLC, Riverside Generating Company, LLC, Stream Energy Pennsylvania, LLC, University Park Energy, LLC and XOOM Energy, LLC. The NRG Companies have separately moved to intervene in this proceeding. See (doc-less) Motion to Intervene of NRG Business Marketing LLC, et al., Docket No. ER26-3515-000 (filed Aug. 31, 2026).3 Terms utilized herein that are not otherwise defined have the meaning ascribed by the PJM IRAS Filing’s proposed definitions or the PJM Tariff.
PDF page 2
2
do not bring new supply where such customers are curtailed before existing pre-emergency and emergency customers.
However, PJM’s proposal contains elements that are unjust, unreasonable, unduly discriminatory, and must be revised. These consist of (i) PJM’s permanent exclusion of every Demand Resource4 that has ever supported a capacity commitment in any prior Delivery Year and (ii) the requirement for new capacity serving New Large Loads to bid into the capacity market as a price-taker for 10 years without certain necessary protections for asset owners. Finally, there are a number of clarifications NRG seeks related to the IRAS requirements around Demand Resources.
I. ABOUT NRG
Through various subsidiaries, NRG owns or controls over 9 GW of generation in PJM as well as generation in adjacent markets that can be imported into the PJM market. Additionally, NRG subsidiaries provide retail power throughout PJM and two NRG subsidiaries provide Demand Resources in PJM. Thus, NRG actively participates in the organized markets administered by PJM, including the PJM capacity market.
II. BACKGROUND
The PJM IRAS Filing creates a new supplemental capacity product through which New Large Loads may provide a load reduction service during periods of insufficient capacity instead
4 This limited protest refers to Demand Resources and Distributed Energy Resources (“DER”) Capacity Aggregation Resources, as the terms are defined by the PJM OATT, as “Demand Resources” to improve readability, but is not intended to refer only to Demand Resources with the term unless the context requires otherwise.
PDF page 3
3
of participating in the Base Residual Auction (“BRA”). IRAS resources will be issued curtailment instructions prior to PJM calling on Pre-Emergency Load Management. For providing the reduction, PJM proposes an IRAS rate equal to 50% of the Non-Performance Charge Rate, with flexibility for Electric Distributors and states to reduce the rate or for eligible New Large Loads to waive compensation entirely.
Instead of participating as an IRAS resource, New Large Loads may instead meet their capacity obligations through a Bring Your Own New Capacity (“BYONC”) option. BYONC is defined as megawatts of new Unforced Capacity (“UCAP”) that meet the eligibility criteria set forth in Tariff, Attachment DD-4, section VI.5 A single physical resource may support multiple BYONC arrangements with different New Large Loads, and a New Large Load may enter into BYONC arrangements with discrete resources.6 BYONC must be supported by: (1) a new-build generation resource (including resources obtaining Capacity Interconnection Rights transferred from deactivated resources); (2) incremental capacity from an uprate; (3) incremental capacity from Surplus Interconnection Service; (4) repowering of a deactivated resource that deactivated prior to April 10, 2026; or (5) incremental capacity from a fuel-type change.7 BYONC may also be supported by Planned Demand Resources or Planned DER Capacity Aggregation Resources. However, PJM has proposed to only permit BYONC to be supported by Demand Resources if those resources “did not previously support a capacity commitment or reduce the amount of capacity needed to meet the PJM Reliability Requirement … for or prior to the
5 Proposed Tariff, Definitions (“Bring Your Own New Capacity”).6 Proposed Tariff, Attach. DD-4, section VII(f).7 Proposed Tariff, Attach. DD-4, section VI(b)(i).
PDF page 4
4
2026/27 Delivery Year” 8 – thus permanently excluding every Demand Resource that has ever supported a capacity commitment in any prior Delivery Year.
Each BYONC must participate as a price taker ($0/MW offer) in BRAs for 10
consecutive Delivery Years, starting with the first Delivery Year of the arrangement. BYONC is also subject to the capacity must-offer requirement and is prohibited from seeking an exception to provide an external sale during the 10-year period. BYONC supported by a Demand Resource or DER Capacity Aggregation Resource also has a 10-year commitment, but the seller may replace its BYONC obligation with a different qualifying resource, subject to conditions. This provides a “bridge to power” allowing near-term demand-supported capacity to be eventually replaced with new generation. Additionally, beginning with the 2029/30 Delivery Year, PJM proposes to exclude from the VRR Curve the MW of New Large Loads that have not entered into BYONC arrangements and do not have allocated capacity (IRAS resources), above and beyond the MW included in the 2028/29 Delivery Year load forecast.
