ER26-3515-000 · 2026-09-03 · American Council on Renewable Energy

Comments of ACORE on PJM Interconnection, L.L.C.'s 08/13/2026 proposal to establish Interim Resource Adequacy Service and a large load registry

PDF page 1

1

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
Docket No. ER26-3515-000

ACORE COMMENTS ON PJM INTERCONNECTION LLC
INTERIM RESOURCE ADEQUACY SERVICE PROPOSAL

 Pursuant to Rule 211 of the Federal Energy Regulatory Commission (Commission) Rules of Practice and Procedure,1 ACORE submits these comments on the PJM Interconnection, L.L.C. (PJM) proposal to establish Interim Resource Adequacy Service (IRAS) and a large load registry (IRAS Proposal) submitted on August 13, 2026 in the above captioned docket. ACORE provides these supportive comments directed at the specific IRAS requirements for Bring Your Own New Capacity (BYONC). ACORE recognizes the immediate need for PJM to address the dramatic increase in demand resulting from the expansion of large loads within its footprint. Any reforms developed to address this need must incent and be aligned with a longer- term contracting paradigm rather than reliance on the short-term volatile pricing in PJM’s annual Reliability Pricing Model (RPM) capacity market.

ACORE therefore supports the requirement for a new large load to contract for new capacity under BYONC to avoid being subject to potential curtailments under IRAS.  Such a requirement will strongly incent longer-term (at least 10 year) contracting with BYONC capacity by the large loads availing themselves of the IRAS BYONC provision.  ACORE is also supportive of the requirement that the BYONC resources participate as a price taker in the Base Residual Auction (BRA) for 10 consecutive Delivery Years and be subject to the RPM’s must

1 18 C.F.R. § 385.211 (2024).

PDF page 2

2

offer requirement during that time frame.2 The submission of capacity as a price taker allows the capacity prices to reflect that these long-term arrangements will settle at a more stable price outside of the volatile clearing prices of the BRAs.

In PJM’s May whitepaper, Powering Reliability Through Market Design, PJM accurately describes the importance of revenue predictability and stability for the development of capital- intensive generation and storage capacity:

In conversations with generation developers, project finance lenders, equity investors and power project consultants in furtherance of this initiative, PJM heard a strikingly consistent message: High capacity prices alone do not drive investment decisions. The barriers cited – repeatedly and across investor types – were revenue durability over the project financing horizon and regulatory stability sufficient to make long-term revenue projections credible.3

In addition to the ten-year price taker requirement, ACORE also appreciates the expansive scope of BYONC to include not only needed new builds, but also capacity obtained through the utilization of Surplus Interconnection Service (SIS), as well as new demand response and distributed energy resources, and other types of capacity expansion. ACORE has long supported a greater use of SIS, especially for storage, but more improvements are needed.4 In a recent letter, PJM President and CEO David Mills stated that: “PJM understands that some aspects of our existing market rules for facilities interconnecting via the SIS process make it challenging for these facilities to provide capacity. Given the abundant interest in leveraging SIS to provide additional capacity, PJM staff and stakeholders recently initiated a workplan to

2 PJM IRAS Proposal at 55-56.
3 PJM Interconnection LLC, Powering Reliability Through Market Design (May 2026) at 32, https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering- reliability-through-market-design.pdf
4 See ACORE comments in support of PJM’s proposal for revisions to its Open Access Transmission Tariff governing Surplus Interconnection Service, Docket No. ER25-778 (Jan. 13, 2025), https://acore.org/resources/acore-comments-on-pjm-surplus-interconnection-service-proposal/

PDF page 3

3

address market rules that are potentially limiting its current use.”5 ACORE supports both the use of SIS for BYONC and the importance of further PJM actions to improve its feasibility. Finally, while not directly within the scope of IRAS but highly relevant to its success, ACORE continues to emphasize that a holistic approach is needed to address both the challenges and opportunities of large load integration. Such an approach will entail additional reforms and improvements that provide greater certainty and stability in the interconnection process,6 Commission action on PJM’s Order No. 1920 compliance filing, and greater development of high-voltage interregional transmission between PJM and other regions. ACORE and our membership look forward to ongoing engagement with the Commission on these important issues.

Respectfully submitted,
/s/ Elise Caplan
Elise Caplan
Vice President, Regulatory Affairs
ACORE
1150 Connecticut Ave NW, Suite 401
Washington, D.C. 20036
(301) 646-7130
caplan@acore.org

September 3, 2026

5 Letter from David Mills, President and CEO, PJM Interconnection LLC to Senator Koch, Delegate Hernandez, and Senator VanValkenburg (August 19, 2026), https://www.pjm.com/- /media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260827-pjm-president-ceo-response- to-indiana-virginia-legislators-letter-regarding-surplus-interconnection-service.pdf.
6 For more details on needed interconnection reforms, see the ACORE Issue Brief, Interconnection Barriers Continue and Fundamental Reforms are Needed (July 2026), https://acore.org/wp- content/uploads/2026/07/ACORE-Issue-Brief-Interconnection-Barriers-Continue-and-Fundamental- Reforms-are-Needed.pdf.

PDF page 4

4

CERTIFICATE OF SERVICE
The undersigned certifies that a copy of this pleading has been served this day upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated this 3rd day of September, 2026.

/s/ Elise Caplan
Elise Caplan