ER26-3515-000 · 2026-09-03 · PPL Electric Utilities Corporation

Motion to Intervene, Protest, and Request for Clarification of PPL Electric Utilities Corporation regarding PJM Interconnection L.L.C.’s Interim Resource…

Text extracted from the eLibrary original (SHA-256 2dba3b8f84e416ed…). Download the original from the official source.

Contents · 6 sections
  1. I. MOTION TO INTERVENE p. 4
  2. II. PROTEST p. 5
  3. A. PJM’s Proposal Unlawfully Requires the Mandatory and Involuntary Designation p. 5
  4. B. The IRAS Filing Contains Several Structural Deficiencies that Should Be Rejected p. 16
  5. III. REQUEST FOR CLARIFICATION p. 21
  6. IV. CONCLUSION p. 24

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

ER26-3515-000 MOTION TO INTERVENE, PROTEST, AND REQUEST FOR CLARIFICATION OF PPL ELECTRIC UTILITIES CORPORATION Pursuant to Rules 211,1 212,2 and 2143 of the Federal Energy Regulatory Commission’s (“FERC” or the “Commission”) Rules of Practice and Procedure, PPL Electric Utilities Corporation (“PPL…
Read this passage Filed comments: Cost allocation

I. MOTION TO INTERVENE

printed heading

Given the direct nexus between the IRAS Filing and PPL Electric’s roles and responsibilities within the PJM Region, PPL Electric has a direct, substantial, and independent interest in this proceeding, which no other party can adequately represent, and respectfully 5 requests that the Commission…
Read this passage

II. PROTEST

printed heading

II.
Read this passage

A. PJM’s Proposal Unlawfully Requires the Mandatory and Involuntary Designation

printed heading · Topic match: Reliability and curtailment

Eligible New Large Loads” shall mean a New Large Load eligible to provide Interim Resource Adequacy Service in accordance with Tariff, Attachment DD-4, section V.17 Interim Resource Adequacy Service is a load reduction service, effective starting with the 2027/2028 Delivery Year, through which…
Read this passage Filed comments: Reliability and curtailment

B. The IRAS Filing Contains Several Structural Deficiencies that Should Be Rejected

printed heading · Topic match: Cost allocation

To this point, PJM explains that the “IRAS rate is compensation for a wholesale load reduction service, but the entities to be paid the rate and the loads to be charged to support such compensation must be determined at the state level consistent with the Electric Distributor’s state-approved load…
Read this passage Filed comments: Cost allocation

III. REQUEST FOR CLARIFICATION

printed heading · Topic match: Cost allocation

To this end, PPL Electric requests that PJM clarify whether it would consider adopting a preference, even short of a strict requirement, for geographic concentration between BYONC generation and the New Large Load it supports, given the transmission planning and cost allocations described above.
Read this passage Filed comments: Cost allocation

IV. CONCLUSION

printed heading

CONCLUSION Wherefore, for the foregoing reasons, PPL Electric respectfully requests that the Commission grant PPL Electric’s timely intervention in this proceeding and accept this Protest into the record.
Read this passage

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.