ER26-3515-000 · 2026-09-03 · Office of the Ohio Consumers' Counsel

Protest of Office of the Ohio Consumers' Counsel to PJM Interconnection, L.L.C.'s 08/13/2026 Interim Resource Adequacy Service Filing

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
PROTEST BY
OFFICE OF THE OHIO CONSUMERS’ COUNSEL
Maureen Willis
Ohio Consumers’ Counsel
Angela O’Brien
Deputy Consumers’ Counsel
Office of the Ohio Consumers’ Counsel
65 East State Street, Suite 700
Columbus, Ohio 43215
Telephone: (614) 466-9531
angela.obrien@occ.ohio.gov
Denise C. Goulet
McCarter & English, LLP
1301 K Street, N.W.
Suite 1000 West
Washington, D.C. 20005
(202) 753-3400
dgoulet@mccarter.com
Special Counsel to the Ohio Office of the Attorney General for the Office of the Ohio Consumers’ Counsel

September 3, 2026

PDF page 2

i
Table of Contents
I. BACKGROUND … 3
II. PROTEST … 7
A. PJM’s IRAS proposal to compensate IRAS load for curtailments is
patently unjust, unreasonable, and unduly discriminatory or
preferential and fails to protect existing consumers … 10
B. FERC should direct PJM to modify the IRAS proposal to include
state consumer advocates in the list of those allowed to access
confidential information in the proposed new Large Load Registry … 20
C. The IRAS Proposal is Unjust and Unreasonable because it fails to
address resource adequacy constraints caused by Existing Large Load
customers (pre June 2027 large loads) … 23
D. PJM’s proposal to rely on state programs for curtailment and
allocation of IRAS program costs to retail consumers is unjust and
unreasonable … 26
E. PJM’s failure to include a penalty for New Large Load customer non-
compliance or under-performance of curtailment directives is unjust
and unreasonable … 28
F. The IRAS proposal is unjust and unreasonable because it does not
contain sufficient protections against double recovery by New Large
Loads of incentive compensation for curtailments … 32
G. FERC should consider directing PJM to directly assign curtailment
obligations and related costs to the New Large Loads driving the
reliability concerns on the grid due to their failure to bring generating
assets to the system to satisfy their capacity obligations … 33
III. CONCLUSION … 34

PDF page 3

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
PROTEST BY
OFFICE OF THE OHIO CONSUMERS’ COUNSEL
On August 13, 2026, PJM Interconnection, L.L.C.’s (“PJM’s”) filed an application in this case to implement a new Interim Resource Adequacy Service (“IRAS”). PJM requests an October 12, 2026 effective data with the IRAS beginning in the 2027/2028 capacity auction Delivery Year.

OCC supports PJM’s proposal to interrupt New Large Loads that connect to the grid without sufficient supporting capacity before curtailing residential and other existing consumers. However, that proposal does not guarantee that it is the New Large Loads that will be curtailed, leaving other consumers at risk of bearing the burden of those curtailments.  Additionally, OCC does not support PJM’s proposal to compensate those New Large Loads for interruptions that are an inherent condition of their receipt of service without providing adequate capacity for their obligations. While the IRAS proposal would establish curtailment conditions for new data centers and large loads (at least 50 MW) that lack sufficient capacity, it fails to ensure that residential consumers will be protected from the costs or operational risks of IRAS. PJM’s proposal will impose excessive rates and curtailments of service on existing consumers in Ohio—consumers who are not causing the incurrence of these costs and operating

PDF page 4

2
conditions.1 It will unreasonably shift the risks and costs associated with acquiring new capacity for large data center loads away from those very customers onto existing consumers in Ohio and elsewhere in PJM.  It also will put existing Ohio consumers at risk of reduced reliability by subjecting them to potential curtailments of electric service when large data center load customers fail to bring sufficient new generating capacity to satisfy their electricity needs. PJM’s proposal essentially places existing Ohio consumers at risk of subsidizing both the cost and consequences of resource inadequacy for large data center loads.

As discussed below, the Federal Energy Regulatory Commission (“FERC”) should reject those portions of the filing that fail to protect Ohio consumers and other consumers in PJM from the risks and costs associated with large data center load. PJM’s proposal will result in excessive, unjust, unreasonable and unduly discriminatory and preferential rates for existing Ohio consumers.

The Office of the Ohio Consumers’ Counsel is the statutory representative of millions of Ohio residential utility consumers, per R.C. Chapter 4911.  OCC actively participates in numerous state and federal regulatory proceedings, including proceedings before FERC. OCC timely intervened in this case on September 3, 2026.2  Ohio residential consumers may be adversely affected if FERC accepts PJM’s proposed IRAS filing without modification. The proposal would require other consumers to pay for resource inadequacy risks and related costs that they did not cause, i.e., risks and costs associated with obtaining adequate generating capacity to satisfy the loads of new Artificial Intelligence (“AI”) and large data center customers.

1 This Protest is submitted pursuant to Rule 211 of the Federal Energy Regulatory Commission Rules of Practice and Procedure, 18 C.F.R. § 385.211. 2 Doc-less Motion to Intervene in PJM Interconnection, L.L.C., Docket No. ER26-3515-000, filed by Office of the Ohio Consumers’ Counsel, available on FERC’s e-library website as Accession Document No. 20260903-5029.

PDF page 5

3
I. BACKGROUND
PJM proposes to implement the IRAS proposal starting with the June 1, 2027 Reliability Pricing Model (“RPM”) Delivery Year.3 The filing proposes to require New Large Loads to be automatically enrolled for IRAS if they fail to bring sufficient capacity to satisfy their capacity obligations.4 PJM offers no proposal to address existing large loads that affected the capacity auctions run prior to the June 1, 2027 cutoff.

PJM represents in the filing that it “hosts the largest concentration of data center load in the world.”5  It states that its load forecast “predicts peak load growth of 32 gigawatts [(“GW”)] from 2024 to 2030, 30 GW of which is projected to be from data centers.”6 PJM explains that the 2027/2028 RPM base residual auction (“BRA”) cleared over 6,600 MW short of the region’s reliability requirement, and that the 2028/2029 RPM capacity auction cleared over 6,800 MW short of that requirement.7 In other words, PJM represents that the addition of new supply has not kept pace with rapid large load demand growth, thus giving rise to the significant tightening of the capacity market in recent years and subsequent resource adequacy shortfalls.8  To mitigate the potential reliability risks associated with resource adequacy shortfalls, PJM proposes the IRAS “as a

3 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and A Large Load Registry to Address  System Reliability at 7 (Aug. 13, 2026) (“IRAS will be available starting with the 2027/2028 Delivery Year, i.e., June 1, 2027”) (hereinafter “IRAS Application”).
4 IRAS Application at 22 (“PJM is proposing Interim Resource Adequacy Service, a new supplemental capacity product through which New Large Loads provide a load reduction service that is a tool available to PJM to manage resource adequacy shortfalls that would otherwise drive shedding of native loads.”)
5 Id. at 13.
6 Id.
7 Id. at 14.
8 Id. at 13.

