ER26-3515-000 · 2026-09-03 · Constellation Energy Generation, LLC

Protest and Comments of Constellation Energy Generation, LLC addressing PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service…

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.:
205(d) Rate Filing: Proposal to Establish
Interim Resource Adequacy Service & a
Large Load Registry to be effective
10/12/2026
)
)
)
)
)
)

Docket No. ER26-3515-000

PROTEST AND COMMENTS OF CONSTELLATION ENERGY GENERATION, LLC
Pursuant to the Commission’s August 13, 2026 notice in the above-captioned proceeding, Constellation Energy Generation, LLC (“Constellation”) submits this protest and these comments addressing issues raised by the August 12, 2026 Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and A Large Load Registry to Address System Reliability (the “PJM Proposal,” “IRAS Proposal,” or “Proposal”).

The Commission should reject the PJM Proposal for multiple independent reasons.  First, adoption of the Proposal falls outside the scope of the Commission’s jurisdiction as defined by the Federal Power Act (“FPA”).  Although PJM’s filing seems to suggest that the Commission should be willing to expand its jurisdiction to address novel problems or those involving technology that—in PJM’s words—would have seemed like “science fiction” to the drafters of FPA Section 201,1 those circumstances cannot justify any departure from the statute’s plain language or the precedent interpreting it.  As those authorities provide, the Commission cannot intrude on the retail sphere by “specif[ying] terms of sale at retail” or otherwise—and “cannot take an action transgressing” that “limit no matter how direct, or dramatic, [the action’s] impact on wholesale

1 PJM Proposal 91, Docket No. ER26-3515-000 (Aug. 13, 2026).

PDF page 2

2

rates” might be.2  Yet that is exactly what PJM’s Proposal seeks to do:  it seeks to impose special burdens on a class of retail load, by requiring new, large retail customers to take interruptible retail service in exchange for federally prescribed compensation.  The Commission cannot accept a Proposal that asks it to regulate based on retail characteristics and force a change in retail rules. Moreover, accepting PJM’s Proposal would send the Commission down a slippery jurisdictional slope, raising the possibility of all sorts of federal regimes governing the service conditions and generation-procurement choices of specific types of retail customers.

Second, PJM has failed to carry its burden to show that the Proposal is not unduly discriminatory or preferential.  PJM singles out New Large Loads for disfavored treatment (potential curtailment) based on their size and their in-service date.  But those distinctions make no material difference to IRAS’s purpose of supporting reliability and capacity.  The capacity of the system is as taxed on a megawatt basis by one fifty-megawatt customer as by fifty one- megawatt customers.  And the system is as burdened by a customer that came into service the day before the New Large Load cutoff as one that came into service the day after.  PJM’s proposal also would discriminate among supply resources, by allowing New Large Loads to avoid potential curtailment only if they make arrangements with qualifying “new” capacity.  But a megawatt of existing capacity provides the same reliability to the system as a megawatt of new capacity, and should be permitted to enter the same commercial arrangements.

Finally, PJM has failed to carry its burden to show that its Proposal is just and reasonable because the Proposal suffers from significant design flaws and a fundamental economic irrationality, such that this Commission’s approval would be subject to reversal on appeal as

2 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 280 (2016), as revised (Jan. 28, 2016) (“EPSA”).

PDF page 3

3

arbitrary and capricious.  PJM’s Proposal to deploy IRAS before Pre-Emergency Load Management Reduction Actions arbitrarily and unreasonably fails to adhere to core economic dispatch principles, fails to reflect any IRAS load curtailment in energy price formation, and fails to maximize social surplus, while also serving no clear reliability purpose and potentially undermining reliability.  In addition, PJM’s Proposal to exclude New Large Loads without sufficient “BYONC” (i.e., “bring your own new capacity”) from the demand curve used in RPM Auctions is an arbitrary and unreasonable step that would significantly undermine the efficient operation of the RPM and exacerbate an existing crisis that PJM itself has identified as a significant problem.  And the Proposal is irrational in other ways as well, including by failing to allow any qualifying BYONC to be replaced by other qualifying BYONC, by limiting the resources that qualify as BYONC to resources that cleared an auction for the first time in the Base Residual Auction for certain delivery years rather than in any auction for those years, and by failing to include incremental capacity created by an energy resource in the definition of BYONC. Taken separately, each of those three flaws is enough to doom the Proposal.  But it is also worth considering the Proposal’s many flaws together as a whole.  Since its beginning decades ago, the PJM market has been premised on the principles that all load is equally entitled to firm service, with a reliability target of one interruption every ten years, and that all generation capable of providing service should be subject to the same rules.  The Proposal abandons those basic principles, without ever acknowledging the fundamental changes it would make.  It singles out one class of load to receive inferior service and treats new resources more favorably than existing resources—and it does so by running roughshod over the jurisdictional line that separates the federal domain from that of the states.  The Commission should reject the Proposal.  And in the

PDF page 4

4

event that the Commission were to accept the Proposal, it should condition acceptance on modification of the Proposal as described in this filing.

BACKGROUND
PJM Interconnection, L.L.C. (“PJM”) has proposed to define certain customers as New Large Loads and subject those customers to Interim Resource Adequacy Service (“IRAS”), a “service to be implemented by PJM … [w]hen triggered by system conditions.”3  Specifically, New Large Loads that do not bring their own qualifying new capacity (known as “BYONC”) in an amount that equals or exceeds their peak load will be subject to involuntary load reductions.4 PJM contends that the IRAS framework will “support system reliability in the PJM Region.”5  PJM states that “the unprecedented addition of large loads, most notably data centers, have given rise to resource adequacy shortfalls—and associated real-time operational issues that IRAS is intended to address.”6  Accordingly, PJM has submitted proposed revisions to its Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to effectuate the IRAS framework.

PJM proposes to define New Large Load based on size and in-service date.  Under the proposed RAA changes, “Large Loads” are customers with cumulative peak load of 50 megawatts or greater “at a single electrical site behind one or more points of interconnection” (and, for configurations involving multiple affiliated facilities or points of interconnection, “all affiliated load facilities within a one-mile radius will be considered a single electrical site”).7  Additionally, under the proposed revised tariff, “New Large Loads” are Large Loads that, after June 1, 2027, go

3 PJM Proposal 1.
4 Id. at 74.
5 Id. at 6.
6 Id.
7 Id. at 5 n.13; Proposed RAA, Definitions – Large Load.

PDF page 5

5

into service, are the incremental increase in an existing Large Load, or are the incremental increase at an existing end-use customer load at a single electrical site to bring it within the definition of Large Load.8  PJM also proposes to create and maintain a Large Load Registry with information about all Large Loads in the PJM region that will be used to identify New Large Loads forced to curtail and to implement IRAS starting in the 2027/2028 Delivery Year.  The information used to develop and maintain the Large Load Registry would be “submit[ted] or cause[d] to be submitted” to PJM by LSEs and validated as needed by Electric Distributors.9

Under PJM’s Proposal, New Large Loads are forced to provide IRAS (and are considered “Eligible New Large Loads”) unless their capacity needs are satisfied by either BYONC or Allocated RBP UCAP MW (described further below).  First, a New Large Load may avoid being forced into IRAS by “contract[ing] with new capacity that meets the BYONC gating criteria.”10 Those requirements “are designed to ensure the capacity is actually new and not repackaged and will provide capacity over at least 10 years.”11  As described in the proposed tariff, qualifying BYONC must be “supported by” one of (1) a new generation resource; (2) incremental capacity created by an “uprate” of existing generation capacity resources, subject to specified requirements regarding how the incremental capacity is created; 12 (3) incremental capacity created by the utilization of Surplus Interconnection Service; (4) repowering of a deactivated generation resource;

(5) incremental capacity created by an existing generation resource changing to a more efficient fuel type; or (6) new Demand Response or DER Capacity Aggregation Resources.13  Second, as

8 Id. at 1 n.2; Proposed Tariff, Definitions – New Large Load.
9 Id. at 45.
10 Id. at 23.
11 Id. 12 As discussed below (see Part IV.C), incremental capacity created by an uprate of energy resources, as well as existing generation capacity resources, should equally count as BYONC.
13 Proposed Tariff, Attachment DD-4, § VI(b)(i)-(ii).

PDF page 6

6

an alternative to BYONC, a New Large Load “may have its IRAS availability reduced by being allocated a share of” Reliability Backstop Procurement Unforced Capacity megawatts (RBP UCAP MW).14  Allocated RBP UCAP MW is allocated at the Electric Distributor zone/area level, and then further allocated by the Electric Distributor “among the New Large Loads located in the Electric Distributor’s zone/area.”15

PJM proposes to implement IRAS, starting with the 2027/2028 Delivery Year, as part of its tiered response to a potential or actual capacity shortage.16  Specifically, “after determining that available economic real-time supply may not be sufficient” to maintain reserves or to keep Interconnection Reliability Operating Limits within prescribed limits, PJM may initiate an IRAS Action.17  IRAS would be deployed after non-firm transmission services are curtailed18 —but “before relying on Demand Resources[] through Pre-Emergency Load Management Reductions Actions.” 19   Under PJM’s proposal, PJM will issue load reduction directives to Electric Distributors, who “must execute” them.20  According to PJM, “[d]irecting an Electric Distributor, rather than a specific end-use customer, to reduce a quantity of load is in keeping with PJM’s

14 PJM Proposal 67.
15 Id. at 68.
16 Id. at 75.  When PJM faces a capacity shortage, it undertakes a cascading series of emergency actions that are aligned with NERC Energy Emergency Alert Level classifications (EEA1 through EEA3).  PJM Manual 13, pp. 24, 32, 83-84, available at https://www.pjm.com/- /media/DotCom/documents/manuals/m13.ashx; see also PJM Proposal 79 Fig. 1.
17 PJM Proposal 75.  Such an IRAS Action would occur “at the beginning of PJM’s actions” under the first alert stage, called EEA1.  PJM Proposal 22; PJM Proposal 80 Fig. 2 (placing “IRAS Large Load reduction” prior to “Pre-Emergency DR” in the chronology of PJM emergency procedures).
18 Id. at 78. 19 Id. at 79 (emphasis in original); Pilong Affidavit 7, 10.
20 PJM Proposal 26, 82; see Proposed Tariff §§ II(e), III(a) (“Electric Distributors shall … execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in the Electric Distributor’s zone/area”).

PDF page 7

7

longstanding practice and reflects and respects the allocation of jurisdiction between the federal and state levels.”21

PJM’s proposal assumes that curtailment decisions as to specific Large Loads “would be worked out through revised state retail tariffs”22 —necessitating that “appropriate, documented state-sanctioned load reduction plans” would either “already [be] in place or will be developed and refined in conjunction” with the rollout of IRAS.23  PJM’s filing acknowledges that such tariffs have not yet been developed, citing “the need to establish retail mechanisms authorizing utilities to curtail designated large commercial and industrial customers.”24  PJM concedes that “states may, of course, establish and enforce their own retail load reduction programs,”25 and “states may each define ‘large loads’ differently for purposes of their retail tariffs, particularly those governing load reduction protocols.”26

PJM also has proposed “a rate for IRAS that is equal to 50% of the Non-Performance Charge Rate.”27  The proposed tariff states that “the Electric Distributor shall be responsible for compensating” the loads that were required to provide IRAS and “shall be responsible for charging customers in its zone/area to fund any such compensation,” unless the Electric Distributor requests that PJM take steps to “assess charges” to “fund such compensation.”28  At the same time, PJM purports to “provide[] Electrical Distributors and states flexibility in the applicable IRAS rate for

21 PJM Proposal 86.
22 Id. at 87.
23 Id. at 6.
24 Id. at 88-89; see id. at 87 (“PJM stands ready to assist states in developing those tariffs if they so desire.”). 25 Id. at 99.
26 Id. at 87.
27 Id. at 102.
28 Proposed Tariff, Attachment DD-4, § X(b)(i)-(ii).

