ER26-3515-000 · 2026-09-03 · PPL Electric Utilities Corporation

Motion to Intervene, Protest, and Request for Clarification of PPL Electric Utilities Corporation regarding PJM Interconnection L.L.C.’s Interim Resource…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)

Docket No. ER26-3515-000

MOTION TO INTERVENE, PROTEST,
AND REQUEST FOR CLARIFICATION OF
PPL ELECTRIC UTILITIES CORPORATION
Pursuant to Rules 211,1 212,2 and 2143 of the Federal Energy Regulatory
Commission’s (“FERC” or the “Commission”) Rules of Practice and Procedure, PPL Electric Utilities Corporation (“PPL Electric”) respectfully moves to intervene in the above-captioned proceeding, provides the following protest (“Protest”), and requests clarification regarding PJM Interconnection L.L.C.’s (“PJM”) Interim Resource Adequacy Service (“IRAS”) Filing.4 PPL Electric greatly appreciates the work of the PJM Board and staff in acting to

address the unique operational, planning, and markets challenges presented by large loads in the PJM Region,5 and PPL Electric remains committed to working towards an enduring

connect and manage framework to “meet the moment.”6  It is in this collaborative spirit that

1 18 C.F.R. § 385.211(a)(1) (“Any person may file a protest to object to any application, complaint, petition, order to show cause, notice of tariff or rate examination, or tariff or rate filing.”).

2 18 C.F.R. § 385.212(a)(1) (“A motion may be filed: [a]t any time, unless otherwise provided.”). 3 18 C.F.R. § 385.214(a)(3) (“Any person seeking to intervene to become a party, other than the entities specified in paragraphs (a)(1) and (a)(2) of this section, must file a motion to intervene.”).

4 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service & a Large Load Registry, Docket No. ER26-3515-000 (Aug. 13, 2026) (hereafter, the “IRAS Filing”).
5 Terms not otherwise defined herein shall have the same meaning as set forth in the PJM Open Access Transmission Tariff (“Tariff”), the Amended and Restated Operating Agreement of PJM Interconnection, L.L.C. (“Operating Agreement”), and the Reliability Assurance Agreement Among Load-Serving Entities in the PJM Region (“RAA”).  Each of these Governing Agreements is currently located under PJM’s “Intra-PJM Tariffs” eTariff title, available here: https://etariff.ferc.gov/TariffBrowser.aspx?tid=1731.
6 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026), LaCerte Concurrence at P 6 (“This is not a time to be cavalier and dodge the urgent need to meet the moment.”).

PDF page 2

2
PPL Electric submits this protest to highlight for the Commission a core reality of the IRAS Filing—it is not legally durable on appeal.

As explained below, because of how PJM has drafted its Tariff language, if accepted without modification, the IRAS Filing would mark the first time in history that the Commission would be requiring the mandatory and involuntary designation of end-use retail customers (Eligible New Large Loads) to provide a FERC-jurisdictional wholesale rate service (IRAS), and the compulsory provision of that FERC-jurisdictional wholesale rate service (IRAS) to a Regional Transmission Organization (“RTO”) pursuant to FERC-approved rates, terms, and conditions in a FERC-approved tariff.  While PJM correctly, and consistent with current process, defers to the applicable Electric Distributor and state/local regulatory authorities in determining which specific individual Eligible New Large Loads within a given zone should actually provide IRAS when called upon, the fact remains that all Eligible New Large Loads (end-use, retail customers) within a zone are assigned responsibility by PJM to provide this wholesale rate service, pursuant to FERC-jurisdictional rates, terms, and conditions, and must provide this wholesale rate service to PJM when called upon.  This exceeds the Commission’s legal authority under the Federal Power Act (“FPA”), under the plain language of the statute and applicable precedents.

PPL Electric agrees with Chairman Swett on the need to create “legally durable”7 solutions in this space.  Because PJM has provided the Commission with broad NRG

7 Id. at Swett Concurrence, P 3 (“I wholeheartedly, fully concur with these orders, which we carefully crafted to execute upon the problems the Secretary identified in a manner that is quick, efficient, and legally durable.”).

PDF page 3

3
flexibility8 in this FPA section 2059 proceeding, PPL Electric offers two alternative routes that the Commission could take to ameliorate the jurisdictional challenges for the IRAS initiative. Option 1 -

Have PJM’s Tariff language stop at the issuance of the
Operating Instruction to Electric Distributors to curtail load, and
leave the rates, terms, and conditions of that load curtailment
service to state and local regulatory authorities—many of whom
have already signed the Ratepayer Protection Pledge.  This
would avoid a scenario where federally imposed obligations are
colliding with state and local-jurisdictional law and tariffs,
including the statutory “obligation to serve,” and would provide
a much more jurisdictionally sound legal pathway to effectuate
connect and manage under FPA section 201.
Option 2 -
Alternatively, make IRAS a voluntary FERC-jurisdictional
service, whereby Electric Distributors and/or large load
customers themselves can voluntarily choose to participate like
any other wholesale market service provider in PJM (including
demand response providers).  Given the enthusiasm with which
many large load developers and Electric Distributors have
signed the Ratepayer Protection Pledge,10 there should clearly
be a high level of interest in voluntarily participating in such a
program.  Such a program would also be consistent with EPSA,11
where the Supreme Court affirmed the Commission’s ability to
create programs that “lure,” rather than force, end-use retail

8 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) (“NRG”).  See IRAS Filing at 9 (“Nevertheless, in the event the Commission deems it necessary, and to help facilitate the Commission’s acceptance of this filing without delay, PJM provides notice that it consents to the Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under FPA section 205 and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching objectives in this filing. While the [sic] each of the reforms proposed in this filing is just and reasonable and act together to advance important resource adequacy objectives, they may also be considered discretely.”). 9 16 U.S.C. § 824d.
10 See Ratepayer Protection Pledge, The White House (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.
11 FERC v. Electric Power Supply Ass’n, 577 U.S. 260, 286 (2016) (“EPSA”).

