Comments of Tesla, Inc. re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-3515
COMMENTS OF TESLA, INC.
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission ("Commission"), Tesla, Inc. ("Tesla") respectfully submits these comments regarding PJM Interconnection, L.L.C.'s ("PJM") proposed Interim Resource Adequacy Service ("IRAS") framework and associated provisions affecting Peak Shaving Adjustments ("PSAs"), Reliability Backstop Procurement ("RBP"), and related resource adequacy mechanisms.
I. INTRODUCTION AND SUMMARY
Tesla does not take a position in these comments on whether the Commission should approve or reject PJM's proposed IRAS construct as a whole. Tesla does, however, respectfully request that the Commission modify PJM's proposal in several important respects to ensure that the final rules do not unnecessarily disadvantage forecast-reducing demand-side reliability solutions relative to supply-side reliability solutions. These modifications are important regardless of the Commission's ultimate disposition of the broader IRAS framework. They improve forecast accuracy, preserve technology neutrality, support resource adequacy, facilitate emerging state-level reliability initiatives, and ensure that customers funding reliability solutions receive comparable treatment regardless of whether those solutions are modeled as incremental supply or forecast reductions.
Specifically, Tesla requests that the Commission:
1. Require that qualifying Peak Shaving Adjustments funded by Large Loads receive the same exemption from IRAS curtailment obligations that PJM proposes to provide through Bring Your Own New Capacity ("BYONC") arrangements, with such
exemption equal to the PJM-approved MW value associated with the applicable PSA;
2. Ensure that reliability mechanisms producing equivalent reductions in PJM reliability requirements receive equivalent regulatory treatment, regardless of whether those reductions are achieved through supply-side capacity additions or forecast-reducing demand-side actions;
PDF page 2
2
3. Direct PJM to expeditiously modernize Manual 19 Attachment D so that residential and commercial customers with eligible technologies, particularly export-capable distributed energy resources, may receive appropriate recognition for verifiable peak- reducing performance;
4. Clarify that, pending Attachment D modernization, PJM may utilize existing Manual 19 Attachment B authorities to recognize committed and verifiable demand-side reductions that lower load forecasts and Reliability Requirements in the same manner that known load additions increase them; and
5. Ensure that baseline methodologies utilized under both Attachment B and Attachment D properly recognize export-related performance and do not terminate measurement of performance merely because a resource becomes a net exporter. These issues affect more than individual market participants. Multiple PJM states are actively pursuing programs designed to reduce peak demand and capacity obligations through resources such as battery aggregations, smart thermostats, electric vehicles, and Virtual Power Plants ("VPPs"). PJM itself has identified Peak Shaving Adjustment mechanisms as an important component of Reliability Backstop Procurement flexibility and potential state-driven solutions. The success of these initiatives depends upon accurate forecasting, appropriate baseline treatment, and equal treatment of equivalent reliability contributions.
II. LARGE LOADS FUNDING PEAK SHAVING ADJUSTMENTS SHOULD RECEIVE THE
SAME IRAS CURTAILMENT TREATMENT AS LARGE LOADS UTILIZING BYONC
Tesla respectfully submits that Large Loads funding qualifying Peak Shaving Adjustment programs should receive the same IRAS curtailment treatment as Large Loads utilizing BYONC arrangements.
Under PJM's proposal, a Large Load that directly procures or funds incremental reliability resources through BYONC receives the benefit of that procurement in the form of relief from IRAS curtailment obligations. The same principle should apply where a Large Load funds reliability through a qualifying Peak Shaving Adjustment that produces a measurable reduction in PJM's Reliability Requirement. From a reliability perspective, the outcome is the same. In each case, the Large Load is paying for capacity or reliability benefits that reduce the amount of residual reliability procurement PJM must otherwise secure. A Large Load funding a qualifying PSA has already paid to reduce the reliability need that IRAS is intended to address. Subjecting that same load to IRAS curtailment obligations while exempting a similarly situated BYONC-supported load would effectively require the customer to pay twice for the same reliability objective.
