Protest of Office of the Ohio Consumers' Counsel to PJM Interconnection, L.L.C.'s 08/13/2026 Interim Resource Adequacy Service Filing
Text extracted from the eLibrary original (SHA-256 d54bb7f9aa9f048e…). Download the original from the official source.
Contents · 17 sections
- A. PJM’s IRAS proposal to compensate IRAS load for curtailments is
- B. FERC should direct PJM to modify the IRAS proposal to include
- C. The IRAS Proposal is Unjust and Unreasonable because it fails to
- D. PJM’s proposal to rely on state programs for curtailment and
- E. PJM’s failure to include a penalty for New Large Load customer non-
- F. The IRAS proposal is unjust and unreasonable because it does not
- G. FERC should consider directing PJM to directly assign curtailment
- I. BACKGROUND
- II. PROTEST
- A. PJM’s IRAS proposal to compensate IRAS load for curtailments is patently
- B. FERC should direct PJM to modify the IRAS proposal to include state
- C. The IRAS Proposal is Unjust and Unreasonable because it fails to address
- D. PJM’s proposal to rely on state programs for curtailment and allocation of
- E. PJM’s failure to include a penalty for New Large Load customer non-
- F. The IRAS proposal is unjust and unreasonable because it does not contain
- G. FERC should consider directing PJM to directly assign curtailment
- III. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
Table of Contents
printed heading
Table of Contents I.Read this passage
A. PJM’s IRAS proposal to compensate IRAS load for curtailments is
printed heading
A.Read this passage
B. FERC should direct PJM to modify the IRAS proposal to include
printed heading · Topic match: Registry access
FERC should direct PJM to modify the IRAS proposal to include state consumer advocates in the list of those allowed to access confidential information in the proposed new Large Load Registry. ........................ 20Read this passage Filed comments: Registry access
C. The IRAS Proposal is Unjust and Unreasonable because it fails to
printed heading · Topic match: Reliability and curtailment
C.Read this passage Filed comments: Reliability and curtailment
D. PJM’s proposal to rely on state programs for curtailment and
printed heading · Topic match: Reliability and curtailment
D.Read this passage Filed comments: Reliability and curtailment
E. PJM’s failure to include a penalty for New Large Load customer non-
printed heading · Topic match: Reliability and curtailment
E.Read this passage Filed comments: Reliability and curtailment
F. The IRAS proposal is unjust and unreasonable because it does not
printed heading
F.Read this passage
G. FERC should consider directing PJM to directly assign curtailment
printed heading · Topic match: Reliability and curtailment
PJM requests an October 12, 2026 effective data with the IRAS beginning in the 2027/2028 capacity auction Delivery Year.Read this passage Filed comments: Reliability and curtailment
I. BACKGROUND
printed heading · Topic match: Reliability and curtailment
There should be a tested, legally enforceable interruption arrangement and penalties to secure performance. 5 customers’ loads would be excluded from the auctions, PJM would still allow these entities to connect to and receive electricity from the system.14 If there are resource shortages in any…Read this passage Filed comments: Reliability and curtailment
II. PROTEST
printed heading · Topic match: Registry access
Second, PJM’s proposed new Large Load Registry unreasonably excludes state consumer advocate offices from the list of entities entitled to access the information to be retained in that registry.Read this passage Filed comments: Registry access
A. PJM’s IRAS proposal to compensate IRAS load for curtailments is patently
printed heading · Topic match: Reliability and curtailment
In contrast, PJM is proposing that consumers throughout its region, including Ohio consumers, will be at risk of: 1. curtailments if these Large Loads fail to bring the generating capacity needed to serve their capacity obligations, especially where state laws may be inadequate to protect them from…Read this passage Filed comments: Reliability and curtailment
B. FERC should direct PJM to modify the IRAS proposal to include state
printed heading · Topic match: Registry access
Additionally, it is unclear how, absent a registry, a Connect & Manage [IRAS] framework could be implemented in a way that protects other end-use consumers from being curtailed in response to a PJM Connect & Manage [IRAS] event.”58 Another stakeholder responded that “[a] registry provides the…Read this passage Filed comments: Registry access
C. The IRAS Proposal is Unjust and Unreasonable because it fails to address
printed heading · Topic match: Cost allocation
To ensure adequate protection for consumers in Ohio and elsewhere in PJM, PJM and FERC must address curtailment priorities for Large Loads that have already cleared in the 2026/2027, the 2027/2028 and the 2028/2029 Delivery Years.Read this passage Filed comments: Cost allocation
D. PJM’s proposal to rely on state programs for curtailment and allocation of
printed heading · Topic match: Reliability and curtailment
As noted on several occasions in this protest, PJM proposes that state legislatures and commissions will address how the curtailments and related costs associated with New Large Load curtailments will be allocated among retail consumers in their states.71 Ohio does not have a state law addressing…Read this passage Filed comments: Reliability and curtailment
E. PJM’s failure to include a penalty for New Large Load customer non-
printed heading · Topic match: Reliability and curtailment
PJM proposes paying New Large Loads for successful reductions in energy consumption, but does not establish a comparably clear customer-level penalty when they fail to reduce consumption in a timely manner, e.g., within ten minutes.Read this passage Filed comments: Reliability and curtailment
F. The IRAS proposal is unjust and unreasonable because it does not contain
printed heading · Topic match: Reliability and curtailment
FERC likewise should direct PJM to implement tariff provisions that would net additional forms of payments for the same curtailment event so that New Large Loads are compensated only once for the same curtailment event.Read this passage Filed comments: Reliability and curtailment
G. FERC should consider directing PJM to directly assign curtailment
printed heading · Topic match: Reliability and curtailment
It directs curtailment orders to Electric Distributors in whose zones New Large Loads are located, leaving it to the states to implement curtailment and cost allocation rules.Read this passage Filed comments: Reliability and curtailment
III. CONCLUSION
printed heading · Topic match: Registry access
The associated costs should not be shifted to other consumers, including residential consumers. 36 WHEREFORE, OCC respectfully requests that FERC protect Ohio consumers by rejecting the curtailment compensation element of PJM’s Interim Resource Adequacy Service proposal in this case; direct PJM to…Read this passage Filed comments: Registry access