PDF page 8

8

its territory,”29 apparently in the sense that the amount can be adjusted downwards, and specifies that “[w]hether a specific New Large Load may be entitled to compensation for provision of IRAS will be determined by state authorities under state law or RERRA as may be applicable.”30 Finally, PJM proposes to exclude New Large Loads from PJM’s capacity-market demand curve (the “Variable Resource Requirement” or “VRR Curve”) beginning with the 2029/2030 Delivery Year, unless those loads have “arrangements with sufficient BYONC.”31  Where New Large Load does contract with sufficient new capacity to avoid IRAS, PJM would add that load to the VRR Curve but require the new capacity to participate in RPM Auctions as a price taker (at an offer of $0/MW) for ten consecutive Delivery Years.32  That approach is a reversal from PJM’s prior development of this proposal, which warned that excluding Large Loads from the demand curve could skew market signals and distort costs to existing customers.33  PJM now asserts that this element of its proposal “is designed to protect residential customers from capacity price increases resulting from the effects of New Large Loads.”34

PJM is requesting expedited approval of the revisions to the Tariff and RAA needed to implement IRAS—effective 60 days after the filing, on October 12, 2026—in part to “support ongoing state efforts to establish retail-level, operational procedures” for reducing New Large Loads without BYONC ahead of other customers.35  PJM does not propose an expiration date for IRAS or a path for Eligible New Large Loads subject to IRAS to transition to non-interruptible service over time, short of fulfilling requirements associated with BYONC.

29 PJM Proposal 102.
30 Id. at 106.
31 Id. at 23.
32 Id. at 55, 57-58.
33 Jan. 16, 2026 Decisional Ltr. at 5.
34 PJM Proposal 23-24.
35 Id. at 8-9.

PDF page 9

9

PROTEST AND COMMENTS36
I. PJM’s Proposal Is Beyond The Commission’s Jurisdictional Reach
A. The Commission’s Jurisdiction Is Subject To Strict Statutory Limits
Section 201(b) of the FPA limits the Commission’s jurisdiction to “the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce.”37  The Commission cannot regulate “any other sale of electric energy.”38 In keeping with those formal limits, Section 201(a) declares that “Federal regulation … extend[s] only to those matters which are not subject to regulation by the States.”39  It also declares that federal regulation “is necessary in the public interest” only as to “that part of [the electric energy] business which consists of the transmission of electric energy in interstate commerce and the sale of such energy at wholesale in interstate commerce.”40  Those declarations “cannot nullify a clear and specific grant of jurisdiction” elsewhere in the statute,41 but they are relevant as a guiding expression of congressional purpose where there is no clear and specific grant of jurisdiction and the Commission is asked to take a novel action.42

36 Constellation does not object on jurisdictional (or other) grounds to the portion of PJM’s Proposal that would establish a Large Load Registry.  Such a registry does not involve interference with the retail market; it is merely an information-gathering exercise that, in and of itself, does not affect retail prices or the service provided to Large Loads or any other category of retail customer.  Moreover, as PJM points out, “the proposed registry will give Electric Distributors and state entities access to critical information they may elect to rely upon when fashioning … load reduction protocols (including through recently-announced VA SCC and DCC state-led workshops).”  PJM Proposal 7.  Accordingly, references below to flaws in PJM’s Proposal do not encompass the portion of the Proposal relating to the registry.

37 FPA Section 201(b)(1), 16 U.S.C. § 824(b)(1).
38 Id.
39 Id. § 824(a).
40 Id. (emphasis added).
41 New York v. FERC, 535 U.S. 1 (2002) (citations omitted).
42 See generally W. Virginia v. EPA, 597 U.S. 697, 721, 724 (2022) (rejecting notion that an agency can “claim to discover in a long-extant statute an unheralded power representing a transformative expansion in [its] regulatory authority,” particularly when that power is of great “economic and political significance”).

PDF page 10

10

In FERC v. EPSA, the Supreme Court interpreted Section 201(b) and established a test for assessing whether the Commission has acted within the scope of its statutory jurisdiction.43  The Commission’s jurisdiction extends only “to rules or practices that directly affect the [wholesale] rate.” 44  And even if a Commission action has that necessary direct effect, the Commission nevertheless cannot intrude on a sphere that is “reserv[ed]” for the states—namely, “retail electricity sales.”45  Because the “wholesale and retail markets in electricity … are not hermetically sealed from each other,” the fact that a Commission action merely affects the retail sphere is not enough to create a jurisdictional problem.46  Conversely, mere effects on wholesale rates are not enough to make a Commission action jurisdictionally permissible:  “FERC cannot take an action transgressing th[e] limit” on intruding on the retail sphere “no matter how direct[] or dramatic” that action’s “impact on wholesale rates” may be.47  Thus, the Commission cannot “specif[y] terms of sale at retail,” which “is a job for the States alone,” even though such a specification could undoubtedly have a significant effect on wholesale rates.48

In deciding whether a proposed Commission action crosses the line into an area reserved for the States, several factors are highly relevant.  First, it is critical to ask whether a Commission action “addresses—and addresses only—transactions occurring on the wholesale market” and

43 577 U.S. at 276-77. 44 Id. at 278.  Unless otherwise indicated, references to “wholesale rates” in these comments refer to “both wholesale rates and the panoply of rules and practices affecting them.”  Id. at 277-78.
45 Id. at 279.
46 Id. at 281; see id. (transactions occurring “on the wholesale market have natural consequences at the retail level”).
47 Id. at 280.
48 Id. (emphasis added); see id. at 266, 280 (rule “compelling every consumer to buy a certain amount of electricity on the retail market” would “exceed FERC’s authority” even though it would “necessarily determine the load purchased on the wholesale market too, and thus would alter wholesale prices”); California v. FERC, 495 U.S. 490, 497 (1990) (discussing “zone of exclusive state jurisdiction”).

PDF page 11

11

whether “every aspect of the regulatory plan happens exclusively on the wholesale market.”49  If so, then the Commission has stayed within the lines that Congress drew in Section 201(b).  Those limitations were central to the Supreme Court’s decision in EPSA that regulation of demand response on the wholesale market was within the scope of the Commission’s power.50 Second, it is important to analyze whether the Commission’s “justifications for

regulating … are all about, and only about, improving the wholesale market” such that the wholesale market, rather than the retail market, is the “target at which” the action “aims.”51  Again, the Supreme Court leaned heavily on that factor in EPSA in upholding the Commission’s action as jurisdictionally proper.52  And in invoking the “target” concept, the Court pointed to general principles of preemption law.  In that context, the Supreme Court has looked past the question of whether a government body is using tools that formally fall within its proper sphere of action and considered whether that body is using those tools to functionally intrude on an area outside of its proper sphere.53

Numerous cases illustrate the “targeting” inquiry.  For instance, in Schneidewind v. ANR Pipeline Co., 485 U.S. 293 (1988), which is cited repeatedly in Oneok, Inc. v. Learjet, Inc., 575 U.S. 373 (2015) (on which EPSA relies), the Supreme Court held a state law invalid because “the things [the state law’s] regulation is directed at, the control of rates and facilities of natural gas companies, are precisely the things over which FERC has comprehensive authority.”54  And in

49 Id. at 282.
50 See id. at 279-289.
51 Id. at 282-83; see id. at 287.
52 See id.
53 See id. at 281-282 (twice citing Oneok, Inc. v. Learjet, Inc., 575 U.S. 373 (2015), in which the Supreme Court emphasized in deciding that the Natural Gas Act does not preempt general state antitrust laws “the importance of considering the target at which the state law aims”).
54 Id. at 308.

PDF page 12

12

Hughes v. Talen Energy Marketing, LLC, 578 U.S. 150 (2016), the Supreme Court rejected Maryland’s program to encourage new generation by requiring a new generator to bid and clear in the capacity market in exchange for a guaranteed capacity price.55  The Court held that the program was unlawful even though it worked entirely through the state-jurisdictional domain of payments to generators from retail customers.  The Court concluded that although Maryland “may regulate within the domain Congress assigned to [it] even when [its] law[] incidentally affect[s] areas within FERC’s domain,”56 “Maryland’s program” was targeted at the wholesale market and in substance “set[] an interstate wholesale rate.”57  Those cases involved a state intruding into the federal sphere, rather than vice-versa—but the “targeting” analysis that they undertake is fully applicable in assessing whether the federal government is intruding into a sphere that the FPA reserves for the States.

Third, it is pertinent whether a proposed Commission action would regulate matters that are “subject to regulation by the States.”58  If the States themselves have the jurisdictional authority to develop rules or approve tariffs that carry out essentially the same action that the Commission is considering, then the federal action in question would cross over into what Section 201 calls “any other sale of electric energy”—i.e., retail sales.59  After all, the States have authority to act only within the retail sphere, and federal action cannot be necessary to carry out the FPA’s core purposes if state regulation is otherwise available. 60   Indeed, in ruling in EPSA that the

55 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 158-59 (2016). 56 Id. at 164.
57 Id. at 163.
58 16 U.S.C. § 824(a).
59 Id. § 824(b)(1); see Entergy Texas, Inc. v. Nelson, 889 F.3d 205, 212 (5th Cir. 2018) (“There is no overlap of jurisdiction.”). 60 See NextEra Energy Res., LLC v. FERC, 118 F.4th 361, 368 (D.C. Cir. 2024) (asking “whether the contested assertion of authority is consistent with the statute’s core purposes”).

PDF page 13

13

Commission had stayed within its jurisdictional limits, the Supreme Court relied on the fact that States had no power to regulate wholesale demand response—which meant that if the Commission could not regulate in that area, then no one could.61

B. The Proposal Exceeds The Statutory Limits On The Commission’s
Jurisdiction By Targeting Retail Activities And Thereby Impermissibly
Intruding Into The States’ Regulatory Sphere
1. PJM’s Proposal Impermissibly Intrudes On The States’ Regulatory
Sphere
The Proposal impermissibly takes a federal reliability function—telling distribution utilities how much load must be shed during an emergency—and transforms it into a federal regulatory regime governing which categories of retail customers must procure generation, which retail customers must accept curtailment if they do not, and how those curtailed customers are to be compensated.

The Proposal regulates and targets New Large Loads, which are a specific type of retail customer.  It does so based on retail characteristics:  the size and newness of individual retail loads. The Proposal seeks to force changes to certain retail terms of service for those disfavored loads, requiring EDCs to develop interruptible service that involves curtailment of New Large Loads that do not bring their own new capacity (the “Eligible” New Large Loads, in the Proposal’s parlance). In doing so, the Proposal imposes direct requirements on retail customers and requires ongoing retail-side administration—for instance, confirmation that loads that have brought new capacity have done so within the limits set forth in the proposal.62  In addition, the Proposal’s primary input

61 See EPSA, 577 U.S. at 289-91.
62 See PJM Proposal 59 (setting forth “[r]eporting arrangements between BYONC and New Large Loads” and a “process for PJM to recognize arrangements between New Large Loads and BYONC”).

PDF page 14

14

for determining the quantity of load each EDC must subject to interruptible supply is a forecasted shortage associated with those Eligible New Large Loads.63

As to compensation, the Proposal is even more intrusive into the retail sphere.  Section X of the proposed tariff revisions fixes the rate that retail customers are paid for IRAS—at “50% of the Non-Performance Charge Rate,” or lower under certain circumstances in which an “Eligible New Large Load elects” to accept less—and requires the EDC to pay that amount and (absent a request from the EDC to PJM for a different arrangement) to fund that amount by assessing charges against retail “customers” in its zone or area so as to pay compensation to other retail customers.64 That is effectively a regulation of a retail rate, even though at a load’s election the amount of compensation can go below the 50% amount that the Proposal specifies.