PDF page 4

4
customers into participating in FERC-jurisdictional wholesale
markets.
Beyond this, PPL Electric also highlights below several structural deficiencies in the IRAS Filing and respectfully requests that the Commission reject or modify these components, consistent with PJM’s NRG invitation.

Finally, PPL Electric respectfully requests that PJM and/or the Commission clarify in this proceeding several important policy and implementation details of the IRAS Filing.

I. MOTION TO INTERVENE
PPL Electric respectfully moves to intervene in the above-captioned proceeding.  PPL Electric is a Pennsylvania corporation and a wholly owned subsidiary of PPL Corporation. PPL Electric is an owner of transmission facilities in PJM Interconnection, L.L.C. (“PJM”), distributes electricity to all retail customers within its service territory in central and eastern Pennsylvania, and is a provider of last resort under Pennsylvania’s Electricity Generation Customer Choice and Competition Act, 66 Pa.C.S.A. § 2801, et seq.  PPL Electric is a designated Load Serving Entity in PJM, and a signatory to the PJM Consolidated Transmission Owners Agreement (“CTOA”) and the RAA.

On August 13, 2026, PJM initiated the above-captioned FPA section 205 proceeding by submitting proposed Tariff and RAA revisions to establish IRAS—a service to be implemented by PJM during periods when there are insufficient resources to reliably meet demand in real time operations.

Given the direct nexus between the IRAS Filing and PPL Electric’s roles and responsibilities within the PJM Region, PPL Electric has a direct, substantial, and independent interest in this proceeding, which no other party can adequately represent, and respectfully

PDF page 5

5
requests that the Commission grant this motion to intervene and that PPL Electric be afforded all the rights of a party to this proceeding.

II. PROTEST
A. PJM’s Proposal Unlawfully Requires the Mandatory and Involuntary Designation of End-Use Retail Customers (Eligible New Large Loads) to Provide a FERC- Jurisdictional Wholesale Rate Service (IRAS), and the Compulsory Provision of that FERC-Jurisdictional Wholesale Rate Service to an RTO, Pursuant to FERC- Approved Rates, Terms, and Conditions in a FERC-Approved Tariff.

The acute appellate risk presented by the IRAS Filing can be summarized by the following five sequential points:

1. IRAS is a new wholesale rate service, subject to the exclusive jurisdiction of the Commission, with rates, terms, and conditions established by the Commission under the Commission-approved PJM Tariff;

2. PJM’s Tariff language makes clear that Eligible New Large Loads are the entities that provide IRAS as a wholesale rate service—not the Electric Distributor or Load Serving Entity;

3. PJM’s Tariff language requires the mandatory and involuntary designation of Eligible New Large Loads to provide IRAS to PJM, and the compulsory provision of IRAS to PJM when called upon by PJM (through an implementing directive issued to the applicable Electric Distributor);

4. Eligible New Large Loads have no contractual privity with PJM, are not subject to a FERC-jurisdictional load interconnection process, and are not public utilities under FPA section 201;12 and

5. The FPA does not grant the Commission the legal authority to force end-use retail customers to be designated to provide a FERC-jurisdictional wholesale rate service, or to compel the provision of that wholesale rate service, pursuant to a FERC- approved Tariff.

PPL Electric describes each of these five points in seriatim below, in subsections II.A.i-v.

12 16 U.S.C. § 824.

PDF page 6

6
i. As proposed, IRAS is a new wholesale rate service, subject to the exclusive jurisdiction of the Commission, with rates, terms, and conditions established by the Commission under the Commission-approved PJM Tariff.

As presented by PJM, IRAS is a new wholesale rate service, with rates, terms, and conditions established under the jurisdictional authority of the Commission.  This is axiomatic from the extensive Tariff and RAA revisions that PJM has submitted in this FPA section 205 proceeding, covering everything from the definition of the service,13 eligibility requirements as to who can provide the service (Eligible New Large Loads),14 and the applicable rates for the service.15  Indeed, proposed Tariff, Attachment DD-4 explicitly states that it “sets forth the terms and conditions governing the provision of Interim Resource Adequacy Service.” Moreover, the intended objective of IRAS is clear and unequivocal—“to maintain system reliability for the purpose of supporting the integration of New Large Loads to the PJM Region that are not in arrangements with new capacity additions to the PJM Region.”16  In other words, IRAS serves a fundamentally PJM-specific regional and FERC-centric purpose, and is not intended to fulfill any smaller state or local jurisdictional legal function under FPA section 201.

Accordingly, as presented by PJM, IRAS is a new wholesale rate service, subject to the exclusive jurisdiction of the Commission, with its rates, terms, and conditions codified in the Commission-jurisdictional PJM Tariff.

