ER26-3515-000 · 2026-09-03 · Talen Energy Corporation

Motion to Intervene and Protest of Talen Energy Corporation re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000

MOTION TO INTERVENE AND
PROTEST OF TALEN ENERGY CORPORATION

PJM Interconnection, L.L.C.’s (“PJM”) Interim Resource Adequacy Service (“IRAS”) and Large Load Registry to Address System Reliability1 proposal should be rejected because it is unjust, unreasonable, and unduly discriminatory.  While Talen appreciates PJM’s goals of protecting ratepayers from rising costs while maintaining reliability, the vehicle chosen by PJM to arrive at that destination is a lemon and, as explained in the attached testimony of Zachary Ming of Energy and Environmental Economics, Inc. (“E3”), will result in inaccurate price signals, early and unnecessary generation resource retirements, and increased prices in the long-term.  First and foremost, however, PJM’s vehicle should not even be on the road because it does not comply with well-established law.

The IRAS Proposal fails to comply with PJM’s Operating Agreement and the Federal
Power Act (“FPA”).2  PJM claims that New Large Load is not similarly situated to other load, including existing Large Load, and thus is not unduly discriminated against under the IRAS Proposal.  PJM’s argument is erroneous and conclusory.  PJM cannot explain how New Large Load is uniquely situated in the context of procuring new capacity and emergency curtailment.  In

1 Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515-000 (filed Aug.13, 2026) (“IRAS Proposal”).
2 16 U.S.C. § 824d(b) (2024) (prohibiting the Federal Energy Regulatory Commission from approving discriminatory tariffs); PJM Operating Agreement, Schedule 1, section 1.7.11(a) (“The standards, policies and procedures of the Office of the Interconnection for declaring the existence of an Emergency, including but not limited to a Minimum Generation Emergency, and for managing, alleviating or ending an Emergency, shall apply to all Members on a non-discriminatory basis.”) (emphasis added).

PDF page 2

2

fact, PJM’s Operating Agreement requires the grid operator to apply emergency procedures “to all Members on a non-discriminatory basis.”3  The IRAS Proposal, contrary to the Operating Agreement, singles out New Large Load for curtailment during NERC Emergency Energy Alert Level 1 (“EEA1”) periods even before Demand Resources that have previously agreed to curtail.4 PJM’s claim that the States retain “exclusive jurisdiction” to determine which specific New Large Load customers will be curtailed is also unavailing.5  PJM proposes to single out which customers to curtail but leave the final “flip the switch” decision to the States.  A State is not truly exercising its “exclusive jurisdiction” if the only decision it is left with is to take the action PJM directs or not act at all.  In effect, PJM is creating an unduly discriminatory tariff regime that unlawfully encroaches on the States’ exclusive jurisdiction.  This is patently unjust and unreasonable.

The IRAS Proposal does not make economic sense either and will not result in the long- term stability that PJM is seeking.  Zachary Ming of E3 explains in his attached testimony that the IRAS Proposal will have “knock-on effects” resulting in uneconomic outcomes and diminished reliability in the long-term.6  Specifically, excluding New Large Load7 from the Variable Resource Requirement (“VRR”) Curve artificially limits competition in the existing capacity market.8  The result will initially be a capacity clearing price that fails to equal net Cost of New Entry (“CONE”),

3
Id.
4
IRAS Proposal at 78-79 (citing PJM Manual 13, section 2.3.1).
5
Id. at 90.
6
See Exhibit A at 20, Testimony of Zachary Ming, Energy and Environmental Economics, Inc. (Sept. 3, 2026) (“Ming Testimony”).

7
Capitalized terms not otherwise defined herein shall have the meaning provided thereto in the IRAS Proposal. 8

See Ming Testimony at 27.

PDF page 3

3

which will lead to a reduced incentive to invest in the existing generation fleet and potentially early retirement of existing resources that are limited to the existing capacity market.9  Therefore, the paradoxical result of PJM’s IRAS Proposal will be increased societal costs and decreased system reliability.

Talen Energy Corporation (“Talen”) agrees that PJM capacity market reform is necessary. The IRAS Proposal is just not the solution.  PJM conducted several Critical Issue Fast Path processes over the past year to address capacity shortfalls and large load demand.  The result of that effort were dozens of rejected proposals, including eleven proposals related to PJM’s “connect and manage” construct—the predecessor to IRAS.10  PJM’s Board eventually overruled the stakeholders’ rejections and moved forward with the rebranded “IRAS” Proposal nonetheless.11 Talen supports holistic market reform that is non-discriminatory, legally durable, and methodical, with short-term and long-term implications in mind.  Such holistic reform should focus on increasing supply in the PJM region by incentivizing new generation resources to come online inside the existing reliability pricing model (“RPM”) structure.  The IRAS Proposal is premature and permanent and should not be adopted because it will circumvent much needed holistic reform.12  Talen respectfully submits this protest (“Protest”) to the IRAS Proposal accordingly13

9 Id. at 28.
10  Stakeholder Process on Backstop Procurement and Connect and Manage Moves Forward, PJM INSIDE LINES (July 1, 2026), available at https://insidelines.pjm.com/stakeholder-process-to-procure-generation-and-serve- large-loads-moves-forward/.
11  See Brooks, Michael and Leith-Yessian, Devin, PJM to Create Large Load Registry, Proposes to Hold Backstop Auction in October, RTO INSIDER (July 28, 2026), available at https://www.rtoinsider.com/137723-pjm-to-create- large-load-registry-proposes-backstop-auction/.
12  See Ming Testimony at 25.
13  Talen is filing this protest pursuant to Rule 211 of FERC’s Rules of Practice and Procedure.  18 C.F.R. § 385.211 (2026).

PDF page 4

4

and requests that the Federal Energy Regulatory Commission (“FERC” or “Commission”) reject PJM’s filing as unjust, unreasonable, and unduly discriminatory.

I. MOTION TO INTERVENE
Pursuant to Rule 214 of the Commission’s Rules of Practice and Procedure,14 Talen respectfully submits this motion to intervene in the above-captioned proceeding.  The formal legal name of Talen is Talen Energy Corporation.  Talen is a corporation organized and existing under the laws of Delaware.  Talen maintains its principal place of business at 2929 Allen Parkway, 22nd Floor, Houston, Texas 77019. Talen is a leading independent power producer and energy infrastructure company which owns and operates approximately 15.7 gigawatts of power infrastructure in the United States.  Talen produces and sells electricity, capacity, and ancillary services into wholesale U.S. power markets, including and primarily in PJM.  Accordingly, the actions taken by the Commission in this matter will directly affect the interests of Talen.  Talen has a direct and material interest in the instant proceeding that no other party can adequately represent.  Talen therefore requests that the Commission grant this motion to intervene and permit Talen to participate in this proceeding with full rights as a party thereto.

II. PROTEST
The existing RPM construct was designed to improve price stability, enhance reliability, and produce accurate price signals to incentivize new generation build.15  The U.S. Supreme Court observed that

[t]he capacity auction serves to identify the need for new generation:
A high clearing price in the capacity auction encourages new
generators to enter the market, increasing supply and thereby
lowering the clearing price in the same-day and next-day auctions

14  18 C.F.R. § 385.214.
15  PJM Interconnection, L.L.C., 117 FERC ¶ 61,331 at PP 68-69 (2006) (internal citation omitted).

PDF page 5

5

three years’ hence; a low clearing price discourages new entry and
encourages retirement of existing high-cost generators.16
PJM has adapted its approach to capacity auctions over past decades to produce more accurate and defined price signals.  For example, PJM’s historical Capacity Credit Market (“CCM”) was replaced by the reliability pricing model (“RPM”) twenty years ago because the CCM did “not enable market participants to see the reliability problems in particular locations” and did “not provide price signals that would elicit solutions to reliability problems in enough time before the problem occurs. . . .”17  If the goal is to produce accurate price signals that send clear messages to new generation to build or to existing and costly generation to retire, then the market—a simulated competitive construct—cannot perform efficiently if PJM interferes with the capacity auctions by implementing artificial caps on supply and demand.  Yet, that is the imprudent design and purpose of the IRAS Proposal.

A. PJM’s proposal to require New Large Loads to procure new capacity or be
subject to curtailment is unjust, unreasonable, and unduly discriminatory, and unlawfully encroaches on State jurisdiction.

Section 205(b) of the FPA prohibits the Commission from approving unjust, unreasonable, and unduly discriminatory tariffs.18  The regulated utility, as the movant under FPA Section 205, carries the burden of proof that its proposal is just and reasonable and not unduly discriminatory “[b]ecause a regulated utility is the party with access to the necessary information [and] bears the risk of an undeveloped or inconclusive record.”19 “Discrimination is undue when there is a

16  Hughes v. Talen Energy Mktg., 136 S. Ct. 1288, 1293 (2016).
17  PJM Interconnection, L.L.C., 117 FERC ¶ 61,331 at P 20.
18  16 U.S.C. § 824d(b).
19  Nantahala Power & Light Co. v. FERC, 727 F.2d 1342, 1351 (4th Cir. 1984); 16 U.S.C. § 824d.

