ER26-3515-000 · 2026-09-03 · Tesla, Inc.

Comments of Tesla, Inc. re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service

Text extracted from the eLibrary original (SHA-256 42b6a57cce88b352…). Download the original from the official source.

Contents · 8 sections
  1. I. INTRODUCTION AND SUMMARY p. 1
  2. II. LARGE LOADS FUNDING PEAK SHAVING ADJUSTMENTS SHOULD RECEIVE THE p. 2
  3. III. PSA PARITY IS ESSENTIAL TO THE SUCCESS OF RBP OPT-OUTS AND STATE-LEVEL p. 4
  4. IV. FEDERAL POWER ACT PRINCIPLES REQUIRE COMPARABLE TREATMENT OF p. 5
  5. V. IMMEDIATE RECOGNITION OF PSA-LIKE DEMAND-SIDE FORECAST REDUCTIONS p. 6
  6. VI. ATTACHMENT B SHOULD RECOGNIZE PSA-LIKE DEMAND-SIDE PROGRAMS p. 7
  7. VII. BASELINE METHODOLOGIES UNDER BOTH ATTACHMENT B AND ATTACHMENT D p. 8
  8. VIII. CONCLUSION p. 9

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission ("Commission"), Tesla, Inc. ("Tesla") respectfully submits these comments regarding PJM Interconnection, L.L.C.'s ("PJM") proposed Interim Resource Adequacy Service ("IRAS") framework and…
Read this passage Filed comments: Reliability and curtailment

I. INTRODUCTION AND SUMMARY

printed heading · Topic match: Reliability and curtailment

Require that qualifying Peak Shaving Adjustments funded by Large Loads receive the same exemption from IRAS curtailment obligations that PJM proposes to provide through Bring Your Own New Capacity ("BYONC") arrangements, with such exemption equal to the PJM-approved MW value associated with the…
Read this passage Filed comments: Reliability and curtailment

II. LARGE LOADS FUNDING PEAK SHAVING ADJUSTMENTS SHOULD RECEIVE THE

printed heading · Topic match: Reliability and curtailment

In each case, the Large Load is paying for capacity or reliability benefits that reduce the amount of residual reliability procurement PJM must otherwise secure.
Read this passage Filed comments: Reliability and curtailment

III. PSA PARITY IS ESSENTIAL TO THE SUCCESS OF RBP OPT-OUTS AND STATE-LEVEL

printed heading · Topic match: Reliability and curtailment

If a Large Load funds a PSA-supported reduction in reliability requirements but remains fully subject to IRAS curtailment obligations from which a BYONC-supported Large Load would be exempt, the practical value of the PSA pathway is substantially diminished.
Read this passage Filed comments: Reliability and curtailment

IV. FEDERAL POWER ACT PRINCIPLES REQUIRE COMPARABLE TREATMENT OF

printed heading

FEDERAL POWER ACT PRINCIPLES REQUIRE COMPARABLE TREATMENT OF EQUIVALENT RELIABILITY OUTCOMES Sections 205 and 206 of the Federal Power Act prohibit rates, terms, conditions, and practices that are unjust, unreasonable, unduly discriminatory, or preferential.3 The Commission has long recognized that…
Read this passage

V. IMMEDIATE RECOGNITION OF PSA-LIKE DEMAND-SIDE FORECAST REDUCTIONS

printed heading · Topic match: Cost allocation

Immediate recognition under existing Attachment B processes of PSA-like demand-side forecast reductions, together with expedited modernization of Attachment D, represents one of the most important near-term opportunities to improve forecast accuracy and resource adequacy.
Read this passage Filed comments: Cost allocation

VI. ATTACHMENT B SHOULD RECOGNIZE PSA-LIKE DEMAND-SIDE PROGRAMS

printed heading

Attachment B already provides a mechanism through which significant forecast adjustments, including reductions, may be reflected in PJM's planning assumptions where supported by appropriate documentation and analysis. 8 Rather, Tesla requests that PJM explicitly recognize that committed and…
Read this passage

VII. BASELINE METHODOLOGIES UNDER BOTH ATTACHMENT B AND ATTACHMENT D

printed heading

BASELINE METHODOLOGIES UNDER BOTH ATTACHMENT B AND ATTACHMENT D MUST PROPERLY RECOGNIZE EXPORT-RELATED PERFORMANCE For both the interim Attachment B pathway and expedited Attachment D reforms, PJM should ensure that baseline methodologies accurately capture the reliability benefits provided by…
Read this passage

VIII. CONCLUSION

printed heading · Topic match: Reliability and curtailment

CONCLUSION For the foregoing reasons, Tesla respectfully requests that the Commission modify PJM's proposal to: 10 1.
Read this passage Filed comments: Reliability and curtailment