The Proposal contends that “[w]hether a specific New Large Load may be entitled to compensation for provision of IRAS will be determined by state authorities,” that as to compensation “PJM is not mandating any action at the retail or state level,” and that “PJM’s proposal” on compensation “imposes no obligation on any state to do anything.”65  That PJM

63 See id. at 82 (“PJM will issue MW load reduction directives to ‘Electric Distributors to implement reductions in load up to, and capped at, the pre-Delivery Year IRAS obligations they were assigned.’”).  As a practical matter, New Large Loads will be data centers or other commercial or industrial customers.  PJM concedes that it “does not contemplate that residential customers or smaller industrial customers would have peak loads anywhere near 50 MW, which represents, roughly, the electricity consumption of between 25,000 and 50,000 homes.”  Id. at 35.
64 Id. at 102 & n.270; Proposed Tariff, Attachment DD-4, § X (“The rate for the provision of Interim Resource Adequacy Service shall be 50% of the Non-Performance Charge Rate specified in Tariff, Attachment DD, section 10A(e), unless any Eligible New Large Load elects to (i) accept in its retail rates a sum less than 50% of the Non-Performance Charge Rate as compensation for the provision of wholesale Interim Resource Adequacy Service, or (ii) waive receipt in its retail rates any compensation for the provision of wholesale Interim Resource Adequacy Service as contemplated by Tariff, Attachment DD-4, section X(c)… . Following an Interim Resource Adequacy Event, unless the Electric Distributor informs the Office of the Interconnection otherwise in accordance with Tariff, Attachment DD-4, section X(b)(ii), the Electric Distributor shall be responsible for compensating all Eligible New Large Loads that provided Interim Resource Adequacy Service for up to the amount of such service provided.”).
65 PJM Proposal 106-107.

PDF page 15

15

leaves to States the details of how to implement IRAS compensation does not change the reality that PJM’s tariff is targeting the retail domain.  PJM asks the Commission to reach directly into the retail sphere by approving a tariff that regulates the retail rate and the funding of compensation to retail customers—and that is not jurisdictionally permissible.

Thus, the Proposal targets a subset of retail customers in an effort to establish the conditions under which those customers receive electric service—i.e., as EPSA put it, the “terms of sale at retail”66—and dictate the resource arrangements necessary to obtain firm service.  Walking through each of the three factors discussed above that are significant in assessing whether Commission jurisdiction exists—whether the proposed action addresses only transactions on wholesale markets, whether that action is justified only by improving the wholesale market and does not target the retail market, and whether the States could regulate in essentially the same way that the Commission is considering 67 —confirms that adoption of PJM’s Proposal is outside of the Commission’s jurisdictional power.

First, PJM’s Proposal does not address only transactions on wholesale markets, and every aspect of the plan does not happen exclusively on the wholesale market.  As discussed, IRAS cannot work without extensive reliance on retail-customer features:  it requires assessing new loads to decide if they constitute New Large Loads, deciding whether such loads are bringing their own new capacity in a manner that PJM considers adequate, eliminating certain New Large Loads from any possibility of curtailment under IRAS, calculating the total number of megawatts to be curtailed in light of an analysis of Eligible New Large Loads, and dictating the not-to-exceed amount of compensation retail customers will be paid and how such compensation is to be funded.

66 EPSA, 577 U.S. at 280.
67 See Part I.A, supra.

PDF page 16

16

PJM also proposes that under IRAS it will directly instruct that curtailment at the retail level be carried out to (in the words of the proposed Tariff modification) “implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in [an] Electric Distributor’s zone/area.”68  And all of that consideration of retail features and intervention in the retail market is in the service of attempting to force the retail customers that fall into the “New Large Loads” category to operate in a certain manner—for instance, by bringing a certain amount of new capacity that is “actually new and not repackaged and will provide capacity over at least 10 years.”69  In short, PJM’s Proposal is suffused with retail-market involvement.

That is a very far cry from the wholesale-only Commission action that the Supreme Court considered in EPSA, in which wholesale-market operators “administer[ed] the entire program” and “those footing the bill” were only “wholesale purchasers.”  577 U.S. at 282.  But it is not dissimilar to an example given in the Supreme Court’s decision in EPSA of a jurisdictionally impermissible Commission action:  “Suppose, to take a far-fetched example, that the Commission issued a regulation compelling every consumer to buy a certain amount of electricity on the retail market. Such a rule would necessarily determine the load purchased on the wholesale market too, and thus would alter wholesale prices.  But even given that ineluctable consequence, the regulation would exceed FERC’s authority, as defined in § 824(b), because it specifies terms of sale at retail—which is a job for the States alone.”70  The thrust of the IRAS Proposal is similar to that example, as the Proposal seeks to force changes in use of retail electricity and the terms of retail sales, whether by

68 Proposed Tariff § III(a).
69 PJM Proposal 23.
70 EPSA, 577 U.S. at 280; see also Br. for FERC, FERC v. EPSA, No. 14-840 (U.S. July 9, 2015), 2015 WL 4237680, at *40 (a “demand-response program in which wholesale-market operators would somehow provide credits on retail bills to any consumer who reduced its expected use of retail electricity (rather than only those consumers who make bids into wholesale markets)” would “run headlong into Section 824(b)(1) by directly altering the terms of retail sales”).

PDF page 17

17

incentivizing New Large Loads to act differently or by punishing New Large Loads that do not do so.

Second, the justifications that PJM offers are not all about improving the wholesale market, and the Proposal targets the retail market.  PJM essentially says as much, making clear that its Proposal is motivated by issues with a specific type of retail customer and intended to change how retail service is provided to such customers.71  And PJM is focused on those large loads even though, from a wholesale-market perspective, it should not matter whether 50 megawatts of new load comes from one Large New Load or from fifty customers at 1 megawatt each; the distinction between those two load compositions arises only in the retail sphere.72

Accordingly, this is not a circumstance in which a Commission action would merely affect the retail sphere as an incidental result of regulation of a wholesale market.  It is in fact exactly the opposite:  the action the Commission is asked to approve targets the retail market as a means of affecting the wholesale market.  Under Section 201, it is impermissible for PJM to use the connection between the wholesale and retail markets to effect change in the federal sphere through adjustments that fall within the retail sphere—“no matter how direct[] or dramatic” the Proposal’s “impact on wholesale rates” would ultimately be.73

The analysis in the Supreme Court’s “targeting” decisions discussing the jurisdictional division of labor between the Commission and the States is therefore directly on point.  Just as in Schneidewind the state law at issue was invalid because “the things [the state law’s] regulation is directed at, the control of rates and facilities of natural gas companies, are precisely the things over

71 E.g., PJM Proposal 6 (asserting insufficient future commitments of capacity in RPM auctions are “primarily driven by the unprecedented addition of large loads, most notably data centers”).
72 See, e.g., Part II.B, infra (discrimination argument).
73 EPSA, 577 U.S. at 280.

PDF page 18

18

which FERC has comprehensive authority,”74 the focus of IRAS is precisely a thing over which the States have authority:  large new retail loads, as defined by retail-specific characteristics. The fact that PJM is seeking to change a wholesale tariff, and otherwise to use federally regulated tools, does not change that analysis.  In this regard, PJM’s Proposal is closely analogous to the state action that the Supreme Court rejected in Hughes v. Talen.  In Hughes, Maryland was formally using state-jurisdictional tools:  payments to generators from retail customers and retail regulation.  But Maryland was doing so in a way that “disregard[ed] interstate wholesale rates FERC ha[d] deemed just and reasonable” by guaranteeing that a generator that bid and cleared in the capacity market would receive a state-determined payment for capacity regardless of the clearing price, thus in substance “set[ting] an interstate wholesale rate.”75

This case is the mirror image of Hughes.  PJM claims to act by using federal tools— wholesale rates and reliability-related load-shedding requirements—but it is using those tools to target the conditions and rates of retail service to a particular class of retail customers:  new large loads.  Accepting PJM’s Proposal would effectively “disregard” state decisions about what retail customers can obtain service and under what conditions.  That makes PJM’s Proposal different than circumstances in which PJM has traditionally been permitted to require load-shedding, because in those circumstances the impermissible input of specific retail characteristics and specific categories of retail customers is not present.  Looking at the target of a proposed action, and what the regulation does in substance, makes clear that PJM’s Proposal is jurisdictionally impermissible because it steps too far over the wholesale/retail line.

74 485 U.S. at 308.
75 EPSA, 577 U.S. at 280.

PDF page 19

19

Third, the States could institute essentially the same regulatory changes that PJM proposes in IRAS.  Nothing would stop the States, via state-jurisdictional tariffs, from developing interruptible services for large retail customers that do not bring their own capacity and for deciding what compensation to provide to affected customers and how to fund it.  Indeed, Virginia has stated that it is working on model state tariffs along those lines that would go into effect before the date when PJM requests that IRAS go into effect.76  The States would, of course, be fully empowered to use specific retail characteristics in deciding which customers would be subject to that regime and its particular incentives and penalties.  And, in doing so, the States would be operating well within their statutorily protected retail sphere, which typically involves (among other things) deciding how different types of retail customers should be treated and incentivizing preferred generation in a way that is not tied to “a generator’s wholesale market participation.”77 That is a strong indicator that the PJM Proposal is outside of the Commission’s jurisdictional power, even though the Proposal would affect wholesale rates.78

In addition, although the Proposal leaves certain matters to state regulation,79 it does not display the kind of “solicitude toward the States” that was persuasive to the Supreme Court in EPSA.  There, the Commission action in question voluntarily gave States a full “veto power” over that action, “allow[ing] any State regulator to prohibit its consumers from making demand

76 See June 20, 2026 Ltr. from Virginia State Corporation Comm’n to PJM (explaining that “many of the tools necessary to achieve the[] objectives” of PJM’s Proposal “fall within state jurisdiction” and stating that Virginia is working on “model retail tariff structures and regulatory frameworks for consideration by interested state commissions”), available at https://perma.cc/S7C6-C86H; PJM Proposal 88.
77 Hughes, 578 U.S. at 166; see, e.g., id. (“Nothing in this opinion should be read to foreclose Maryland and other States from encouraging production of new or clean generation through measures ‘untethered to a generator’s wholesale market participation.’  So long as a State does not condition payment of funds on capacity clearing the auction, the State’s program would not suffer from the fatal defect that renders Maryland’s program unacceptable.”  (citation omitted)).
78 See p. 10, supra.
79 See PJM Proposal 85-93.

PDF page 20

20

response bids in the wholesale market.”80  That was what the Court referred to when it discussed “a program of cooperative federalism, in which the States retain the last word,” and it was the “finishing blow” that persuaded the Court that the Commission did not “aim[] to obliterate[]” the States’ “regulatory authority.” 81   Although PJM labels the Proposal a form of “cooperative federalism,”82 the label here is misplaced.  The Proposal does not give States veto power and, more to the point, it does aim to interfere with the retail sphere and override state authority—while leaving to the States only a few minor or essentially illusory tasks (as further described below).83

2. PJM’s Proposal Is Not Jurisdictionally Permissible Merely Because
Electric Distributors, In Coordination With The States, Would
Ultimately Select The Specific Customers To Be Curtailed
PJM argues that its Proposal is saved by leaving to the state regulatory sphere the choice of which particular identifiable retail customers will be subject to curtailment under IRAS.84  But that aspect of the Proposal does not render it jurisdictionally permissible.

That is because, regardless of which particular customers are ultimately curtailed, the imposition of the obligation to effectuate curtailment in the first place is necessarily a function of examining the load and generation commitments of a particular type of retail customer.  The Commission does not have the jurisdictional authority to approve a proposal that tries to shape and regulate the retail sphere in those ways,85 regardless of which customers among the disfavored group are ultimately affected and regardless of which entity makes that ultimate choice.

80 EPSA, 577 U.S. at 287-88. 81 Id. 82 PJM Proposal 2, 85, 87.
83 See Part I.B.2, infra.
84 See, e.g., PJM Proposal 86 (“Directing an Electric Distributor, rather than a specific end-use customer, to reduce a quantity of load is in keeping with PJM’s longstanding practice and reflects and respects the allocation of jurisdiction between the federal and state levels.”).
85 See pp. 13-15, supra.