PDF page 6

6

difference in rates or services among similarly situated customers that is not justified by some legitimate factor.”20

The Commission has explained that similarly situated does not mean that customers must be without difference.21  Rather, “it means that there are no differences that are material to the inquiry at hand.”22  The Commission has also held that “entities are similarly situated if they are in the same position with respect to the ends that the law seeks to promote or the abuses that it seeks to prevent, even if they are different in many other respects.”23  For example, in Calpine Oneta Power, L.P.,24 the Commission held that new and existing generators were similarly situated for purposes of providing reactive power because they were equally capable of providing that service.25  In Iberdrola Renewables, Inc. v. Bonneville Power Admin.,26 the Commission held that “non-[f]ederal resources are similarly situated to [f]ederal hydroelectric and thermal resources for purposes of transmission curtailments because they all take firm transmission service.”27 The purpose of the IRAS Filing is to address a capacity shortfall, which means procuring new capacity and curtailing load during emergency events.  Most load can procure new capacity prior to and after commencing service.  Moreover, requiring curtailment of New Large Load in the

20  El Paso Natural Gas Co., 104 FERC ¶ 61,045, at P 115 (2003), reh’g denied, 106 FERC ¶ 61,233 (2004) (internal citations omitted).
21  New York Independent System Operator, 162 FERC ¶ 61,124 at P 10 (2018).
22  Id.
23  Id. 24  116 FERC ¶ 61,282 (2006) (“Calpine Oneta”).
25  Id. at P 36. 26  137 FERC ¶ 61,185 (2011) (“Iberdrola”).
27  Id. at P 62.

PDF page 7

7

broad sense fails to take into consideration both that not all New Large Load is so flexible and that certain load other than New Large Load is also capable of electing to curtail.  PJM’s proposed disparate treatment of New Large Load is therefore unjust, unreasonable, and unduly discriminatory.

1. PJM’s requirement that only New Large Load execute contracts with
BYONC resources or be subject to curtailment is unjust, unreasonable, and
unduly discriminatory.
PJM is only requiring New Large Load to contract with BYONC resources to avoid
curtailment.  PJM does not dispute this disparate treatment.  Instead, PJM attempts to argue that New Large Load is not similarly situated to any other load.  What PJM means is that the IRAS Proposal admittedly discriminates against New Large Load, but PJM does not believe it is “undue” discrimination.  PJM is mistaken.  The evidence presented by PJM to justify its argument is limited to two statements:  (1) members of Congress have said that it would not be unduly discriminatory to treat data centers differently given their “incomparably large energy demands, how quickly data centers can come online, and their unique potential to impact the reliability of the electric grid”;28 and (2) an out-of-context statement by the Commission  that “large loads constitute ‘a separate category of load’ because of their “size, operational behavior, and unique potential to impact the transmission system.”29  However, these are mere differences in customer profiles and cannot support a finding of differences “that are material to the inquiry at hand.”30  The inquiry at hand is

28  IRAS Proposal at 95-96 (citing Letter from the Members of Congress to David E. Mills, PJM Board Chair, PJM Interconnection, L.L.C., 4 (Nov. 5, 2025), https://www.pjm.com/-/media/DotCom/about-pjm/who-we- are/publicdisclosures/2025/20251106-congressional-letter-re-cifp-lla.pdf [https://perma.cc/ZKA9-Q5LZ]).

29  IRAS Proposal at 95-96 (citing PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 50 (2026) (“PJM June 2026 Order”)).
30  See New York Independent System Operator, 162 FERC ¶ 61,124 at P 10.

PDF page 8

8

which loads are capable of bringing their own new capacity and which loads are capable of electing to curtail in emergency events.

Nearly all new commercial load is capable of procuring new capacity.  PJM does not limit bilateral capacity markets to specific customers, nor does PJM limit capacity transactions to only large loads.  In fact, PJM’s Capacity Exchange system allows unit-specific bilateral transactions of as little as 0.1 MW.31  This means that New Large Load, existing Large Load, new commercial load, and others are “in the same position with respect to the ends that” the IRAS Proposal “seeks to promote.”32

Resources beyond just New Large Load are also capable of electing to curtail service during emergency events, e.g., large commercial industrial customers and existing Large Load. Existing Large Load is completely indistinguishable from New Large Load in this context, just as new and existing generation resources were equally capable of providing reactive power service in Calpine.33  This is also similar to federal and non-federal generation resources being equally able to curtail transmission service in Iberdrola.34  Although the customers at issue in Iberdrola were all taking firm transmission service, the only reason New Large Load would be taking a different service here, i.e., IRAS, is because PJM would force them to do so.

PJM attempts to build its argument for discriminating against New Large Load based on prior Commission language from the recent series of show cause orders issued to the six regional

31  PJM Manual 18 at Section 4.6.2.
32  See New York Independent System Operator, 162 FERC ¶ 61,124 at P 10.
33  See Calpine Oneta, 116 FERC ¶ 61,282.
34  See Iberdrola, 137 FERC ¶ 61,185.

PDF page 9

9

grid operators.35  Although the Commission proposed a definition for large load in the show cause orders, the Commission was not implying that discriminating against such large load was just and reasonable.  Moreover, the broad definition of large load that the Commission used in the show cause orders is not applicable to the inquiry at hand in this proceeding.  Even the Commission recognized in the show cause orders that only “flexible large loads that are willing and able to limit their use of the transmission system under certain conditions” should be offered a different transmission service.36  The Commission clarified that “‘flexible’ large loads are a subset of large loads, as used in [that] order, that are not co-located with generation, but are willing and able to limit their energy withdrawals from the transmission system under certain conditions.”37 Therefore, PJM’s reliance on the Commission’s recent show cause orders to discriminate against New Large Loads is misplaced.

2. Certain features of the IRAS Proposal are also unjust and unreasonable
due to PJM’s arbitrary and disparate treatment of load.
a. The IRAS Proposal arbitrarily sets an unsupported floor for New
Large Load.
The size of a particular load is irrelevant to an inquiry regarding which entities can curtail. Nonetheless, the IRAS Proposal sets a 50 MW floor for New Large Load.  PJM has not provided any justification for this disparate treatment of load, nor can it.

Take an electric arc furnace facility (steel plant) in Pennsylvania for example.  Electric arc furnaces are now the predominant method for steel production in the country and consume 40-200

35  IRAS Proposal at 96 (arguing that the Commission acknowledged that large loads are ‘a separate category of load’”) (citing PJM June 2026 Order, 195 FERC ¶ 61,211 at P 50).
36  PJM June 2026 Order at P 3.
37  Id.

PDF page 10

10

MW of electricity.38  Steel mills can temporarily shut down if needed during power shortages.39 Under the IRAS Proposal, a 50 MW electric arc furnace would be curtailed first as a New Large Load, even though a 40 MW electric arc furnace in the same region could similarly reduce its respective load (and be compensated by PJM for doing so).  There is no difference between these customers with respect to the inquiry at hand.  In fact, they are equally capable of providing the ends that PJM seeks.  Accordingly, PJM’s disparate treatment of New Large Load under the IRAS Proposal is unjust, unreasonable, and unduly discriminatory.

b. The IRAS Proposal provides PJM with unjust, unreasonable, and
unfettered discretion to issue curtailment directives.
Well-established Commission precedent provides that matters directly affecting rates must be included in an RTO’s filed tariff if the matter “significantly affects rates, terms, and conditions” of service, are readily susceptible of specification, and not generally understood in a contractual agreement.40  The IRAS Proposal provides that PJM will determine a quantity of MW that load in a zone/area needs to curtail to maintain system reliability and will instruct the Electric Distributor

38  Tita, Bob, AI Data Centers Have Been Great for The Steel Industry. Now, a Power Crisis Looms: Steelmakers Warn of Competition for Electricity From Their Newest Big Customer, WALL STREET JOURNAL (June 29, 2026), available at https://www.wsj.com/business/energy-oil/ai-data-centers-power-competition-steel-48a17dbd.
39  Id.  Other non-large load can also curtail.  For example, paper mills can act as a distributed energy resource by “burn[ing] black liquor (a paper-manufacturing byproduct) to generate electricity for their own operations or to feed back into the system.”  The Many Types of Distributed Energy Resources, Common and Obscure, PJM INSIDE LINES (Aug. 14, 2019), available at https://insidelines.pjm.com/the-many-types-of-distributed-energy- resources-common-and-obscure/.
40  Energy Storage Ass’n v. PJM, 162 FERC ¶ 61,296 at P 103 (2018) (“Energy Storage Ass’n”) (citing Midcontinent Indep. Sys. Operator, Inc., 158 FERC ¶ 61,003 at P 69 (2017); PacifiCorp, 127 FERC ¶ 61,144 at P 11 (2009); City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (finding that utilities must file “only those practices that affect rates and service significantly, that are reasonably susceptible of specification, and that are not so generally understood in any contractual arrangement as to render recitation superfluous”); Public Serv. Comm'n of N.Y. v. FERC, 813 F.2d 448, 454 (D.C. Cir. 1987) (holding that the Commission properly excused utilities from filing policies or practices that dealt with only matters of “practical insignificance” to serving customers);  Midwest Indep. Trans. Sys. Operator, Inc., 98 FERC ¶ 61,137, at 61,401 (2002), clarification granted, 100 FERC ¶ 61,262 (2002) (“It appears that the proposed Operating Protocols could significantly affect certain rates and services and as such are required to be filed pursuant to Section 205.”)).

