ER26-3515-000 · 2026-09-03 · The Retail Energy Supply Association
Motion to Intervene and Comments of The Retail Energy Supply Association re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service
PDF page 1
4928-6149-2173.1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
MOTION TO INTERVENE AND COMMENTS OF
THE RETAIL ENERGY SUPPLY ASSOCIATION
Pursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission’s
(“Commission’s”) Rules of Practice and Procedure, 18 C.F.R. §§ 385.211 and 385.214, the Retail Energy Supply Association (“RESA”)1 hereby files this Motion to Intervene and Comments in the above-referenced proceeding, in which PJM Interconnection, LLC (“PJM”) seeks to revise the Reliability Assurance Agreement (“RAA”) of its Open Access Transmission Tariff (“Tariff”) to establish Interim Resource Adequacy Service (“IRAS”). IRAS would be a service utilized solely during periods when there are insufficient resources to reliably meet demand in real time operations.
RESA files these Comments to express the need for market certainty, stability and clarity and the importance of the granular allocation of costs using principles of cost causation. As described below, significant changes to the PJM market design can cause harm if implemented to upset settled expectations of Market Participants and if a change in market design creates rate
1 The comments expressed in this filing represent the position of the Retail Energy Supply Association (RESA) as an organization but may not represent the views of any particular member of the Association. Founded in 1990, RESA is a broad and diverse group of more than twenty retail energy suppliers dedicated to promoting efficient, sustainable and customer-oriented competitive retail energy markets. RESA members operate throughout the United States delivering value-added electricity and natural gas service at retail to residential, commercial and industrial energy customers. More information on RESA can be found at www.resausa.org.
PDF page 2
24928-6149-2173.1
shock. In particular, RESA does not believe that compensation is appropriate for large loads that are curtailed when they are allowed to interconnect and receive service prior to all necessary infrastructure being in place. In support of this Motion to Intervene and Comments, RESA submits as follows:
I. MOTION TO INTERVENE
A. Correspondence and Communications
Correspondence and communications regarding this matter should be addressed to the following person(s), and the same should also be designated for service on the Commission’s official list for this proceeding:
Elizabeth W. Whittle
Charles Iannello
Nixon Peabody LLP
Interstate Gas Supply, LLC
799 Ninth Street, N.W.
6100 Emerald Parkway
Suite 500
Dublin, OH 43016
Washington, DC 20001
217-899-2537
202-585-8338
charlie.iannello@igs.com
ewhittle@nixonpeabody.com
B. RESA
RESA is a non-profit trade association of independent corporations that are involved in the competitive supply of electricity and natural gas to end-use consumers. RESA and its members are actively involved in retail electricity and natural gas markets throughout the United States in states that have implemented markets that allow entities other than the incumbent electric or natural gas utility to provide commodity electric and gas service. RESA members are Load Serving Entities (“LSEs”) active in the following RTO/ISOs: PJM, ISO New England, Inc. (“ISO-NE”), Midcontinent Independent System Operator, Inc. (“MISO”), New York Independent System
PDF page 3
34928-6149-2173.1
Operator, Inc. (“NYISO”), and California Independent System Operator, Inc. (“CAISO”). RESA
members possess market-based rate authority from the Commission.
C. Motion to Intervene
On August 13, 2026, PJM made a filing to modify the RAA provisions of its Tariff to
impose IRAS that would enable PJM to prioritize load reduction in zones/areas where New Large Loads have not brought their own new capacity or had their capacity needs covered through the Reliability Backstop Procurement (“RBP”). New Large Loads would be able to avoid the
condition on taking transmission service by bringing new capacity to the system. According to PJM, the IRAS proposal is within the Commission’s jurisdiction, but acknowledges that the states will have a role in load reduction.
RESA, with members who are active in PJM markets, have an interest in this proceeding
that cannot be represented by any other party, moves to intervene.