BYONC BRA participation requirements (including the price-taker obligation) are extinguished if IRAS is not needed for three consecutive Delivery Years. At that point, BYONC resources become regular Capacity Resources, though still subject to the general capacity must- offer requirement. If the PJM Region meets its reliability requirements for three consecutive Delivery Years and then re-enters shortage, the “new” benchmark resets. Demand-side capacity would then be measured against registration “in the Delivery Year prior to the first Delivery Year” in which PJM is again short of capacity.
8 Proposed Tariff, Attach. DD-4, section VI(b)(ii).
PDF page 5
5
III. COMMENTS IN SUPPORT OF THE PJM IRAS FILING
In general, NRG supports PJM’s IRAS Filing. PJM proposes to require Load Serving Entities (“LSEs”) to “bring new capacity in an amount that equals or exceeds its New Large Loads’ peak load or be subject to load reduction requests during Emergencies prior to Pre- Emergency Load Management Response.”9 PJM notes that it is “currently short of capacity and looking to reestablish healthy capacity reserve margin.”10 PJM’s approach is commonsense: New Large Loads must be supported by Capacity Resources. Furthermore, NRG supports the requirement that the BYONC capacity be “new” generation.
NRG also supports PJM’s proposal to curtail New Large Loads before existing customers, including Pre-Emergency and Emergency Demand Response customers. Specifically, the PJM IRAS Filing provides that “PJM can call on IRAS load reductions prior to calling on Pre-Emergency Load Management Reductions Actions when needed to avoid a capacity shortage.”11 As PJM notes, this provision does not identify the specific load that an Electric Distributor must reduce.12 Rather, the Electric Distributor, in coordination with the appropriate states and/or Relevant Electric Retail Regulatory Authorities, LSEs, and LSE customers, will determine which loads should ultimately be curtailed.13 The proposed curtailment obligation
9 PJM IRAS Filing at 3-4, 49.10 Id. at 52.11 PJM IRAS Filing at 25 (citing Proposed Tariff, Attach. DD-4, Section 1(b)).12 PJM IRAS Filing at 26.13 Id. Nonetheless, PJM should consider clarifying that if Electric Distributors, in coordination with these entities, do not take action, PJM will use the registry to curtail New Large Loads ahead of all other loads.
PDF page 6
6
gives states and LSEs latitude to curtail efficiently and, in particular, to prioritize customers that curtail voluntarily. The construct also provides a “bridge to power” that protects existing customers.
IV. LIMITED PROTEST
Pursuant to the Commission’s Rule 211,14 NRG provides the following limited protest. As written, the tariff proposed by PJM fails to be just and reasonable and is unduly discriminatory because it (i) excludes otherwise capable Demand Resources based on an unwarranted permanent bar to such resources that have participated in any prior BRA; and
(ii) imposes an overly broad and unjust and unreasonable ten-year price-taker obligation on all BYONC resources.
PJM has consented to the Commission’s exercise of authority to modify or sever any element of the filing to the extent necessary, so long as the modification is consistent with PJM’s overarching objectives.15 Thus, the Commission has authority to modify PJM’s proposed tariff in the manner proposed by NRG by directing a compliance filing.16 NRG’s modest proposals do not
14 18 C.F.R. § 385.211.
15 PJM IRAS Filing at 9 (citing NRG Power Marketing LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017)).16 N.Y. Indep. Sys. Operator, Inc., 188 FERC ¶ 61,051, at P 22 n.36 (2024) (citing NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114-15 (D.C. Cir. 2017)) (“the Commission has ‘authority to propose modifications to a utility’s [FPA section 205] proposal if the utility consents to the modifications.’ ”).