PDF page 21

21

In any event, under IRAS, the States are not truly free to curtail retail customers—the selected customers are for practical purposes, and are intended to be, predetermined by PJM’s focus on Eligible New Large Loads—that is, large loads that did not bring their own new capacity.86  PJM’s Proposal declares that “it does not mandate any state-specific action”; it “avoids the potential for conflicts with state policy determinations”; and it “respect[s] state law choices about whether and how to facilitate implementation of a wholesale paradigm.”87  But the proposed changes to the Tariff and the Proposal itself are to the contrary.

The proposed changes to the Tariff state that the PJM “Office of Interconnection shall … request Electric Distributors to direct that a quantity of Eligible New Large Load Amounts in their respective zone(s)/area(s) be reduced in accordance with an Interim Resource Adequacy Service Action” and that “Electric Distributors shall … execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in the Electric Distributor’s zone/area.”88  In addition, the proposed tariff provision on compensation specifically talks about “compensating all Eligible New Large Loads that provided [IRAS]” and “charging customers in its zone/area to fund any such compensation.”89 The submission could therefore hardly be clearer that under PJM’s Proposal there is no unbounded choice about which retail customers to curtail; rather, IRAS curtailment is only for customers in a specific retail-customer category.

86 E.g., PJM Proposal 86 (“In a Delivery Year in which IRAS applies, PJM will identify, for each zone/area, the Eligible New Large Load Amounts, i.e., MW quantities that are eligible to be called upon to reduce load under IRAS”).
87 Id. at 107-108.
88 Proposed Tariff §§ II(e), III(a) (emphasis added).  Those proposed tariff changes also state that IRAS “is a load reduction service, effective starting with the 2027/2028 Delivery Year, through which Eligible New Large Loads may be compensated for providing load reductions,” and that the proposed registry will “inform which New Large Loads are eligible to be called on to provide” IRAS.  Id. at I(a), I(c).
89 Proposed Tariff § X(b)(i) (emphasis added).

PDF page 22

22

As if that were not enough, PJM’s Proposal says exactly the same thing in numerous places:
• “IRAS is a supplemental capacity product through which Eligible New Large Loads may be directed by the Electric Distributor to reduce their load in response to an Interim Resource Adequacy Service Action called by PJM… . In other words, IRAS is needed to manage the capacity needs of New Large Loads that have not satisfied their capacity needs on their own.”90

• IRAS “will be applicable to ‘[N]ew Large Loads that, as of June 1, 2027, do not bring sufficient capacity to serve their resource adequacy needs and cannot otherwise be served at the 1-in-10 reliability standard[,]’ with load reductions under the service occurring before deployment of Pre-Emergency Load Management.”91

• “IRAS, as proposed, is a service that specifically allows for Large Loads to interconnect without bringing their own capacity, on the condition that ‘they must reduce their load or switch to on-site backup resources under specific, limited’ emergency conditions.”92

• “At bottom, ‘exclusive jurisdiction’ rests with the states to ensure that the appropriate retail customers, i.e., New Large Loads, including data centers—and not residential customers or small industrial customers—are reduced when system conditions call for PJM to require load reductions according to IRAS.”93

Those are just a few of many similar examples.  Accordingly, the notion that selection of retail customers for curtailment under IRAS will extend beyond Large Loads is belied by numerous aspects of the Proposal.

In addition, even setting those statements aside, it beggars belief that under IRAS States would in fact curtail residential customers or other customers that do not fall within the Eligible New Large Load category.  States surely have an incentive to avoid doing so as a political and public-relations matter.  And, as noted, the whole structure of IRAS is designed to disfavor New Large Loads that do not bring their own new capacity by making them subject to a new curtailment regime that is intended to kick in before Pre-Emergency Load Management Reductions.94  If those

90 PJM Proposal 75-76.
91 Id. at 17 (quoting PJM Board July 2026 Decisional Ltr. at 2).
92 Id. at 39 (citation omitted).
93 Id. at 90-91 (quoting PJM Interconnection, 190 FERC ¶ 61,115 at P 68).
94 See p. 6, supra.

PDF page 23

23

New Large Loads are not disfavored in that way, then their incentive to bring their own new capacity would be seriously reduced, and IRAS would no longer carry out the function for which it is intended.  Moreover, the IRAS procedures for curtailment in advance of the existing Pre- Emergency Load Management Reductions would be undermined, as that existing reduction procedure can apply to all kinds of retail customers and is a workable means of interrupting service to reduce load.

For all of those reasons, the supposed “choice” that States are given under the PJM Proposal is illusory.  The curtailment that the Proposal envisions will undoubtedly be carried out against a specific class of retail customers, defined by specific characteristics—just as the amount of any curtailment requirement is dictated by that specific class of customers with those specific characteristics.  That means that the practical effect of IRAS is the same as if PJM directly picked the New Large Loads for interruptible service, which—as PJM recognizes—would be

jurisdictionally impermissible.95
3. Other Considerations Also Cut Against Exercise Of Jurisdiction
Although the Commission need not go further to conclude that jurisdiction is lacking here, it is also worth noting that accepting PJM’s Proposal is not necessary to address large new load issues and would likely have cascading negative effects when the Commission attempts in the future to answer jurisdictional questions like the one posed here.

PJM’s filing all but insists that there is such an immense real-world problem arising from large new loads that the Commission must accept PJM’s specific IRAS Proposal.96  Of course, the

95 PJM Proposal 92 (“[I]n recognition of the jurisdictional divide between PJM and the states and/or RERRAs, PJM will not direct reductions to specific New Large Loads pursuant to IRAS.”).  In this way, the PJM Proposal can be understood to recognize that it is intruding into the retail sphere on curtailment, but then to try to pull back from the jurisdictional precipice at the last moment—to no avail.
96 See, e.g., PJM Proposal 6 (asserting that insufficient capacity commitments have been “primarily driven by the unprecedented addition of large loads, most notably data centers”); id. at 21 (asserting that PJM’s

PDF page 24

24

seriousness of a practical problem is no justification for distorting the plain meaning of a binding jurisdictional statute.97  In any event, PJM’s premise is wrong, because there are other ways to address the problem that do not create jurisdictional issues.  As noted, the States could develop interruptible services for large retail customers that do not bring their own capacity, if the States— with which PJM has been consulting 98 —perceive that a serious problem exists that needs solving.99  And the Commission itself could act in ways that do not raise the fatal jurisdictional issues presented by the IRAS Proposal.  For instance, the Commission could explore other ways to incentivize additional capacity resources, including adding voluntary demand response projects with limited call options.  Last fall, a coalition of supply-side companies, including Constellation, joined with several of the largest data center owners to propose just such additional demand response products.100  Another option would be a return to “market fundamentals” through other market improvements, as discussed in the recent Statement of Principles Regarding PJM signed by National Energy Dominance Council officials and the governors of the States located in the PJM, to spur investment in generation resources.101

There is therefore no reason to accept PJM’s suggestion that the Commission is presented here with a choice between adopting PJM’s Proposal and some sort of large-new-load-inflicted

capacity shortfall is due particularly to “the ‘unprecedented surge in data center load’ at a faster pace than new supply can come online” (citation omitted)).

97 See, e.g., Pereira v. Sessions, 585 U.S. 198, 200 (2018) (explaining that practical considerations “do not justify departing from [a] statute’s clear text”). 98 PJM Proposal 3 (IRAS framework “developed following consultations and discussions with states and stakeholders”).
99 See p. 19, supra.
100 See 20251107-item-03c---joint-stakeholders-proposal.pdf.  As PJM’s Proposal states, PJM also has made other filings with the Commission recently, and plans to make yet others later, to address large new load issues.  PJM Proposal 18-20.
101 See Statement of Principles Regarding PJM, available at https://www.energy.gov/documents/statement- principles-regarding-pjm.

PDF page 25

25

disaster.102  Ahead of the final stakeholder meeting, PJM itself dropped the concept of mandatory curtailment entirely in favor of a proposal that featured only a large load registry.  In advocating for its revised proposal, PJM noted the “issues associated with PJM’s jurisdictional authority to implement its [original] proposal” and the risk of “extended litigation over its authority.”103  PJM also stated that among the Board-level considerations in developing a revised registry-only proposal was the desire to “[r]espect[] jurisdictional boundaries between PJM and states.”104  After the stakeholder process was completed, PJM reversed itself and included the mandatory curtailment proposal in the filing at issue here.105

At the same time, there is a serious risk that accepting PJM’s Proposal as within the scope of the Commission’s jurisdiction would effectively destroy the statutorily mandated distinction between the wholesale and retail spheres.  Retail power is of course inevitably connected to the wholesale market, as such power must be bought at wholesale and transmitted to the distribution system before a retail customer can use it.  If the Commission could permissibly authorize PJM to shape retail service through a wholesale tariff that relies on specific retail-customer characteristics, then it is difficult to see how the statute would bar use of such a federal lever in a wide variety of other situations to target disfavored features of the retail market.  In other words, if PJM’s Proposal

102 See PJM Proposal 16 (“All 11 proposals regarding the concepts addressed by IRAS failed to achieve two-thirds stakeholder support.”); PJM Overrules Its Own Two Thirds Vote (Aug. 14, 2026), https://servola.de/journal/pjm-board-overrules-two-thirds-vote-on-curtailment/.
103  PJM Connect & Manage CIFP Proposal Stage at 1, available at https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02a---pjm-stage-4-proposal- --connect-and-manage---executive-summary.pdf.
104 Id. at 4.
105 PJM to Create Large Load Registry, Proposes to Hold Backstop Auction in October, RTO Insider (July 28, 2026) (“The [PJM’s] board’s decision revives mandatory curtailment after PJM staff dropped the concept from their proposal days before the final CIFP meeting, citing questions stakeholders raised around the RTO’s jurisdictional authority to require curtailment.”), available at https://www.rtoinsider.com/137723-pjm-to-create-large-load-registry-proposes-backstop-auction/.

PDF page 26

26

were jurisdictionally permissible, then so too would be a proposal under which PJM (or some other RTO or ISO) were permitted to ration electric service based on (for instance) use of behind-the- meter solar, deployment of LED lightbulbs, residential demand-response participation, or residential use of energy-star heat pumps.  The upshot would be that States’ independent authority over the retail sphere would be displaced in all kinds of circumstances, contrary to Congress’s statutory design and to the Supreme Court’s analysis in EPSA.106  The Commission should not start down that slippery slope.

Moreover, the Commission should be especially reluctant to do so given the novelty of PJM’s Proposal.  When agencies “‘claim to discover in a long-extant statute an unheralded power’ representing a ‘transformative expansion in [its] regulatory authority,’” there is strong reason for skepticism, particularly when that power is of great “economic and political significance.”107  Here, PJM’s Proposal undermines the obligation to serve all customers, which is a fundamental principle of state-regulated utility service, and does so by relying on the actions of and targeting disfavored retail customers.  That is in and of itself enough to counsel great caution in accepting PJM’s Proposal and to take special care before acting in what is, at a minimum, a highly jurisdictionally questionable area.

C. The Proposal Exceeds The Statutory Limits On The Commission’s
Jurisdiction Because The Proposal Does Not Directly Affect Wholesale Rates
Finally, insofar as PJM’s Proposal is tied to specific retail-customer characteristics, it fails the first part of EPSA’s jurisdictional test:  it does not directly affect wholesale rates.

106 See pp. 10-13, supra.
107 W. Virginia, 597 U.S. at 724; see, e.g., Presidential Memorandum, Directing the Repeal of Unlawful Regulations (Apr. 9, 2025).