PDF page 11

11

to curtail such MW quantity, which will be equal to or less than the Eligible New Large Load Amount.41  The IRAS Proposal is silent, however, with respect to how PJM will determine the MW quantity to be curtailed or which Electric Distributors will be instructed to curtail.  The ability to curtail load and the potential to receive IRAS payments for such action certainly and significantly affects the rates, terms, and conditions of IRAS.  PJM must also have a process that is capable of being translated in written form to make such determinations and include those determinations in its Tariff.  Moreover, this proposal is a novel construct introduced for the first time by PJM and is not generally understood under traditional Tariff contractual arrangements. Therefore, under FERC’s “rule of reason” doctrine, PJM must include specific language regarding how it will determine the MW quantity to be curtailed and which Electric Distributors it will instruct to do so.  The potential for arbitrary and capricious decision-making in PJM’s process is too great to move forward without such specification.  Load being served under IRAS cannot make informed commercial decisions if it must read tea leaves to determine when and how much it will be curtailed in a region-wide reliability event.

PJM carries the burden to prove that the IRAS Proposal is just and reasonable.42  The economic reality of the IRAS Proposal is that it will result in inaccurate price signals, early and unnecessary generation retirements, increased prices in the long term, and its implementation will be left to an opaque process known only to PJM.  The Commission cannot find such results to be just and reasonable and thus must reject the IRAS Proposal.

41  IRAS Proposal at 86-87 (defining Eligible New Large Load Amount as “the MW value of load that an Eligible New Large Load in a given zone/area may be required to be made available to IRAS.”).
42  See 16 U.S.C. § 824d.

PDF page 12

12

c. The IRAS proposal fails to account for New Large Load that
previously contracted for capacity from existing resources.
Chairman Laura Swett assured stakeholders that the Commission’s actions with respect to large load reforms and procedures “are not intended to disrupt existing commercial agreements.”43 Talen has previously explained that PJM’s reliability backstop procurement (“RBP”) proposal would result in such load paying incremental capacity charges under the RBP.44  This is harmful to the entire market because “uncertainties regarding rate stability and contract sanctity can have a chilling effect on investments and a seller’s willingness to enter into long-term contracts and this, in turn, can harm customers in the long run.”45  PJM is inserting additional uncertainty into the market through the forced interruption of service to certain New Large Loads that are not allocated RBP capacity and costs.  Accordingly, the IRAS Proposal fails to even treat New Large Load on a consistent basis and unjustly introduces a chilling effect on investments in PJM.

3. PJM’s directive to curtail New Large Load unlawfully commandeers the
States’ exclusive jurisdiction.
The FPA properly establishes the Commission’s jurisdiction over wholesale activity, while States retain their exclusive jurisdiction to regulate retail transactions.46  The FPA follows the Tenth Amendment of the U.S. Constitution, which provides that “[t]he powers not delegated to the United States by the Constitution, nor prohibited by it to the States, are reserved to the States

43  Statement of FERC Chairman Laura Swett, FERC Open Meeting (June 18, 2026) at 10:42, https://ferc.gov/news- events/events/june-18-2026-open-meeting-10082025.
44  Motion to Intervene and Request for Clarification of Talen Energy Corporation, Docket No. EC26-3380-000 (filed Aug. 21, 2026).
45  Market–Based Rates for Wholesale Sales of Electric Energy, Capacity and Ancillary Services by Public Utilities, Order No. 697, 72 Fed. Reg. 39,904, 119 FERC ¶ 61,295, at P 6 (2007).
46  16 U.S.C. § 824(b).

PDF page 13

13

respectively, or to the people.”47  This does not mean the Commission cannot take action that would indirectly impact retail rates or State regulatory practices.  Such is an inevitability in an industry subject to multiple jurisdictions.  However, there are limits on the Commission’s ability to impact State practices.

The U.S. Supreme Court has clarified the “anti-commandeering doctrine” over years of precedent.  Most pertinent here, in New York v. United States,48 the Court held that “Congress may not commandeer the States’ legislative processes by directly compelling them to enact and enforce a federal regulatory program . . . .”49  In that case, Congress passed a law requiring States to either establish nuclear waste disposal sites or, if a State chose not to establish such waste sites, the State would be required to take title to the waste and be liable for any damage to the generator or owner as a result of the State’s failure to take prompt possession.  The option to establish waste sites was encouraged through monetary incentives.  The Court held that this choice “would effectively ‘commandeer’ States into the service of federal regulatory purposes” and in reality “the States’ ‘choice’ is no choice at all.”50

The IRAS Proposal similarly leaves States with no “choice.”  PJM claims that its proposal does not infringe on States’ exclusive jurisdiction because the decision “rests with the [S]tates to ensure that the appropriate retail customers, i.e., New Large Loads, including data centers—and not residential customers or small industrial customers—are reduced when system conditions call

47  U.S. Const., 10th Amen.
48  505 U.S. 144 (1992).
49  Id. at 145.
50  Id. at 146 (internal citations omitted).

PDF page 14

14

for PJM to require load reductions according to IRAS.”51  However, PJM also explains that the entities directing load reductions “will be guided by the Large Load Registry.”52  In other words, PJM will provide the incentive and tools to curtail a specific class of customers, but argues that its hands are clean because it does not make the ultimate decision.  The ultimate decision is left to States, LSEs, and Electric Distributors or, if these entities do not act accordingly, residential customers and other small industrial load will bear additional costs in a manner inconsistent with cost causation principles.  This is not a “choice” at all.  Rather, PJM has commandeered State regulatory constructs and entities to implement its IRAS Proposal.  Such a result cannot stand under the Constitution and well-established precedent.

PJM relies heavily on the Ratepayer Protection Pledge53 and the Statement of Principles Regarding PJM, which was signed by 13 governors of the PJM States, to justify the IRAS Proposal.54  Notwithstanding PJM’s reliance on these sources, they do not supersede the Constitution.  Even if the governors of each State publicly supported the IRAS Proposal, the IRAS Proposal would still run afoul of the anti-commandeering doctrine.  The Court in New York v. United States explained there that New York officials’ support of the legislation was irrelevant because “[t]he Constitution does not protect the sovereignty of States for the benefit of States or state governments . . . [t]o the contrary, the Constitute divides authority between federal and state

51  IRAS Proposal at 90-91.
52  Id. at 92.
53  See, e.g., id. at 4 (citing Ratepayer Protection Pledge, The White House (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ ratepayer-protection-pledge/ [https://perma.cc/N8PH-K82T] (“Ratepayer Protection Pledge”)).
54  Id. at 6.

PDF page 15

15

governments for the protection of individuals.”55  Thus, the Court held, “departure from the constitutional plan cannot be ratified by the ‘consent’ of state officials.”56  So too here, the Ratepayer Protection Pledge and Statement of Principles, while informative, cannot usurp the principles of federalism.  The IRAS Proposal rests on a quasi-federal governmental entity commandeering the role of States by directing curtailment of a class of end-use customers.  PJM will dispute this claim based on the “choice” presented to States, LSEs, and Electric Distributors, but the choice is illusory at best.

PJM’s argument cannot find refuge under EPSA either.57  The Court in that case held that the Commission’s regulation of demand response as permissible because it only addressed “transactions occurring on the wholesale market” and was intended to “enhance the wholesale, not retail, electricity market.”58  The IRAS Proposal is not so limited here.  The IRAS Proposal requires Electric Distributors to coordinate with PJM on developing and maintaining the Large Load Registry, including by providing applicable state retail tariffs or contractual obligations.59  PJM even acknowledges that the implementation of the compensation scheme under IRAS “relies on application of state retail law.”60 Any one of these issues is fatal to the legality of the IRAS Proposal and, taken in the aggregate, the IRAS Proposal is certainly an overstep and encroachment

55  New York v U.S., 505 U.S. at 181.
56  Id. at 182.
57  See IRAS Proposal at 91 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 266 (2016) (“EPSA”).
58  EPSA, 577 U.S. 282, 287.
59  IRAS Proposal at 26.
60  Id. at 106.

PDF page 16

16

on States’ exclusive jurisdiction.  As a result, the Commission must reject the IRAS Proposal as unjust and unreasonable.