PDF page 7
7
conflict with PJM’s Board Directive, or with the objectives reflected in the Critical Issue Fast Path’s (“CIFP”) accelerated stakeholder process related to the PJM IRAS Filing.17
A. New Demand Resources Should Be Permitted to Bid into the Market to Support New Large Loads Regardless of Prior Market Participation
PJM states that new capacity, BYONC, is at a basic level, “megawatts of Unforced Capacity” and thus is “consistent with how Capacity Resources under PJM’s capacity market design are also MW and not the underlying physical resource.”18 PJM explains that BYONC is “designed to offset the capacity need presented by the New Large Load.”19 PJM further explains that “new capacity may be supported by generation, storage, or demand-side resources that meet certain gating criteria.”20
However, PJM’s “gating criteria” for BYONC applicable to Demand Resources include a requirement that Planned Demand Resources “did not previously support a capacity commitment or reduce the amount of capacity needed to meet the PJM Region Reliability Requirement … for or prior to the 2026/2027 Delivery Year.”21 This means that PJM has permanently excluded every Demand Resource that has ever supported a capacity commitment in any prior Delivery
17 See PJM IRAS Filing at 17-18 (citing Letter from Paula Conboy, Chair, PJM Board of Managers, Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop Procurement and Connect and Manage, 1 (July 27, 2026), https://www.pjm.com/- /media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-board- decisional-letter-on-cifp-reliability-backstop-procurement-and-connect-and-manage.pdf (“PJM Board Directive”).18 PJM IRAS Filing at 51.19 Id.20 Id. at 53.21 PJM IRAS Filing at 54 (emphasis supplied) (citing Proposed Tariff, Attach. DD-4, Sections VI(b)(i)(1)-(5)).
PDF page 8
8
Year even though Demand Resources have proven their value in PJM. They have been critical in mitigating emergencies and have helped to “avoid the cost of dispatching [or building] additional generation or involuntarily curtailing load.”22 In 2025 alone, PJM successfully relied on Demand Resources that provided more than 4,000 MW of capacity during emergencies.23 Under PJM’s proposal, a customer location that participated as a Demand Resource as far back as 200624 and later ceased participation would be ineligible to participate as a BYONC capacity resource. The ban on eligibility applies even if the ownership or occupancy at the customer location has changed or if there are new flexibility capabilities. For example, a customer location that ceased participation as a Demand Resource in 2010 and was no longer in any way considered an existing capacity resource would be banned from participation in BYONC. This exclusion is patently unjust, unreasonable, and unduly discriminatory.25 First, this restriction applies only to Demand Resources, not to retired generators or storage resources that exited the market but could reactivate their Capacity Interconnection Rights.26 Deactivated generators also may be “repower[ed]” if they were deactivated before April
22 Fed. Energy Reg. Comm’n, 2025 Assessment of Demand Response and Advanced Metering, 16 (Dec. 2025) https://www.ferc.gov/news-events/news/ferc-staff-issues-2025- assessment-demand-response-and-advanced-metering.23 Id. at 17. 24 PJM Interconnection, L.L.C., 115 FERC ¶ 61,079, at P 84 (2006).25 Xcel Energy Servs. Inc. v. FERC, 41 F.4th 548, 559 (D.C. Cir. 2022) (explaining discriminatory standards and referencing the Commission policy that “the Commission can promote market entry by ensuring that all generators compete on a level playing field”).26 IRAS Filing at 53-54 (citing Proposed Tariff, Attach. DD-4, Sections VI(b)(i)(1)-(5)).
PDF page 9
9
10, 2026 and be considered “new” capacity that can qualify as BYONC.27 PJM has provided no explanation or support for allowing deactivated generation that had once participated in a prior BRA to participate as BYONC, while excluding Demand Resources that also had participated in a prior BRA from qualifying as BYONC.28 The fact that “new” Demand Resources can qualify for BYONC just like new generation necessarily means that the nature of the Capacity Resource is not a relevant factor to discriminate or differentiate for inclusion as BYONC.29 Therefore, this inconsistent treatment of retired generation and Demand Resources that had participated in prior BRAs is de facto unjust, unreasonable, and unduly discriminatory.