13 See Proposed Tariff, Definitions I-J-K (“Interim Resource Adequacy Service shall mean a load reduction service through which New Large Loads reduce load as directed by the applicable Electric Distributor in response to an Interim Resource Adequacy Service Action requested by the Office of the Interconnection. Such reductions in load may be eligible for compensation pursuant to Attachment DD-4, section X.”).
14 See Proposed Tariff, Attachment DD-4, Section V.
15 Id. at Section X.
16 Id. at Section I.

PDF page 7

7
ii. PJM’s Tariff language makes clear that Eligible New Large Loads are the entities that provide IRAS—not the Electric Distributor or Load Serving Entity.

The Tariff language accompanying the IRAS Filing is unambiguous—Eligible New Large Loads (i.e., end-use retail customers) are the entities that “provide” IRAS as a FERC- jurisdictional wholesale rate service.

Eligible New Large Loads” shall mean a New Large Load eligible to provide Interim Resource Adequacy Service in accordance with Tariff, Attachment DD-4, section V.17 Interim Resource Adequacy Service is a load reduction service, effective starting with the 2027/2028 Delivery Year, through which Eligible New Large Loads may be compensated for providing load reductions requested by the Office of the Interconnection to maintain system reliability for the purpose of supporting the integration of New Large Loads to the PJM Region that are not in arrangements with new capacity additions to the PJM Region;18

The Large Load Registry maintained by the Office of the Interconnection, pursuant to the Reliability Assurance Agreement, shall inform which New Large Loads are eligible to be called on to provide Interim Resource Adequacy Service;19

The Office of the Interconnection Shall . . . determine the megawatt quantity of New Large Loads eligible to provide Interim Resource Adequacy Service in each Electric Distributor zone/area for a given Delivery Year.20

All Eligible New Large Loads shall be available to be requested to provide Interim Resource Adequacy Service by the Office of the Interconnection.21

17 Proposed Tariff, Definitions E-F.
18 Proposed Tariff, Attachment DD-4, Section I(a).
19 Id. at Section I(c).
20 Id. at Section II(c).
21 Id. at Section IV(a).

PDF page 8

8
For purposes of removing its eligibility to provide Interim
Resource Adequacy Service, a New Large Load may enter into
arrangements with BYONC supported by one or more resources.
While under PJM’s proposal, Electric Distributors and Load Serving Entities play an important role in “implementing” IRAS,22 they are not the entities actually “providing” IRAS as a wholesale, Commission-jurisdictional rate service to PJM.  This dynamic can be seen under PJM’s proposed compensation scheme as well, where the Eligible New Large Load is the entity entitled to compensation for providing IRAS service, notwithstanding that the Electric Distributor and state/local regulatory authorities can determine the implementation (and the ultimate applicability) of this compensation.23

iii. PJM’s Tariff language requires the mandatory and involuntary designation of Eligible New Large Loads to provide IRAS to PJM, and the compulsory

provision of IRAS to PJM when called upon by PJM (through an
implementing directive issued to the applicable Electric Distributor).
Under PJM’s proposed Tariff language, Eligible New Large Loads (i.e., end-use retail customers) are automatically designated as IRAS service providers by PJM.  In other words, designation as an entity that must provide FERC-jurisdictional wholesale IRAS service to PJM when called upon is mandatory, and this designation is made exclusively by PJM under its proposed Tariff language.

(c) The Large Load Registry maintained by the Office of the
Interconnection, pursuant to the Reliability Assurance
Agreement, shall inform which New Large Loads are eligible
to be called on to provide Interim Resource Adequacy
Service.24

22 See, e.g., id. at Section III(a) (“Electric Distributors shall . . . execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in the Electric Distributor’s zone/area . .  .”).  See also id. at Section III(c) (“Electric Distributors shall . . . implement compensation program consistent with Tariff, Attachment DD-4, section X.”).
23 See id. at Section X.
24 Proposed Tariff, Attachment DD-4, Section I(c).

PDF page 9

9
All New Large Loads shall be Eligible New Large Loads to the
extent that the sum of a New Large Load’s Eligible New Large
Load Amount is less than the New Large Load’s registered
peak load (in MW), as provided in the Large Load Registry.
New Large Loads with a cumulative installed capacity
equivalent of their BYONC arrangements and assigned
Allocated RBP UCAP MW that equals or exceeds the New
Large Load’s registered peak load, as provided in the Large
Load Registry, shall not be Eligible New Large Loads. New
Large Loads that are located within an FRR Service Area cannot
be Eligible New Large Loads.25
The Office of the Interconnection shall . . . identify Eligible
New Large Loads.26
While a New Large Load can theoretically reduce or eliminate its classification as an Eligible New Large Load and as an IRAS service provider via BYONC, this process too is exclusively determined pursuant to the terms and conditions of the FERC-jurisdictional PJM Tariff. For purposes of removing its eligibility to provide Interim

Resource Adequacy Service, a New Large Load may enter into
arrangements with BYONC supported by one or more
resources.27
Once designated as an Eligible New Large Load by PJM, PJM’s proposed Tariff language states that an Eligible New Large Load “shall” be available to provide IRAS when PJM sends out an implementing Operating Instruction to an applicable Electric Distributor. All Eligible New Large Loads shall be available to be requested

to provide Interim Resource Adequacy Service by the Office of
the Interconnection.
PJM explains that “in recognition of the jurisdictional divide between PJM and the states and/or RERRAs, PJM will not direct reductions to specific New Large Loads pursuant to