B. Even if the IRAS Proposal stood on solid legal ground—which it does not—
the proposal is unjust and unreasonable because it will ultimately result in
increased costs and could lead to further unduly discriminatory behavior.
It is a well-accepted economic principle that competitive markets result in fair prices for goods, incentivize innovation, and encourage overall market efficiency, as further described in the attached Affidavit of Zachary Ming.61  Such markets, however, are difficult to develop organically in industries with high cost of entry.  Governmental or quasi-governmental organizations may design and oversee regulated markets under operational parameters that the regulators believe would simulate the results that a competitive market would produce.  PJM’s capacity market is a prime example of such a simulated market.  The simulated market results will inevitably start to diverge from true competitive market outcomes as more artificial interference is introduced to the market design.  The IRAS Proposal and its ultimate impact on PJM’s capacity market is no exception.  The IRAS Proposal will result in reduced competition, increased pricing, and new entry of uneconomic resources.62

1. The IRAS Proposal will reduce competition in a simulated market that is
designed to replicate competition.
PJM proposes to exclude New Large Loads “from the VRR Curve starting with the
2029/2030 Delivery Year, regardless of whether PJM is experiencing a shortfall that triggers IRAS in the relevant Delivery Year,” unless the New Large Load has entered into a bring your own new capacity (“BYONC”) arrangement.63  What this means practically is that there will be separate

61  See Ming Testimony at 7.
62  See id. at 26.
63  IRAS Proposal at 110.

PDF page 17

17

markets for indistinguishable capacity.64  Existing resources will be subject to the artificially limited RPM market and new capacity will naturally seek more valuable bilateral contracts with New Large Load in the bilateral (out-of-) market.  This prevents two identical resources from competing head-to-head.

The IRAS Proposal involves removing New Large Load demand from the existing RPM market in an attempt to lower base residual auction (“BRA”) and incremental auction clearing prices in the near-term.  As the Supreme Court has recognized, lower clearing prices discourage new investment and encourage retirement of existing generators.65  PJM is aware of this undesirable effect of its proposal.  In fact, with respect to the IRAS Proposal’s predecessor, “connect and manage,” PJM explained that it would not remove connect and manage load from the RPM market because “including connection and manage [load] in the RPM Auction continues to provide price signals for new investment . . . .”66  Despite this logical conclusion reached by PJM only three months prior to filing the IRAS Proposal, PJM has reversed course and will now allow this exact scenario to play out.

Under this predictable scenario, existing resources will receive a clearing price in the BRA and incremental auctions that may fail to equal net CONE, resulting in the existing resources no longer being economic.67  In the other artificial and inflated New Large Load market, the contract prices available to new resources will be greater than the RPM clearing prices.  New resources will

64  See Ming Testimony at 16 (explaining the market available to New Large Load and the market available to “all other loads”).
65  Hughes, 136 S. Ct. at 1293.
66  Ming Testimony at 25 (citing Connect and Manage PJM Package, PJM (May 27, 2026), available at https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-item-04--- connect-and-manage-pjm-package---pjm-presentation.pdf)).
67  Id. at 18, 20-21.

PDF page 18

18

logically choose to enter more profitable, bilateral New Large Load market rather than compete in the BRA.68  This will create real challenges for existing generation.

It may very well be the case that it is less expensive for an existing generator to invest in retrofits or repowerings of active but aging resources than it is for a new generator to come online; however, the artificially suppressed BRA clearing price will make such investments in existing generation uneconomic, while new generation can recoup its investment through bilateral contracting.69  It will not take long for residential ratepayers to feel the results.

2. The IRAS Proposal will ultimately result in increased prices.
Early retirement of existing resources, a market clearing price that begins to clear at less than net CONE,70 and the incentivization for new capacity to bilaterally contract with New Large Load will diminish the reliability of PJM’s system.  PJM will then have a limited set of levers to pull.  It may run another backstop procurement auction (again resulting in the allocation of reliability backstop procurement costs across LSE zone/areas), enter into off-market reliability must run contracts with generators to stave off retirement, or increase the demand curve to restore a long-run average price of net CONE.71  Each of the levers will increase prices.  Therefore, any theoretical consumer savings from the initial price suppression in the BRA resulting from the IRAS Proposal are temporary vapors because the IRAS Proposal will end up costing consumers more in the long run.

68  Although the IRAS Proposal requires the New Large Load and new capacity to enter the RPM once there is a binding contract between the two, this will not rectify the damage to the RPM market. The entry of load and corresponding capacity will be a wash, i.e., the benefit of the new supply will be negated by the impact of the increased demand from New Large Load.
69  Ming Testimony at 28.
70  Id. at at 27-28.
71  Id. at 22.

PDF page 19

19

3. The IRAS Proposal could result in the uneconomic entry of new
generation.
As explained above, the new bilateral market for New Large Load will result in increased prices for such capacity.  There are several plausible scenarios under which IRAS could incentivize New Large Load to procure such BYONC, even though it is unnecessary and inefficient from a PJM system standpoint.  For example, PJM could implement IRAS because of a near-term capacity shortfall.  New Large Load would procure BYONC resources to avoid being curtailed.  The capacity shortfall may be alleviated in a year or two, but the BYONC resource is contracted at a higher rate for 20 years.  In this scenario it would have been more economically efficient to increase the capacity shortfall for a limited year or two rather than increase the capacity surplus for a larger number of years.72

Simply put, PJM has not satisfied its burden to demonstrate that the IRAS Proposal is not unjust, unreasonable, or unduly discriminatory. The Ming Testimony and its application of the IRAS Proposal to realistic and predictable hypotheticals actually demonstrate the opposite.  The Commission must reject the IRAS Proposal accordingly.

72  See id. at 26.

PDF page 20

20

III. CONCLUSION
PJM needs to go back to the drawing board to develop significant and more holistic capacity market reforms that encourage accurate market pricing signals, can be implemented on a non-discriminatory basis, and provide PJM customers with a safe and reliable future.  That may take the form of longer forward-term BRAs, e.g., 5 years in advance of the Delivery Year rather than 3 years, to allow new capacity to respond to accurate market pricing signals, and additional review of the VRR Curve and must-offer rules.  Talen does not imply that this is an easy task; however, this is the burden that the operator of the largest capacity market in the country carries. Talen looks forward to working with PJM and FERC on such reforms.

The IRAS Proposal is not the reform PJM needs.  Simply put, the IRAS filing is unjust and unreasonable for the reasons discussed herein.  Talen respectfully submits this Protest accordingly and requests that the Commission reject the IRAS Proposal in its entirety.

       Respectfully Submitted,
 /s/ Jennifer Mansh

Jennifer Mansh
Senior Vice President, Regulatory
Counsel
Talen Energy Corp.
600 Hamilton Street, Suite 600
Allentown, PA 18101
Jennifer.Mansh@talenenergy.com
 /s/ John Decker

John Decker
Andrew DeVore
Cassidy Hall
Kirkland & Ellis LLP
1301 Pennsylvania Avenue, N.W.
Washington, D.C. 20004
(202) 389-3470
(202) 389-3117
John.decker@kirkland.com
andrew.devore@kirkland.com
cassidy.hall@kirkland.com

Counsel for Talen Energy Corporation

Dated: September 3, 2026

PDF page 21

EXHIBIT A
TESTIMONY OF ZACHARY MING
ENERGY AND ENVIRONMENTAL ECONOMICS, INC.

PDF page 22

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
Testimony of Zachary Ming
 Partner
Energy and Environmental Economics, Inc.
On behalf of
Talen Energy Corporation
September 3, 2026

PDF page 23

2
Table of Contents
1
Introduction … 3 2

Background and Overview of IRAS … 6 3

Economic Impact of IRAS … 16 4

Recommendations & Summary … 28

PDF page 24

3
Talen Energy Corporation
1

2
PJM Interim Resource Adequacy Service
3

4

5
Testimony of Zachary Ming, Partner, Energy and Environmental Economics, Inc. 6

1 Introduction
7
Q1.
PLEASE STATE YOUR NAME, OCCUPATION, AND BUSINESS
8
ADDRESS.
9
A1.
My name is Zachary Ming. My current position is Partner at Energy and 10

Environmental Economics, Inc. (“E3”). My business address is 44 Montgomery 11

Street Suite 1250, San Francisco, California 94104.
12
Q2.
PLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY.
13
A2.
I am filing this testimony as an independent expert, and it represents my own 14

positions and perspectives. This testimony was funded by Talen Energy 15

Corporation (“Talen”).
16
Q3.
PLEASE DESCRIBE YOUR PROFESSIONAL BACKGROUND AND
17
EXPERIENCE.
18
A3.
I received a B.S. in Civil and Environmental Engineering (Atmosphere and Energy 19

program) with a Minor in Economics, and an M.S. in Management Science and 20

Engineering (Energy track), both from Stanford University. For thirteen years I 21

have held various roles at E3, an energy consulting firm specializing in the 22

economics of the electricity system where I am currently a Partner. In addition to 23