Second, there is no justification for such discriminatory treatment.30 The discriminatory treatment of previously enrolled Demand Resource locations excludes gigawatts of potential Demand Resources from qualifying as BYONC. As noted, generation that has deactivated can
27 Id.28 West Deptford Energy, LLC v. FERC, 766 F.3d 10, 20-22 (D.C. Cir. 2014) (“the Commission would have to provide a reasoned analysis, resting on articulated objective, nondiscriminatory, and evenhanded criteria, that would justify treating [one generator] differently than the generators in all those other cases.”); FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 292 (2016), as revised (Jan. 28, 2016) (noting FERC’s position that demand response and other generators should be treated equally because “both provide the same value to a wholesale market”).29 Tenaska Clear Creek Wind, LLC v. FERC, 108 F.4th 858, 868 (D.C. Cir. 2024) (citation omitted) (“[U]ndue discrimination occurs when similarly situated entities are charged different rates for no good reason.”); Black Oak Energy, LLC v. FERC, 725 F.3d 230, 239 (D.C. Cir. 2013) (allowing FERC to rely upon “differences between parties that are relevant to the achievement of permissible policy goals”).30 PJM Interconnection, L.L.C., 115 FERC ¶ 61,079, at P 72-73 (2006) (“We encourage PJM to examine and incorporate reasonable accommodations to maximize demand response participation in the capacity market.”); 16 U.S.C. § 824d; Wisconsin Pub. Power, Inc. v. FERC, 493 F.3d 239, 246 (D.C. Cir. 2007) (“Section 205 … prohibits undue discrimination in rates, charges, or terms of service.”).
PDF page 10
10
repower or obtain new interconnection rights and participate as BYONC. By contrast, a Demand Resource that once participated in a BRA as a Capacity Resource does not need to be repowered or obtain new interconnection rights to participate. Allowing such Demand Resources to qualify as BYONC can add meaningful capacity immediately by improving the utilization of existing resources,31 while aiding PJM in reestablishing the “healthy capacity reserve margins” it seeks through the IRAS Filing.32 Moreover, unlike generators or storage resources, Demand Resources can grow or shrink in response to price signals. That flexibility is a feature, not a flaw; when power prices are high due to demand, Demand Resources can offer greater participation.33 And unlike physical generation facilities, Demand Resources can respond with little delay to changes in demand signals.34
Third, allowing Demand Resources that have ceased participation in BRAs in prior Delivery Years to qualify as BYONC is consistent with limiting BYONC eligibility for generation to new resources. Existing generation resources in PJM are required to offer their available unforced capacity into the capacity market. Therefore, existing generation in PJM already participates in the BRA and should not be allowed to withdraw from the capacity market in order to qualify as BYONC as discussed herein. Demand Resources voluntarily participate in the capacity market. Thus, Demand Resources that have participated in past Delivery Years, but
31 New York Indep. Sys. Operator, Inc., 147 FERC ¶ 61,152, at P 20 (2014) (noting resources “such as demand response and repowering options” provide “shorter term capacity responses” to meet capacity needs).32 PJM IRAS Filing at 52.33 Dept. of Energy, Benefits of Demand Response in Electricity Markets and Recommendations for Achieving Them, at 13-15 (Feb. 2006).34 Id.
PDF page 11
11
ceased participation as Capacity Resources prior to 2026/27, should be allowed to qualify as BYONC, as allowing such participation has no negative implications on future BRAs. Taken together, these factors contradict how PJM proposes treating these resources. Indeed, the flexible and voluntary nature of Demand Resource participation in the PJM capacity market supports inclusion of Demand Resources as BYONC, as Demand Resources can provide significant immediate capacity to help serve New Large Load rather than relying on IRAS. NRG further notes that PJM’s IRAS Filing is inconsistent with the proposal approved by the PJM Board. PJM’s July 31, 2026, version of the IRAS proposal – the final public version before the PJM IRAS Filing that was approved by the PJM Board – would only restrict Demand Resources that had participated in the 2026/27 or 2027/28 Delivery Year.35 This three-year limited lookback is just, reasonable, and not unduly discriminatory because it treats all Capacity Resources equally.36 As proposed, the PJM Board has not reviewed the issue herein to deem it non-discriminatory.37 However, in the IRAS Filing, PJM bars participation by Demand
35 PJM, PJM Interim Resource Adequacy Service Detailed Proposal, at 7 (July 31, 2026) https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260731/20260731- item-02b---cifp-framework-for-service-during-periods-of-insufficient-resource-adequacy--- executive-summary---redline.pdf.36 Alabama Elec. Co-op., Inc. v. FERC, 684 F.2d 20, 29 (D.C. Cir. 1982) (“In the typical case, where the section 205(b) challenge is raised against a rate design calling for different rates to customer classes which are similarly situated.”); New York Pub. Serv. Comm’n v. New York Indep. Sys. Op., Inc., 153 FERC ¶ 61,022, at P 79 (2015) (finding a narrowly tailored exemption was appropriate).37 PJM Operating Agreement § 7.7(vii) (requiring the PJM Board to “review for consistency with the creation and operation of a robust, competitive and non-discriminatory electric power market in the PJM Region any change to rate design or to non-rate terms and conditions proposed by Transmission Owners for filing under section 205 of the Federal Power Act”).