25 Id. at Section V(a).
26 Id. at Section II(b).
27 Id. at Section V(c).

PDF page 10

10
IRAS,” but rather, “PJM is leaving it to Electric Distributors, in coordination with the appropriate states and/or RERRAs, LSEs, and LSE customers to determine which loads should ultimately reduce subject to IRAS.”28  This framing of the proposal’s jurisdictional challenges misses the point.  The issue is not about which entity gets to identify the specific individual Eligible New Large Loads that must provide IRAS when PJM calls for it.  The issue is that, when called upon to provide IRAS under that process, the Eligible New Large Load cannot say no.  It must, pursuant to a FERC-approved Tariff, provide IRAS as a FERC-jurisdictional wholesale rate service to PJM.  Put another way, the jurisdictional concern is not with the logistics of the “top-down,” directive to provide IRAS, but rather with the “bottom-up” requirement that IRAS be provided by the Eligible New Large Load when called upon by the Electric Distributor.  Or, as PJM describes it, “IRAS is a supplemental capacity product through which Eligible New Large Loads may be directed by the Electric Distributor to reduce their load in response to an Interim Resource Adequacy Service Action called by PJM.”29 Indeed, under PJM’s proposed Tariff language, the Electric Distributor is functionally little more than a conduit to implement PJM’s Operating Instruction.  This fact is built into the very definition of Interim Resource Adequacy Service, and Interim Resource Adequacy Service Action.

“Interim Resource Adequacy Service” shall mean a load
reduction service through which New Large Loads reduce load
as directed by the applicable Electric Distributor in response to
an Interim Resource Adequacy Service Action requested by the
Office of the Interconnection. Such reductions in load may be
eligible for compensation pursuant to Attachment DD-4, section
X.

28 IRAS Filing at 92.
29 Id. at 74.

PDF page 11

11
“Interim Resource Adequacy Service Action” shall mean an Operating Instruction, as defined by NERC, issued from the Office of the Interconnection to reduce load prior to calling on Pre-Emergency

Load
Management
Reductions
after
determining that available economic real-time supply may not be sufficient to maintain reserves to meet applicable Reserve Requirements and/or Interconnection Reliability Operating Limits within prescribed limits and prevent cascading outages. While the Electric Distributor is the entity that is picking the specific individual Eligible New Large Loads to provide IRAS, it is simply a vehicle through which PJM “instruct[s] the implementation of an Interim Resource Adequacy Service Action.” Starting with the 2027/2028 Delivery Year, the Office of the Interconnection may, in accordance with the Manuals, instruct the implementation of an Interim Resource Adequacy Service Action prior to calling on Pre-Emergency Load Management Reductions Actions after determining that available economic real-time supply may not be sufficient to maintain reserves to meet applicable Reserve Requirements and/or Interconnection Reliability Operating Limits within prescribed limits and prevent cascading outages;30

Electric Distributors shall:
execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in the Electric Distributor’s zone/area, which is an area within a Zone for which the relevant Electric Distributor specifies a separate Obligation Peak Load MW value and is a service area of an Electric Distributor that is a separately identifiable, geographic area bounded by wholesale metering;31

This language does not solve the core jurisdictional problem, since the retail load is still being required to take action pursuant to an FPA jurisdictional tariff.  The obligation under

30 Proposed Tariff, Attachment DD-4, Section I(b).
31 Id. at Section III(a).

PDF page 12

12
the tariff is not on the Electric Distributor, but forwarded onto its retail end-use customers (the Eligible New Large Loads) to provide the wholesale service under the tariff.

iv. Eligible New Large Loads have no contractual privity with PJM, are not
subject to a FERC-jurisdictional load interconnection process, and are not
public utilities under FPA section 201.
In many instances, Electric Distributors32 and Load Serving Entities33 are not public
utilities by default, as defined in the FPA, and are therefore excluded from the Commission’s general rate and transmission jurisdiction under FPA section 201.34  These entities may

nonetheless voluntarily agree to become subject to a multitude of obligations and requirements from PJM by virtue of signing the PJM Operating Agreement (for Electric Distributors) and

RAA (for Load Serving Entities), which in addition to being FERC-filed tariffs,35 are also
contracts.  This framework can also apply to end-use retail customers who choose to participate in PJM’s demand response market.  These entities are not jurisdictional public utilities solely

32 Under the Operating Agreement, Electric Distributor means “a Member that: 1) owns or leases with rights equivalent to ownership electric distribution facilities that are used to provide electric distribution service to electric load within the PJM Region; or 2) is a generation and transmission cooperative or a joint municipal agency that has a member that owns electric distribution facilities used to provide electric distribution service to electric load within the PJM Region.”).
33 Under the Operating Agreement, a Load Serving Entity is defined as “any entity (or the duly designated agent of such an entity), including a load aggregator or power marketer, (i) serving end-users within the PJM Region, and (ii) that has been granted the authority or has an obligation pursuant to state or local law, regulation or franchise to sell electric energy to end-users located within the PJM Region. Load Serving Entity shall include any end-use customer that qualifies under state rules or a utility retail tariff to manage directly its own supply of electric power and energy and use of transmission and ancillary services.”). 34 16 U.S.C. § 824(b)(1) (“The Commission . . . shall not have jurisdiction . . . over facilities used in local distribution . . .”).  See also 16 U.S.C. § 824(f) (“No provision in this subchapter shall apply to, or be deemed to include, the United States, a State or any political subdivision of a State, an electric cooperative that receives financing under the Rural Electrification Act of 1936 or that sells less than 4,000,000 megawatt hours of electricity per year, or any agency, authority, or instrumentality of any one or more of the foregoing, or any corporation which is wholly owned, directly or indirectly, by any one or more of the foregoing, or any officer, agent, or employee of any of the foregoing acting as such in the course of his official duty, unless such provision makes specific reference thereto.”).
35 18 C.F.R. § 35.2(c)(1) (“The term tariff as used herein shall mean a statement of (1) electric service as defined in paragraph (a) of this section offered on a generally applicable basis, (2) rates and charges for or in connection with that service, and (3) all classifications, practices, rules, or regulations which in any manner affect or relate to the aforementioned service, rates, and charges.”).