PDF page 6

4
mechanism to support reliability while allowing New Large Loads to connect even when new capacity supply lags behind load growth.”9

PJM proposes to define “New Large Load” as an “end-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June 1, 2027, that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load.”10  After June 1, 2027 and going forward, PJM proposes that to the extent three consecutive Delivery Years fall short of procuring capacity needed to serve all loads on the system, New Large Load shall mean end-use customer load that is either (a)  Large Load that goes into service after June 1 of the first Delivery Year for which the capacity procurement requirements of the Tariff are not met or (b) incremental load in-service after June 1 of the first Delivery Year for which the capacity procurement requirements of the Tariff are not met.11 PJM, however, does not explain the justification for the cut-off or how pre-existing Large Loads in PJM’s forecasts will be treated.

New Large Load customers would be excluded from the RPM capacity auctions to be run starting with the 2029/2030 Delivery Year unless and until these customers can acquire the generating capacity needed to serve their loads.12  PJM represents that excluding both the loads and capacity of these New Large Load entities from the RPM BRAs would protect residential consumers from the costs associated with serving such loads.13  Although the New Large Load

9 Id. at 13-14.
10 Id. at 1, n.2.
11 Id.
12 Id. at 23.
13 Id. at 23-24.  The central risk is that this protection works only if the large load is genuinely interruptible.  If a state lacks an enforceable curtailment mechanism (see infra) or the large load fails to reduce, PJM will have excluded its demand from capacity procurement while still allowing it to consume electricity. Exiting consumers would then bear the reliability consequences. There should be a tested, legally enforceable interruption arrangement and penalties to secure performance.

PDF page 7

5
customers’ loads would be excluded from the auctions, PJM would still allow these entities to connect to and receive electricity from the system.14

If there are resource shortages in any given year, PJM dispatchers would call an IRAS emergency before calling on certain other load shedding events.15 PJM dispatchers would direct the Electric Distributor(s) in whose zone(s) the New Large Loads that have not procured sufficient generating capacity are located to shed load in an amount necessary to address the resource shortages.16 PJM anticipates implementing IRAS when “(1) it is no longer able to maintain reserves in the RTO or a zone; or (2) there are insufficient resources to keep IROLs [Interconnection Reliability Operating Limits] within defined operating limits in order to prevent instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the interconnection.” 17

 PJM proposes to leave the question of who within each zone would have to shed the load needed to restore system reliability to the states.18  In other words, the states would have to set up the rules for retail curtailments.19 It is possible under this proposal that an Electric Distributor could shut off power to all customers in the zone, even existing consumers, during the emergency if a state does not have a program to protect residential and other consumers from these PJM- directed curtailments.20  Ohio currently does not have such a program.

14 Id. at 13-14.
15 Id. at 75, 79.
16 Id. at 79. 17 Id. at 75.
18 Id. at 82-85.
19 Id. at 86-87.
20 Id. at 90-91.

PDF page 8

6
PJM also proposes to “compensate” the New Large Loads for the interruption through a new federal charge imposed on the Electric Distributor.21 PJM likened its proposal here to the Pre-Emergency Load Response Program in which it compensates entities willing to discontinue service at an early stage of the emergency causing the need for curtailment.22 PJM states that the IRAS compensation charge is for “a wholesale load reduction service, but the entities to be paid the rate and the loads to be charged to support such compensation must be determined at the state level.”23 States could work out an arrangement with the New Large Load that would have the New Large Load forego compensation, thus saving other consumers in the zone from having to pay those costs.24

Although the IRAS proposal applies only to New Large Loads, PJM proposes to maintain a Large Load Registry that would incorporate information on all Large Loads in the region, including information that identifies the entities, their peak loads, their locations and Electric Distributor zones, their in-service dates, peak load shaving capability, if any, ramp rates, back-up generation if any, and other related information.25  PJM proposes to define Large Load as “end- use customer(s) load that has a cumulative peak load of 50 megawatts or greater at a single electrical site behind one or more points of interconnection . . . .”26 PJM further proposes that for configurations involving multiple affiliated load facilities or multiple points of interconnection with affiliated load facilities behind them, “all affiliated load facilities within a one-mile radius will be

21 Id. at 99.
22 Id. at 99-100.
23 Id. at 104.
24 Id. at 105.
25 Id. at 28-29, and 37.
26 Id. at 31.

PDF page 9

7
considered a single electrical site as further described in the PJM Manuals.”27 PJM represents that it will provide access to that information on a confidential basis to authorized state commissions, Transmission Owners, the Independent Market Monitor for PJM (“IMM”), Electric Distributors, FERC and Load Serving Entities.28  PJM argues the purpose of the Registry is to provide transparency and “key information” for state and retail entities.29 But under PJM’s proposal, independent state consumer advocates are not permitted access to the confidential registry. The filing provides additional details regarding how the proposed new IRAS would be implemented.  While OCC is not providing a complete summary of all those details in this Protest, it has summarized above the foundational elements that raise significant concerns for Ohio consumers.

II. PROTEST
The PJM grid must be maintained to ensure reliable and adequate generation and transmission services.  FERC has an obligation to ensure that this objective is satisfied in a manner that ensures just, reasonable, and not unduly discriminatory or preferential rates for services.  In fact, FERC’s primary obligation is to provide consumers a “complete, permanent and effective bond of protection from excessive rates and charges.”30

PJM seeks in this filing to ensure that New Large Loads that do not bring sufficient generating capacity to the system to satisfy their capacity obligations are placed at risk of curtailment when capacity is insufficient to satisfy their needs. This objective is laudable. It  is intended to protect existing consumers from the resource scarcity that could result from the

27 Id.
28 Id. at 28.
29 Id. at 29, 37-38.
30 Atl. Seaboard Corp. v. FPC, 397 F.2d 753, 756 (4th Cir. 1968), quoting Atl. Refining Co. v. Pub. Serv. Comm’n of N.Y., 360 U.S. 378, 388 (1959).

PDF page 10

8
addition of significant new large loads to the system without also adding significant new generating resources.  Indeed, OCC agrees that a reasonable and affordable system to implement this objective is urgently needed given the capacity shortages forecast to start with the 2027/2028 Delivery Year and continue into the 2028/2029 Delivery Year.

OCC supports PJM’s proposal to interrupt New Large Loads that connect without sufficient supporting capacity before curtailing residential and other existing consumers. However, OCC is concerned that the PJM’s design of that program will not achieve PJM’s intent, leaving consumers other than Large Load and New Large Load customers at risk of curtailment.  OCC also does not support compensating those New Large Loads for interruptions that are an inherent condition of receiving service without adequate capacity.  Nor does OCC support the portions of PJM’s proposal that would leave the details of curtailment implementation to the states.

PJM’s proposed IRAS program, as detailed in its filing, does not deliver the protection needed for consumers who are not data centers.  PJM’s proposed program will result in subsidized rates for existing Large Loads and New Large Loads in the PJM region. And PJM’s proposal will result in excessive and unduly discriminatory rates for existing consumers in Ohio and elsewhere in PJM.

 OCC protests PJM’s filing for three primary reasons.  First, PJM provides no reasoned explanation for its compensation proposal. Why should existing consumers whose capacity obligations are procured in the RPM auctions have to compensate New Large Loads for curtailments when those New Large Loads have not procured sufficient capacity to meet their capacity obligations? PJM’s zone-wide compensation proposal should be rejected.  At a minimum, if compensation is to occur, (it should not occur) it should be directly assigned to the

PDF page 11

9
participating New Large Load customer causing the shortages or waived by that customer as a condition of IRAS service, with no curtailments for or recovery from residential consumers.  A strong penalty on New Lard Loads for non-compliance with curtailment directives would ensure reliability for the grid in a more just and reasonable manner.

