Comments and Limited Protest of NRG Business Marketing LLC, et. al. re the Interim Resource Adequacy Service proposed by PJM Interconnection, L.L.C
Text extracted from the eLibrary original (SHA-256 62da697077062d57…). Download the original from the official source.
Contents · 8 sections
- I. ABOUT NRG
- II. BACKGROUND
- III. COMMENTS IN SUPPORT OF THE PJM IRAS FILING
- IV. LIMITED PROTEST
- A. New Demand Resources Should Be Permitted to Bid into the Market to Support
- B. Capacity Serving New Large Loads Should Not Be Required to Bid into the BRA as
- V. NRG SEEKS CLARIFICATION, OR IN THE ALTERNATIVE, TARIFF
- VI. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
However, PJM’s proposal contains elements that are unjust, unreasonable, unduly discriminatory, and must be revised.Read this passage Filed comments: Reliability and curtailment
I. ABOUT NRG
printed heading
ABOUT NRG Through various subsidiaries, NRG owns or controls over 9 GW of generation in PJM as well as generation in adjacent markets that can be imported into the PJM market.Read this passage
II. BACKGROUND
printed heading · Topic match: Connecting load and generation
For providing the reduction, PJM proposes an IRAS rate equal to 50% of the Non-Performance Charge Rate, with flexibility for Electric Distributors and states to reduce the rate or for eligible New Large Loads to waive compensation entirely.Read this passage Filed comments: Connecting load and generation
III. COMMENTS IN SUPPORT OF THE PJM IRAS FILING
printed heading · Topic match: Registry access
Specifically, the PJM IRAS Filing provides that “PJM can call on IRAS load reductions prior to calling on Pre-Emergency Load Management Reductions Actions when needed to avoid a capacity shortage.”11 As PJM notes, this provision does not identify the specific load that an Electric Distributor must…Read this passage Filed comments: Registry access
IV. LIMITED PROTEST
printed heading
LIMITED PROTEST Pursuant to the Commission’s Rule 211,14 NRG provides the following limited protest.Read this passage
A. New Demand Resources Should Be Permitted to Bid into the Market to Support
printed heading · Topic match: Reliability and curtailment
Taken together, these factors contradict how PJM proposes treating these resources.Read this passage Filed comments: Reliability and curtailment
B. Capacity Serving New Large Loads Should Not Be Required to Bid into the BRA as
printed heading
Capacity Serving New Large Loads Should Not Be Required to Bid into the BRA as a Price Taker for 10 Years Without a Replacement Mechanism PJM proposes that “BYONC must participate, as a price taker (i.e. $0/MW offer) in RPM Auctions for 10 consecutive Delivery Years.”42 PJM states that the BYONC…Read this passage
V. NRG SEEKS CLARIFICATION, OR IN THE ALTERNATIVE, TARIFF
printed heading · Topic match: Reliability and curtailment
However, the Commission must require PJM to provide clarity on how a Curtailment Service Provider (“CSP”) will be required to demonstrate each year of a 10-year period for a Demand Resource.58 Matters that significantly affect the rates, terms and conditions of service must be specified in the…Read this passage Filed comments: Reliability and curtailment
VI. CONCLUSION
printed heading
CONCLUSION NRG respectfully requests that the Commission order PJM to make a compliance filing, based on this protest and any responsive pleadings filed by PJM, to revise PJM’s tariff consistent with the changes proposed herein, thus ensuring that PJM’s tariff is just and reasonable and not unduly…Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 3rd day of September 2026.Read this passage