PDF page 13

13
by virtue of selling demand response into PJM’s markets.36  Nonetheless, they may voluntarily agree to take on obligations to PJM by becoming PJM Members and executing the Operating

Agreement.  PJM is correct in its assessment that the Operating Agreement and RAA can and do create these obligations and requirements on entities that are otherwise excluded from the Commission’s general rate and transmission jurisdiction under FPA section 201.37

Yet none of these traditional jurisdictional or contractual “hooks” are present under
PJM’s IRAS proposal.  Eligible New Large Loads (i.e. end-use retail customers) are required to provide IRAS when commanded by PJM (through the Electric Distributor), yet these entities are not jurisdictional public utilities under FPA section 201 and have no contractual privity with PJM through which they have voluntarily agreed to assume the obligations associated

with providing this service.  These entities have not agreed to undertake such obligations with PJM as a condition of their load interconnection, because the terms and conditions of service to end-use customers, including their connection to the system, lies solely within the purview of individual states and RERRAs, not PJM or FERC.

36 See, e.g., EnergyConnect, Inc., 130 FERC ¶ 61,031 (2010) (“[W]here an entity is only engaged in the provision of demand response services, and makes no sales of electric energy for resale, that entity would not own or operate facilities that are subject to the Commission's jurisdiction and would not be a public utility that is required to have a rate on file with the Commission. While jurisdictional facilities may include contracts, memoranda and other records utilized in connection with jurisdictional sales, we do not regard agreements to provide services from only demand response resources to be jurisdictional facilities because they involve agreements to reduce demand, i.e., agreements not to purchase electric energy under certain circumstances, rather than agreements to sell electric energy at wholesale. Such agreements are not jurisdictional facilities that cause a seller to be a public utility.”). 37 IRAS Filing at 46 (“Authority exists today in the Operating Agreement to require Electric Distributors to provide to PJM all System, accounting, customer tracking, load forecasting (including all load to be served from its System) and other data necessary or appropriate to implement or administer [the Operating Agreement], and the Reliability Assurance Agreement[.]”).  See also IRAS Filing at 81 (“Indeed, the Operating Agreement explicitly authorizes PJM to coordinate the curtailment or shedding of load, or other measures appropriate to alleviate an Emergency, in order to preserve reliability in accordance with NERC, or Applicable Regional Entity principles, guidelines and standards, and to ensure the operation of the PJM Region in accordance with Good Utility Practice and this Agreement where an “Emergency” is defined as a condition that requires implementation of emergency procedures as defined in the PJM Manuals.”).

PDF page 14

14
The absence of these jurisdictional and contractual “hooks” leads to only one possible outcome—PJM’s proposal would use the Commission’s general rate and transmission jurisdiction under FPA section 201 to directly impose requirements on entities that are excluded from that jurisdiction by the same statutory section, and have not voluntarily agreed to become subject to those requirements.  For the reasons described below in the next section, this is beyond the Commission’s legal authority under the FPA, and is not legally durable on appeal.

v. The FPA does not grant the Commission the legal authority to force end-
use retail customers to be designated to provide a FERC-jurisdictional
wholesale rate service, or to compel the provision of that wholesale rate
service, pursuant to a FERC-approved Tariff.
Simply put, in the IRAS Filing PJM is asking the Commission to do something that it is not statutorily permitted to do under the FPA.  As the D.C. Circuit has noted on more than one occasion, “as a federal agency, FERC is a creature of statute, having no constitutional or common law existence or authority, but only those authorities conferred upon it by Congress.”38  There is nothing in the FPA that grants the Commission the legal authority to force end-use retail customers (in this case, Eligible New Large Loads) to be designated to provide a FERC-jurisdictional wholesale rate service (IRAS), or to compel the provision of that wholesale rate service, pursuant to a FERC-approved tariff.  PJM cites to two primary legal authorities in support of the IRAS Filing, but as explained below, neither of these supports the action that PJM is suggesting the Commission take here.

First, PJM cites to the Supreme Court’s ruling in EPSA, correctly noting that there “the Supreme Court held that the Commission’s regulation of demand response ‘addresses—and

38 Atlantic City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir.2002) (quoting Michigan v. EPA, 268 F.3d 1075, 1081 (D.C. Cir. 2001)).

PDF page 15

15
addresses only—transactions occurring on the wholesale market’ and takes aim at ‘enhanc[ing] the wholesale, not retail, electricity market.”39  PJM also correctly describes the Court’s holding that “the Commission’s rules for demand response withstood the Electric Power Supply Association’s jurisdictional challenge by respecting the division of federal/state authority set forth in the FPA.”40  Yet EPSA affirmed the Commission’s legal authority under the FPA to set the rates, terms, and conditions of voluntary wholesale demand response programs administered by RTOs.  EPSA is therefore inapposite to the proposition before the Commission under the IRAS Filing—the mandatory and involuntary designation of end-use retail customers (Eligible New Large Loads) to provide a FERC-jurisdictional wholesale rate service (IRAS) under the PJM Tariff, and the compulsory provision of that service pursuant to the rates, terms, and conditions of the PJM Tariff.