PDF page 25

4
full-time consulting work at E3, I teach a graduate-level course at Stanford 1

University titled Electricity Economics.
2
Q4.
PLEASE DESCRIBE YOUR QUALIFICATIONS AS IT RELATES TO THE
3
TOPICS OF RELIABILITY, CAPACITY MARKET DESIGN, AND
4
GENERATION INVESTMENT ECONOMICS.
5
A4.
In my role as Partner at E3, I oversee projects across a number of areas including 6

reliability, capacity market design, and generation investment economics. I have 7

authored several reports related to reliability that evaluate the most cost-effective 8

pathway to meeting long-term system needs, including Resource Adequacy for the 9

Energy Transition: A Critical Periods Reliability Framework and its Applications 10

in Planning and Markets,1 Assessment of Market Reform Options to Enhance 11

Reliability of the ERCOT System,2 and Long-Run Resource Adequacy under Deep 12

Decarbonization Pathways for California.3  I have worked on resource adequacy 13

and capacity market design topics in PJM, MISO, ERCOT, CAISO, NYISO, and 14

ISO-NE. I have worked with generators, developers, investors, and utilities in 15

assessing the economics of new generation opportunities. Most broadly, I lead E3 16

teams that help develop system-wide solutions that are both economic and reliable. 17

1 Energy & Environmental Economics, Inc., Critical Periods Reliability Framework, E3 (Aug. 2025), https://www.ethree.com/wp-content/uploads/2025/08/E3_Critical-Periods-Reliability-Framework_White- Paper.pdf.
2 Energy & Environmental Economics, Inc., Assessment of Market Reform Options to Enhance Reliability of the ERCOT System (Nov. 10, 2022), https://www.ethree.com/wp-content/uploads/2023/05/E3- PUCT_Assessment-of-Market-Reform-Options-to-Enhance-Reliability-of-the-ERCOT-System_11.10.22- Sent.pdf.
3 Energy & Environmental Economics, Inc., Long Run Resource Adequacy under Deep Decarbonization Pathways for California (June 2019), https://www.ethree.com/wp- content/uploads/2019/06/E3_Long_Run_Resource_Adequacy_CA_Deep-Decarbonization_Final.pdf.

PDF page 26

5
Q5.
HAVE YOU PREVIOUSLY TESTIFIED BEFORE THE FEDERAL
1
ENERGY REGULATORY COMMISSION (“FERC”)?
2
A5.
Yes, I have testified multiple times before FERC. My previous testimony has 3

covered various topics related to rate design and wholesale markets in PJM, 4

including the capacity market price cap,4 the participation of reliability must run 5

(“RMR”) units in the capacity market,5 PJM’s filing to use marginal effective load 6

carrying capability (“ELCC”) as the basis for resource accreditation in the capacity 7

market,6 and co-location rate design.7 I have also testified before FERC on behalf 8

of MISO in their proposal to implement the direct loss of load (“DLOL”) 9

methodology for resource accreditation8 and on the topic of ISO-NE’s “Pay-for- 10

Performance” capacity market construct. 9 Additionally, I have testified before 11

state, provincial, and territorial public utility commissions in Oregon, Texas, South 12

Carolina, Colorado, New Brunswick, and Puerto Rico on topics relating to 13

reliability, resource adequacy, market design, and rate design.
14
Q6.
WHAT IS THE PURPOSE OF THIS TESTIMONY?
15
A6.
The purpose of my testimony is to illustrate how the Interim Resource Adequacy 16

Service (“IRAS”), despite being designed as a means to “protect residential 17

customers from capacity price increases” actually does the opposite. 10  I 18

4 Docket EL25-46-000.
5 Docket EL24-148.
6 Docket ER24-99-000.
7 Dockets EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000.
8 Docket ER24-1638. 9 Docket EL25-106-000. 10 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry, at 5, FERC Docket No. ER26-3515-000, August 13, 2026, accession no. 20260813-5118, https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20260813-5118&optimized=false. [hereinafter PJM Filing]

PDF page 27

6
demonstrate how IRAS creates an expectation of reduced future capacity market 1

prices which reduces new investment and retention of existing resources. The 2

paradoxical impact of this is higher prices and lower reliability. I conclude with the 3

recommendation that FERC should reject PJM’s IRAS proposal.
4
Q7.
PLEASE PROVIDE AN OUTLINE OF YOUR TESTIMONY.
5
A7.
My testimony is organized as follows:
6
• In Section 2, I provide background on the PJM capacity market, including how 7

PJM uses price signals to incent the entry of new resources and retention of 8

existing resources. I also provide an overview of salient features of PJM’s 9

proposed IRAS;
10
• In Section 3, I illustrate the economic impacts of IRAS, including how it would 11

1) reduce new investment and retention of existing resources and 2) hinder 12

competition between resources serving new large loads and existing loads. I 13

demonstrate how both factors increase societal costs, increase consumer prices, 14

and decrease reliability; and
15
• In Section 4, I summarize my arguments and recommendations.
16
2 Background and Overview of IRAS
17
Q8.
PLEASE PROVIDE AN OVERVIEW OF HOW PJM ENSURES
18
RESOURCE ADEQUACY.
19
A8.
PJM’s principal means of ensuring resource adequacy is the Reliability Pricing 20

Model, more colloquially known as the PJM capacity market. The capacity market 21

PDF page 28

7
provides price signals to secure sufficient capacity to satisfy PJM’s reliability 1

standard.11
2
Q9.
HOW DO PRICE SIGNALS SECURE SUFFICIENT CAPACITY?
3
A9.
The capacity market is designed to provide the additional revenues that generation 4

resources require to recover their full costs beyond what they earn in the energy 5

and ancillary service markets. Without this additional revenue, investors in 6

generation would not recover their full costs and would reduce investment in both 7

new generation and in retention of existing generation. Specifically, the required 8

additional revenue is the net Cost of New Entry (“net CONE”).
9
The capacity market is designed to run once per year, and prices fluctuate 10

on a year-to-year basis based on supply and demand. A capacity market designed 11

to produce an average price of net CONE in the long-run provides sufficient 12

revenues for investors to recover their full costs and sends the signal that they 13

should invest.
14
Q10. PLEASE DESCRIBE THE MECHANISM USED TO DETERMINE
15
CAPACITY MARKET PRICES IN ANY GIVEN YEAR.
16
A10. PJM determines capacity market prices each year based on the intersection between 17

an administratively-determined demand curve and a supply curve formed from 18

supplier bids. The demand curve is also known as the Variable Resource 19

Requirement (“VRR”) curve.
20

11 In PJM, the specified resource adequacy target is 0.1 days/year loss of load expectation (“LOLE”). This target aims to ensure that loss-of-load events should occur no more frequently than one day in every ten years.

PDF page 29

8
The VRR curve is defined by three points that PJM calls A, B, and C, which 1

are derived for each auction using multiple key inputs:
2
• The estimated gross Cost of New Entry (“CONE”) for a selected 3

reference technology;
4
• A forecast of the reference technology’s net energy and ancillary service 5

revenues expected from the PJM market; and
6
• PJM’s reliability requirement expressed in unforced capacity (“UCAP”) 7

MW.
8
Gross CONE reflects the annualized capacity and fixed operating cost of 9

the reference technology and is the total amount of revenue that a new resource 10

would need to recover to justify entering the market. Estimated net energy and 11

ancillary service revenues are subtracted from gross CONE to calculate net CONE, 12

which is the amount of revenue that a new resource would need to recover through 13

the capacity market after accounting for net revenues earned in PJM’s other 14

markets. The reliability requirement is the amount of UCAP MW capacity needed 15

to achieve the reliability standard.
16
Points A, B, and C are calculated for each auction using these core 17

parameters. For the latest auction for the 2028/2029 Delivery Year (held in July 18

2026), these points were calculated using the following formulas: 19

A. For a UCAP MW quantity equal to 99% of the reliability requirement, the 20

price is equal to the greater of (i) 1.15 times gross CONE minus 0.75 times 21

energy and ancillary service revenues and (ii) 0.20 times gross CONE. 22

PDF page 30

9
B. For a UCAP MW quantity equal to 101.5% of the reliability requirement, 1

the price is equal to half of the price value used for point A.
2
C. For a UCAP MW quantity equal to 106% of the reliability requirement, the 3

price is equal to zero.12
4
In the case of the 2028/2029 Delivery Year auction, there was an additional 5

final step where both a price cap of $325/MW-day and price floor of $175/MW- 6

day were applied to the curve.13 This demand curve is illustrated in the figure 7

below.
8
Figure 1: VRR curve used by PJM in the BRA (Not to Scale)
9

10
Q11. PLEASE DESCRIBE THE INTENDED GOAL IN STRUCTURING THE
11
DEMAND CURVE.
12
A11. The demand curve is designed to accomplish two goals. First, it is structured to 13

deliver dynamic price signals such that prices rise when the system needs additional 14

12 PJM OATT § 5.10.a.ii.
13 PJM Interconnection L.L.C, 2028/2029 BRA Supply Curves(July 17, 2026), https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-supply-curves.pdf.

