ER26-3515-000 · 2026-09-03 · Ohio Federal Energy Advocate

Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate on PJM Interconnection, L.L.C.’s filing to establish Interim…

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.                                    )                          Docket No. ER26-3515-000

COMMENTS OF THE PUBLIC UTILITIES COMMISSION OF OHIO’S
OFFICE OF THE FEDERAL ENERGY ADVOCATE

On August 13, 2026, PJM Interconnection, L.L.C. (PJM) filed, pursuant to section 205 of the Federal Power Act, revisions to the PJM Open Access Transmission Tariff (OATT) and the Reliability Assurance Agreement (RAA) to establish a new Interim Resource Adequacy Service (IRAS). PJM proposes IRAS as a condition of transmission service for New Large Load (NLL), as defined in the filing, to be used during periods when there are insufficient resources to reliably meet demand in real time operations starting with the 2027/2028 Delivery Year (i.e., June 1, 2027). When triggered by system conditions, IRAS will enable PJM to prioritize load reduction in zones/areas where NLLs have not brought their own new capacity or had their capacity needs covered through the Reliability Backstop Procurement (RBP).1

To support the IRAS framework, PJM proposes numerous revisions to the OATT and/or RAA to include, among others, 1) incorporating definitions of Large Load, New Large Load, and Eligible New Large Load; 2) clarifying a Load Serving Entity’s (LSE) obligation to bring new capacity in an amount equal to or exceeding the peak load of the NLL it serves or be subject to load curtailment prioritization during emergencies; 3) establishing a Large Load Registry and requiring LSEs and electric distribution utilities (EDUs) to provide information to the Registry as necessary for PJM to determine the megawatt (MW) quantity of IRAS responsibility by

1 PJM Transmittal Letter at 1-2.

PDF page 2

2
zone/area; 4) establishing curtailment prioritization for Eligible NLL during emergency grid conditions; and 5) establishing a compensation scheme for Eligible NLL that has provided IRAS load reduction service.

The Office of the Federal Energy Advocate (Ohio FEA) of the Public Utilities Commission of Ohio (PUCO), fulfilling its statutory duty to advocate on behalf of Ohio’s retail electricity consumers,2 offers the following comments for consideration by the Federal Energy Regulatory Commission (Commission).

I. Background
PJM’s capacity market, called the Reliability Pricing Model (RPM), is designed to ensure long-term grid reliability by procuring the appropriate amount of supply needed to meet predicted peak load, plus an adequate reserve margin, three years in the future. A primary objective of the capacity market is to match (or balance) power supply with future demand, thereby creating long-term price signals to attract needed investments to ensure resource adequacy. Under the RPM, capacity resources are procured by PJM through an annual, competitive Base Residual Auction (BRA).

In December 2025, the BRA conducted for the 2027/2028 Delivery Year represented the first time in recent history that large load additions significantly increased PJM’s load forecast which, in turn, significantly increased the PJM Region Reliability Requirement, in megawatts, PJM sought to procure in the auction. The auction resulted in a capacity procurement that was 6,517 MW short of the PJM Region Reliability Requirement and 5.6 percent below the target 20% Installed Reserve Margin (IRM).3 Similarly, in July 2026, the BRA conducted for the

2 Ohio Revised Code 4928.24.
3 PJM 2027/2028 Base Residual Auction Reserve Target Shortfall Report, February 9, 2026, available at https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-2028/2027-2028-bra-reserve- target-shortfall-report.pdf at 1.