Second, PJM similarly cites to the Commission’s 2025 ruling on the Midcontinent Independent System Operator, Inc.’s (“MISO”) Revised Expedited Resource Addition Study (“ERAS”) proposal41 for the proposition that placing the responsibility to determine which specific individual Eligible New Large Load will provide IRAS on PJM’s command with state and local regulatory authorities is “permissible and not an improper delegation of federal authority to the states.”42  PJM’s reliance on the MISO order is similarly misplaced.  As noted above, the jurisdictional concern is not with the logistics of the “top-down,” directive to provide IRAS, but rather with the “bottom-up” requirement that IRAS be provided by the Eligible New Large Load when called upon by PJM, through the Electric Distributor.  MISO’s

39 IRAS Filing at 91 (citing EPSA, 577 U.S. at 282, 287).
40 Id. (citing EPSA, 577 U.S. at 288-91).
41 Midcontinent Indep. Sys. Operator, Inc., 192 FERC ¶ 61,064 at P 99 (2025).
42 IRAS Filing at 92.

PDF page 16

16
ERAS proposal created a framework for the expedited study of generator interconnection requests to address urgent, near-term resource adequacy and reliability needs.  It did not compel involuntary participation in that process.  Importantly, it was also focused on generator interconnection—an area that the Commission has clear jurisdiction over going back at least to Order No. 200343 and Tennessee Power.44  The Commission has never claimed such organic jurisdiction over retail load interconnection, which is the core problem that IRAS seeks to address.

B. The IRAS Filing Contains Several Structural Deficiencies that Should Be Rejected or Modified under PJM’s NRG Invitation.

i. Allowing Electric Distributors and state and local regulatory authorities to determine the wholesale rate paid for IRAS service is an impermissible

delegation of the Commission’s wholesale rate-making authority under the
FPA, and violates the Commission’s requirement under Part 35 that rates be
stated “clearly and specifically” within a filed tariff.
As referenced above, IRAS is a wholesale, FERC-jurisdictional service.  Yet PJM’s proposed Tariff language would turn over the ability to set and modify the rate paid for this wholesale service entirely to entities that do not have the legal authority to set and modify wholesale rates—Electric Distributors, and state and local regulatory authorities.  Specifically, PJM proposes a rate for IRAS that is equal to 50% of the Non-Performance Charge Rate, but notes that “the wholesale IRAS rate is flexible and can be further reduced to less than 50% of the Non-Performance Charge Rate if the Eligible New Large Load accepts in its retail rate a

43 Standardization of Generator Interconnection Agreements and Procedures, 104 FERC ¶ 61,103 at P 12 (2003) (“Order No. 2003”) (“Interconnection is a critical component of open access transmission service, and standard interconnection procedures and a standard agreement applicable to Large Generators will serve several important functions.”).

44 Tennessee Power Co., 90 FERC ¶ 61,238, 61,761-62 (2002) (“Tennessee Power”) (finding that interconnection is a critical component of open access transmission service and thus is subject to the requirement that utilities offer comparable service under the OATT.).

PDF page 17

17
sum less than 50% of the Non-Performance Charge Rate.”45  To this point, PJM explains that it “is not mandating how IRAS-directed load reductions are to be compensated,” but is instead “proposing a just and reasonable maximum rate for such service.”46  As PJM further explains, “given that the Electric Distributors, in accordance with state programs, will have identified the loads to be reduced, it is the responsibility of the Electric Distributor and its applicable state regulator to determine the appropriate compensation scheme.”47  According to PJM, under its proposal “[w]hether a specific New Large Load may be entitled to compensation for provision of IRAS will be determined by state authorities under state law or RERRA as may be applicable.”48

This is impermissible under the FPA, where only the Commission may set and modify rates for wholesale services.  As the Court stated in EPSA, the FPA “leaves no room either for direct state regulation of the prices of interstate wholesales or for regulation that would indirectly achieve the same result.”49  The Court highlighted this fact again that very same year in Hughes, noting that “[a] State must [] give effect to Congress’ desire to give FERC plenary authority over interstate wholesale rates, and to ensure that the States do not interfere with this authority.”50  PJM’s proposal would not just allow states to “interfere” with FERC’s authority over interstate wholesale rates, it would delegate to states, local regulatory authorities, and Electric Distributors the ability to set and modify the interstate wholesale rate for IRAS,

45 IRAS Filing at 102.
46 Id. at 27.
47 Id. at 28.
48 Id. at 106.
49 EPSA, 577 U.S. at 288 (citing N. Natural Gas Co. v State Corp. Comm’n of Kan., 372 U.S. 84, 91 (1963) (internal quotation marks omitted)).
50 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164 (2016) (“Hughes”).

