ER26-3515-000 · 2026-09-03 · The Retail Energy Supply Association

Motion to Intervene and Comments of The Retail Energy Supply Association re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service

Text extracted from the eLibrary original (SHA-256 86ac81e0920d9259…). Download the original from the official source.

Contents · 7 sections
  1. I. MOTION TO INTERVENE p. 2
  2. A. Correspondence and Communications p. 2
  3. B. RESA p. 2
  4. C. Motion to Intervene p. 3
  5. II. COMMENTS p. 3
  6. A. The Commission Should Reject PJM’s Proposal to Compensate New Large Loads p. 4
  7. B. Market Certainty, Transparency and Stability are Critical to Market p. 6

Read topic-matched comments in ER26-3515

Topics in the text: Cost allocation · Reliability and curtailment · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

ER26-3515-000 MOTION TO INTERVENE AND COMMENTS OF THE RETAIL ENERGY SUPPLY ASSOCIATION Pursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission’s (“Commission’s”) Rules of Practice and Procedure, 18 C.F.R. §§ 385.211 and 385.214, the Retail Energy Supply Association (“RESA”)1…
Read this passage Filed comments: Cost allocation

I. MOTION TO INTERVENE

printed heading

I.
Read this passage

A. Correspondence and Communications

printed heading

Correspondence and Communications Correspondence and communications regarding this matter should be addressed to the following person(s), and the same should also be designated for service on the Commission’s official list for this proceeding: Elizabeth W.
Read this passage

B. RESA

printed heading

RESA RESA is a non-profit trade association of independent corporations that are involved in the competitive supply of electricity and natural gas to end-use consumers.
Read this passage

C. Motion to Intervene

printed heading

Motion to Intervene On August 13, 2026, PJM made a filing to modify the RAA provisions of its Tariff to impose IRAS that would enable PJM to prioritize load reduction in zones/areas where New Large Loads have not brought their own new capacity or had their capacity needs covered through the…
Read this passage

II. COMMENTS

printed heading · Topic match: Registry access

This Large Load Registry will “aid PJM in administering recent resource adequacy initiatives, including IRAS.”4 Finally, beginning with the 2029/2030 Delivery Year, PJM proposes to exclude certain New Large Loads from the Variable Resource Requirement (“VRR”) Curve.
Read this passage Filed comments: Registry access

A. The Commission Should Reject PJM’s Proposal to Compensate New Large Loads

printed heading · Topic match: Cost allocation

RESA asks that the Commission take note of the need for market certainty and stability and the importance of granular cost allocations consistent with cost causation principles.10 In light 8 IRAS Filing letter at 99. 9 PJM Proposed Tariff, Attachment DD-4, section X (b)(ii). 10 Cost causation…
Read this passage Filed comments: Cost allocation

B. Market Certainty, Transparency and Stability are Critical to Market

printed heading · Topic match: Cost allocation

There is no one model – 11 Ratepayer Protection Pledge, The White House (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ ratepayer-protection-pledge/ [https://perma.cc/N8PH-K82T] (“Ratepayer Protection Pledge”). 7 4928-6149-2173.1 competitive wholesale markets and the introduction of…
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated in Washington, DC this 3rd day of September 2026.