Second, PJM’s proposed new Large Load Registry unreasonably excludes state consumer advocate offices from the list of entities entitled to access the information to be retained in that registry. The Registry is designed to contain precisely the information needed by state commissions, state consumer advocates, Electric Distributors and LSEs to evaluate retail curtailment and cost allocation. OCC is an independent, statutorily-created representative of residential consumers.  OCC is not part of the Public Utilities Commission of Ohio (“PUCO”). Access to the Registry by the PUCO does not give OCC access to that information. PJM’s proposal would permit other participants in the industry, utilities and LSEs which may have commercial interests in serving the load, to obtain this confidential information. At the same time, it would bar access to that information by the statutory representative of the consumers potentially charged for IRAS compensation and potentially bearing the interruptions in service from curtailments.

 Third, PJM’s proposal attempts to protect existing consumers from the resource shortages resulting from New Large Loads coming on the system as of June 1, 2027.  But PJM has not supported the cutoff date, nor explained how pre-cutoff Large Load additions will be treated.  Yet  PJM’s filing admits that those Large Loads were primarily responsible for the shortfall of capacity procurement under two prior BRA Delivery Years ( 2027/2028 and 2028/2029).

PDF page 12

10
FERC should reject PJM’s proposal to impose a federal compensation charge for curtailments associated with the failure of New Large Loads to bring sufficient capacity to satisfy their capacity obligations.  Instead it should (a) direct PJM to adopt strong penalties for non-compliance with curtailment directives; (b) expand the list of entities entitled to access the Large Load Registry to include state consumer advocate offices; (c) direct PJM to develop and file a curtailment plan that addresses emergency priorities for pre-cutoff (June 1, 2027) existing Large Load additions, including those associated with already run auctions for the 2027/2028 and 2028/2029 Delivery Years, i.e., the recent Delivery Years where resource adequacy obligations were not met; and (d) grant the additional relief proposed in this Protest.

A. PJM’s IRAS proposal to compensate IRAS load for curtailments is patently unjust, unreasonable, and unduly discriminatory or preferential and fails to protect existing consumers.

There is no justification for compensating New Large Loads for curtailment during periods of resource shortages when those loads have failed to bring sufficient capacity to the system. PJM’s resource adequacy rules encompassed in the PJM Reliability Assurance Agreement Among Load Serving Entities are designed to obligate LSEs to bring sufficient capacity to the grid to meet the capacity needs of the consumers they serve.  PJM’s IRAS proposal would allow New Large Load customers to connect to the system without an obligation to bring sufficient capacity to satisfy their needs.  Treating the removal of the risk New Lare Load customers have caused as a separately compensable service and assigning the costs to existing consumers improperly shifts to other consumers costs attributable to the conditional service furnished to the New Large Load.  In that sense, PJM’s proposal is fundamentally

PDF page 13

11
inconsistent with the White House Ratepayer Protection Pledge, posted on the White House website on March 4, 2026.31

That Pledge, now signed by over 300 organizations including many of the large data centers and electric utilities in the nation,32 commits in relevant part that Large Loads will

1. build, bring, or buy the new generation resources and electricity needed to satisfy their new energy demands, paying the full cost of those resources whether by building, or buying from, new or otherwise additive power plants;

2. pay for all new power delivery infrastructure upgrades required to service their data centers, including adequate network upgrade costs to ensure that these expenses are not passed on to the ordinary household; and

3. pay these rates for the power and related infrastructure that are brought online to service their data centers, whether they use the electricity or not.33

This commitment calls for the imposition of the costs and burdens associated with these very large load electricity customers on the large load electricity customers themselves.

In contrast, PJM is proposing that consumers throughout its region, including Ohio consumers, will be at risk of:

1. curtailments if these Large Loads fail to bring the generating capacity needed to serve their capacity obligations, especially where state laws may be inadequate to protect them from such curtailments;

2. paying generating and transmission capacity costs associated with these new loads; and
3. compensating these New Large Loads for any curtailments if generating capacity shortages occur and PJM must curtail load to retain reliability in the region. 31 White House Ratepayer Protection Pledge, available at https://www.whitehouse.gov/releases/2026/03/ratepayer- protection-pledge/

32 Data Centers Pay their Way; Ratepayers pay theirs, “A public commitment that hyperscalers, AI companies and the utilities and data-center developers behind them will build, bring or buy every kilowatt their facilities need – and cover every dollar of the infrastructure that delivers it;” available at https://www.whitehouse.gov/ratepayer- protection-pledge/
33 Supra, n.31.

PDF page 14

12
Although the intent of PJM’s IRAS proposal is to target the New Large Loads with the curtailment orders, that intent will not necessarily be achieved.  By design, PJM is proposing merely to direct the Electric Distribution in whose zone the New Large Load is located to curtail energy usage, and leaves the question of which end use customers will have to curtail to the states. But as discussed later in section II.D of the Protest, not all states in PJM have laws regarding large load-related curtailments.  Nor do they have laws regarding who pays for the compensation that will be required under PJM’s FERC-jurisdictional tariff.  Ohio is one such state.  Consequently, OCC protests PJM’s proposal to provide compensation to New Large Loads in the event they are curtailed under the new program. At a minimum, if compensation is to occur (and it should not), compensation and administrative costs of the IRAS should be directly assigned to the participating New Large Load or waived, with no recovery from residential consumers.

The only possible explanation PJM offers for its IRAS proposal is its inapposite reference to its non-comparable program for compensating Pre-Emergency Load Response participants.34 This program allows PJM to call upon Pre-Emergency Load Response participants to curtail their loads in response to PJM’s issuance of a pre-emergency call for load reductions due to growing near-term generating capacity scarcity. Under this program PJM charges the participants that underperform or pays those who overperform 50% of the capacity Non-Performance Charge rate.35 PJM argues that “[f]rom a customer perspective, the non-performance rate appropriately reflects that load paid for capacity but did not get the benefit of the Pre-Emergency Load

34 IRAS Application at 101, 103.
35 Id. at 103.

PDF page 15

13
Response Program that PJM called upon at a time when the PJM system was in stressed system conditions.”36 PJM proposes to use this rate as the compensation charge for IRAS curtailments. But there is a big difference between the two programs that makes compensating New Large Loads under the IRAS program unreasonable. The Pre-Emergency Load Response participants that are compensated for curtailment during pre-emergency conditions are existing customers whose loads are within the load growth forecasts of the RPM auction parameters.  In other words, PJM is procuring generating capacity on their behalf.  The system is designed to serve them.

In contrast, the New Large Loads subject to IRAS curtailments will receive accelerated access to the grid despite insufficient capacity and are curtailed only because the condition supporting that access has occurred.37 Unlike Pre-Emergency Load Response participants, IRAS loads will not be included in the RPM auction parameters.38 That means that unlike the Pre- Emergency Load Response participants, PJM has not procured capacity to serve New Large Load capacity obligations. The system is not designed to reliably serve their electricity needs. Instead, the IRAS program will rely on curtailment options when generating capacity shortages exist.