PDF page 3

3
2028/2029 Delivery Year cleared 6,831 MW below the PJM Region Reliability Requirement and 5.6 percent below the 20% IRM.4

Over this time, PJM undertook various efforts to address the increasingly urgent resource adequacy needs of the region, including establishing a Reliability Resource Initiative and then an Expedited Interconnection Track to expedite the interconnection of new capacity resources, and initiating multiple Critical Issue Fast Path (CIFP) stakeholder processes to address the challenge of maintaining reliability while efficiently integrating new large loads, namely data centers. In August 2025, PJM initiated a broad CIFP on Large Load Additions, which the PJM Board of Managers (PJM Board) addressed in a decisional letter in January 2026.5 The PJM Board directed PJM, among other endeavors, to implement a “connect-and-manage” framework for new large loads that do not bring their own new generation with curtailment expected to occur prior to the deployment of pre-emergency Demand Response, subject to stakeholder development of the appropriate operational framework.6

In March 2026, PJM initiated a Connect and Manage Senior Task Force, which later merged with the CIFP on the RBP. The CIFP held lengthy discussion over two months and considered nearly a dozen “connect-and-manage” solution packages; however, the members failed to endorse a package to the PJM Board to conclude the effort. As a result, on July 27, 2026, the PJM Board issued a decisional letter setting forth the framework contained in the

4 PJM 2028/2029 Base Residual Auction Report, July 14, 2026, available at https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results-report.pdf at 3. 5 PJM Board Decisional Letter, January 16, 2026, available at https://www.pjm.com/-/media/DotCom/about- pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-load- additions.pdf.
6 Id. at 4-5.

PDF page 4

4
instant docket, renaming “connect-and-manage” as Interim Resource Adequacy Service.7 The Ohio FEA supports the filing.

II. Comments
A. Data Centers Are the Large Loads Driving Historic Demand.
As an initial matter, the Ohio FEA maintains that data centers are the large loads driving historic demand in the PJM footprint and, therefore, PJM should define Large Load to be specific to data centers, not all loads of a designated size. It has become obvious to most that data centers are unique large loads that warrant distinction from other commercial or industrial customers. Ohio was one of the first states to establish data center tariffs with a defined data center customer class, and the Ohio FEA recommends PJM do likewise.8

PJM goes on to define New Large Load for purposes of applying a Bring Your Own New Capacity (BYONC) construct, and Eligible New Large Load for purposes of determining an IRAS obligation based on whether NLL fulfills its BYONC requirement. Eligible NLL is calculated as the difference between a NLL’s registered peak load in MW and its BYONC arrangements and/or Allocated RBP Unforced Capacity in MW, as reported in the Large Load Registry.9 Again, no distinction is made between the computational loads that are directly responsible for the current state of resource adequacy – such as hyperscale data centers and cryptocurrency miners – and traditional manufacturing loads that drive American industry. As this nation, under the current administration’s leadership, works to onshore and expand domestic

7 PJM Board Decisional Letter, July 27, 2026, available at https://www.pjm.com/-/media/DotCom/about-pjm/who- we-are/public-disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement-and- connect-and-manage.pdf.
8 The PUCO has approved, or is currently in the process of reviewing, this tariff for each of its EDUs.
9 Proposed PJM Tariff Attachment DD-4, Section V.

PDF page 5

5
manufacturing, it is counterproductive to place additional constraints on traditional manufacturers and other non-data center large loads.

B. BYONC Is Necessary to Avoid Curtailment and Maintain Reliability.
The Ohio FEA supports a BYONC framework and PJM’s proposal to incent LSEs to bring new capacity resources to bear commensurate with the addition of NLL, which PJM defines to mean new or incremental large loads that go into service after June 1, 2027. We agree that bringing new capacity to match new large load is the optimal solution to address resource adequacy concerns and is strongly preferred to IRAS. However, given the challenges of bringing new capacity resources online to meet new demand in the near term, we find PJM’s BYONC proposal to be reasonable. PJM proposes that, starting on June 1, 2027, any NLL that has not yet brought new capacity would be subject to priority curtailment during emergency grid conditions (i.e., IRAS Action). As the electric grid is and will continue to be stressed by an imbalance between demand and supply, IRAS Action is a critical operational tool for PJM to use when system conditions threaten reliability in real time. As further discussed below, this tool also protects other non-large load customers from curtailment. To avoid potential IRAS Action, NLL must contract with new capacity that meets the BYONC gating criteria, including that the new capacity will be available for at least 10 years.