PDF page 3
3
The distinction between the two approaches is one of accounting treatment rather than reliability outcome. BYONC-supported megawatts reduce the amount of reliability procurement PJM must otherwise obtain through additional supply. PSA-supported megawatts reduce the amount of reliability procurement PJM must otherwise obtain by lowering forecasted reliability requirements. Both mechanisms reduce the quantity of remaining reliability procurement required from PJM. Both improve resource adequacy. Both reduce obligations that otherwise would have been imposed upon the broader market. Accordingly, the exemption from IRAS curtailment obligations associated with a qualifying Large Load-funded PSA should be equal to the MW value approved by PJM for that PSA. Where PJM has determined through its established Peak Shaving Adjustment processes that a PSA produces a specified reduction in Reliability Requirements, the Large Load responsible for funding that reduction should receive an equivalent MW quantity of relief from IRAS curtailment obligations. This approach aligns the scope of the exemption directly with the reliability value recognized by PJM, ensures that customers receive credit only for verified and approved reliability contributions, and places PSA-funded reliability solutions on equal footing with BYONC-supported reliability solutions that produce equivalent reliability outcomes.
Tesla is aware of no reliability, operational, market design, or regulatory rationale that would justify disparate treatment between these equivalent reliability outcomes. To the contrary, unequal treatment would materially devalue PSA-supported reliability solutions, undermine investment in customer-funded peak-shaving programs, and create an artificial preference for one reliability mechanism over another despite equivalent reliability outcomes. The importance of this parity extends beyond individual customer economics. PJM's proposed Reliability Backstop Procurement opt-out framework and several emerging state- level initiatives contemplate circumstances in which Large Loads may fund peak-shaving and Virtual Power Plant programs that offset incremental load growth through PSA-based mechanisms. The viability of these frameworks depends upon Large Loads receiving reliability treatment commensurate with the reliability value they fund. If Large Loads can secure curtailment relief through BYONC but not through a PJM-approved PSA that delivers an equivalent reliability benefit, the economic rationale for utilizing PSA-supported solutions is substantially diminished.
Accordingly, the Commission should modify PJM's proposal to ensure that Large Loads supported by qualifying PSA megawatts receive IRAS curtailment relief equal to the PJM- approved MW value of the applicable PSA, consistent with the treatment provided to Large Loads utilizing BYONC arrangements.
PDF page 4
4
III. PSA PARITY IS ESSENTIAL TO THE SUCCESS OF RBP OPT-OUTS AND STATE-LEVEL
RELIABILITY INITIATIVES
The consequences of unequal treatment extend far beyond individual customer economics. Multiple PJM states are actively working toward implementation of technology-neutral programs intended to reduce zonal capacity obligations through dispatchable distributed energy resources and Virtual Power Plants. Many of these initiatives rely, either explicitly or implicitly, upon the Peak Shaving Adjustment framework contained in Manual 19
Attachment D.
Likewise, PJM has identified Peak Shaving Adjustments as a mechanism that may support state-directed approaches to Reliability Backstop Procurement and enable customers or states to address reliability needs through targeted peak reduction efforts. The success of these initiatives depends on a straightforward principle: a Large Load that pays for reliability should receive the reliability value created by that payment.
This principle is particularly important for emerging initiatives in Virginia and New Jersey, where policymakers have explored frameworks under which Large Loads could support Virtual Power Plant deployments and peak reduction programs that offset incremental load additions through PSA-based mechanisms.12 Those programs depend upon the ability of Large Loads to fund reliability solutions that reduce PJM Reliability Requirements and receive treatment comparable to that provided under BYONC.
If a Large Load funds a PSA-supported reduction in reliability requirements but remains fully subject to IRAS curtailment obligations from which a BYONC-supported Large Load would be exempt, the practical value of the PSA pathway is substantially diminished. Such a result would undermine the economic foundation of the Reliability Backstop Procurement opt-out concept, weaken state-directed reliability initiatives, discourage investment in customer-
1 See, e.g., In the Matter of Establishing New Jersey's Virtual Power Plant Program, N.J. Board of Public Utilities, Straw Proposal, Docket No. QO26030099 (filed March 31, 2026), available at https://nj.gov/bpu/pdf/publicnotice/VPP%20Straw%20Proposal%20Final.pdf (proposing a structured statewide framework to aggregate distributed resources for peak load shaving and grid support); An Act Concerning the Provision of Electricity to Certain Data Centers, N.J. Stat. Ann. § 48 (enacted as New Jersey Bill A796/S731, July 7, 2026), text available at https://njleg.state.nj.us/bill-search/2026/A796 (requiring special tariffs for data centers with large energy demands to protect grid costs and encourage demand reduction measures).