PDF page 12
12
Resources that had ever been Capacity Resources in any prior BRA, without explaining the departure from the proposal submitted to the Board.
The IRAS Filing contemplates that, if the PJM Region meets its reliability requirements for three consecutive Delivery Years and then re-enters shortage, the “new” benchmark resets. At that point, the demand-side gating criterion measures against registration “in the Delivery Year prior to the first Delivery Year” in which the PJM Region is short of capacity.38 Here, PJM itself recognizes a lookback-window approach is workable and reasonable. There is no principled justification for the asymmetry of applying a lookback in one context but not in the related Demand Resources context. To address this unjust, unreasonable, and unduly discriminatory treatment, NRG requests that the Commission adopt a three-year lookback window rather than a permanent exclusion.39 Namely, PJM should permit Demand Resources that have not participated in the three most recent BRAs to qualify for BYONC.
The overly broad ineligibility is inconsistent with the policy announced by the Secretary of Energy to leverage available backup generation to address the United States’ reliability challenges and other grid challenges.40 There are gigawatts of backup generation that were once eligible and did participate in demand response but subsequently discontinued participation. Demand response participation by backup generators may become economically viable through
38 PJM IRAS Filing at 55 (citing Proposed Tariff, Attach. DD-4, Section VI(b)(ii)(1)).39 Id.40 Letter from Sec. of Energy Christopher Wright to Reliability Coordinators, Leveraging Backup Generation Facilities During Energy Emergencies (Jan. 22, 2026) https://www.energy.gov/documents/leveraging-backup-generation-facilities-during-energy- emergencies (suggesting reliability coordinators “deliberately prioritize the dispatch order of backup generation to achieve the greatest benefit to the bulk power system while balancing mission-essential functions”).
PDF page 13
13
BYONC arrangements and should be considered as new resources. The BYONC mechanism would present a powerful means to leverage this latent backup generation capacity to meet today’s reliability challenges and foster economic growth. PJM’s ban on prior customer location eligibility to participate in BYONC undermines the Secretary of Energy’s directive to develop and encourage backup generation resources.
In short, a Demand Resource that chooses to re-enter the market still provides new capacity to the system, just as a generator that undertakes an uprate project adds new capacity. To arbitrarily exclude a Demand Resource from participating solely because it had participated in past BRAs, while simultaneously permitting reactivated or repowered generators to qualify, is unjust, unreasonable, and unduly discriminatory.41
B. Capacity Serving New Large Loads Should Not Be Required to Bid into the BRA as a Price Taker for 10 Years Without a Replacement Mechanism
PJM proposes that “BYONC must participate, as a price taker (i.e. $0/MW offer) in RPM Auctions for 10 consecutive Delivery Years.”42 PJM states that the BYONC arrangement “serves as the commitment to provide [] capacity.”43 PJM further states that because the “resource is already obligated to provide the capacity, its incremental, going-forward avoidable costs to secure the RPM commitment are zero.”44 The ten-year price-taker obligation is not just and reasonable as applied to all Capacity Resources, including generation, storage, and demand-side resources. NRG’s protest on this point is not limited to Demand Resources. NRG requests that
41 See n.29, supra.42 PJM IRAS Filing at 55-56.43 Id. at 57.44 Id. at 58-59.
PDF page 14
14
the Commission direct PJM to provide opportunities to reflect costs in offers for unknown and/or unknowable costs imposed upon the Capacity Resource owner and not otherwise recoverable under the terms of the asset owner’s bilateral contracts with large loads.