C. Registry Is Key to Successful Implementation.
The Ohio FEA appreciates PJM’s proposal to establish a Large Load Registry, which is fundamental to the IRAS framework and necessary for successful state implementation. As described in the filing,

PJM will use the registry to determine the quantity of [NLL] by zone/area
and allocate IRAS responsibility to each zone/area accordingly, starting
with the 2027/2028 Delivery Year. States may leverage the Large Load
Registry to inform the implementation of retail constructs including load

PDF page 6

6
reduction priorities and cost allocation at the retail level to appropriate
end-use customers.10

The Ohio FEA agrees that the registry will be extremely helpful in assisting states with standardizing data around large loads generally and is a necessary component for administering the IRAS framework. Details around the proposed registry highlight the significant and ongoing collaboration of many parties that will be necessary to execute a connect-and-manage program. Consistent with state public record laws and administrative procedures, state commissions routinely receive and maintain confidential information from regulated utilities and suppliers, parties to legal proceedings, auditors, project developers, competitive auction bidders, etc. Thus, there should be no concern about data protection standards for state commissions with access to the registry. On the contrary, the only way that states, LSEs, EDUs, and PJM can reasonably be expected to accurately co-manage a program like IRAS is through a centralized repository like the Large Load Registry.

D. IRAS Actions Must Precede Other Emergency Actions to Protect Other
Customers.

PJM’s filing describes the current practices set forth in PJM Manual 13 for when capacity shortages give rise to emergency procedures, including three levels of NERC Energy Emergency Alert Levels (EEA1 through EEA3), with EEA3 being the highest alert level. PJM also describes the way it would incorporate IRAS Actions into those emergency procedures.11 While PJM explains that grid operators have the flexibility to implement emergency procedures in whatever order is required to ensure system reliability, the Ohio FEA strongly supports PJM’s proposal to generally sequence IRAS Actions first at the beginning of an EEA1.12 The electric grid is

10 PJM Transmittal Letter at 28-29.
11 Pilong Affidavit at 7-12. 12 Id.at 6.

PDF page 7

7
increasingly constrained by the addition of large loads; therefore, it is reasonable for large loads that do not play a role in remedying the supply and demand imbalance to be curtailed prior to other load. This is an essential element of PJM’s proposal. Deploying IRAS Actions prior to deploying Pre-Emergency Load Management Reductions will protect other customers from a wide range of pre-emergency (EEA1) and emergency (EEA2) actions that otherwise would impose significant financial impact and shift reliability risk to other customers. Further, prioritizing IRAS Actions is a necessary step to comply with the Statement of Principles Regarding PJM, as signed by the National Energy Dominance Council and the 13 PJM governors, and the Ratepayer Protection Pledge.

Should PJM fail to prioritize IRAS Actions, such as re-sequence them to occur just prior to the issuance of manual load shed under an EEA3, damage to retail ratepayers will already have been done. During emergency system conditions, the dispatch of Emergency Demand Response Resources (generally under EEA2) will cause energy prices to rise dramatically for all loads. Non-essential building loads will be curtailed. Emergency back-up generators will be dispatched. These costly and harmful scenarios could all be avoided (or at least minimized) by deploying IRAS Actions first, at the beginning of an EEA1, as PJM proposes. Also importantly, as PJM notes, if PJM were to call IRAS Actions after Demand Response Resources have been exhausted, this would eliminate the incentive of NLL to contract for new capacity because they would be insulated from curtailment by Demand Response.13 Putting IRAS in the privileged position of being deployed after Emergency Demand Response would serve as a perverse incentive for NLL to actually prefer IRAS over bringing new capacity to the system as required to ensure resource adequacy and reliability.