2 Virginia Senate Bill 371 (Acts of Assembly Chapter 0378), Va. Code Ann. § 56-596.7 (enacted April 8, 2026), text available at https://lis.virginia.gov/bill-details/20261/SB371 (mandating large electric utilities to petition for voluntary demand flexibility programs targeting high energy demand customers to lower total grid system load).
PDF page 5
5
funded reliability solutions, and create an artificial preference among reliability mechanisms despite equivalent reliability outcomes.
Likewise, limiting PSA eligibility to participants in the RBP would limit the benefits of large- load funded PSA-eligible load reduction programs to only a subset of large load coming online in the near future, rather than establishing a more permanent pathway for large load customers to fund demand-side programs that can reduce zonal capacity obligations and provide immediate ratepayer benefits.
The Commission should therefore ensure that Large Load-funded PSA programs receive treatment equivalent to Large Load-supported BYONC arrangements wherever they produce equivalent reductions in PJM reliability requirements.
IV. FEDERAL POWER ACT PRINCIPLES REQUIRE COMPARABLE TREATMENT OF
EQUIVALENT RELIABILITY OUTCOMES
Sections 205 and 206 of the Federal Power Act prohibit rates, terms, conditions, and practices that are unjust, unreasonable, unduly discriminatory, or preferential.3 The Commission has long recognized that similarly situated customers and resources should not receive materially different treatment absent a legitimate basis for differentiation.4 The Commission's comparability principles have consistently focused on substance rather than form. Where two mechanisms provide equivalent service, equivalent value, or equivalent system benefit, disparate treatment requires a demonstrable justification tied to operational or reliability differences.
Those principles are directly applicable here.
A Large Load that funds reliability through a qualifying Peak Shaving Adjustment and a Large Load that funds reliability through BYONC have each taken action to reduce PJM's remaining reliability procurement requirement. Likewise, a resource that reduces net demand through reduced consumption and a resource that reduces net demand through increased exports can produce equivalent reductions in PJM's expected reliability requirements. The reliability outcome is what matters.
3 Federal Power Act §§ 205-206, 16 U.S.C. §§ 824d-824e.4 See, e.g., Order No. 888, Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, FERC Stats. & Regs. ¶ 31,036 (1996); Order No. 890, Preventing Undue Discrimination and Preference in Transmission Service, FERC Stats. & Regs. ¶ 31,241 (2007).
PDF page 6
6
Absent a demonstrated reliability distinction, differential treatment elevates accounting form over reliability substance and risks creating an undue preference for one reliability mechanism over another.
Accordingly, the Commission should modify PJM's proposal to ensure that:
1. Reliability mechanisms producing equivalent reliability outcomes receive equivalent treatment;
2. Supply-side and forecast-reducing reliability solutions are evaluated on a technology-neutral basis;
3. Export-capable distributed resources are not disadvantaged relative to traditional load-reducing resources;
4. Baseline methodologies appropriately recognize both load reductions and export- related performance; and
5. PSA-supported reliability contributions funded by Large Loads receive treatment equivalent to BYONC-supported reliability contributions where both reduce PJM reliability requirements to the same extent.
Such treatment is consistent with longstanding Commission policy favoring comparability, non-discrimination, and competition among resources capable of producing equivalent reliability benefits.
V. IMMEDIATE RECOGNITION OF PSA-LIKE DEMAND-SIDE FORECAST REDUCTIONS
UNDER ATTACHMENT B AND EXPEDITED ATTACHMENT D MODERNIZATION ARE
NECESSARY REGARDLESS OF THE ULTIMATE IRAS OUTCOME
Regardless of the Commission's disposition of the broader IRAS proposal, PJM should adopt reforms that remove remaining barriers to both supply-side and demand-side participation by distributed energy resources and aggregations in order to create simpler pathways for much-needed capacity to provide untapped value.