It makes sense to compensate existing Pre-Emergency Load Response participants for curtailment because their loads are covered by RPM auctions.  They are compensated for the inconvenience of having to shed load during emergencies. And their participation in the program is voluntary.  But where the capacity needed to serve the New Large Loads is not part of the RPM capacity procurement auction to begin with, their participation in IRAS is not voluntary,

36 Id.
37 Id. at 1.
38 Id. at 23.

PDF page 16

14
and PJM clearly is not procuring sufficient generating capacity to cover their loads, it makes no sense to compensate these New Large Loads for curtailment. Under that scenario, New Large Load customers should be curtailed first and without compensation, especially without compensation from other customers whose capacity obligations are covered by the auctions. These New Large Loads are imposing a huge new burden on the system that is

unprecedented and unlike the minimal load growth forecasts for existing Pre-Emergency Load Response customers. The forecast peak load for the 2028/2029 Delivery Year BRA was 165,954 MW.39 This is 0.8%, above the forecast peak load of 164,579 MW for the prior 2027/2028 BRA.40 In contrast, as noted above, PJM anticipates an increase in load due to the influx of New Large Load customers of 30 Gigawats (“GW”), or 30,000 MW, from 2024 to 2030.41 An increase of 30,000 MW over the current forecast peak load of 164,579 MW for the 2028/2029 Delivery Year represents a total increase of 18% during that period, or an average of 3% annually.42 This impact on resource adequacy is significantly larger than the 0.8% increase in load forecasted from the 2027/2028 to the 2028/2029 Delivery Year which includes Pre- Emergency Load Response customers.

In other words, it simply is not reasonable to develop IRAS rules based on the Pre- Emergency Load Response program rules. The impact of the New Large Loads on the system has been so significant as to provoke PJM to propose this new curtailment program to protect

39 2028/2029 RPM Base Residual Auction Planning Period Parameters at 1 (May 12, 2026), available at https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-report.pdf
40 Id. 41 IRAS Application at 13.  The IRAS Application calculates this forecast as 30 Gigawats of new large loads.  Given that 1,000 MW is equal to 1 GW, the 30 GW forecast is the equivalent of 30,000 MW of new load in PJM over a six year period. Two of those years are now behind us.
42 30,000 MW represents an 18.2% increase over the 164,579 MW of demand forecasted for the 2027/2028 Delivery Year.

PDF page 17

15
reliable electric service in the region during generation scarcity emergencies. While it may have been reasonable to compensate voluntary Pre-Emergency Load Response participants to curtail loads under the design parameters of that program, it simply makes no sense to pay New Large Loads for involuntary curtailments when (1) PJM has not had sufficient notice of their interconnection in time to procure new generating capacity on their behalf, (2) they have not brought their own sufficient generating capacity to the system to serve their needs, and (3) their loads are not included in the RPM parameters.

To illustrate the unreasonableness of PJM’s proposal, consider the following example. The Governor of Ohio is holding a meeting to discuss the importance of affordable electricity in the state..  The Governor has invited entities that represent transmission owners and consumers to this meeting and tells everyone participating to bring their own lunch. A new entity finds out about the meeting, and the day before the meeting informs the Governor that it too is a consumer and plans to attend the meeting.  Only this new entity brings 25,000 to 50,000 people with it to the meeting.  None of these people bring their own lunch. The Ohio Governor has not included these entities in its plans for this meeting given the short one-day notice and does not have enough food to serve lunch to all these unanticipated meeting participants.  As a result, the Governor must tell the late-notice guests that they cannot share the food of those who were invited and who brought their own lunches. Under the PJM IRAS model, the Ohio Governor would have to compensate the uninvited guests for going without food during lunch, potentially at the expense of the other participants.

This example is not outrageously exaggerated, nor is it unreasonable. PJM’s filing states that the peak loads of 50-MW New Large Load customers are roughly equivalent to the electricity

PDF page 18

16
demands of 25,000 and 50,000 residential homes.43  In effect, the load associated with just one New Large Load customer will equal the load of a mid-sized city in the PJM region. The New Large Loads anticipated to interconnect to the PJM system that are not bringing their own generating capacity (food) will impose a huge drain on the system with relatively short notice, especially considering PJM’s three-year forward procurement model for capacity auctions.  Existing consumers in Ohio and elsewhere in PJM should not be paying these New Large Loads for their “curtailment inconvenience” when these new loads caused the shortage conditions by not procuring sufficient generating capacity, and by being unable or unwilling to secure that needed new capacity.

PJM also attempts to justify its proposed compensation scheme by arguing that “[u]nder conditions of tightening supply and demand, it is a measured and well-considered response to permit the new demand causing the shortfall on the system to interconnect, subject to load reduction under limited emergency conditions, but receive compensation for that load reduction.” 44  In support, PJM cites to an order on rehearing in a generator interconnection complaint case: Tenaska Clear Creek Wind, LLC v. Sw. Power Pool, Inc., 183 FERC ¶ 61,043 at P 24 (2023) (“Tenaska II”).

 That case does not support PJM’s premise that interconnections allowed under limited emergency conditions may receive compensation for that curtailment.  In Tenaska II, FERC dismissed a complaint in which the generator argued that its facility had been unjustly curtailed.45 As PJM correctly notes in footnote 264 of the IRAS Application, FERC found that curtailment may be appropriate where a generator begins commercial operation before the

43 IRAS Application at 35. 44 Id. at 99 (emphasis added).
45 Tenaska Clear Creek Wind, LLC, 183 FERC ¶ 61,043 at P 24.

PDF page 19

17
network upgrades needed to accommodate its reliable interconnection to the grid are completed.46 But unlike PJM’s characterization of this order, the ruling says nothing about a compensation payment for those curtailments.

Although FERC did not address the question of compensation for the generator
interconnection curtailments in Tenaska II, it did reject Tenaska’s request for refunds of more than $9 million in alleged lost revenues during the curtailment events.47 In fact, FERC’s rulings in Tenaska I and Tenaska II support a program of curtailment without compensation where the commercial operation of the interconnection customer begins before service can be reliably provided because of the need for new infrastructure investment in the region. FERC found in Tenaska II that “[s]ubjecting the interconnection customer that causes the need for upgrades in this manner ensures that the interconnection customer, bears the system- reliability burdens that flow from its decision to operate prior to completion of the required network upgrades.”48 FERC further found that curtailment in Tenaska II was appropriate because the curtailment occurred “on the basis that it [the generator], as an interconnecting facility, was subject to limited operation.”49 Like the generator in Tensaka I and Tenaska II, curtailment without compensation of a load interconnection customer is appropriate where the customer is being interconnected and begins taking service before sufficient generating facilities have been constructed to provide reliable service.

The sole purpose of the IRAS program is to allow interconnection of New Large Loads before there is sufficient generating capacity to reliably serve their needs.  But, like the tariff in

46 Id.
47 Tenaska Clear Creek Wind, LLC v. Sw. Power Pool, Inc., 181 FERC ¶ 61,225, at PP 19, 61 (2022) (“Tenaska I”).
48 Tenaska II at P 24.
49 Id. at P 25.