A ten-year capacity obligation for a resource is significant.45 Participation as an existing Capacity Resource in PJM is subject to a must-offer requirement for capacity auctions only three years into the future.46 A ten-year must-offer commitment with a mandatory zero-dollar offer compounds the significance of the commitment.47 Circumstances may change materially during a ten-year bilateral agreement between third parties, potentially altering a facility’s operating costs in unpredictable ways. For instance, new environmental obligations may arise that require capital expenditures, a facility may suffer a catastrophic loss, or fuel may become prohibitively expensive in a constrained region. Given the corresponding requirement to offer into the BRA at zero-cost for 10 years, a BYONC resource cannot be economically replaced as operating and market conditions evolve. As a result, this market construct is effectively designed to keep
45 Though hypothetically, a BYONC price-taker obligation may cease if PJM has met the Reliability Requirement for three years, the practical reality is that the obligation will remain through several additional BRAs, which occur three years in advance of performance. For instance, if PJM has thrice met its Reliability Requirement in 2032 – the last date that Reliability Backstop Procurement resources are eligible for market entry under a parallel tariff proposal by PJM – BYONC resources will not know whether they retain an obligation until 2034. By that time, BRAs will have occurred through 2037/38. In this plausible scenario, a BYONC resource would be required to offer as a price taker well past when PJM demonstrates sufficient capacity to meet all load.46 PJM Capacity Manual 18 § 5.7 (rev. 62, Dec. 17, 2025).47 The Commission has previously found that even a five-year must-offer obligation may be unjust and unreasonable because it ultimately undercompensated sellers. See, e.g., California Indep. Sys. Operator Corp., 118 FERC ¶ 61,097, at P 5 (2007) (discussing the Commission’s finding that a must-offer obligation lasting five years to be unjust and unreasonable and undercompensated sellers), vacating on other grounds, City of Anaheim, Cal. v. FERC, 558 F.3d 521, 526 (D.C. Cir. 2009).
PDF page 15
15
economically inefficient generators operating, potentially at a loss, rather than allowing more efficient resources to displace them.
The Commission should direct PJM to include the opportunity for such costs to be reflected in subsequent capacity auctions should conditions such as those described above arise. The PJM Tariff already has mechanisms for other resources to reflect their costs through unit specific Avoidable Cost Rate (“ACR”) offers.48 NRG proposes a similar approach here. This would ensure in the limited cases where otherwise unforeseen circumstances are unaddressed or are at issue in bilateral transactions, the resource owner has an opportunity (but not the guarantee) to recover such unforeseen costs.49 The ACR approach also offers benefits to PJM customers: (1) the market receives the benefit of the zero-offer price for ten years in most cases, absent detailed showings; (2) in extraordinary circumstances, the Capacity Resource serving a New Large Load is able to continue doing so while recovering exceptional and unforeseen costs;
(3) more economic resources are able to enter the market and replace highly inefficient Capacity Resources; and (4) reliability is improved over the course of the IRAS-imposed commitments.50 Additionally, to the extent PJM imposes a price-taker requirement on BYONC resources, the requirement should not apply to excess capacity beyond the BYONC commitment. If a 1,200-MW generation facility has committed 700 MW as BYONC, the remaining 500 MW
48 PJM Tariff, Attach. DD §§ 6.4(b) & 6.7. Specifically, the proposed ACR, and all “data and documentation” shall be submitted to the IMM for consideration.49 If these costs are inframarginal, there is no impact on auction outcomes, but provides significant assurances for the resource owner. If the resource is extramarginal as a result of these costs, the large load will bear the responsibility to replace it or be subject to IRAS service.50 The alternative may be generator bankruptcy that will benefit neither PJM, its customers nor the generator.
PDF page 16
16
should be permitted to bid economically into the BRA. PJM’s own filing acknowledges that a physical resource may support multiple BYONC arrangements, each of which may be in an arrangement with different New Large Loads.51 PJM provides no justification for requiring non- BYONC MW to offer at zero when those MW are not committed to any New Large Load and would otherwise compete in the market on economic terms. To the extent PJM disagrees with this clarification, NRG requests that the Commission direct non-BYONC MW from the same Capacity Resource be permitted to offer economically into the RPM Auction.