PDF page 18

18
including the ability to set the rate to $0.  To this point, PJM explains that the “IRAS rate is compensation for a wholesale load reduction service, but the entities to be paid the rate and the loads to be charged to support such compensation must be determined at the state level consistent with the Electric Distributor’s state-approved load reduction plans and other state- approved programs, rates, and rules.”51

Beyond this impermissible delegation, this compensation scheme also fails to meet the Commission’s regulations implementing FPA section 205(c), which are unambiguous—clarity and specificity are required when rates and charges are filed with the Commission. Every public utility shall file with the Commission and post, in

conformity with the requirements of this part, full and complete
rate schedules and tariffs and those service agreements not
meeting the requirements of § 35.1(g), clearly and specifically
setting forth all rates and charges for any transmission or sale
of electric energy subject to the jurisdiction of this
Commission, the classifications, practices, rules and regulations
affecting such rates, charges, classifications, services, rules,
regulations or practices, as required by section 205(c) of the
Federal Power Act (49 Stat. 851; 16 U.S.C. 824d(c)).52
The Commission has explained that an RTO has “[an] obligation to set forth its Commission- jurisdictional rates clearly and specifically in its tariff.”53  The need to set forth rates and charges “clearly and specifically” is essential for the Commission’s own FPA section 205(c) analysis, as “[a] minimum level of specificity within the tariff is necessary for the Commission to determine whether the charges that result are just and reasonable.”54  It is also important in

51 IRAS Filing at 104. This presents jurisdictional issues somewhat similar those at issue in Mass. Dep’t of Pub. Utils. v. FERC, 729 F.2d 886, 888 (1st Cir. 1984).  Here, instead of a state directing a public utility to file a particular FERC jurisdictional tariff, the state is setting the rate that is enforced under a federal tariff.  In either case, the state, not the public utility or FERC, is setting the FERC jurisdictional rate.
52 18 C.F.R. § 35.1(a) (emphasis added).
53 Cal. Indep. Sys. Operator Corp., 112 FERC ¶ 61,009 at P 114 (2005).
54 Id.

PDF page 19

19
fulfilling the fundamental purpose of FPA section 205(c) to provide notice to customers, as the requirement “allows [] customers the opportunity to assess for themselves whether they were properly charged.”55  Yet here, the wholesale rate paid or the charges imposed on funding customers from PJM’s proposed Tariff language in proposed Attachment DD-4, Section X, are unascertainable because the specific wholesale rate actually charged would be determined by entities wholly outside of the PJM Tariff.  Furthermore, the delegation of the wholesale rate setting function to Electric Distributors and state/local regulatory authorities would deny customers the protections afforded by FPA section 206.  If a customer viewed a charge for IRAS as too high, or not properly implemented, a complaint under FPA section 206 would be of little use, since the rate is being set outside of the PJM Tariff by entities other than the Commission, where FPA section 206 is legally incognizable.

ii. PJM has not explained why it is appropriate to exclude New Large Loads from the VRR Curve to avoid charging customers, simultaneously charge

those same customers in order to pay New Large Loads to provide IRAS, and deploy IRAS before demand resources for which customers have already been charged via the capacity market.

Under the IRAS Filing PJM proposes to, beginning with the 2029/2030 Delivery Year, exclude from the demand curve (i.e., the VRR Curve used in RPM Auctions) the MW of New Large Loads that have not entered into BYONC arrangements or do not have Allocated RBP UCAP MW, over and above the MW of New Large Loads that were included in the load forecast for the 2028/2029 Delivery Year.56  This, by definition, means that end-use retail customers (including the New Large Loads themselves) will receive the benefit of not being charged for the capacity necessary to support these New Large Loads.  However, these benefits

55 Id.
56 IRAS Filing at 109.

PDF page 20

20
are not sustained under PJM’s proposal since customers would be separately charged to compensate Eligible New Large Loads for providing IRAS.57  This concept stands out even more when considering that, according to PJM, IRAS will be deployed before demand resources that customers have already paid for via the capacity market.58  In other words, under PJM’s proposal: (i) customers (including New Large Loads themselves) will receive the benefit of not being charged for capacity by virtue of New Large Loads being excluded from the VRR Curve; (ii) customers will then be charged anyway in order to pay Eligible New Large Loads to provide IRAS; and (iii) PJM will deploy IRAS before calling demand resources, which customers have already paid for via the capacity market.  PJM has simply not justified why this approach is logically consistent from a policy perspective, much less just and reasonable under FPA section 205.

iii. PJM’s Proposed Tariff Language Fails to Require Any Geographic Nexus Between BYONC Generation and the Load It is Intended to Offset, Which

Will Shift Generation Constraints Into Transmission Constraints and Impose Additional Costs on Other Customers.

PJM’s proposed BYONC provisions impose no requirement that generation supporting a BYONC arrangement be located in the same Locational Deliverability Area, Zone, or other defined geographic proximity to the New Large Load it is intended to offset.59  This issue was raised repeatedly during the Critical Issue Fast Path (“CIFP”) process, where the Joint EDCs and other stakeholders proposed various locational requirements for BYONC, but the PJM Board declined to adopt any such requirement.  As a Transmission Owner in PJM, PPL Electric is concerned that allowing BYONC generation to be sited anywhere on the system, without

57 See Proposed Tariff, Attachment DD-4, Section X.
58 IRAS Filing at 74-75, 79.
59 See id. at 23, 50-55.

PDF page 21

21
regard to its proximity to the load it offsets, will not eliminate resource adequacy risk so much as convert generation-related constraints into transmission-related constraints.  These transmission constraints must then be addressed via new transmission facilities that take years to plan, permit, and build, and the costs of which will ultimately be borne by other zonal customers.  PJM has failed to justify why these eminently foreseeable cost shifts under the IRAS Filing are just and reasonable under FPA Section 205.

III. REQUEST FOR CLARIFICATION
PPL Electric respectfully requests that PJM or the Commission provide clarification in this proceeding on several important components of the IRAS Filing.