PDF page 20

18
effect in Tenaska I and Tenaska II, that interconnection occurs subject to the right of the grid operator to curtail service until generating capacity is sufficient to allow connection to the grid. FERC should reject PJM’s attempt to bootstrap compensation for curtailment where customers interconnect before they can be reliably served into the ruling in Tenaska II.  FERC did not require compensation of curtailed generators in Tenaska II – indeed, FERC did not even consider the question of compensation.  FERC similarly should not require compensation here. The provisions of the Southwest Power Pool (“SPP”) tariff at issue in Tenaska II provide the best example for how to move forward with New Large Loads interconnections before sufficient generating capacity is available to reliably serve their loads. Those provisions limit generator interconnection customer operations and provide for curtailments in times of scarcity until needed new infrastructure is in place. As FERC found in Tenaska II, this process allows the interconnection customer “to decide whether to operate its generating facility under limited operation pending availability of full interconnection capacity.”50  FERC properly concluded that “[t]he alternative is that the generating facility does not operate until full interconnection capacity is available.”51

Curtailment without compensation is also the model in SPP’s recently approved
Conditional High Impact Large Load Service (“CHILLS”) interruptible transmission interconnection program.52 That program allows interconnection of large load customers for transmission service before needed new transmission network upgrades are constructed to reliably provide that service, subject to curtailment when needed to maintain transmission system

50 Id. at P 29.
51 Id.
52 Southwest Power Pool, Inc., 195 FERC ¶ 61,196 (2026).

PDF page 21

19
reliability.53 Similar to the generation interconnection rules involved in Tenaska I and Tenaska II, CHILLS loads are not compensated for those curtailments.54  Instead of compensation payments for curtailments, CHILLS customers are penalized for failure to follow curtailment orders.55 Both SPP’s generator interconnection rules and its CHILLS rules serve as more apt models for PJM’s IRAS curtailment rule than the Pre-Emergency Load Response program PJM used to design the curtailment rules for IRAS customers.

PJM is proposing to pay very large entities that have recently appeared on the system for the “risk” that these New Large Loads will be curtailed. And yet these customers did not timely notify PJM of their inability to acquire sufficient generating capacity to satisfy their needs and did not bring their own capacity to the system. Why reward these entities for a situation they created by compensating them?  The reduction in energy usage (via the curtailment) merely eliminated the incremental demand they created or materially aggravated. The New Large Load is the principal cost-causer because its uncovered demand creates the IRAS obligation. Existing residential consumers do not cause the IRAS curtailments.

Any reliability benefit other consumers receive is principally the removal of a risk introduced by the new load itself.  Charging households for that mitigation shifts the consequences of the New Large Load’s conditional interconnection to customers who did not cause it. In other words, there is no reasoned justification for the compensation proposal, or to put existing consumers at risk of paying for that compensation charge.

The compensation proposal also is completely inconsistent with the White House Ratepayer Protection Pledge that new large loads absorb the costs and risks associated with their

53 Id. at P 7.
54 Id. at PP 31, 85, 97-99.
55 Id.

PDF page 22

20
interconnection requests.  PJM has not provided an adequate or reasoned explanation for a federal charge to compensate entities for curtailment when those entities failed to bring capacity to the system sufficient to serve their needs.  Accordingly, FERC should reject the curtailment compensation element of PJM’s proposed IRAS program.

B. FERC should direct PJM to modify the IRAS proposal to include state
consumer advocates in the list of those allowed to access confidential
information in the proposed new Large Load Registry.
OCC supports PJM’s proposal to create a Large Load Registry that will track up-to-date information related to the location, generating capacity needs, load needs and other information related to interconnection of Large Loads to the PJM grid. However, PJM’s proposal to exclude state consumer advocates from the category of entities eligible to access that confidential Large Load Registry information is not just and reasonable. OCC, a statutorily-mandated state consumer advocate office, represents end-use customers service by PJM’s markets and has the same need for transparency and access to this information as do the entities PJM proposes to allow access to this information.

PJM relies in part on its justification for the Large Load Registry on the support provided by stakeholders. PJM reports that 82% of stakeholders supported a Large Load Registry, and this support extends across a broad swath of often divergent stakeholder views in the region.56 PJM represents that this support includes 18 Electric Distributors, 16 End-Use Customers, six Generation Owners, seven Other Suppliers, and seven Transmission Owners.57 The reasons provided by these stakeholders for their support, as recounted by PJM in its IRAS Application, are similar to the reasons OCC and other state consumer advocate offices need this information.

56 Id. at 31, n.
57 Id.

PDF page 23

21
For example, PJM represents that one comment received in its Reliability Backstop Procurement and IRAS poll states that “[a]bsent a registry, it is unclear how other end-use consumers could be insulated from these costs. . . . Additionally, it is unclear how, absent a registry, a Connect & Manage [IRAS] framework could be implemented in a way that protects other end-use consumers from being curtailed in response to a PJM Connect & Manage [IRAS] event.”58  Another stakeholder responded that “[a] registry provides the transparency needed to identify new large loads, their locations, and whether they have secured qualifying BYONC [Bring Your Own New Capacity] or other reliability arrangements.”59  Still another stated that “[a] registry is one means of satisfy[ing] the principle of ensuring that costs of new capacity required to serve new large load (i.e., data centers) should be allocated to data centers.”60

Notwithstanding this broad stakeholder support for the critical and greatly needed transparency the Large Load Registry would provide, PJM proposes to restrict access to that information.  Access would only be permitted to authorized state commissions, Transmission Owners, Electric Distributors, Load Serving Entities (“LSEs”), the IMM and this Commission.61 With respect to inclusion of authorized state commissions in the group  allowed to access the Registry, PJM argued that “[s]tates may leverage the Large Load Registry to inform the implementation of retail constructs including load reduction priorities and cost allocation at the retail level to appropriate end-use customers.”62 PJM further explained that “[t]he Large Load

58 IRAS Application at 30, n.85.
59 Id. at 30-31.
60 Id. at 31.
61 IRAS Application at 28.
62 Id. at 29.

PDF page 24

22
Registry will assist states in administering their respective programs at the retail level while allowing each state to retain the flexibility to administer those programs, including the flexibility to determine when and whether Large Loads and Existing Large Loads have demonstrated that their loads are matched with new capacity that they have procured to serve their needs.”63 State consumer advocate offices, like OCC, are statutorily mandated to represent the interests of residential consumers in their respective states. Authorized state commissions need to access confidential Registry information to assess the impact of Large Loads in their states and to ensure just and reasonable cost and curtailment allocations for their retail customers.  State consumer advocates need access to that information as well. State consumer advocates like OCC are statutorily obligated to advocate for residential consumers in their state and ensure that any retail programs to share costs or curtailment impacts are just and reasonable for those consumers. State consumer advocates in PJM will not be able to provide robust advocacy for their consumers without access to the confidential information in the Large Load Registry. Consumer advocates need this information for the same reasons the state commissions need this information.

More importantly, state consumer advocates seeking to protect retail consumers in state proceedings involving Large Load have no other means to obtain this critical information.  They will find their efforts to obtain that information in state proceedings stymied by the proposed confidentiality provisions in the Large Load Registry tariff.  Without a federal rule providing for registry access, state consumer advocates will most likely be denied access to this essential information in the state proceedings.