13 PJM Transmittal Letter at 80.

PDF page 8

8
E. States Must Have Flexibility to Determine IRAS Action Compensation.
The need for curtailment, and therefore compensation, would not exist but for Eligible NLL connecting to the system before adequate supply is available. The foundation of PJM’s IRAS proposal, if approved by the Commission, is that Eligible NLL will be able to connect to the grid prior to meeting the BYONC requirement. Thus, the Eligible NLL will benefit from the capacity market and appropriately pay capacity costs. Under IRAS, the capacity market will still serve as the primary vehicle to incent resource adequacy in the PJM region, and most capacity resources will still be obligated to make a cost-based bid into the energy market. And as recognized by PJM’s Effective Load Carrying Capability accreditation methodology, capacity will continue to have value across all hours and seasons, not only during critical peak hours. Accordingly, Eligible NLL will derive capacity market benefits most of the time (i.e., all intervals during which they are not called upon to curtail pursuant to an IRAS Action). However, the Ohio FEA recognizes that Eligible NLL subject to priority curtailment may not receive the full benefit afforded to other capacity backed loads. While allowing Eligible NLL to connect to the system and benefit from the capacity market without bringing new supply could be considered a form of compensation, some stakeholders in the CIFP process asserted that a level of compensation may be appropriate. To address the issue, PJM proposes a wholesale compensation rate equal to 50% of its existing Non-Performance Charge Rate but asserts that the wholesale rate is flexible and can be reduced to less than 50% of the Non-Performance Charge Rate based on retail rates.14 In establishing the wholesale compensation rate, PJM specifically states:

Nothing in this Tariff, Attachment DD-4, section X shall interfere with any
Eligible New Large Load’s election to (i) accept in its retail rates a sum less than 50% of the Non-Performance Charge Rate as compensation for the

14 Id. at 102.

PDF page 9

9
provision of wholesale Interim Resource Adequacy Service, or (ii) waive
receipt in its retail rates any compensation for the provision of wholesale Interim Retail Adequacy Service.15

While offering no opinion on whether the proposed 50% of the Non-Performance Charge Rate is just and reasonable, the Ohio FEA appreciates the deference shown to states to further determine IRAS compensation through retail ratemaking.16 States may find it necessary or appropriate to consider whether compensation is consistent with the Ratepayer Protection Pledge and/or other commitments to insulate other customers from cost shifting that could arise if Eligible NLL is compensated for IRAS Action. Accordingly, as PJM describes, states may determine, through their retail tariffs or other regulatory mechanisms, whether IRAS compensation should be 50% of the Non-Performance Charge Rate or lower, even zero. Should the Commission find there to be a lack of clarity on PJM’s proposed compensation framework, we request the Commission affirm in its Order that states have optionality to determine the level of IRAS compensation at the retail level.

III. Conclusion
PJM’s IRAS is a timely effort to confront reliability concerns caused by significant data center load growth in the region. The proposed BYONC construct, the Large Load Registry, and the curtailment prioritization of certain loads when necessary to ensure reliability during emergency conditions will all require massive new coordination effort by PJM, states, EDUs, and LSEs. Together we must ensure that new resources are secured to meet new demand while mitigating any compounding effect on PJM grid operations, markets, or other ratepayers.

15 Proposed PJM Tariff Attachment DD-4, Section X(c).
16 PJM Transmittal Letter at 106-107.

PDF page 10

10
Respectfully submitted,
D. Andrew Wilson
Ohio Attorney General

John H. Jones
Section Chief

/s/ Thomas G. Lindgren

Thomas G. Lindgren
Assistant Attorney General
Public Utilities Section
30 East Broad Street, 16th Floor
Columbus, Ohio 43215-3414
614.644.8768 (telephone)
866.818.6152 (facsimile)
Thomas.Lindgren@OhioAGO.gov

On Behalf of the Public Utilities
Commission of Ohio’s Office of the
Federal Energy Advocate

September 3, 2026

PDF page 11

11
CERTIFICATE OF SERVICE

I hereby certify that I have on this date caused a copy of the foregoing document to be served on each person included on the official service list maintained for this proceeding by the Commission’s Secretary, by electronic mail or such other means as a party may have requested, in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.  Dated this the 3rd day of September 2026, at Columbus, Ohio.

/s/ Thomas G. Lindgren

Thomas G. Lindgren
Assistant Attorney General