PDF page 27

27

It may be true that load additions, taken as a whole, directly affect wholesale rates.  But PJM’s Proposal is not directed at load additions as such—that is, at all load additions, whether they are large or small or somewhere in between.  Rather, the Proposal is directed only at load additions that are individually 50 megawatts or greater and that enter after a certain date.  There is no difference, from the standpoint of assessing the effect on wholesale rates, between (a) a single load addition of 50 megawatts and (b) fifty load additions of one megawatt each, or between (a) a load that enters on June 1, 2027, and (b) a load that enters on May 31, 2027.108  In each instance, (b) can affect wholesale prices the same as (a).

Because the PJM Proposal addresses only the former situations and not the latter ones, it is far from apparent that the effect that the Proposal would have on wholesale rates is sufficiently direct.  The distinctions drawn by PJM’s Proposal do not directly affect wholesale rates—and a proposal in this context that did have such a direct effect would account for all additional load, regardless of its size or when it energizes.

The PJM Proposal takes a much more roundabout approach precisely because its focus is not wholesale rates at all—it is rather the behavior of specific types of retail customers.  Regulation of the retail sphere undoubtedly does affect wholesale rates down the line, but it does not affect those rates sufficiently directly to pass the EPSA test.109  A contrary view would improperly give Section 201 “near-infinite breadth” and swallow up the States’ area of jurisdictional authority.110

D. The Authorities On Which PJM Relies Do Not Support Jurisdiction Here
PJM tries to analogize its IRAS Proposal to various prior decisions by courts and this Commission.  But none of those authorities justifies the Commission’s exercise of jurisdiction here.

108 See p. 2, supra.
109 See EPSA, 577 U.S. at 277-79.
110 Id. at 278.

PDF page 28

28

For instance, PJM tries to rely on EPSA itself.111  But, as discussed above, although EPSA sets forth the governing jurisdictional test, the facts here are readily distinguishable from the facts in EPSA.  There, the challenged wholesale rule regulated participation in a wholesale market, as a retail customer voluntarily offered a demand reduction into a FERC-jurisdictional wholesale market and received wholesale-market compensation.112  That rule affected retail sales, but the nature of the retail service was not an input to the wholesale rule.113  Here, the nature of the retail service is just such an input, and IRAS effectively regulates the conditions under which certain specified customers consume retail power.

PJM also relies on decisions such as New PJM Companies, 107 FERC ¶ 61,272 (2004), for the proposition that the Commission has decided that PJM can determine the location, quantity and timing of curtailment, while a distribution utility determines the manner in which retail load is actually curtailed. 114   But New PJM Companies involved procedures for a transmission emergency—and no one questions that Commission-mandated curtailment can be proper in that circumstance.  The problem here is distinctions and curtailment rules based on specific retail characteristics, with the resulting intrusion into the retail jurisdictional sphere; that problem did not arise in New PJM Companies.

In addition, PJM cites the Commission’s 2025-2026 Large Load proceedings and says that they establish that Large Loads implicate both federal and state interests.115  That is undoubtedly true, but it says nothing about whether the specific design of the PJM Proposal is jurisdictionally permissible.  As discussed, there are alternative ways that the Commission could regulate Large

111 PJM Proposal 91.
112 See EPSA, 577 U.S. at 278-79.
113 See id. at 281. 114 E.g., PJM Proposal 85 n.228.
115 E.g., id. at 2, 89.

PDF page 29

29

Loads that would not present the same jurisdictional problems that doom IRAS.116  And the Commission and States could take separate actions, each in their own jurisdictional sphere, that would harmoniously address large-load-related issues.

II. The Commission Would Unduly Discriminate Based On Load Size, Load Date, And Resource Vintage If It Accepted PJM’s Proposal

PJM’s Proposal unduly discriminates in at least two respects:  (1) against certain load, based on load size and load in-service date, and (2) against certain generation, based on resource vintage.  Those are independent reasons why the Commission should reject the Proposal.

A. The Commission Must Reject The Proposal Unless PJM Shows That The
Proposal Is Not Unduly Discriminatory And Preferential
The FPA prohibits undue discrimination in utility rates and dealings.  Specifically, under FPA Section 205, a utility is barred from “grant[ing] any undue preference or advantage,” “subject[ing] any person to any undue prejudice or disadvantage,” or “maintain[ing] any unreasonable difference in rates, charges, service, facilities, or in any other respect.”117  If the Commission finds that a “rate, charge, or classification” is “unduly discriminatory or preferential,” it must “determine the just and reasonable rate, charge, classification, rule, regulation, practice, or contract to be thereafter observed and in force, and … fix the same by order.”118 Congress also prohibited undue prejudice or disadvantage in the specific circumstance at issue here:  the accommodation of anticipated capacity shortages.  Section 202(g) of the FPA (added by the Public Utilities Regulatory Act of 1978) mandates certain Commission obligations with respect to “any anticipated shortage of electric energy or capacity which would affect [any]

116 See p. 24, supra.
117 16 U.S.C. § 824d(b).
118 16 U.S.C. § 824e(a).

PDF page 30

30

utility’s capability of serving its wholesale customers.”119  In that circumstance, the Commission “shall require” each utility to “accommodate” such capacity shortage “in a manner” that “provide[s] that all persons served directly or indirectly by such public utility will be treated, without undue prejudice or disadvantage.”120

The trigger for Section 202(g) has plainly been met, as PJM’s proposal is (by its own account) motivated by “[i]nsufficient commitments of capacity” in the 2027/2028 and 2028/2029 RPM Auctions that PJM says “have given rise to resource adequacy shortfalls.”121  There is also no question that New Large Loads qualify as “persons served directly or indirectly” by the public utilities within PJM. 122  Thus, in addition to reviewing the Proposal under Section 205, the Commission must ensure that IRAS complies with the mandate of Section 202(g), where Congress expressly reiterated that discrimination should be avoided even when the system faces a shortfall. In substance, that means that the Commission must ensure that IRAS “equitably accommodate[s] service” to “direct retail customers,” including New Large Loads.123

Under the FPA, it is PJM, as the filer of the tariff revision, that bears the burden to show that its proposal is not unduly discriminatory.124  The Commission, in turn, must “provide an adequate explanation before it treats similarly situated parties differently.” 125   In evaluating discrimination, the “critical determination” is whether a difference in treatment is “unreasonable

119 16 U.S.C. § 824a(g).
120 16 U.S.C. § 824a(g).
121 PJM Proposal 6. 122 61 Fed. Reg. 41,780 (Aug. 12, 1996) (stating that Section 202(g) requires “contingency plans respecting shortages of electric energy or capacity which would equitably accommodate service to both direct retail customers and those served by utilities supplied at wholesale by the public utility” (emphasis added)).
123 Id.
124 Sacramento Mun. Utility Dist. v. FERC, 616 F.3d 520, 537 (D.C. Cir. 2010); Electricity Consumers Resource Council v. FERC, 747 F.2d 1511, 1515 (D.C. Cir. 1984). 125 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 267 (D.C. Cir. 2014).

PDF page 31

31

or undue.”126  Undue discrimination means that a practice “provides different treatment to different classes of entities” and those entities are “similarly situated.”127  The determination that entities are similarly situated “does not mean that there are no differences between them,” but only “that there are no differences that are material to the inquiry at hand.”128

B. PJM’s Proposal Unduly Discriminates Based On Load Size And Load Date
PJM’s Proposal unduly discriminates against Large Load customers because it singles them out for interruptible service and load reduction based on their size and date of entry—yet those characteristics are not material distinctions justifying that unfavorable treatment. The Proposal by its terms differentiates New Large Load based on size and date of entry. Large Load is defined as “end-use customer(s) load that has a cumulative peak load of 50 megawatts or greater at a single electrical site behind one or more points of interconnection.”129 And New Large Load is defined as “Large Load that is in-service after June 1, 2027,” with the “relevant in-service date” potentially shifting in future years.130  The Proposal then treats New Large Load unfavorably:  Eligible New Large Load is subject to curtailment, in the event of a shortage, before Pre-Emergency Load Management Reductions or emergency measures are taken.131

Yet New Large Loads are similarly situated to relevant comparators, notwithstanding their size and date of entry.  The stated purpose of IRAS is to address “resource adequacy shortfalls—

126 Complex Consol. Edison Co. of New York, Inc. v. FERC, 165 F.3d 992, 1013 (D.C. Cir. 1999).
127 Calpine Corp., 171 FERC ¶ 61,035, P 318 (2020); Complex Consol. Edison Co. of New York, Inc. v. FERC, 165 F.3d 992, 1013 (D.C. Cir. 1999).
128 Calpine Corp., 171 FERC ¶ 61,035, P 318.
129 PJM Proposal 31.  Under certain circumstances, “all affiliated load facilities within a one-mile radius will be considered a single electrical site.”  Id.
130 Id.
131 See id. at 21-22.

PDF page 32

32

and associated real-time operational issues.”132  Although aggregate load size surely matters to resource adequacy, PJM has not demonstrated that individual customer load size is relevant to the resource-adequacy harm that the Proposal seeks to address—except to the extent that individual customers contribute to aggregate load.  The baseline equitable principle, which PJM has not contested, is that every customer “is economically marginal,” meaning that “the costs of increased demand may equitably be attributed to every user.”133  Specifically, PJM has not shown that there is a material difference with respect to resource adequacy between one new 50 MW facility and 50 new one MW facilities in the same area.  Yet PJM proposes that only New Large Loads would be prioritized for service interruptions.

PJM also has failed to demonstrate that the date of interconnection is relevant to any operational and resource adequacy challenges created by the load.  Indeed, setting aside the fact that PJM’s justification for distinguishing Large Loads based on size is unjustified, PJM’s own stated rationale for differentiating New Large Loads has nothing to do with date in service; it relates only to “size, operational behavior, and unique potential to impact the transmission system.”134  Yet under the Proposal, a data center that achieved commercial operation on May 31, 2027, is exempt from IRAS entirely—free from pressure to enter into new-capacity arrangements, and free from the threat of load reduction requests that precede pre-emergency load management response. 135   By contrast, a nearby, identically sized data center that achieves commercial operation on June 1, 2027, is subject indefinitely to the consequences of IRAS.

132 PJM Proposal 6; see id. (“The IRAS and the related revisions proposed herein support system reliability in the PJM Region”).
133 BNP Paribas, 743 F.3d at 268-69 (quoting Southeastern Michigan Gas Co. v. FERC, 133 F.3d 34, 41 (D.C. Cir. 1998)).
134 PJM Proposal 96. 135 Id. at 17.

PDF page 33

33

The D.C. Circuit has rejected a Commission decision that would have allowed a scheme, like PJM’s Proposal, that disfavored new customers—there, by charging new customers, but not historic customers, for the cost of base gas replenishment needed to maintain service levels.136 The court of appeals reasoned that the Commission’s “cost causation” principle “generally calls for giving the same treatment to new and continuing customers.”137  That approach is economically rational:  “Where ‘all customers cause the incurrence of the costs,’” sharing burdens equally among customers “forces each set ‘to weigh the marginal benefits of the capacity to them against the marginal costs they impose on society by continuing to make demands.’”138  Here, all load—large and small, new and old—equally cause the need for capacity.  Accordingly, arbitrarily singling out a subset of load as PJM proposes is inconsistent with the FPA and governing precedent. The Commission’s recent order in Basin Electric Power Cooperative also is instructive.139 Basin submitted a Section 205 proposal to establish special wholesale power sales rate schedules for cryptocurrency (“crypto”) operations and other new large loads.140  Specifically, Basin wanted to charge loads related to crypto mining operations in a different (and more expensive) way than other loads.141  Basin also sought to impose the same rate structure as for crypto loads on non- crypto loads larger than 75 MW, but would have allowed those large loads to transition to the (cheaper) generally applicable rate schedule with five years’ notice.142

136 BNP Paribas, 743 F.3d at 266.  Although the case involved the Natural Gas Act, that statute has a parallel requirement that rates must not be unduly discriminatory, see 15 U.S.C. § 717c(b), and the Court expressly recognized the “rough equivalence” between the Natural Gas Act and the FPA, BNP Paribas, 743 F.3d at 269-70.
137 Id. at 268. 138 Id. at 268 (quoting 1 Alfred E. Kahn, The Economics of Regulation 140 (1988) (citation omitted)).
139 Basin Electric Power Cooperative, 188 FERC ¶ 61,132 (2024).
140 Id. P 1.
141 Id. P 10.
142 Id. PP 17, 18.