63 Id.

PDF page 25

23
That lack of transparency for consumers is egregious, unjust and unreasonable. By excluding authorized state consumer advocates from the Registry, PJM’s proposal unduly discriminates against consumer representatives in violation of sections 205 and 206 of the Federal Power Act, 16 U.S.C. §§ 824d and 824e, and in violation of long-held judicial precedent prohibiting such undue discrimination.64 PJM provides no reason for excluding OCC and other PJM state consumer advocates from access to the Registry. Furthermore, FERC itself has recognized the importance of sufficient transparency regarding Large Loads and expressed concern that “without sufficient transparency . . . stakeholders may lack information and visibility regarding the costs driven by large load additions.”65

The Large Load Registry is too important to eliminate from PJM’s proposal given the critical need for the transparency the Registry will provide. Thus, rejection of the proposal would not be just or reasonable.  Yet excluding state consumer advocate offices from having access to that information is not just and reasonable either. FERC should direct PJM to amend the proposed tariff language to allow access to the Large Load Registry by state consumer advocate offices, their attorneys and retained experts, subject to the same certification, nondisclosure and data-security requirements applicable to the Authorized State Commissions.

C. The IRAS Proposal is Unjust and Unreasonable because it fails to address
resource adequacy constraints caused by Existing Large Load customers
(pre June 2027 large loads).
 The IRAS proposal addresses what happens only with respect to New Large Loads, and any incremental increases to existing Large Loads, that seek interconnection to the system on or

64  See, e.g., New England Power Gen. Ass’n. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (citing BP Energy Co. v. FERC, 828 F.3d 959, 968 (D.C. Cir. 2016) (“vacating finding of no undue discrimination where Commission identified differences between two natural-gas companies but failed to adequately explain why they provide a rational basis for the difference in treatment”)).
65 IRAS Application at 48, citing PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211 at P 74 (2026).

PDF page 26

24
after June 1, 2027.66 Yet, the last three BRAs in RPM, i.e., auctions for the 2026/2027, the 2027/2028 and the 2028/2029 Delivery Years, all cleared short of the PJM reliability requirement for RPM auctions.67 The last two cleared short by more than 6,600 MWs each – and PJM represents that the reason for this shortfall is anticipated Large Loads on the system forecasted for those periods.68  PJM states that “in recent years, the majority of the new load that has come onto the PJM system has been Large Load,” and therefore, PJM proposes to limit the MW quantity of Large Load that may be subject to reduction under  IRAS to the MW value of New Large Load that has not brought their own capacity.”69

The failure of the IRAS curtailment proposal to address both existing (pre June 2027) and New Large Loads makes the proposal unjust and unreasonable.  OCC supports PJM’s intent in the IRAS proposal to interrupt New Large Loads that connect without sufficient supporting capacity before curtailing residential and other existing consumers.  OCC does not, however, support leaving the allocation of those curtailments to non-existent state laws.  Nor does it support compensating those New Large Loads for interruptions that are an inherent condition of receiving service without adequate capacity.  Such customers should bear the consequences of their decision to take conditional service. The associated costs should not be shifted to other consumers, including residential consumers.

But relief regarding cost and curtailment allocations is also urgently needed with respect to forecasted existing Large Load already included in the RPM auction parameters for near-term Delivery Years, especially given the resource shortages in those BRA clearing results. PJM’s 66 IRAS Application at 1.

67 Id. at 39, n.108.
68 Id. at 39.
69 Id.

PDF page 27

25
proposal does not address a plan for shortages in the prior auctions attributable to forecast load additions occurring before the cutoff.  Yet all of the reasons PJM lays out in the IRAS Application that support the need for the IRAS program for New Large Loads apply equally to existing Large Loads incorporated in RPM auctions run for the past three Delivery Years. To ensure adequate protection for consumers in Ohio and elsewhere in PJM, PJM and FERC must address curtailment priorities for Large Loads that have already cleared in the 2026/2027, the 2027/2028 and the 2028/2029 Delivery Years.

The White House Ratepayer Protection Pledge commits to holding residential consumers harmless from the effects of Large Loads on transmission rates, on procurement costs for needed generating capacity, and from curtailments related to transmission and resource scarcities.70 The failure of the filing to address this concern is inconsistent with the White House agenda, and results in unjust, unreasonable, and unduly discriminatory and preferential rates for consumers. Both existing and future ratepayers need the protections of the IRAS proposal. Moreover, the White House Ratepayer Protection Pledge does not distinguish between consumers taking service today and those taking service next year, or in three years.  FERC should condition its acceptance of PJM’s IRAS program on a directive that PJM submit a proposal for how curtailments for scarcity emergencies associated with existing Large Loads on the system prior to June 1, 2027 will be addressed in the near term. This program is urgently needed so that state commissions and state consumer advocates will have the information they need to develop retail curtailment plans for shortages associated with these existing Large Loads and any related cost.

70 White House Ratepayer Protection Pledge, available at https://www.whitehouse.gov/ratepayer-protection-pledge/

PDF page 28

26
D. PJM’s proposal to rely on state programs for curtailment and allocation of
IRAS program costs to retail consumers is unjust and unreasonable.
As noted on several occasions in this protest, PJM proposes that state legislatures and commissions will address how the curtailments and related costs associated with New Large Load curtailments will be allocated among retail consumers in their states.71  Ohio does not have a state law addressing allocations of costs or curtailment obligations among retail consumers in relation to the IRAS or other federal large load regulatory programs.  Nor does it have state- jurisdictional tariffs that address these issues.

Ohio does have one state jurisdictional utility, American Electric Power (“AEP”), that has a tariff for assigning the costs associated with generation procurement and transmission and distribution investment associated with Large Load interconnections. The PUCO approved a multi-party settlement, supported by OCC and others, that implements a special tariff.72 AEP’s tariff, however, does not adequately protect consumers from the federal

curtailments PJM is proposing for large load customers. Under this state tariff, AEP generally can curtail nonresidential customer service in an emergency, if the nonresidential customer is violating the tariff or engaging in activity that is otherwise unlawful.  Under the large load interconnection tariff changes agreed upon in the settlement, AEP can curtail data center load if that load has Behind the Meter generation.73  The minimum demand calculation allows netting to include consideration of the customer’s firm commitments to reduce load with Behind the Meter

71 IRAS Application at 2-3, 7, 26, 101, 104-106.
72 In the Matter of the Application of Ohio Power Company for New Tariffs Related to Data Centers and Mobile Data Centers, Opinion and Order (Jul. 9, 2925), in PUCO Case No. 24-508-EL-ATA (“AEP July 2025 Order”); see also In the Matter of the Application of Ohio Power Company for New Tariffs Related to The Standard Service Offer Service for Data Center Load, Finding and Order (Aug. 5, 2026) in PUCO Case No. 26-113-EL-ATA (“AEP August 2026 Order”).  While there are additional matters pending or contemplated to implement specific data center load tariffs for American Transmission Systems, Inc., Dayton Power and Light Company and Duke Energy Ohio, to date the PUCO has not adopted orders establishing programs for these utilities.
73 Id.

PDF page 29

27
generation.74 To ensure that the customer’s election to net does not result in it exceeding its contract capacity, equipment must be in place and maintained to instantaneously curtail load equal to or greater than the Behind the Meter generation output, subject to the then-current technical requirements of the transmission provider.75 The objective of this requirement is to ensure that the data center load does not exceed its contracted capacity.  The only other reference to curtailment in that Order is the finding that “[w]hile we recognize 10/10 Stipulation signatories state that data centers can curtail their loads during peak times, regardless, the Company still needs to invest in its transmission system to serve the incoming data center capacity.”76

For purposes of the IRAS program, the Ohio AEP tariff does not address curtailment priorities and related cost allocations.  More importantly, no protections exist currently for consumers of the three other utilities in the state.  There is no guarantee under Oho law that all Oho consumers, even customers of AEP, will be protected against the cross-subsidies inherent in PJM’s IRAS proposal. It is fundamentally unreasonable for PJM to rely on a system of shared state-federal jurisdiction to resolve a problem raised directly by its proposed wholesale IRAS program where inadequate protections exist at the state level.

