ER26-3515-000 · 2026-09-03 · Ohio Federal Energy Advocate

Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate on PJM Interconnection, L.L.C.’s filing to establish Interim…

Text extracted from the eLibrary original (SHA-256 1b2f5f8e7b20a8ea…). Download the original from the official source.

Contents · 9 sections
  1. I. Background p. 2
  2. II. Comments p. 4
  3. A. Data Centers Are the Large Loads Driving Historic Demand. p. 4
  4. B. BYONC Is Necessary to Avoid Curtailment and Maintain Reliability. p. 5
  5. C. Registry Is Key to Successful Implementation. p. 5
  6. D. IRAS Actions Must Precede Other Emergency Actions to Protect Other p. 6
  7. E. States Must Have Flexibility to Determine IRAS Action Compensation. p. 8
  8. III. Conclusion p. 9
  9. D. Andrew Wilson p. 10

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Registry access · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

PJM proposes IRAS as a condition of transmission service for New Large Load (NLL), as defined in the filing, to be used during periods when there are insufficient resources to reliably meet demand in real time operations starting with the 2027/2028 Delivery Year (i.e., June 1, 2027).
Read this passage Filed comments: Reliability and curtailment

I. Background

printed heading · Topic match: Reliability and curtailment

A primary objective of the capacity market is to match (or balance) power supply with future demand, thereby creating long-term price signals to attract needed investments to ensure resource adequacy.
Read this passage Filed comments: Reliability and curtailment

II. Comments

printed heading

II.
Read this passage

A. Data Centers Are the Large Loads Driving Historic Demand.

printed heading · Topic match: Registry access

Eligible NLL is calculated as the difference between a NLL’s registered peak load in MW and its BYONC arrangements and/or Allocated RBP Unforced Capacity in MW, as reported in the Large Load Registry.9 Again, no distinction is made between the computational loads that are directly responsible for…
Read this passage Filed comments: Registry access

B. BYONC Is Necessary to Avoid Curtailment and Maintain Reliability.

printed heading · Topic match: Reliability and curtailment

PJM proposes that, starting on June 1, 2027, any NLL that has not yet brought new capacity would be subject to priority curtailment during emergency grid conditions (i.e., IRAS Action).
Read this passage Filed comments: Reliability and curtailment

C. Registry Is Key to Successful Implementation.

printed heading · Topic match: Registry access

States may leverage the Large Load Registry to inform the implementation of retail constructs including load 6 reduction priorities and cost allocation at the retail level to appropriate end-use customers.10 The Ohio FEA agrees that the registry will be extremely helpful in assisting states with…
Read this passage Filed comments: Registry access

D. IRAS Actions Must Precede Other Emergency Actions to Protect Other

printed heading · Topic match: Reliability and curtailment

IRAS Actions Must Precede Other Emergency Actions to Protect Other Customers.
Read this passage Filed comments: Reliability and curtailment

E. States Must Have Flexibility to Determine IRAS Action Compensation.

printed heading · Topic match: Reliability and curtailment

States Must Have Flexibility to Determine IRAS Action Compensation.
Read this passage Filed comments: Reliability and curtailment

III. Conclusion

printed heading · Topic match: Cost allocation

The proposed BYONC construct, the Large Load Registry, and the curtailment prioritization of certain loads when necessary to ensure reliability during emergency conditions will all require massive new coordination effort by PJM, states, EDUs, and LSEs.
Read this passage Filed comments: Cost allocation

D. Andrew Wilson

printed heading

Lindgren Assistant Attorney General Public Utilities Section 30 East Broad Street, 16th Floor Columbus, Ohio 43215-3414 614.644.8768 (telephone) 866.818.6152 (facsimile) Thomas.Lindgren@OhioAGO.gov On Behalf of the Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated this the 3rd day of September 2026, at Columbus, Ohio. /s/ Thomas G.
Read this passage