Immediate recognition under existing Attachment B processes of PSA-like demand-side forecast reductions, together with expedited modernization of Attachment D, represents one of the most important near-term opportunities to improve forecast accuracy and resource adequacy.
These reforms are necessary so that verified peak-reducing resources and programs, particularly those serving residential and small commercial customers with eligible technologies, and especially resources with injection capability, can be accurately reflected as downward adjustments to the load forecast and Reliability Requirement. Doing so will
PDF page 7
7
improve forecast accuracy, reduce capacity cost exposure for all ratepayers, improve the accuracy of zonal reliability signals, allow aggregators to stack wholesale and retail value streams in a non-duplicative manner, and ensure that the growing fleet of residential batteries and other distributed energy resources can contribute to resource adequacy. Multiple PJM states are actively working toward implementation of technology-neutral programs specifically designed to reduce zonal capacity purchase obligations for the benefit of ratepayers. In order for these programs to work, they explicitly require or will rely upon the Peak Shaving Adjustment mechanism under Manual 19 Attachment D. In parallel, PJM has identified Peak Shaving Adjustments as a means through which states, utilities, or Load Serving Entities may address reliability needs through targeted peak reduction efforts rather than relying exclusively upon traditional procurement pathways.
These parallel state and PJM initiatives underscore the urgency of clarifying the application of Attachment B to PSA-like demand-side forecast reductions and expediting modernization of Attachment D. Without prompt, non-discriminatory operationalization of these Manual 19 tools, including modern measurement and verification approaches suitable for residential and injection-capable resources, state programs and PJM's own reliability frameworks cannot deliver their intended wholesale forecast and Reliability Requirement reductions. Under any IRAS outcome, improved load forecast accuracy and the ability of customers with eligible distributed energy resources, especially those with injection capability, to provide verifiable system benefits are foundational. Manual 19 Attachments B and D already contain the mechanisms necessary to accomplish those objectives. They require only prompt operationalization and targeted modernization to ensure that committed and measurable peak reductions lower the unrestricted forecast and resulting Reliability Requirement in the same manner that verified load additions increase them.
VI. ATTACHMENT B SHOULD RECOGNIZE PSA-LIKE DEMAND-SIDE PROGRAMS
PENDING ATTACHMENT D MODERNIZATION
Attachment B already establishes a process through which Electric Distribution Companies and Load Serving Entities may propose significant forecast adjustments so that PJM's load forecast accurately reflects known deviations not captured by the underlying forecast model.
Tesla is not requesting a new category of load forecast adjustment. Nor is Tesla suggesting that Attachment B lacks authority to recognize forecast reductions. Attachment B already provides a mechanism through which significant forecast adjustments, including reductions, may be reflected in PJM's planning assumptions where supported by appropriate documentation and analysis.
PDF page 8
8
Rather, Tesla requests that PJM explicitly recognize that committed and verifiable demand- side programs designed to reduce peak demand and Reliability Requirements may be submitted and evaluated under Attachment B using a framework that mirrors the established Peak Shaving Adjustment process contained in Attachment D. Specifically, demand-side programs seeking Attachment B treatment should be subject to substantially the same requirements that currently apply to Peak Shaving Adjustments, including plan documentation, performance commitments, officer certification, data submission requirements, review processes, and future performance accountability. Doing so ensures that forecast-recognized demand reductions are supported by the same level of rigor and oversight currently applied to forecast-recognized Peak Shaving Adjustments. The principal area in which Attachment B treatment should differ from the existing Attachment D framework is measurement and verification.
Attachment B should utilize measurement and verification methodologies already established elsewhere in PJM manuals, including Customer Baseline Load methodologies, Metered Generator Output methodologies, and other approaches suitable for export- capable distributed energy resources. Such methodologies should be applied in a manner that appropriately recognizes export-related performance and avoids understating the reliability value provided by injection-capable resources, as discussed in Section VII below. At the same time, Attachment D should be modernized on an expedited basis so that the same types of resources can be recognized directly through the Peak Shaving Adjustment framework itself and utilize equivalent export-aware measurement and verification approaches.