PJM should not rely on hypothetical state action to establish that IRAS is a deliverable resource-adequacy service. Unless an Electric Distributor has enforceable retail authority, customer specific arrangements, telemetry and tested ten-minute curtailment capability, its assigned IRAS curtailment quantity is merely a paper resource.  PJM nevertheless proposes to rely on that quantity for emergency operations and ultimately exclude the associated load from

74 Id.
75 Id.
76 Id. at 77.

PDF page 30

28
capacity procurement. This transfers the risk of nonperformance to existing consumers. That is unjust and unreasonable and contrary to the Ratepayer Protection Pledge.

FERC should reject PJM’s approach. Instead, FERC should condition acceptance on PJM’s filing of a modification to the IRAS proposed tariff language. The modification should require PJM to verify that an effective state-approved tariff or binding contract makes the associated reduction legally and operationally enforceable. If PJM cannot make that verification, then the tariff should require that the New Large Load customer be directly assigned the curtailment risk and associated costs as a condition of IRAS, interconnection to the grid and provision of electric service without the required capacity resource support.

E. PJM’s failure to include a penalty for New Large Load customer non-
compliance or under-performance of curtailment directives is unjust and
unreasonable.
PJM proposes paying New Large Loads for successful reductions in energy consumption, but does not establish a comparably clear customer-level penalty when they fail to reduce consumption in a timely manner, e.g., within ten minutes.  Without enforceable contracts, telemetry, testing and penalties, Ohio households could remain exposed to emergency outages. Regulatory obligations need enforcement penalties to ensure compliance with tariff rules. PJM is no stranger to a penalty structure to ensure market participant compliance with its tariff rules.  Such penalties already exist in the RPM capacity auction tariffs for generating resource, demand response and transmission upgrade non-performance events.77

77 See, e.g., PJM Open Access Transmission Tariff, ATT DD, section 7.1 (Generator Resource Reliability Test Failure Charge); R section 8.1 (Capacity Resource Deficiency Charge); section 10A Charges for Non-Performance and Credits for Performance); section 10B (Charges and Credits for Curtailments During Non-PAI Event); section 11A (Demand Response Resource Test Failure Charge); and section 12 (Qualifying Transmission Upgrade Compliance Penalty Charge). .

PDF page 31

29
The PJM IMM reports related to specific demand response non-performance support the need for a penalty for curtailment non-compliance. Those reports indicate that during the January 25, 2026 demand response event, actual compliance with the requirements for curtailments amounted to only 50 to 58%.78  For the June, July, and August demand response events in 2025, demand response providers’ performance ranged from 49 to 70%.79 This level of curtailment performance is unacceptable.

Moreover, the PJM IMM has recently criticized the insufficiency of PJM’s existing demand response non-performance penalties, and has proposed modifications. The IMM report, presented to the PJM Markets and Reliability Committee on April 22, 2026, states that PJM’s proposed demand response tariff changes (a) allow payment for demand response even when dispatch results in increased loads; (b) make it profitable for demand response even when these resources provide zero performance (e.g., with zero performance, demand response resources are still able to retain 87.8% of their RPM revenues in non-Performance Assessment Intervals); (c) provide proposed penalties for non-performance that are significantly weaker than the existing penalties for simply failing a demand response test; and (d) fail to provide for return of penalties to load that paid for the capacity.80  The IMM concluded that the proposed penalty structure will not provide effective performance incentives, and that there should be no payment for zero 78 Market Monitor Report to the PJM Members Committee at Slides 4, 9-10 (Jun. 24, 2026), presented by Marketing Analytics, LLC, available on the PJM website at https://www.pjm.com/-/media/DotCom/committees- groups/committees/mc/2026/20260624/20260624-item-07---market-monitoring-report---presentation.pdf. 79 DR Nonperformance Penalties Report to the PJM Markets Implementation Committee at Slides 12-14 (Jan. 20, 2026), presented by Marketing Analytics, LLC, available on the PJM website at https://www.pjm.com/- /media/DotCom/committees-groups/committees/mic/2026/20260120/20260120-item-01-3---load-management-- price-responsive-demand-event-performance---imm.pdf.

80 IMM Comments on Proposed DR Penalties as Slides 2, 18-20, Monitoring Analytics, LLC, presentation to the PJM Markets and Reliability Committee (Apr. 22, 2026), available on the PJM website at

PDF page 32

30
performance.81 As the IMM demonstrates, the likelihood of non-compliance with curtailment directives during system emergencies by demand response providers is not speculative. The need for strong penalties for non-performance of load shedding or curtailment activities is paramount, including curtailments associated with the IRAS program.  In his comments on PJM’s Reliability Backstop Procurement (“RBP”) proposal in Docket No. ER26- 3380-000, the IMM stated that “[a]llowing the new data center to designate its own load as Annual DR further creates an opportunity to avoid the curtailment obligation that would otherwise apply to the load under PJM’s Interim Resource Adequacy Service (“IRAS”). In effect, the data center can transform a reliability obligation imposed on an inadequately supplied large load into a self-designated RBP offset, while providing PJM with a demand side resource whose availability is dependent on emergency curtailment rather than an economically dispatchable supply resource.”82 The IMM concludes that “[i]n substance, the proposal allows the large load to satisfy the reliability obligation created by its own demand by making itself a demand response resource, even though that resource provides a fundamentally different and less durable reliability product than the capacity procurement it displaces.”83

As noted in section II.A earlier, even SPP’s new large load interruptible transmission tariff, the CHILLS program, includes a penalty for over-use of the transmission system on an interruptible basis.84 While SPP’s proposed penalty for CHILLS customers is not a curtailment penalty per se, it achieves a similar objective.  As FERC explained in accepting SPP’s proposed penalty for excessive use of the transmission system on an interruptible basis, “SPP’s proposed

81 Id. at Slide 21.
82 Protest of Independent Market Monitor for PJM at 23, PJM Interconnection, L.L.C. Docket No. ER26-3380-000 (Aug. 21, 2026), available on FERC’s e-library website as Accession Document No. 20260821-5317.
83 Id. at 24.
84 Southwest Power Pool, Inc., 195 FERC ¶ 61,196 at P 98.

PDF page 33

31
penalty structure for instances in which CHILLS Customers use transmission service in excess of their CHILLS Reserved Capacity is also just and reasonable and not unduly discriminatory or preferential because it ensures that CHILLS Customers pay for unreserved use of SPP’s transmission system based on the amount and duration of such unreserved use.  As described above, SPP’s proposed penalty amount increases as any unreserved use is repeated,” and “will help deter CHILLS Customers from repeatedly failing to adhere to their CHILLS Reserved Capacity amounts.”85

In essence, PJM’s IRAS program works in a manner similar to the SPP CHILLS
interruptible transmission program.  Large data center loads on the SPP system are required to take CHILLS interruptible transmission service on an interim basis until the network upgrades needed to reliability accommodate their interconnection to the system can be built.  PJM’s IRAS program pursues a similar objective, albeit in the capacity side of operations as opposed to the transmission side of operations.