First, PPL Electric requests that PJM confirm on the record in this proceeding that it can in fact implement the mechanisms contemplated by the IRAS Filing between the requested effective date of October 26, 2026, and June 1, 2027, when IRAS would become available for use by PJM as a wholesale rate service.  Because so much of the IRAS Filing relies on cooperation among PJM’s fourteen distinct state jurisdictions and the diverse array of local regulatory authorities, Electric Distributors, and Load Serving Entities therein, this confirmation by PJM may very well help put these jurisdictions “on notice” as to the expectation and spur action to prepare.  PPL Electric remains concerned that this timeframe is simply too short for all of these external, non-PJM actors to stand up implementation regimes, but an “on-the-record” guidepost from PJM, the Commission, or both may help motivate at least some of these entities to seize the initiative and “meet the moment.”60 Second, PPL Electric requests that PJM provide further detail in this proceeding regarding how RBP UCAP MWs will be allocated to a given zone for purposes of offsetting

60 Supra note 6.

PDF page 22

22
IRAS responsibilities.  Under PJM’s proposed Tariff, Attachment DD-4, section IX, each Electric Distributor allocated RBP UCAP MWs must inform PJM of how RBP UCAP MWs should be further allocated among the New Large Loads located in the Electric Distributor’s zone/area.  However, in the event that the Electric Distributor has not informed PJM of how its RBP UCAP MWs should be further allocated by April 1 before a given Delivery Year, PJM must then allocate the RBP UCAP MWs to the Electric Distributor’s zone/area pro-rata among all New Large Loads located in the zone/area.  PPL Electric is concerned about the practical logistics of this proposal and the potential for inconsistency in allocation methods, given the extreme diversity among Electric Distributors and state/local regulatory authorities across the PJM Region.  Additional detail from PJM in this proceeding regarding its expectations and how it plans to deal with this contingency would be helpful as PPL Electric and other entities look to implementation.

Third, PPL Electric requests clarification on the application of UCAP and ICAP in the context of BYONC.  While PJM proposes to define BYONC as “megawatts of Unforced Capacity that meet the eligibility criteria set forth in Tariff, Attachment DD-4, section VI,”61 PJM also notes that “the ICAP equivalent of this Accredited UCAP value is used to reduce a New Large Load’s potential IRAS availability.”62  PPL Electric is unclear from the IRAS Filing as to the reasoning for using these two different values in these two different contexts, and requests further explanation from PJM as to the implications of using these two very different values.

61 Proposed Tariff, Definitions A-B.
62 IRAS Filing at 65-66.

PDF page 23

23
Fourth, PPL Electric seeks clarity from PJM regarding the requirement in proposed Tariff, Attachment DD-4, Section VII(e), which states that “BYONC that is in an arrangement with a New Large Load must remain in such arrangement with that New Large Load unless and until the New Large Load is permanently out-of-service.”  PPL Electric is unclear if the purpose of this provision is that a BYONC must stay in an arrangement with a New Large Load for the term of the contract underpinning the BYONC arrangement, or if the purpose of this provision is to force BYONC MWs to permanently be associated with that New Large Load.  It is also unclear if this obligation expires once BYONC has participated as a price taker for the first 10 years.  PPL Electric requests that PJM provide clarification on this point as well. Fifth, PPL Electric requests clarification regarding an apparent inconsistency between PJM’s proposed Tariff language and its transmittal letter description of the IRAS compensation scheme.  While the transmittal letter states that “it is the responsibility of the Electric Distributor and its applicable state regulator to determine the appropriate compensation scheme,”63 proposed Tariff, Attachment DD-4, Section X contains no reference to any Electric Distributor or state/RERRA role in setting or approving the compensation rate.  Rather, it addresses only a New Large Load’s own “election” to reduce or waive the applicable rate.64 PPL Electric requests that PJM clarify how the state/RERRA role described in the transmittal letter is intended to be implemented under the actual proposed Tariff language, and, if that role is not reflected in the Tariff, that PJM revise proposed Section X accordingly. Finally, PPL Electric requests that PJM clarify whether and how PJM intends to address the transmission cost-shifting risk created by geographically unconstrained BYONC

63 Id. at 28.
64 Id. at 107.

PDF page 24

24
arrangements, as noted above.  To this end, PPL Electric requests that PJM clarify whether it would consider adopting a preference, even short of a strict requirement, for geographic concentration between BYONC generation and the New Large Load it supports, given the transmission planning and cost allocations described above.

IV. CONCLUSION
Wherefore, for the foregoing reasons, PPL Electric respectfully requests that the Commission grant PPL Electric’s timely intervention in this proceeding and accept this Protest into the record.  PPL Electric also requests that either PJM or the Commission provide additional clarity regarding the items described above in Part III, and provide any additional guidance deemed appropriate.

Respectfully submitted,

Steven Nadel
Senior Counsel
PPL Services Corporation
645 Hamilton Street, Suite 601
Allentown, PA 18101
Tel: (610) 774-4102
SMNadel@pplweb.com
/s/ Thomas DeVita
Thomas S. DeVita
Kimberly B. Frank
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202.778.9064
kimberly.frank@klgates.com
thomas.devita@klgates.com

Counsel for PPL Electric
Dated: September 3, 2026

PDF page 25

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Respectfully submitted,

/s/Stuart Robbins
Associate
K&L Gates LLP
1601 K Street, NW
Washington, DC 20006
Tel: 202-778-9148
stuart.robbins@klgates.com

Dated: September 3, 2026