Under this approach, Attachment B serves as an immediately available pathway for recognizing committed forecast reductions using the proven administrative framework of Attachment D, while Attachment D modernization proceeds through the stakeholder process.
This clarification would improve forecast accuracy, facilitate state-directed peak reduction initiatives, and ensure that committed and measurable demand-side actions lower the unrestricted forecast and resulting Reliability Requirement in the same manner that significant known load additions increase them.
VII. BASELINE METHODOLOGIES UNDER BOTH ATTACHMENT B AND ATTACHMENT D
MUST PROPERLY RECOGNIZE EXPORT-RELATED PERFORMANCE
For both the interim Attachment B pathway and expedited Attachment D reforms, PJM should ensure that baseline methodologies accurately capture the reliability benefits provided by modern export-capable forecast modifying resources.
PDF page 9
9
Existing Manual 11 baselines were developed for demand-side wholesale supply resources. Limitations on export, which currently apply to supply resources, should not be imposed on demand-side forecast modifying resources.
Baseline methodologies should therefore measure actual system impacts rather than rely upon assumptions developed for a purely consumptive load environment.
For example, a customer may already be exporting power during a system peak event when a dispatch signal from a smart thermostat, battery aggregation, electric vehicle program, or other demand-side mechanism may further reduce load wholesale supply resources. The resulting reliability benefit does not cease once the customer's net consumption reaches zero.
To the contrary, the system receives additional reliability value because net load reduction continues to increase beyond that point.
Accordingly, any Customer Baseline Load methodology utilized under either Attachment B or Attachment D should continue measuring performance beyond the point at which exports begin rather than terminating performance recognition at the net-export threshold. Similarly, where Metered Generator Output ("MGO") methodologies are utilized under either Attachment B or Attachment D to establish performance for battery energy storage systems participating through Peak Shaving Adjustment programs or comparable forecast-reducing mechanisms, the baseline should appropriately exclude prior event days and other distortive operating periods.
In particular, where net-metered battery systems have previously discharged during peak events, those event days should not be allowed to suppress future baseline values in a manner that understates actual reliability contributions. Baseline methodologies should estimate expected performance absent the reliability action being measured rather than embedding prior dispatch events into future baseline calculations.
The relevant question should not be whether a resource reduced consumption or increased exports. The relevant question should be whether the resource produced a measurable reduction in PJM's expected reliability requirement.
Baseline methodologies under both Attachment B and Attachment D should be designed accordingly.
VIII. CONCLUSION
For the foregoing reasons, Tesla respectfully requests that the Commission modify PJM's proposal to:
PDF page 10
10
1. Require equivalent treatment of Large Load-funded PSA-supported and BYONC- supported reliability contributions for purposes of IRAS curtailment obligations, including IRAS curtailment relief equal to the PJM-approved MW value associated with a qualifying PSA;
2. Apply longstanding Federal Power Act comparability and non-discrimination principles to ensure that reliability mechanisms producing equivalent reliability outcomes receive equivalent treatment;
3. Ensure that the final IRAS framework preserves the viability of Reliability Backstop Procurement opt-outs and state-directed reliability initiatives that rely upon PSA- based mechanisms;
4. Encourage expedited modernization of Manual 19 Attachment D;
5. Recognize Manual 19 Attachment B as an appropriate interim mechanism for PSA- like demand-side forecast reductions utilizing the administrative framework of Attachment D and modernized measurement and verification methodologies; and
6. Ensure that baseline methodologies under both Attachment B and Attachment D appropriately recognize export-related performance and that MGO and related methodologies appropriately measure net-metered battery performance. Respectfully submitted,
Tesla, Inc.
By: /s/ Jaden D. Crawford
Jaden D. Crawford
Head of VPP Policy, North America
Tesla, Inc.
jadcrawford@tesla.com
Dated: September 3, 2026