PDF page 31

10
capacity and vice versa. Second, it is designed to deliver an average long-run price 1

of net CONE (i.e., the “reference price”) across many years. An investor must 2

expect that the capacity market will deliver this long-run average net CONE price 3

to invest in new capacity. PJM designs the demand curve such that some years will 4

yield prices higher than net CONE, some years would yield lower prices, but prices 5

would average to net CONE across all years. This is illustrated in the figure below. 6

Figure 2: Distribution of Expected Capacity Market Prices from VRR Design Study14 7

8
The implementation of both a price cap and a price floor has the theoretical 9

potential to narrow the range of pricing outcomes while preserving the long-run 10

average price signal of net CONE. However, because the price cap was
11
implemented during the current conditions of capacity shortage while the price 12

floor was not implemented during the preceding conditions of capacity excess, it is 13

14 Graph showing simulated results cleared price for 2026/2027 VRR curve. Dark grey bar represents median results. Reference price is equal to the Administrative Reference Price ($350/MW-day UCAP), which is a Net CONE Proxy. PJM Interconnection L.L.C, Sixth Review of PJM’s Variable Resource Requirement Curve 52 ( April 9, 2025), at , https://www.pjm.com/-/media/DotCom/committees- groups/committees/mic/2025/20250411-special/item-1-03-sixth-review-of-pjm-vrr-curve.pdf

PDF page 32

11
likely that this market intervention is suppressing long-run average prices below 1

net CONE.
2
Q12. WHAT RECENT TRENDS HAS PJM OBSERVED IN THE CAPACITY
3
MARKET?
4
A12. In recent years, PJM has observed a level of load growth that has not been present 5

since at least the conception of the Reliability Pricing Model capacity market in 6

2007. This load growth is primarily driven by an increase in new large loads, 7

namely data centers. The impact of this load growth has been an increase in the 8

capacity price. Both of these trends are illustrated in the figure below. 9

In addition, recent capacity market auctions have cleared short of the 10

required quantity of capacity to meet PJM’s reliability requirement. For example, 11

the auction for the 2027/2028 Delivery Year (held in July 2026) cleared short by 12

6,831 MW.
13

PDF page 33

12
Figure 3: Illustration of Recent Trends in PJM Capacity Market15
1

2
Q13. WHAT HAS BEEN THE RESPONSE TO THESE TRENDS?
3
A13. These trends have prompted concerns that the growth driven by new large loads is 4

unfairly increasing electricity costs for residential consumers. This led to a 5

15 PJM Interconnection, L.L.C.,  PJM Load Forecast Report 9 (July 14, 2026), at 9, https://www.pjm.com/- /media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf. PJM Interconnection, L.L.C., 2028/2029 Base Residual Auction Results Report 6 (2025), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra- results-report.pdf.

PDF page 34

13
Statement of Principles Regarding PJM, a joint policy directive signed by all PJM 1

state governors along with Secretary of Interior and Secretary of Energy urging 2

PJM to “protect residential customers from capacity price increases.”16 In response, 3

the PJM Board initiated a Critical Issue Fast Path process to engage stakeholders in 4

solutions to this challenge.17
5
Q14. WHAT PROPOSALS HAS PJM RECENTLY FILED REGARDING THESE
6
CAPACITY MARKET ISSUES?
7
A14. PJM has recently filed two proposed changes regarding the capacity market to 8

FERC for approval.
9

First, PJM has proposed to hold a one-time Reliability Backstop
10
Procurement (“RBP”) for new capacity in response to capacity shortfall observed 11

in the most recent auction.
12

Second, PJM has proposed to implement a new Interim Resource Adequacy 13

Service (“IRAS”).18  Under this service, new large loads must either (a) bring new 14

generation supply sufficient to serve their peak demand, or (b) agree to receive 15

interruptible service. Loads can satisfy the requirement to bring new generation 16

either by entering into a bilateral arrangement with a new resource, referred to as 17

Bring Your Own New Capacity (“BYONC”), or by being allocated a share of 18

PJM’s RBP.
19

16 U.S. Dep't of Energy, Statement of Principles Regarding PJM (Jan. 15, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm.
17 PJM, Critical Issue Fast Path – Reliability Backstop Procurement / Connect & Manage, https://www.pjm.com/committees-and-groups/cifp-rbp.
18 PJM Filing, at 2.

PDF page 35

14
Q15. PLEASE DESCRIBE THE KEY FEATURES OF PJM’S IRAS PROPOSAL
1
IN MORE DETAIL.
2
A15. Under the IRAS proposal, PJM would create a permanent requirement for new large 3

loads to bring new capacity into the market to cover their peak demand if the PJM 4

system does not have sufficient capacity to meet the reliability requirement.19 A 5

new large load is defined as a load that is 50 MW or greater that goes into service 6

after June 1, 2027.20  Failing to bring new capacity into the market would result in 7

the new large loads being interrupted before PJM takes other existing emergency 8

actions, such as pre-emergency load management reductions.
9
New large loads can satisfy the requirement to bring new capacity into the 10

market in two distinct ways. First, the load can be allocated a portion of the cost of 11

PJM’s RBP procurement.21  However, because the RBP is proposed as a one-time 12

procurement, this is likely to only be available for new large loads in the near-term. 13

Second, new large loads can enter into a BYONC bilateral arrangement with a new 14

generating resource. 22  Information about both RBP allocations and BYONC 15

arrangements for each large load would be captured as part of a new “Large Load 16

Registry” that will be maintained by PJM.23
17
Q16. HOW ARE THE PROPOSED IRAS REQUIREMENTS APPLICABLE TO
18
NEW LARGE LOADS DIFFERENT FROM THE REQUIREMENTS THAT
19

19  Id. at 27. 20  Id. at 44–45.
21 Id. at 320. 22  Id. at 14.
23 Id. at 43.

PDF page 36

15
APPLY TO ALL OTHER LOADS ON THE SYSTEM (I.E., EXISTING
1
LOADS AND NON-LARGE NEW LOADS)?
2
A16. The key difference is that under PJM’s proposal, new large loads can only procure 3

capacity through the BYONC or RBP construct, while all other loads (i.e., not new 4

large loads) would retain the option to procure their capacity either through a 5

bilateral BYONC construct or through the capacity market. As is generally true, 6

optionality has value (or conversely, reduced optionality is costly). Depriving new 7

large loads the option to procure capacity through the capacity market is 8

discriminatory and costly, as these loads may perceive that procuring capacity 9

through the capacity market will be lower cost than a BYONC construct that likely 10

requires upfront capital or entering into a long-term contract.
11
Q17. HOW IS DEMAND FROM NEW LARGE LOADS INCORPORATED INTO
12
THE CAPACITY MARKET UNDER PJM’S IRAS PROPOSAL?
13
A17. There are two ways in which demand from new large loads will (or will not be) 14

incorporated into the capacity market under PJM’s IRAS proposal. If the new large 15

load brings online a new BYONC resource or is allocated a portion of RBP, the 16

demand from the new large load and the supply from the new capacity will both be 17

incorporated into the capacity market. If the new large load does not BYONC and 18

is instead subject to IRAS, PJM will not include its demand in the capacity market.24 19

24 Id. 115.

PDF page 37

16
3 Economic Impact of IRAS
1
Q18. WHAT IS THE OVERALL IMPACT OF PJM’S IRAS PROPOSAL?
2
A18. The overall impact of PJM’s IRAS proposal is that it would increase societal costs, 3

increase consumer prices, and reduce reliability. It does this through two primary 4

mechanisms:
5
• Reduction in new investment and retention of existing resources; and 6

• Hindrance of competition between resources serving new large loads and 7

existing loads.
8
I address each of these in turn, including a step-by-step overview of the chain of 9

events that cause costs to rise and reliability to degrade.
10
3.1 Reduction in New Investment and Retention of Existing Resources 11