V. NRG SEEKS CLARIFICATION, OR IN THE ALTERNATIVE, TARIFF
MODIFICATIONS, PERMITTING EXPANDED DEMAND RESPONSE
CAPACITY TO BE TREATED AS NEW CAPACITY
NRG has identified four areas in the IRAS Filing that lack clarity, and to the extent these areas are inconsistent with NRG’s requested clarification, are unjust and unreasonable because they are discriminatory. First, existing Demand Resources should be permitted to offer BYONC in excess of prior capacity offers as “new” capacity. Second, any resource that would qualify as “new” capacity can also be eligible to serve as replacement capacity for Demand Resources. Third, curtailment-based Demand Resources should be eligible for BYONC without requiring generation or storage assets at the location. Fourth, the methodology used to determine eligibility of Demand Resources must be defined.
51 See Proposed Tariff, Attach. DD-4, section VII(f).
PDF page 17
17
First, NRG seeks clarification, or an amendment of the proposed tariff, that an existing Demand Resource could offer BYONC in excess of prior capacity offers,52 consistent with other Capacity Resources that may include uprates and Surplus Interconnection Service capacity.53 With this clarification, additional investments may be encouraged at an existing “registered location” such as construction of behind-the-meter generation, on-site battery storage, or other customer-site enhancements, even if that resource previously supported a capacity commitment.54 Similarly, treating increased Demand Resource capacity as “new” capacity provides a comparable benefit to PJM customers.55 Thus, this clarification would ensure that Demand Resources are treated the same as other Capacity Resources and ensure that Demand Resources are available to offset New Large Loads.
Second, the IRAS Filing does not clearly define what may serve as replacement capacity for BYONC Demand Resources, except that it would “need to be supported by the certification required by Tariff, Attachment DD-4, section VII(a)(ii)”, that circularly requires compliance with Attachment DD-4, Section VIII.56 NRG seeks clarification, or an amendment to the tariff, that any resource that would qualify as “new” capacity can also be eligible to serve as replacement
52 NRG seeks this clarification for the PJM proposed permanent bar or the NRG proposed modification that would limit the restriction to 2026/27 BRA participation, whichever is adopted by the Commission.53 See Proposed Tariff, Attach. DD-4, section VI(b)(i)(2) & (3).54 See PJM IRAS Filing at 54.55 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 292 (2016), as revised (Jan. 28, 2016).56 See IRAS Filing at 56-67; see also Proposed Tariff, Attach. DD-4, section VIII(e).
PDF page 18
18
capacity for Demand Resources committed to an existing BYONC arrangement under Attachment DD-4, section VIII(e).
Third, NRG seeks clarification that Demand Resources achieving load reductions through curtailment alone, without the installation of new generation or storage assets, are eligible for BYONC. As proposed, the IRAS tariff requires that demand-side BYONC be composed of locations “at which an incremental amount at that location is the result of the registration of new generation or storage assets at the location.”57 This language appears to compound the historical- participation exclusion with a separate requirement for new physical assets at the location. If so, this would exclude the vast majority of curtailment-based Demand Resources, which achieve reductions through operational adjustments rather than new “generation or storage assets.” Curtailment-based Demand Resources provide the same reliability value as a generator obtaining new Capacity Interconnection Rights. Their exclusion would be unjust and discriminatory. Fourth, the methodology used to determine eligibility of Demand Resources must be defined. NRG recognizes that the demand-side BYONC replacement mechanism was developed through the CIFP stakeholder process and supports the concept of permitting replacement capacity for demand-side BYONC. However, the Commission must require PJM to provide clarity on how a Curtailment Service Provider (“CSP”) will be required to demonstrate each year of a 10-year period for a Demand Resource.58 Matters that significantly affect the rates, terms and conditions of service must be specified in the tariff.59 PJM’s proposed tariff states:
57 See Proposed Tariff, Attach. DD-4, section VI(b)(ii)(1).58 See PJM IRAS Filing at 66; Proposed Tariff, Attachment DD-4, section VII(i)(ii)59 See, e.g., PJM Interconnection, L.L.C., 171 FERC ¶ 61,145 at P 20 (2020) (finding PJM’s inclusion of threshold criteria in a manual insufficient, and directing inclusion in the tariff); see also City of Cleveland, Ohio v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (holding
PDF page 19
19
Demand Resources or DER Capacity Aggregation Resources, the
Accredited UCAP shall be the Accredited UCAP for the RPM Auction in
which the BYONC cleared for the initial Delivery Year the BYONC is in
an arrangement with the New Large Load and must be demonstrated
each year for a 10-year period using the Demand Response or DER
Capacity Aggregation Resources installed capacity for the first Delivery Year after the BYONC is in an arrangement with the New Large Load. For
Demand Resources or DER Capacity Aggregation Resources that are also
the actual New Large Load, there is no demonstration required for the
initial Delivery Year only to not be an Eligible New Large Load.60
NRG seeks clarification that the 10-year demonstration is made by showing the “installed capacity for the first Delivery Year after the BYONC is in an arrangement with the New Large Load.”61 More specifically, that PJM’s proposed language does not mean that incremental customers that make up an aggregation must have a 10-year commitment to make this demonstration. If PJM disagrees with this interpretation, that would be unjust and unreasonable and unduly discriminatory, and NRG requests the Commission direct amendments. It must be recognized that a Demand Resource is typically an aggregated portfolio that may be composed of many Demand Resource registrations, each representing an individual customer location. Such aggregations are composed of heterogeneous and highly variable customers, each having different negotiated contract length and expirations and each of them experiencing changes in the way they consume electricity over time. Aggregation activities by CSPs are what allows a diverse, evolving group of customers to provide a firm capacity resource.