PJM’s IRAS proposal contains neither non-performance, nor excessive take penalties for failure of a New Large Load customer to comply with curtailment directives under the program. Instead of imposing a penalty for non-compliance with curtailment directives, PJM seeks to compensate such entities through an incentive to encourage such compliance. As discussed in section II.A above, that proposed incentive is unjust, unreasonable and unduly discriminatory and preferential in a situation where New Large Load is allowed to interconnect only on condition that their loads can be curtailed in the event of a system resource shortage. Reliability and resource adequacy are too important to leave to the hope that incentives will encourage good

85 Id.

PDF page 34

32
behavior. Strong penalties are more appropriate under such circumstances, such as the strong penalties for non-performance of capacity obligations under the RPM rules. FERC should reject the curtailment compensation proposal and direct PJM instead to adopt a penalty for New Large Load non-compliance with curtailment directives.  PJM might argue that its proposal contemplates issuance of the curtailment directive to the Electric Distributor in whose zone the New Large Load is located, rather than to the New Large Loads, and thus there is no direct nexus between the New Large Load and PJM’s directives to justify a penalty. This argument and proposal are seriously flawed.

  Imposing curtailment penalties on the Electric Distributor suffers from the same problem that invades all of PJM’s IRAS proposal. The objective is to allow New Large Loads to interconnect to the system and receive electricity services regardless of whether they bring sufficient generating capacity to satisfy their capacity obligations. But PJM proposes no direct measures to order New Large Loads to do anything, even when critically needed to ensure grid reliability.  FERC should direct PJM to correct this flaw and impose curtailment non- performance penalties directly on New Large Loads as a condition of their interconnection to the system and receipt of energy from the system.

F. The IRAS proposal is unjust and unreasonable because it does not contain sufficient protections against double recovery by New Large Loads of

incentive compensation for curtailments.
The IRAS proposal does not appear to contain rules preventing double recovery by New Large Loads under potentially overlapping programs.  For example, the IRAS program is a capacity market program, designed to allow New Large Loads to interconnect even in the absence of sufficient generation capacity to meet their needs so long as they participate in the IRAS curtailment program.  However, these loads may also be eligible for discounted

PDF page 35

33
transmission rates if they take interruptible transmission services or may be eligible for demand response payments in the capacity and energy markets. In other words, New Large Load customers may be eligible for multiple incentive payments associated with the same curtailment event.

At a minimum, FERC should direct PJM to require New Large Loads to disclose all payments received under all PJM market programs for the same curtailment event.  FERC likewise should direct PJM to implement tariff provisions that would net additional forms of payments for the same curtailment event so that New Large Loads are compensated only once for the same curtailment event. Absent such a disclosure obligation and a pricing structure that prevents double payment for the same event, there would be no mechanism to ensure that consumers in Ohio and elsewhere in PJM do not pay excessive rates for electricity services in PJM’s markets.

G. FERC should consider directing PJM to directly assign curtailment
obligations and related costs to the New Large Loads driving the reliability concerns on the grid due to their failure to bring generating assets to the system to satisfy their capacity obligations.

Much of the electric utility industry, large data center loads and even the White House agree that existing consumers on the system should be held harmless from the costs and risks of New Large Load interconnections to the grid. The White House has even titled its webpage addressing this matter “Data Centers Pay their Way; Ratepayers pay theirs.”86 In keeping with this commitment, the IMM stated in his alternative proposal to PJM’s RBP program that “[t]he most important criterion for evaluating proposals to address how to reliably serve new data center load is the assignment of the costs and risks associated with LSEs

86 Supra, n.32.

PDF page 36

34
serving data center load.”87 The IMM explains that “the failure to exclude new data center load from the BRAs, as PJM proposes, would by definition impose significant costs on other customers and therefore violate the basic principle that data center costs should not be imposed on other customers.”88

The IRAS proposal suffers from similar flaws.  It directs curtailment orders to Electric Distributors in whose zones New Large Loads are located, leaving it to the states to implement curtailment and cost allocation rules. It provides incentive compensation for New Large Load compliance and yet fails to implement penalties for non-compliance with curtailment directives. Simply put, the IRAS program does not satisfy the all encompassing objectives of the White House Ratepayer Protection Pledge – that existing consumers be truly held harmless from the risks and costs associated with both existing Large Loads and New Large Loads. Only direct and complete assignment of these costs and risks to the Large Load customers will fulfill this promise. Consequently, FERC should direct PJM to submit a compliance filing that requires direct assignment to New Large Loads taking IRAS of curtailment directives, related penalties and associated costs as a condition to interconnection without bringing adequate generating capacity as required under the Reliability Assurance Agreement capacity obligation rules.

III. CONCLUSION
OCC supports PJM’s proposal to interrupt New Large Loads that connect without sufficient supporting capacity before curtailing residential and other existing consumers.  OCC

87 Monitoring Analytics, Critical Issue Fast Path Proposed Reliability Backstop Auction Proposal (Jun. 30, 2026), available at https://www.monitoringanalytics.com/reports/Presentations/2026/IMM%20Backstop%20auction%20design%20pro posal%20-%20V6%202026.06.19.pdf (“IMM RBP Proposal”).
88 Id.

PDF page 37

35
does not, however, support the proposal to saddle the states with the obligation of ensuring New Large Loads bear the consequences of their actions, nor does it support compensating those New Large Loads for interruptions that are an inherent condition of receiving service without adequate capacity. Such customers should bear the consequences of their decision to take conditional service. The associated costs should not be shifted to other consumers, including residential consumers.

PDF page 38

36
WHEREFORE, OCC respectfully requests that FERC protect Ohio consumers by
rejecting the curtailment compensation element of PJM’s Interim Resource Adequacy Service proposal in this case; direct PJM to expand the list of entities entitled to access the Large Load Registry to include state consumer advocate offices; direct PJM to submit a filing to address curtailments that could be associated with Large Loads included in the RPM auctions for the 2026/2027, the 2027/2028 and the 2028/2029 Delivery Years; and grant the additional forms of relief requests in this Protest.

Respectfully submitted,
Maureen Willis
Ohio Consumers’ Counsel
/s/ Angela O’Brien
Angela O’Brien
Deputy Consumers’ Counsel
Office of the Ohio Consumers’ Counsel
65 East State Street, Suite 700
Columbus, Ohio 43215
Telephone: (614) 466-9531
angela.obrien@occ.ohio.gov
/s/ Denise C. Goulet
Denise C. Goulet, Esq.
McCarter & English, LLP
1301 K Street, N.W.
Suite 1000 West
Washington, D.C. 20005
(202) 753-3400
dgoulet@mccarter.com
Special Counsel to the Ohio Office of the Attorney
General for the Office of the Ohio Consumers’
Counsel
DATED:  September 3, 2026

PDF page 39

37
CERTIFICATE OF SERVICE
I hereby certify that I have on this date served a copy of the foregoing document via electronic mail upon all parties of record on the Commission’s official service list in this proceeding. Dated in Columbus, Ohio this 3rd day of September, 2026.

/s/ Denise C. Goulet
Denise C. Goulet
McCarter & English, LLP
1301 K Street, N.W.
Suite 1000 West
Washington, D.C. 20005
(202) 753-3400
dgoulet@mccarter.com