PDF page 34

34

Basin argued that the differential treatment of crypto loads and large loads was justified because of the volatility of those loads.  Serving crypto loads through market-price pass-throughs was necessary, Basin asserted, to reduce the risk that Basin would “construct new generation to serve Crypto Loads that will ultimately relocate in the near future,” as that would “result in stranded assets.”143  For large loads, Basin stated, federal tax incentives had spurred investment in “large industrial, manufacturing, commercial, and innovative facilities,” but such funding could be “easily withdrawn,” again creating the risk that investment costs related to new generation resources could be stranded.144

The Commission rejected Basin’s proposal as unduly discriminatory.145  The Commission explained that there was “a risk of stranded assets when any large project is built in Basin’s service territory,” yet Basin subjected only crypto loads to disfavored treatment.146  Even though Basin claimed that both crypto loads and large loads were volatile, only crypto loads were excluded from the generally applicable rate schedule indefinitely—while large loads could transition to the generally applicable rate schedule after five years.147  And there was no showing that crypto loads were “more likely to ‘quickly shut down and move’” than other large loads, such as data centers.148 Although the Commission was “sympathetic to Basin’s concerns regarding its ability to serve load growth reliably and economically,” it rejected the proposal as unlawful discrimination.149 The Commission’s rejection of Basin’s proposal maps directly onto PJM’s Proposal here. PJM has raised concerns about load growth, resource adequacy, and reliability, but PJM fails to

143 Id. P 16.
144 Id. P 63.
145 Id. P 94.
146 Id. P 95.
147 Id. P 97.
148 Id. P 97.
149 Id. P 99.

PDF page 35

35

support the premise of its Proposal that New Large Loads pose a greater threat to those values than other kinds of load.  There is a risk of resource adequacy implications for all loads (regardless of individual size or date of interconnection).

PJM claims that “[t]he IRAS framework does not single out New Large Loads … because they are new or large.”150  But the Proposal demonstrates just the opposite:  it defines New Large Loads exclusively based on their date and size.  PJM also argues that Large Loads can “pose[] specific challenges to transmission system operation.”151  To be sure, new data centers may be large and fast-growing, as well as politically salient.  But the question for purposes of the discrimination inquiry is not whether Large Loads are different; they are indisputably larger, as a categorical matter.  The question is whether they are different in a way that is “material to the inquiry at hand.”152  Because PJM has not shown that 50 megawatts of large load has a different impact on reliability than 50 aggregate megawatts of small load, PJM’s proposed differential treatment as to interruptible service and curtailment is not warranted.

PJM also points to a recent Commission decision accepting a proposal by Southwest Power Pool (“SPP”) to add a new large load service product dubbed Conditional High Impact Large Load Service (“CHILLS”).153  The analogy between IRAS and CHILLS does not hold.  As a threshold matter, “participation in CHILLS is entirely voluntary.”154  CHILLS provides “an accelerated path towards transmission service” for large loads that could not yet obtain firm transmission service

150 PJM Proposal 99.
151 Id. at 96 (citation omitted); see also id. at 99 (contending that Large Loads “are the cause of the recent reliability shortfall” because of “their inherent concentration of demand and the rapidity at which their cumulative demands have grown”).
152 Transmission Agency of N. Cal. v. FERC, 628 F.3d 538, 549 (D.C. Cir. 2010).
153 Southwest Power Pool, Inc., 195 FERC ¶ 61,196, P 84 (2026); see PJM Proposal 97.
154 195 FERC ¶ 61,196, at P 103.

PDF page 36

36

because network upgrades were not yet in place.155  And for such loads, it offers “a new non-firm transmission service” that “is subject to curtailment and interruption on a non-discriminatory basis when the transmission system is constrained or under emergency or other unforeseen conditions.”156  In approving CHILLS, the Commission emphasized “key limitations … such as the interim nature of the service” and its “maximum term of seven years.”157  By contrast, the IRAS program is not voluntary, it is not interim, and it carries no maximum term.  Nor is it consistent with the nature of non-firm transmission service, which is classified and compensated differently.158  Instead, IRAS imposes an involuntary curtailment condition on certain large firm Network Integration Transmission Service (“NITS”) customers—without any expiration date and before even relying on Pre-Emergency Load Management Reductions or emergency measures.159 PJM also suggests that the Proposal does not unduly discriminate against New Large Load customers because they will still be served by LSEs taking NITS and “will—like other NITS customers—have their transmission service curtailed after non-firm customers.”160  But the fact

155 Id. P 41.
156 Id. P 7, 10.
157 Id. P 84.
158 See PJM Interconnection, 195 FERC ¶ 61,209, P 551 (2026) (approving PJM’s Interim NITS service product as just and reasonable because it was “consistent with … the nature of the transmission service as a non-firm transmission service for which Eligible Customers do not pay generation capacity charges”).
159 PJM also argues that Large Loads can be treated “as a separate category” consistent with a recent Commission order to show cause.  See PJM Proposal 96 & n.259 (citing June 2026 Order to Show Cause, 195 FERC ¶ 61,211, P 50 (2026)).  The order to show cause responded to an advance notice of proposed rulemaking (ANOPR) addressing “urgent challenges associated with providing the transmission service needed to serve the ongoing influx of large loads while maintaining reliability and affordability.”  Id. P 1. That context was different, because it recognized that large loads may present distinct transmission-service issues with respect to reliability.  Id. P 1.  The Commission did not make any merits determination on a specific proposal, and it expressly did not address the appropriate treatment of large loads with respect to the need for generation capacity.  To the contrary, the Commission acknowledged that resource adequacy was “not expressly contemplated in the ANOPR” and simply ordered PJM to submit a future informational report on resource adequacy.  Id. PP 102, 104.
160 PJM Proposal 94, 100.

PDF page 37

37

that Eligible New Large Loads retain their status as “NITS customers” is beside the point.  The problem is not how New Large Loads are labeled or even how they are treated vis-à-vis non-firm customers.  It is that they are subject to IRAS based on size and in-service date—in other words, subject to curtailment before other NITS customers unless they incur the unique burden of bringing their own new capacity—even though those characteristics do not correlate to the loads’ relative impacts on the stated objectives of IRAS.

C. PJM’s Proposal Unduly Discriminates Based On Resource Vintage
The IRAS proposal also is unduly discriminatory because it treats existing and new capacity resources differently.  Under the Proposal, if “a New Large Load does not want to provide IRAS, it needs to contract with new capacity that meets the BYONC gating criteria, which are designed to ensure the capacity is actually new and not repackaged and will provide capacity over at least 10 years.”161  “[C]apacity already on the system would not fall within the definition of BYONC.”162  Yet PJM says nothing to justify why “new” capacity is different from existing generation when existing and new resources provide the very same call option for capacity, energy, and ancillary services products.163  It should not matter whether a Large Load customer contracts with a new gas plant or contracts with an existing plant; in both cases, the grid will benefit from megawatts in the same way.

161 Id. at 23; see id. at 50 (“PJM is proposing to allow New Large Loads to remove themselves—in whole or in part—from the MW eligible for IRAS where such loads bring new capacity to the PJM region”).
162 Id. at 52; see id. (“the capacity must be new to the PJM system, not just new to the capacity market”).
163 BYONC resources must meet specific eligibility requirements described in PJM’s Proposed Tariff, Attachment DD-4, § VI(b).  They must (i) “be supported by one of” (1) a new-build generation resource;
(2) incremental capacity created through an uprate of Existing Generation Capacity Resources; (3) incremental capacity created by utilization of Surplus Interconnection Service; (4) repowering of a deactivated generation resource that deactivated prior to April 10, 2026; (5) incremental capacity created by an Existing Generation Capacity Resource’s change to a more efficient fuel type; or (ii) be Demand Resources or DER Capacity Aggregation Resources that meet specified conditions.

PDF page 38

38

Indeed, the general rule is that “new entrants and existing suppliers” should be “compensated comparably,” absent a demonstration why they are not comparable for relevant purposes.164  As the D.C. Circuit has explained, any proposal that differentiates between new and existing generators must demonstrate “how” new and existing suppliers “are not similarly situated and in what respects the reasons are material” to the proposal.165

Thus, the Commission has rejected a PJM proposal to provide price assurance to new entry projects because it failed to adequately serve PJM’s twin objectives—to “attract new entry when needed” but also “to retain existing efficient capacity.”166  The Supreme Court in Hughes v. Talen acknowledged the Commission’s reasoning:  “Both new entry and retention of existing efficient capacity are necessary to ensure reliability and both should receive the same price so that the price signals are not skewed in favor of new entry.”167  Applying similar principles, the Commission also rejected PJM’s recent proposal to implement a framework for computing Effective Load Carrying Capability (“ELCC”) for certain supply resources.168  The proposal included a “transition mechanism” that resulted in favorable treatment for resources that entered the market earlier, which the Commission rejected as undue discrimination. 169   The Commission reasoned that existing resources and newer resources “are similarly situated” because they “share a common set

164 PJM Interconnection, LLC, 128 FERC ¶ 61,147, P 103 (2009); see id. n. 60 (citing 1 Alfred E. Kahn, The Economics of Regulation 140 (1970), for the proposition that “prices for new and existing customers should be the same”).
165 New England Power Generators Ass’n, Inc. v. FERC, 881 F.3d 202, 213 (2018) (granting petitions for review that challenged a provision allowing new suppliers to lock in a guaranteed auction price for seven years, as well as a provision requiring a locked-in supplier to offer capacity as a price-taker).
166 PJM Interconnection, LLC, 128 FERC ¶ 61,157, P 102.
167 Hughes, 578 U.S. at 158 (quoting PJM, 128 FERC ¶ 61,157).
168 PJM Interconnection, LLC, 175 FERC ¶ 61,084, P 5 (2021).  In the Commission’s order, ELCC resources were defined as resources that are unable to maintain output at a stated capability continuously on a daily basis without interruption. 169 Id. P 8.

PDF page 39

39

of operational characteristics and are reasonably homogeneous with respect to their impact on system resource adequacy.”170  Nonetheless, the Commission explained, PJM’s Proposal would “unreasonably discount the capacity value of ELCC Resources that enter the market at a later date, despite the fact that these resources are likely to provide similar capacity value to existing ELCC resources”—thus demonstrating undue discrimination.171

The IRAS proposal similarly fails to demonstrate “how” new and existing resources “are not similarly situated and in what respects the reasons are material” to the proposal.172  PJM’s stated objective through IRAS is to “restor[e] resource adequacy” by assuring sufficient capacity to serve load, especially New Large Loads.173  Yet PJM would treat two generating resources differently based on whether they are “new,” even if they can provide the exact same capacity. That is contrary to the straightforward principle that “[b]oth new entry and retention of existing efficient capacity are necessary to ensure reliability.”174

The practical effect and design of PJM’s Proposal underscore that it intentionally disfavors capacity that would aid the system simply because it is not BYONC-qualifying new capacity.  In practice, the Proposal will disadvantage existing resources in a manner that is self-reinforcing: existing resources are excluded from providing capacity that protects against IRAS, making it less likely that those resources will contract with a New Large Load, depriving them of a significant source of revenue, and making it more likely they will exit the market and increase the resource

170 Id. P 108.
171 Id. P 17 (emphasis added); see id. P 108 (“The transition mechanism would discriminate between resources in a class based on vintage despite the fact that all resources within a class bear equal responsibility for the decrease in the capacity contribution of their ELCC Class.”).
172 New England Power Generators, 881 F.3d at 213 (granting petitions for review that challenged a provision allowing new suppliers to lock-in a guaranteed auction price for seven years, as well as a provision requiring the locked-in suppliers to offer capacity as a price-taker).
173 PJM Proposal 17.
174 Hughes, 578 U.S. at 158 (citing PJM Interconnection, LLC, 128 FERC ¶ 61,275 (2009)).