that under Section 205, a party must file “those practices that affect rates and service significantly, that are realistically susceptible of specification, and that are not so generally understood in any contractual arrangement as to render recitation superfluous.”).
60 Proposed Tariff, Attachment DD-4, section VII(i)(ii) (emphasis added).61 Id. (emphasis added).
PDF page 20
20
In PJM, the quantum of Demand Resources that a customer can provide is capped at its Peak Load Contribution (“PLC”).62 Individual contributions to an aggregator’s portfolio change annually and may be difficult to predict more than one year into the future. Individual customer volumes of participating demand response expands and contracts based upon PLC as well as customer usage patterns. Businesses and homes change owners/tenants and new occupants may decide to start or stop participation in demand response. Technology evolves. Equipment gets old and may be replaced. Batteries, distributed generation, electric vehicles, etc., all can change customer PLC and load reduction capabilities. This diversity and the ebb and flow of customer demand response capabilities is managed by aggregators – who can add new customers to replace customers who depart or whose flexible capability declines. However, in the aggregate, the volume of the Demand Resource is reliable.
PJM’s proposal, if interpreted inconsistently with NRG’s approach, would mandate individual customer locations to make the required eligibility showing for the full 10-year period. This is anathema to long-standing Commission-approved approaches for demand response portfolio management.63 The Commission should specify that Demand Resources may
62 PJM Capacity Market, Manual 18 § 4.3.7 (rev. 62, Dec. 17, 2025).63 Participation of Distributed Energy Res. Aggregations in Markets Operated by Reg’l Transmission Organizations & Indep. Sys. Operators, Order No. 2222, 172 FERC ¶ 61,247, at P 337 (2020) (“We find that the incremental impacts on RTO/ISO markets and operations that would result from the addition or removal of individual distributed energy resources from a distributed energy resource aggregation, after the initial registration, are likely to be minimal and thus individual distributed energy resources should generally be able to enter and exit distributed energy resource aggregations participating in RTO/ISO markets without impairing safety and reliability”) reh’g granted, Order No. 2222-A, 174 FERC ¶ 61,197 at P 71, reh’g granted, Order No. 2222-B, 175 FERC ¶ 61,227 (2021).
PDF page 21
21
participate at the aggregator level and need not show individual contracts with each sub-resource within a CSP contain a 10-year commitment.
VI. CONCLUSION
NRG respectfully requests that the Commission order PJM to make a compliance filing, based on this protest and any responsive pleadings filed by PJM, to revise PJM’s tariff consistent with the changes proposed herein, thus ensuring that PJM’s tariff is just and reasonable and not unduly discriminatory.
Respectfully submitted,
/s/ Michael A. Yuffee
Michael A. Yuffee
Joe Bower
BAKER BOTTS LLP
700 K Street NW
Washington, DC 20001
Cortney Madea Slager
Vice President & Assistant General Counsel
Brianna Anderson
Regulatory Counsel
NRG Energy, Inc.
804 Carnegie Center
Princeton, NJ 08540
Counsel for the NRG Companies
Dated September 3, 2026
PDF page 22
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document on each person designated on the official service list compiled by the Secretary in the above-captioned proceeding.
Dated at Washington, D.C., this 3rd day of September 2026.
Joe Bower
Joe Bower