II. COMMENTS
PJM’s IRAS proposal includes three substantive tariff changes in addition to creating the
program. First, PJM proposes to modify the RAA to “clarify” that it is the LSE’s obligation to bring new capacity in an amount equal to or greater than its New Large Loads’2 peak load or be
2 PJM proposes to add definitions for Large Load and New Large Load. “Large Load” is defined as “end- use customer(s) load that has a cumulative peak load of 50 MW or greater at a single electrical site behind one or more points of interconnection, where for configurations involving multiple affiliated load facilities or multiple points of interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-mile radius will be considered a single electrical site as further described in the PJM Manuals.” “New Large Load” is defined as “ end-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June 1, 2027, that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load. . . .” The proposed definition notes that if there are three consecutive Delivery Years where there is no capacity shortfall, then New Large Load means: “end-use customer load that is either (a) a Large Load that goes into service after June 1 of the Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV9b)(III) are not met or (b)
PDF page 4
44928-6149-2173.1
subject to load reduction during Emergencies prior to Pre-Emergency Load Management Response.3 Second, PJM proposes to modify the RAA to establish a Large Load Registry that will be maintained by PJM with information submitted by third parties. This Large Load Registry will “aid PJM in administering recent resource adequacy initiatives, including IRAS.”4 Finally, beginning with the 2029/2030 Delivery Year, PJM proposes to exclude certain New Large Loads from the Variable Resource Requirement (“VRR”) Curve. PJM asserts that the effect of this change is to “protect residential customers from capacity price increases. . . .”5 Under IRAS, PJM may direct any Electric Distributor zone/area to reduce load up to the MW quantity of capacity attributable to Eligible New Large Loads in the zone/area. The Electric Distributor affected by this direction will determine which load to reduce, consistent with state regulatory rules. In short, IRAS is “a mechanism to support reliability while allowing New Large Loads to connect even when new capacity supply lags behind load growth.”6
A. The Commission Should Reject PJM’s Proposal to Compensate New Large Loads
for Curtailment
One additional feature of IRAS is that New Large Loads would be compensated to the extent that they reduce load when directed by PJM.7 The proposed rate would equal 50% of the Non-Performance Charge Rate. PJM notes that the rate could be lower if the New Large Load incremental load in-service after June 1 of the first Delivery Year for which the requirements of Tariff, Attachment D-4, section IV9b)(iii) are not met that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load.”
3 IRAS filing letter at 4.4 IRAS filing letter at 5.5 IRAS Filing letter at 5-6.6 IRAS Filing letter at 14.7 See, PJM Proposed Tariff, Attachment DD-4, sections IV(b)(i)-(ii).
PDF page 5
54928-6149-2173.1
accepts in its retail rate something less. PJM attempts to distinguish compensation under IRAS from other load reduction by alleging that current rapid load growth in Large Loads is different than historical load growth, “in both their inherent concentration of demand and the rapidity at which their cumulative demands have grown throughout PJM.”8 In short, under the IRAS, a New Large Load can interconnect, but must either bring its own capacity or provide IRAS. While these Large Loads may be a primary reason for the rapid load growth in PJM, interconnecting and receiving service before there is capacity to support the New Large Load is the benefit that Large Loads receive by participating in PJM before such capacity is available to support them. There should be no reason to also compensate the Large Load for being curtailed when that is the result of the benefit of their bargain. Moreover, PJM’s proposed compensation methodology, along with the uncertainty as to the actual rate that will be paid once each state makes that determination, creates significant market uncertainty. Section X(b)(ii) of the IRAS Tariff clearly states that LES’s will incur charges to compensate large loads for reductions.9 This risk cannot be appropriately hedged or managed by an LSE and, therefore, adds uncertainty to the market. Any compensation to a large load customer is a penalty to the customers in that Electric Distributor’s Zone.
RESA asks that the Commission take note of the need for market certainty and stability and the importance of granular cost allocations consistent with cost causation principles.10 In light
8 IRAS Filing letter at 99.9 PJM Proposed Tariff, Attachment DD-4, section X (b)(ii).10 Cost causation requires “all approved rates reflect to some degree the costs actually caused by the customer who must pay them.” K N Energy v FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); Midwest ISO Transmission Owners v FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004).