PDF page 40

40

adequacy shortfall.175  As a matter of design, PJM’s Proposal also would exclude from the demand curve the megawatts of New Large Loads that have not entered into BYONC arrangements or do not have RBP UCAP MW.176  PJM would seek to artificially “protect residential customers from capacity price increases resulting from the effects of New Large Loads”177 by including New Large Loads in the VRR Curve only where they have capacity arrangements, so that “the impact of including such load in the demand curve is counterbalanced by the inclusion of a commensurate amount of additional Capacity Resources that are added to the supply curve.”178 The result is a design that intentionally blunts the market signals that would have encouraged new entry and the retention and cultivation of existing resources, replacing those signals with a pathway to encourage only BYONC-qualifying capacity.  That design privileges new resources while discouraging other resources, even though those others are likewise capable of providing the very same reliability value through megawatts.  That provides still more evidence that PJM’s Proposal unduly discriminates and should be rejected.  Even “a difference in treatment otherwise justified” (which the vintage distinction is not) “might be less so if it had an anticompetitive impact.”179

175 See pp. 51-52, infra (further discussing this problem).
176 PJM Proposal 109; see id. at 110-111 (justifying this exclusion based on “commitment of New Large Loads to cover their own energy and capacity needs”).
177 Id. at 23-24.
178 Id. at 115.
179 Town of Norwood v. FERC, 202 F.3d 392, 404 (1st Cir. 2000) (“the agency might be faulted if it declined even to inquire into a well-supported claim of this kind”).

PDF page 41

41

III. The Commission Must Reject PJM’s Proposal Because Market Design Flaws Make The Proposal Unjust And Unreasonable

Under Section 205 of the FPA, PJM bears the burden to demonstrate both that its proposed tariff revisions are not unduly discriminatory and that they are “just and reasonable.” 180  To evaluate whether the tariff can be approved as just and reasonable, the Commission must engage in reasoned decision making,181 including by “examin[ing] the relevant data and articulat[ing] a rational connection between the facts found and the choice made.”182

The Proposal fails that test on several grounds.  First, curtailing New Large Load before calling on emergency resources is irrational and detrimental to proper energy price formation and reliability.  Second, excluding New Large Load from the VRR Curve used in RPM Auctions to the extent that the load lacks sufficient BYONC (or Allocated RBP UCAP MW) will substantially undermine RPM’s operation and harm the capacity market and customers, reflecting the overall economic irrationality of the Proposal and its inconsistency with the design of the market.  Third, the Proposal unreasonably fails to allow any qualifying BYONC to be replaced by other qualifying BYONC and unreasonably limits the resources that qualify as BYONC to resources that cleared an auction for the first time in the Base Residual Auction for certain delivery years rather than in any auction for those years.  In explaining those points below, Constellation cites and relies on the accompanying September 3, 2026 affidavit of Aaron T. Patterson (which is attached to this filing as Appendix A).

180 16 U.S.C. §§ 824d(a)-(e), 824e(a); Advanced Energy Management Alliance v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017).

181 TransCanada Power Marketing Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. 2015).
182 West Deptford Energy, LLC v. FERC, 766 F.3d 10, 17 (D.C. Cir. 2014) (citation omitted).

PDF page 42

42

A. PJM’s Proposal To Curtail New Large Load Prior To Calling On Emergency
Resources Is Unjust And Unreasonable
When faced with a potential or actual capacity shortage, PJM currently undertakes a cascading series of emergency actions that are aligned with NERC Energy Emergency Alert Level classifications (EEA1 through EEA3).  PJM proposes to place IRAS “at the beginning of PJM’s actions” in the event of an EEA1 situation 183 —meaning that an IRAS Action would be implemented to reduce load prior to calling on Pre-Emergency Load Management Reductions.184 In other words, “while IRAS and Pre-Emergency Load Management Reductions would both be categorized as EEA1 actions, … PJM will generally call on IRAS before Pre-Emergency Load Management Reductions to address an Emergency.”185

PJM’s Proposal to call on IRAS prior to Demand Response is not just or reasonable.  The bedrock principle of least-cost economic dispatch ordinarily calls for using available resources in increasing order of marginal cost, which maximizes the total social surplus for all market participants.186  Although emergency conditions may alter certain dispatch priorities, they do not eliminate the benefits of taking less costly actions before more costly actions of materially equal reliability.187  By contrast, deploying higher-cost emergency actions before lower-cost actions of

183 PJM Proposal 22; see id. at 80, Fig. 2 (placing “IRAS Large Load reduction” prior to “Pre-Emergency DR” in the chronology of PJM emergency procedures).

184 Pilong Affidavit ¶ 20; see id. ¶ 26 (“In real-time, PJM Dispatch will deploy Interim Resource Adequacy Service Actions before Pre-Emergency Load Management Reduction Actions.”).  Pre-Emergency Load Management Reduction Actions are the final step in EEA1, taken just before Emergency Load Reduction Action, which triggers an escalation to EEA2.  PJM Manual 13, at pp. 82-83.
185 PJM Proposal 82.  PJM proposes to revise its Tariff to define an Interim Resource Adequacy Service Action as an Operating Instruction “to reduce load prior to calling on Pre-Emergency Load Management Reductions after determining that economic real-time supply may not be sufficient to maintain reserves to meet applicable Reserve Requirements and/or Interconnection Reliability Operating Limits within prescribed limits and prevent cascading outages.”  PJM Proposal 84 n.224.
186 Patterson Affidavit ¶ 11.
187 Id. ¶ 12.

PDF page 43

43

equivalent effect “unnecessarily increases the total costs borne by market participants and reduces total surplus.”188

As a result, “during emergency conditions PJM should seek to take lower cost actions before it takes higher cost actions if possible” and “should design its emergency action protocols and emergency action deployment order accordingly.” 189  Prior to its IRAS proposal, PJM’s approach aligned with those principles:  for instance, PJM represented in an August 2025 presentation that an effective Operating Reserve Demand Curve “should ensure that 1) all more cost-effective actions are taken prior to engaging more expensive emergency procedures,” and “2) that those costs are made transparent to the market.”190

Yet PJM now proposes to curtail IRAS load before calling on Demand Response, which blatantly violates the core least-cost dispatch principle because curtailment of IRAS load is likely to be significantly more costly than Demand Response.191  Loads offering Demand Response represent a self-selected population that has voluntarily agreed to curtail in response to PJM instruction in emergency conditions, in exchange for compensation as capacity resources in the RPM Auction and a minimum dispatch payment per MW-hour of curtailment when deployed.192 Those loads have already weighed their own assessment of interruption costs—from business disruption or similar harms—against an established compensation scheme and determined that the trade-off is economically beneficial to them.193  By contrast, Eligible New Large Loads that would

188 Id. 189 Id.
190 PJM, Operating Reserve Demand Curves at 14, https://www.pjm.com/-/media/DotCom/committees- groups/task-forces/rcstf/2025/20250813/20250813-item-03---operating-reserve-demand-curves.pdf (last updated Aug. 13, 2025).
191 Patterson Affidavit ¶ 14.
192 Id. ¶ 15.
193 Id.

PDF page 44

44

be subject to IRAS have not made such a choice.  Loads subject to IRAS may include customers that have not elected Demand Response precisely because their own interruption costs are too high or their operating characteristics prevent them from meeting the notice and response time required to provide Demand Response.194  By reducing IRAS load before calling on customers that have voluntarily offered load reductions, PJM would intentionally and unnecessarily prioritize higher- cost over lower-cost actions—contrary to fundamental principles of economic and market rationality.195

PJM has not pointed to any reliability or resource adequacy benefit that would justify that unreasonable result.  In fact, IRAS curtailments would be implemented by EDCs rather than directly by PJM, and the manner in which curtailment is physically implemented would be left to the States, making physical performance in response to PJM instruction less certain and less visible. By contrast, Demand Response resources are deployed directly in response to PJM instruction and have undergone a rigorous accreditation process to verify that they can perform as required; they also are subject to testing and performance measurement and can be penalized for nonperformance.196

For that reason, too, PJM’s Proposal to prioritize curtailment of IRAS is fundamentally irrational.  PJM assumes that IRAS is effectively a reliable capacity resource without any PJM- overseen accreditation or performance assurance whatsoever.

PJM contends that its sequence is rational on the ground that engaging Pre-Emergency Load Management before IRAS “would reduce the incentive for New Large Loads to bring new

194 Id. ¶ 17.
195 Id. ¶ 18.
196 See generally RAA Schedule 9.2, available at https://agreements.pjm.com/raa/43707; PJM Manual 18, available at https://www.pjm.com/-/media/DotCom/documents/manuals/m18.ashx.

PDF page 45

45

capacity to the system, as they would be insulated by the Demand Resource capacity products.”197 Market incentives point the opposite way:  placing properly compensated voluntary load reduction ahead of involuntary load reduction in the hierarchy of emergency actions will support the efficient functioning of the PJM energy market, which will in turn provide the market price signals necessary to stimulate the addition of new resources when needed. 198  In any event, PJM’s purported rationale is not sufficient to justify sequencing a less economically rational and potentially less reliable option above voluntary, accredited Demand Response during a capacity shortage.

PJM also has suggested that deploying Demand Response prior to IRAS would reduce the economic incentive for customers to offer Demand Response199—but that concern is misplaced. Demand Response receives both a capacity payment and a per-MWh payment for deployment.  In contrast, PJM proposes that IRAS would receive no capacity payment; for deployment, PJM proposes a rate for IRAS of no more than 50 percent of the capacity Non-Performance Charge Rate and potentially far less than that amount.200  The result is an estimated payment around $5,000 per MWh of curtailment for Demand Response, compared to $1,500 per MWh of curtailment for IRAS.201  Given those “starkly different economics,”202 a significant amount of load would likely remain willing to elect to provide voluntary Demand Response.

197 PJM Proposal 80. 198 See, e.g., Energy Price Formation, FERC, https://www.ferc.gov/industries-data/electric/electric-power- markets/energy-price-formation  (last updated June 17, 2020) (when “actions taken to avoid reserve deficiencies are not priced appropriately … , the price signals sent when the system is tight will not incent appropriate short- and long-term actions by resources and load”). 199 PJM Proposal 80.
200 Id. at 102.
201 Patterson Affidavit ¶ 17. 202 Id.

PDF page 46

46

B. PJM’s Proposal To Exclude New Large Load Without Sufficient BYONC
From The Demand Curve Used In RPM Auctions Is Unjust And Unreasonable
PJM also proposes to exclude New Large Load from the VRR Curve used in RPM Auctions to the extent that the load lacks sufficient BYONC (or Allocated RBP UCAP MW).203  That exclusion is unjust and unreasonable because it will substantially undermine the RPM’s structural integrity, removing actual demand without removing a matching amount of accredited capacity (as PJM does with the Fixed Resource Requirement option).  That will harm long-term resource adequacy, the capacity market, and customers’ pocketbooks by muting the price signals that are necessary to encourage new entry and retain existing resources.  Indeed, this aspect of the Proposal highlights the degree to which the Proposal is inconsistent with the market’s design and undermines the RPM’s ability to attract and retain market-based supply—thereby exacerbating an existing negative spiral that PJM itself has identified as a serious threat.204 Under normal circumstances, new load growth would be reflected in the RPM demand curve, which in turn would send a market signal that additional supply is needed and that existing supply should be retained.205  PJM proposes to instead exclude New Large Loads from the demand curve to the extent that they lack arrangements with sufficient BYONC.  The result is that no demand signal will be sent to the market in connection with any New Large Load that enters without sufficient BYONC.  If New Large Load does contract with sufficient new capacity to avoid IRAS, PJM proposes to add that load to the VRR Curve but require a commensurate quantity of BYONC to participate in RPM Auctions as a price taker (i.e., at an offer of $0/MW) for ten

203 PJM Proposal 109.  The exclusion would begin with the 2029/2030 Delivery Year.  See id.
204 Patterson Affidavit ¶ 44.
205 Id. ¶ 31.

