ER26-3515-000 · 2026-09-03 · Talen Energy Corporation

Motion to Intervene and Protest of Talen Energy Corporation re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service

Text extracted from the eLibrary original (SHA-256 648dfb54d1885379…). Download the original from the official source.

Contents · 8 sections
  1. I. MOTION TO INTERVENE p. 4
  2. II. PROTEST p. 4
  3. A. PJM’s proposal to require New Large Loads to procure new capacity or be p. 5
  4. B. Even if the IRAS Proposal stood on solid legal ground—which it does not— p. 16
  5. III. CONCLUSION p. 20
  6. A. For a UCAP MW quantity equal to 99% of the reliability requirement, the p. 29
  7. B. For a UCAP MW quantity equal to 101.5% of the reliability requirement, p. 30
  8. C. For a UCAP MW quantity equal to 106% of the reliability requirement, the p. 30

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

The IRAS Proposal is premature and permanent and should not be adopted because it will circumvent much needed holistic reform.12 Talen respectfully submits this protest (“Protest”) to the IRAS Proposal accordingly13 9 Id. at 28. 10 Stakeholder Process on Backstop Procurement and Connect and Manage…
Read this passage Filed comments: Registry access

I. MOTION TO INTERVENE

printed heading

Talen therefore requests that the Commission grant this motion to intervene and permit Talen to participate in this proceeding with full rights as a party thereto.
Read this passage

II. PROTEST

printed heading

PROTEST The existing RPM construct was designed to improve price stability, enhance reliability, and produce accurate price signals to incentivize new generation build.15 The U.S.
Read this passage

A. PJM’s proposal to require New Large Loads to procure new capacity or be

printed heading · Topic match: Cost allocation

Well-established Commission precedent provides that matters directly affecting rates must be included in an RTO’s filed tariff if the matter “significantly affects rates, terms, and conditions” of service, are readily susceptible of specification, and not generally understood in a contractual…
Read this passage Filed comments: Cost allocation

B. Even if the IRAS Proposal stood on solid legal ground—which it does not—

printed heading · Topic match: Cost allocation

PJM proposes to exclude New Large Loads “from the VRR Curve starting with the 2029/2030 Delivery Year, regardless of whether PJM is experiencing a shortfall that triggers IRAS in the relevant Delivery Year,” unless the New Large Load has entered into a bring your own new capacity (“BYONC”)…
Read this passage Filed comments: Cost allocation

III. CONCLUSION

printed heading

That may take the form of longer forward-term BRAs, e.g., 5 years in advance of the Delivery Year rather than 3 years, to allow new capacity to respond to accurate market pricing signals, and additional review of the VRR Curve and must-offer rules.
Read this passage

Table of Contents

printed heading · Topic match: Reliability and curtailment

I have 7 authored several reports related to reliability that evaluate the most cost-effective 8 pathway to meeting long-term system needs, including Resource Adequacy for the 9 Energy Transition: A Critical Periods Reliability Framework and its Applications 10 in Planning and Markets,1 Assessment…
Read this passage Filed comments: Reliability and curtailment

A. For a UCAP MW quantity equal to 99% of the reliability requirement, the

printed heading

For a UCAP MW quantity equal to 99% of the reliability requirement, the 20 price is equal to the greater of (i) 1.15 times gross CONE minus 0.75 times 21 energy and ancillary service revenues and (ii) 0.20 times gross CONE. 22 9
Read this passage

B. For a UCAP MW quantity equal to 101.5% of the reliability requirement,

printed heading

For a UCAP MW quantity equal to 101.5% of the reliability requirement, 1 the price is equal to half of the price value used for point A. 2
Read this passage

C. For a UCAP MW quantity equal to 106% of the reliability requirement, the

printed heading · Topic match: Reliability and curtailment

PJM has recently filed two proposed changes regarding the capacity market to 8 FERC for approval. 9 First, PJM has proposed to hold a one-time Reliability Backstop 10 Procurement (“RBP”) for new capacity in response to capacity shortfall observed 11 in the most recent auction. 12 Second, PJM has…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 3rd day of September, 2026. /s/ Andrew DeVore Andrew DeVore Kirkland & Ellis LLP 1301 Pennsylvania Avenue, N.W.