Q19. WHAT WOULD BE THE IMMEDIATE IMPACT ON THE CAPACITY
12
MARKET OUTLOOK DUE TO IMPLEMENTING IRAS?
13
A19. The immediate impact of implementing IRAS would be an expectation of reduced 14

future capacity market prices. This is the case for two reasons.
15
First, IRAS creates an expectation of reduced future market prices because 16

it asymmetrically prevents price increases from growth in new large loads without 17

protecting prices from downside risk. IRAS structurally prevents new large loads 18

from increasing prices because it either requires new large loads to BYONC or be 19

interruptible. In either case, new large loads do not increase capacity market prices 20

because they either 1) bring new supply that exactly offsets their new demand or 2) 21

their demand is excluded from the capacity market. On the other hand, IRAS 22

PDF page 38

17
introduces future downside price risk. As an example, imagine a new large load 1

that, after investing in a new generation resource through a BYONC arrangement, 2

reduces its demand or leaves the market entirely. The reduction in demand could 3

be caused by any number of factors, including global market dynamics for compute 4

or changes in policy and regulation. If demand is reduced, the BYONC resource 5

would still exist and contribute to excess capacity in the market, which would 6

decrease prices.
7
Second, IRAS creates an expectation of reduced future market prices 8

because it can incentivize uneconomic entry of new generation resources. Imagine 9

a situation where a new large load that requires firm service is forced to make a 10

long-term investment through BYONC arrangement because the market has a 11

short-term capacity deficiency for one year even though the market is projected to 12

have excess capacity in the long-term. New capacity in this case may be 13

uneconomic if it is less costly to incur the costs of a larger short-term shortfall than 14

the costs of additional unneeded capacity for many years. This uneconomic excess 15

capacity will put downward pressure on prices.
16
This phenomenon of expected reduced future capacity market prices due to 17

IRAS is illustrated in the figure below.
18

PDF page 39

18
Figure 4: Impact of IRAS on Future Price Expectations in PJM Capacity Market 1

2
Q20. ISN’T THE EXPECTATION OF REDUCED FUTURE MARKET PRICES
3
A BENEFIT TO CONSUMERS?
4
A20. If only it were that easy. However, consumers ultimately do not benefit from these 5

reduced market prices because of the knock-on effects that come from the market 6

reacting and responding to this decrease in future price expectations. 7

Q21. HOW WILL THE MARKET REACT AND RESPOND TO THE
8
EXPECTATION OF REDUCED FUTURE MARKET PRICES?
9
A21. Very simply, the market will react and respond to expected reduced future market 10

prices with reduced new entry and increased retirements. This is because 11

investment decisions are based on expectations of pricing over the life of the 12

PDF page 40

19
investment. This reduced investment and increased retirement will paradoxically 1

cause market prices to increase and reliability to decline in the near-term in an effort 2

to re-equilibrate to the new normal of increased future downside risk. 3

The next step in this chain reaction is that PJM will observe the reduction 4

in system reliability and be compelled to take steps to rectify this outcome. The tool 5

that PJM has to rectify this outcome is the structure of the capacity market demand 6

curve. PJM would necessarily need to increase the demand curve in order to induce 7

additional capacity into the market to achieve the reliability standard. The end result 8

is that (as is the case with most market intervention) the “consumer savings” from 9

price suppression are illusory. This dynamic is illustrated in the figure below. 10

Figure 5: Illustration of Price and Reliability Dynamics Due to Introduction of IRAS 11

12

PDF page 41

20
Q22. HOW IN PRACTICE WOULD PJM INCREASE THE DEMAND CURVE?
1
A22. The capacity market demand curve is an administratively-determined curve that 2

PJM periodically reevaluates through a study and stakeholder review process to 3

ensure that it is delivering the appropriate balance of price and reliability.25 It is 4

through this process that PJM would surface any deficiencies in the current curve 5

and make adjustments. There are several ways the VRR curve can be increased, 6

including increasing the maximum price of the curve, increasing the UCAP MW 7

quantity for point B on the curve, elongating the tail of the curve by increasing the 8

UCAP MW quantity for point C, or a combination of all of these adjustments. 9

Q23. ARE THERE OTHER EXAMPLES WHERE EXPECTATIONS OF
10
FUTURE EVENTS IMPACT CURRENT MARKET PRICES?
11
A23. Yes, there are examples both inside and outside the electricity sector where 12

expectations of future events impact current market prices. For example, analysis 13

prepared for PJM demonstrates that lower expected long-term capacity market 14

pricing requires much higher near-term pricing in order to support investment.26 15

Outside of electricity, the potential for future geopolitical instability can increase 16

oil prices through a “risk premium.”
17

25 PJM OATT § 5.10.a.iii.
26 Sixth Review of PJM’s Variable Resource Requirement Curve at 68, BRATTLE, (Apr. 9, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2025/20250411-special/item- 1-03-sixth-review-of-pjm-vrr-curve.pdf (the “same [battery] resource will require a much higher price … in the first three years … if future prices will return to the lower long-run price … over years 4-10 of the asset life”).

PDF page 42

21
Q24. IS THE DYNAMIC OF REDUCED FUTURE CAPACITY MARKET
1
PRICES
MATERIAL
ENOUGH
TO
IMPACT
NEAR-TERM
2
INVESTMENT AND RETIREMENTS?
3
A24. Yes, the magnitude of new large load growth forecasted to enter the PJM system 4

makes the downside price risk I describe above very material. PJM forecasts a
5
reliability requirement of approximately 200 GW in 203527, a 55 GW28 increase
6
from today.29 This projected growth is primarily driven by new large loads. If even 7

just 10% of this increased demand (i.e., 5.5 GW) were to disappear after bringing 8

online new capacity, this could be material enough to decrease the market clearing 9

price by almost 50%.30 The magnitude of this impact demonstrates that this is a 10

very material potential future risk.
11

27 This is found from taking projected peak load for 2035 and multiplying it by the Forecast Pool Requirement (FPR) from the 2028/2029 BRA:  216,872 × 0.92 = 198,872 MW. The forecasted peak load can be found here: PJM Inside Lines, PJM’s Updated 20-Year Forecast Continues To See Significant Long-Term Load Growth, (January 14, 2026)_, https://insidelines.pjm.com/pjms-updated-20-year-forecast- continues-to-see-significant-long-term-load-growth/.

28 This is found by taking the 2028/2029 Reliability Requirement adjusted for FRR and subtracting the forecasted 2035 Reliability Requirement adjusted for FRR: 198,872-145,149 = 53,723 MW. See infra note 36 for 2028/2029 Reliability Requirement adjusted for FRR..

29 This is the 2028/2029 Reliability Requirement adjusted for FRR found from: PJM Interconnection, L.L.C., Planning Period Parameters for Base Residual Auction, (July 27, 2026) https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-planning-period-parameters-for- base-residual-auction.xlsx. 30 Example assumes: Gross CONE of 600 $/MW-day UCAP, E&AS Value of 300 $/MW-day UCAP, VRR curve determined using same methodology as 2028/2029 BRA, and 2028/2029 Forecast Pool Requirement (FPR). Supply curve shape chosen to imitate curve from 2026/2027 BRA result found from: PJM Interconnection, L.L.C., 2026/2027 BRA Supply Curves, (August 1, 2025), https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/2026-2027/2026-2027-bra-supply-curves.pdf. Inspiration for Gross CONE and E&AS values from: PJM Interconnection, L.L.C., Planning Period Parameters for Base Residual Auction, (July 27, 2026) https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029- planning-period-parameters-for-base-residual-auction.xlsx.

PDF page 43

22
Figure 6: Example of How a Decrease in Load in the Market Causes a Material Price 1

Decrease
2

3
Q25. ARE THERE ANY OTHER MECHANISMS THROUGH WHICH IRAS
4
IMPACTS INVESTMENT AND RETENTION SIGNALS IN THE
5
CAPACITY MARKET?
6
A25. Yes. Even if we were to assume that all new large load is permanent and that no 7

uneconomic entry of new generation resources occurs, the introduction of IRAS 8

would still chill new investment and retention of resources in the capacity market. 9

The underlying reason for this is that IRAS, just like the currently imposed price 10

cap, fundamentally and artificially limits the auction clearing price. This deprives 11

the market of the ability to send a long-term average price equal to net CONE. 12

Investors made previous investments on the expectation that future capacity prices 13

would reflect actual market conditions, including increased demand for new large 14

PDF page 44

23
loads. Depriving those investors of the ability to realize market-driven pricing sends 1

the signal that future high prices cannot be trusted. This fundamentally chills 2

investment which, once again, paradoxically increases near-term pricing. 3

Q26. HAS PJM SUFFICIENTLY EVALUATED THE IMPACT OF MAKING
4
IRAS A PERMANENT FEATURE OF THE CAPACITY MARKET?
5
A26. No. Separate from PJM’s current RBP and IRAS proposals to address the near-term 6

reliability and price issues that I describe above, “the PJM Board has directed staff 7

to undertake a holistic review of the capacity market design.”31 This holistic review 8

will evaluate long-term structural changes to the PJM market that will be in place 9

for many decades. Nonetheless, PJM’s proposal to make IRAS a permanent feature 10

of the capacity market circumvents this process by implementing a long-term 11

market design change that results in permanent price suppression in the capacity 12

market that PJM has not sufficiently evaluated.
13
Q27. HAS PJM ITSELF OPINED ON THE LONG-TERM SIGNALS SENT BY
14
EXCLUDING DEMAND FROM NEW LARGE LOADS THAT DO NOT
15
BYONC?
16
A27. Yes. Before PJM’s current proposal to FERC that excludes demand from new large 17

loads in the capacity market that do not BYONC, PJM had previously proposed the 18

opposite. Specifically, PJM stated that “connect and manage load will not be 19

31 PJM Interconnection, L.L.C., Powering Reliability Through Market Design, 3, (May 6, 2026) https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering- reliability-through-market-design.pdf.