PDF page 6
64928-6149-2173.1
of today’s ever increasing capacity prices, rate shock caused by mis-allocated costs will cause significant harm to those entities who are not causing the costs to increase. While there are significant risks posed by the RBP that RESA identified in its Protest, IRAS adds to those risks. Any New Large Load that is curtailed would not have been on the PJM system had it not made the agreement to interconnect without providing necessary capacity. The New Large Load agrees to be curtailable in exchange for IRAS. The interconnection of the New Large Load without capacity is the benefit and compensation is duplicative and would reward a New Large Load taking IRAS. Here, compensation for IRAS is not consistent with cost causation principles and is unjust and unreasonable. In fact, as noted by PJM, a zero-dollar “rate” is consistent with the Ratepayer Protection Pledge.11
B. Market Certainty, Transparency and Stability are Critical to Market
Participants, such as RESA Members
RESA members purchase services in the RTO/ISO markets such as energy, capacity and ancillary services, but they offer more than just electricity service to their customers. Competitive retail suppliers may provide retail energy to end-use customers at contracted fixed or variable prices which are tied to wholesale electricity prices. Retail suppliers may offer demand response services – assisting customers in reducing peak demand and receiving benefits for reducing consumption at peak times. Retail suppliers may offer energy efficiency services to assist customers in reducing their electricity consumption. Retail suppliers may offer electricity with a certain component of renewable energy – or all renewable energy. There is no one model –
11 Ratepayer Protection Pledge, The White House (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ ratepayer-protection-pledge/ [https://perma.cc/N8PH-K82T] (“Ratepayer Protection Pledge”).
PDF page 7
74928-6149-2173.1
competitive wholesale markets and the introduction of retail choice in states such as Ohio, Illinois, Pennsylvania, New Jersey, Delaware and Maryland, have allowed significant innovation, which has reduced consumption of energy, lowered prices, and provided valuable services to consumers. Competitive retail suppliers operate in an environment of risk. Retail suppliers are unlike traditional utilities in several important ways. For example, retail suppliers are not cost-based regulated by state public utility commissions (although they comply with a myriad of state requirements to be authorized to provide energy-related products and services to retail customers). Retail suppliers do not have a mechanism to defer costs, like traditional utilities, and thus bear the risk of wholesale market volatility and uncertainty. Retail suppliers do not have a specified service area. They contract with customers bilaterally. Generally, these contracts are long-term – of a duration of one to five years. As a result, when a contract expires, it may or may not be renewed. Thus, a customer today may not be a customer tomorrow. As a result, charges allocated to a utility service area or load zone must be properly allocated to the appropriate retail end use customer, even if the customer has changed suppliers or returned to default service (i.e. the customer is served by different LSEs).
To offer valuable and innovative services at competitive prices, retail suppliers participating in competitive wholesale markets require market certainty, transparency and stability. Market certainty, transparency and stability allow retail suppliers to offer products and services that they know they can deliver during the term of the applicable contract. The importance of having confidence in the competitive wholesale market cannot be overstated. As with products and services offered by retail suppliers, the contracts vary by company, by service, by customer type, by term and other conditions. If competitive retail suppliers are participating in default
PDF page 8
84928-6149-2173.1
service programs, those programs often require winning suppliers to agree to a standard form contract, which may or may not address unanticipated market changes, including changes to capacity cost allocations caused by RBP and the new IRAS.
This IRAS program, especially when coupled with the RBP, filed by PJM in Docket No. ER26-3380, may fundamentally alter the risks and credit exposure of all customers in a utility service area depending on how IRAS is implemented.12
WHEREFORE, RESA respectfully requests that RESA’s Motion to Intervene is granted and its Comments considered by the Commission in this proceeding.
Respectfully submitted,
Elizabeth W. Whittle
Elizabeth W. Whittle
Counsel for
The Retail Energy Supply Association
Of Counsel:
Nixon Peabody LLP
799 9th Street, N.W.
Suite 500
Washington, DC 20001
202-585-8338
ewhittle@nixonpeabody.com
Dated: September 3, 2026
12 On August 21, 2026, RESA filed a Protest of the RBP.