PDF page 45

24
removed from the [Reliability Pricing Model] auction.”32 PJM’s stated rationale for 1

this was that “including connect and manage [load] in the [Reliability Pricing 2

Model] auction continues to provide price signals for new investment.” 33 So 3

clearly, PJM recognizes that excluding IRAS demand impacts long-term price 4

signals and reduces the incentive for new entry and retention of existing resources. 5

Q28. ARE ANY OF YOUR CONCLUSIONS IMPACTED BY THE FACT THAT
6
IRAS IS ONLY ACTIVE DURING PERIODS OF CAPACITY SHORTAGE?
7
A28. No. As I describe above, BYONC can suppress prices during periods of both 8

capacity shortage (when IRAS is active) and during periods of capacity surplus 9

(when IRAS becomes inactive). Suppressing prices at any time, including during 10

times of shortage, hinders the ability of the demand curve to provide a long-run 11

average price equal to net CONE.
12
3.2 Hindrance of Competition Between Resources Serving New Large
13
Loads and Existing Loads
14
Q29. ARE THERE OTHER ECONOMIC IMPACTS THAT WOULD RESULT
15
FROM THE INTRODUCTION OF IRAS?
16
A29. Yes. Another key impact of the introduction of IRAS is the creation of two different 17

markets (the market to serve new large loads and the market to serve all other loads) 18

with two different prices for otherwise identical products (capacity). The 19

32 “Connect and manage” was PJM’s previous term for what they now call IRAS. PJM Interconnection, L.L.C., Connect and Manage PJM Package, 29, (May 27, 2026) https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-item-04---connect-and-manage- pjm-package---pjm-presentation.pdf. 33 Id. at 29.

PDF page 46

25
bifurcation of the same product into two different markets hinders competition 1

between resources in each market, which ultimately increases societal costs. 2

Q30. HOW DOES MARKET BIFURCATION HINDER COMPETITION AND
3
INCREASE SOCIETAL COSTS?
4
A30. Bifurcating the market increases societal costs because it can require one market to 5

procure more expensive capacity when it might be available for less cost in the 6

other market. In the case of IRAS, it is plausible that capacity market prices will 7

not be high enough to retain existing resources let alone induce new entry. In this 8

case, existing resources may retire. At the same time, IRAS requires new large 9

loads to procure new capacity. Thus, new large loads would unnecessarily incur the 10

higher cost of building new generation when it could have been more economic to 11

invest in retaining existing generation. This dynamic is illustrated in the figure 12

below.
13

PDF page 47

26
Figure 7: Illustration of How Market Bifurcation Can Lead to a Lower Cost Resource Being 1

Crowded Out by a Higher Cost Resource
2

3
The outcome illustrated above is particularly relevant for cases where 4

existing resources are contemplating expensive investments (such as repowering of 5

an existing but aging resource) that are still more economic than developing a new 6

resource. The result is that society pays more for the new resource when it could 7

have received the same reliability benefit by paying less for the existing resource. 8

Q31. ARE THE INEFFICIENCIES OF A BIFURCATED MARKET WELL-
9
ESTABLISHED?
10
A31. Yes. As one example, the market monitor for the New York Independent System 11

Operator (“NYISO”) examined capacity market outcomes under both a “uniform” 12

PDF page 48

27
and “bifurcated” market structure between new and existing resources. 34 The 1

market monitor found that “approaches with price discrimination [i.e., bifurcation] 2

incentivize less efficient behavior, ultimately resulting in greater need for 3

expensive new capacity over time.”
4
More generally, economists have found that a uniform price market (i.e., 5

not a bifurcated market) promotes efficiency and maximizes social welfare. For 6

example, preeminent energy economists Peter Cramton and Steven Stoft state that 7

“the uniform-price auction yields a competitive equilibrium, and the competitive 8

equilibrium is efficient: the outcome maximizes social welfare.”35 FERC has also 9

found that “paying all cleared … resources a uniform price [will] send an efficient 10

price signal, and be consistent with long-standing Commission policy approving 11

uniform clearing prices.”36 In other words, a market that sends the same uniform 12

price to all supply is able to harness competition to meet demand for electricity at 13

the lowest total societal cost.
14

15

34  Potomac Economics, MMU Analysis of Capacity Market Structure, 18, (May 22, 2025) https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-item-04--- connect-and-manage-pjm-package---pjm-presentation.pdf.

35 Peter Cramton & Steven Stoft, Uniform-Price Auctions in Electricity Markets. Pg 8. (Mar. 20, 2006), https://www.cramton.umd.edu/papers2005-2009/cramton-stoft-clearing-price-markets.pdf.
36 Frequency Regulation Compensation in the Organized Wholesale Power Markets, Order No. 755-A, 138 FERC ¶ 61,123, at 2 (2012).

PDF page 49

28
4 Recommendations & Summary
1
Q32. PLEASE PROVIDE A SUMMARY OF THE CONCERNS RAISED IN
2
YOUR TESTIMONY.
3
A32. The key concerns I raise in my testimony are:
4
• IRAS creates a discriminatory requirement for new large loads to bring their 5

own new capacity to the market or face priority interruption. This same 6

requirement does not apply to all other loads that retain the option to procure 7

capacity from the capacity market.
8
• The introduction of IRAS will paradoxically increase societal costs, 9

increase consumer prices, and degrade reliability. It does this through two 10

primary mechanisms:
11
1. A reduction in new investment and reduction in retention of existing 12

resources. This itself is caused by:
13
▪ The expectation of reduced future capacity market prices due 14

to the introduction of asymmetric downward price risk and 15

incentivization of uneconomic new entry; and
16
▪ A chilling of investment due to the prevention of new large 17

loads from increasing current prices.
18
2. Hindrance of competition between resources serving new large 19

loads and existing loads.
20

PDF page 50

29
Q33. WHAT IS YOUR OVERALL ASSESSMENT OF IRAS?
1
A33. While IRAS appears to be a genuine attempt to “protect residential customers from 2

capacity price increases,” the problem is it does exactly the opposite.37 In this 3

regard, IRAS is simply a new spin on the intuitive but ultimately self-defeating idea 4

of providing consumer benefits through price suppression (i.e., price manipulation). 5

If it were possible to provide consumer benefits through price suppression, PJM 6

has many tools at its disposal and could have done so long ago. Chief among these 7

options would be simply reducing the capacity market demand curve to “reduce” 8

prices. However, this doesn’t work, because the market adapts and responds and 9

ultimately forms the prices that are necessary to cover resource costs, even at the 10

expense of reliability due to reduced entry and increased exit. The fact that IRAS 11

will increase societal costs, increase consumer prices, and degrade reliability 12

demonstrates that this is not the solution that PJM needs.
13
Q34. IN LIGHT OF THE ARGUMENT YOU MAKE, DO YOU HAVE ANY
14
RECOMMENDATIONS?
15
A34. The overarching goal of the capacity market should be to maximize efficiency, 16

which simply means providing reliability at the lowest total societal cost. Such an 17

outcome ultimately minimizes consumer costs – an idea reinforced by leading 18

energy economists:
19
“As with any type of productive investment, the goal should be to
20
minimize the total cost of production and delivery. If the market is 21

37 PJM Filing, at 5.

PDF page 51

30
competitive or the regulation effective, these costs savings will be 1

passed through to consumers.”38
2
To minimize societal costs, all resources should face the same non- 3

discriminatory price signal (i.e., a uniform market clearing price). PJM should 4

implement long-term market reforms to provide a sufficient uniform price signal to 5

both new and existing resources to meet all demand (not just demand associated 6

with new large loads).
7
I therefore recommend that PJM should not move forward with the IRAS 8

proposal as it is distortionary, discriminatory, bifurcates the market, unnecessarily 9

increases societal costs and consumer prices, and front-runs PJM’s long-term 10

market design reforms.
11
Q35. DOES THIS CONCLUDE YOUR TESTIMONY?
12
A35. Yes.
13

38 Steven Stoft, Problems of Transmission Investment in a Deregulated Power Market, in Competitive Electricity Markets and Sustainability 6 (François Lévêque ed., 2006).

PDF page 52

CERTIFICATE OF SERVICE

I hereby certify that I have this day caused to be served the foregoing document upon each person designated on the official service list compiled by the Secretary in this docket. Dated at Washington, D.C. this 3rd day of September, 2026.

   /s/ Andrew DeVore

Andrew DeVore
Kirkland & Ellis LLP
1301 Pennsylvania Avenue, N.W.
Washington, D.C. 20004

Counsel for Talen Energy Corporation