PDF page 47

47

consecutive Delivery Years, regardless of whether the load stays on the system.206  PJM labels that “an effectively price-neutral outcome” that offsets additional demand by supply priced at zero.207 Thus, whether New Large Load contracts with BYONC or enters without it, the RPM will create no meaningful price signal that incremental supply is needed to meet new load, no matter how substantial the need for new supply to serve that load may be.208  Those features of PJM’s Proposal will render the RPM fundamentally incapable of accurately reflecting a need for capacity to support demand from New Large Load, 209 in violation of “the first principles of capacity markets.”210

PJM’s Proposal incorrectly assumes that IRAS itself will resolve the resource adequacy need created by the entry of the excluded Large Load. 211   In other words, PJM’s Proposal contemplates that excluding Eligible New Large Load from the demand curve is functionally equivalent to incorporating that load into the demand curve along with an equivalent amount of capacity.212  That is an unjust, unreasonable, and indefensible market maneuver.  IRAS is not an accredited capacity resource that will reliably offset the incremental reliability requirement of Eligible New Large Loads.213  It is, at best and by PJM’s own label, a “supplemental capacity

206 PJM Proposal 55, 57-58.  Requiring BYONC to offer into the RPM at $0/MW disconnects the actual price of capacity providing BYONC, as secured via bilateral arrangements entered into outside of the RPM, from the price of that capacity as reflected in the market—meaning that BYONC cannot send a reliable price signal as to the need for or cost of new capacity.  Patterson Affidavit ¶ 30.
207 PJM Proposal 58.
208 Patterson Affidavit ¶¶ 30-31. 209 Id.
210 ISO New England Inc., 162 FERC ¶ 61,205 P 21 (2018) (“A capacity market should facilitate robust competition for capacity supply obligations, provide price signals that guide the orderly entry and exit of capacity resources, result in the selection of the least-cost set of resources that possess the attributes sought by the markets, provide price transparency, shift risk as appropriate from customers to private capital, and mitigate market power.”). 211 Patterson Affidavit ¶ 32.
212 Id.
213 Id. ¶ 34.

PDF page 48

48

product.”214  Nor is IRAS a customer-desired solution; rather, it imposes a mandatory interruptible service on customers without their election.

The problems with PJM’s Proposal to exclude certain New Large Load from the demand curve do not end there.  PJM’s Proposal further specifies that New Large Loads without BYONC should be excluded from the RPM curve “regardless of whether PJM is experiencing a shortfall that triggers IRAS in the relevant Delivery Year.”215  The practical result is that in delivery years when IRAS is not triggered, the New Large Load excluded from the demand curve would be backed by no resources at all on the capacity side.216  In that circumstance, the RPM is distorted even further, because the excluded New Large Load will be physically present and will have the same service priority as other loads, but PJM’s capacity market “will simply pretend it is not there.”217

PJM contends that including Eligible New Large Load in the demand curve “would fail to recognize that New Large Loads have committed to ‘build, bring, or buy the new generation resources and electricity needed to satisfy their new energy demands,’” which PJM asserts is consistent with the Ratepayer Protection Pledge. 218  But alignment with the Pledge is not a substitute for necessary economic signals that are relied on to produce properly functioning capacity markets.  If approved, PJM’s exclusion proposal would force the RPM to permanently reflect a fictional reliability outcome—one that is necessarily different from, and less demand-

214 PJM Proposal 74.  That is distinct from a “Capacity Resource,” which is defined in the PJM tariffs as a resource that has met the qualification requirements to participate in the PJM capacity market.  See, e.g., PJM Glossary, https://www.pjm.com/Glossary.aspx#index_C, (last accessed September 2, 2026).
215 PJM Proposal 110.
216 Patterson Affidavit ¶ 33.
217 Id. 218 PJM Proposal 110 (citation omitted).

PDF page 49

49

intensive than, the actual on-the-ground resource adequacy situation.219  Put another way, PJM’s Proposal would create the illusion that no net New Large Load demand exists on the system, even if there is substantial need for new supply to serve New Large Load.220

That outcome is directly contrary to PJM’s own stated objectives.  In a January 2026 decisional letter, the PJM Board identified the objective of providing “the appropriate price signals to support the timely development of new capacity resources” and ensuring that the markets “retain structural integrity during the pendency of this review and beyond.”221  Indeed, the PJM Board previously specified that its proposal did not suggest “remov[ing]” new large load “from the capacity market,” 222  as doing so would “result in large new loads avoiding capacity costs altogether, with those costs shifted to existing customers.”223  PJM reversed course, however, and has now proposed to ignore actual market signals and rely instead on a purposefully skewed representation of demand.  Doing so would erode the investor confidence necessary to ensure resource adequacy at just and reasonable rates224 by blunting the signal for existing resources to remain in and new resources to enter the capacity markets, thus intensifying the market stagnation

219 Patterson Affidavit ¶¶ 36-37.
220 Id. ¶ 38.
221 Jan. 16 Ltr. at 3, 5; id. at 7 (recognizing that PJM’s markets must “deliver clear and transparent price signals regarding the resources needed to maintain grid reliability”), available at https://www.pjm.com/- /media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of- the-cifp-process-large-load-additions.pdf. 222 Id. at 5.
223 Id.  Likewise, in a May 6 white paper addressing reliability and market design, PJM reinforced that “the efficacy of a competitive market relies on its ability to send accurate price signals that reflect the true state of the system,” and that only “[w]hen those signals align with physical reality” will “the market effectively coordinate[] entry and exit.”  PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment to Support Durable Reliability, at 11, https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering- reliability-through-market-design.pdf (last updated May 6, 2026).
224 ISO New England Inc., 162 FERC ¶ 61,250 at P 21.

PDF page 50

50

that PJM has identified as a significant detriment to stimulating sufficient investment to support durable reliability.225

For all of those reasons, exclusion of certain load from the demand curve reflects economic irrationality that is fundamentally inconsistent with the Commission’s objectives. 226   More specifically, the Commission has recognized that capacity-market rules may be unreasonable when they override and conflict with economic rationality in the market. 227   In one example, the Commission struck down provisions of PJM’s tariff as unjust, unreasonable, and unduly discriminatory because subsidies paid outside the RPM allowed certain resources to “reduce the price of their offers into capacity auctions below the price at which they otherwise would offer.”228 The Commission reasoned that the relevant tariff provisions “fail[ed] to protect the integrity of competition in the wholesale capacity market against unreasonable price distortions and cost shifts caused by out-of-market support.”229  Although IRAS involves a different mechanism, the same principle applies.

Further, the RPM-related aspects of IRAS are unjust and unreasonable because they are fundamentally incompatible with the basic market design of a capacity auction.  As the Commission has explained, the RPM was designed to “creat[e] accurate price signals to incent

225 Patterson Affidavit ¶ 47; see Powering Reliability Through Market Design at 6 (describing a “Credibility Trap” that occurs when “high scarcity prices” that are economically necessary to signal the need for investment become … “the triggers [for governmental intervention] that undermines [the credibility of those same prices],” leading investors to “discount revenue signal” and capital to “stay[] on the sidelines”), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20260520/20260520- powering-reliability-through-market-design (last updated May 20, 2026). 226 See 18 CFR § 2.22(b)(3) (“Transmission pricing should promote economic efficiency”); ISO New England Inc., 162 FERC ¶ 61,205, at ¶ 21. 227 See Calpine Corp. v. PJM Interconnection, LLC, 163 FERC ¶ 61,236 (2018), reh’g denied, 171 FERC ¶ 61,034 (2020).
228 Id. P 2.
229 Id. P 150.

PDF page 51

51

new generation.  It is designed to encourage market signals, not interfere with them.”230  Not only does excluding New Large Load without BYONC from the demand curve and forcing BYONC to be a $0/MW price-taker interfere with RPM market signals, it actively and intentionally suppresses the ability of RPM to incentivize capacity and retain existing capacity.  Through these two aspects of the IRAS proposal, PJM is essentially abandoning the fundamental theory underlying RPM (and capacity markets generally) and asserting that an extra-market intervention is needed to incentivize new capacity.  But on a basic level, PJM has not adequately established through its proposal that RPM’s market-based ability to incentivize new capacity is broken.  And even had PJM made that showing, a just and reasonable proposed fix for that issue would be to work within the current market—i.e., attempt to strengthen the signals that the RPM sends to incentivize capacity—rather than actively working to weaken those signals through a capacity product that exists outside of the market and serves to further undermine its proper functioning.

As Mr. Patterson explains, these twin market-suppressing features of IRAS are “the latest in a series of recently-implemented or pending actions by PJM that will collectively destroy the ability of RPM to meet the resource adequacy needs of PJM going forward,” unless the Commission takes action to reverse the trend.231  By creating one after another “special, high-value discriminatory pathways” for new capacity entry, PJM continues to gradually erode the incentive for capacity resources to enter the market traditionally, via the RPM.232  When higher-priced, lower-risk pathways for new entry exist—such as through the proposed BYONC contracts—no

230 PJM Interconnection, LLC, 117 FERC ¶ 61,331, at P 69 (2006); see id. P 68 (detailing “the Commission’s concerns that appropriate price signals are available to provide incentives to construct facilities necessary for regional reliability”); see also PJM Interconnection, LLC, 167 FERC  ¶ 61,029, at ¶ 16 (2019) (VRR Curve designed to “produce accurate market signals that will encourage appropriate capacity investment and achieve an adequate level of reliability”).
231 Patterson Affidavit, Part IV & ¶¶ 41, 43.
232 Id. ¶ 45.

PDF page 52

52

rational capacity provider will enter via the RPM, which renders such resources “new” for only one year, and afterwards locks them out of the ability to use any subsequently created, higher- value, new-only resource pathway.233  Instead, the rational approach becomes to hold out for the next capacity-related intervention by PJM—or, for existing resources, to exit the market entirely.234 Meanwhile, each special extra-market entrance pathway that results in new capacity being bid into the RPM as a price-taker artificially lowers the clearing price for capacity, depressing market prices for existing resources and further suppressing the ability of the RPM to send the proper price signals to incentivize new capacity and retain existing capacity, as originally intended.235  The economic irrationality of this vicious cycle leads to “a market that is continually in a spiraling crisis,” eroding long-run reliability.236

In sum, the Commission should not endorse an economically irrational response to a resource adequacy problem, artificially and unreasonably shift system costs among participants, and mute market signals that would ordinarily feed demand.  Indeed, PJM has already told the Commission as much, by publishing a white paper describing the so-called “Credibility Trap” that occurs when providers of capacity lack confidence that the market will provide the compensation necessary to support the entry or retention of that capacity.237  The Proposal is exactly the kind of intervention that would exacerbate that problem.  The Commission should reject that harmful approach as unjust and unreasonable.

233 Id. ¶¶ 45-47.
234 Id. ¶¶ 47-48.
235 Id. ¶¶ 42, 46, 51.
236 Id. ¶ 50.
237 Id. ¶ 44 (discussing PJM white paper).

PDF page 53

53

IV. If the Commission Nonetheless Were To Accept PJM’s Unlawful Proposal, It Should Condition Acceptance On Certain Small Modifications

The Commission should reject the Proposal due to the defects described above.  If the Commission were to choose to accept the Proposal, however, the Commission should exercise its authority to condition such acceptance on three small modifications identified below. As PJM acknowledges in its filing,238 the Commission may under certain circumstances condition the acceptance of a Section 205 filing on modifications, as provided under the FPA and consistent with NRG Power Marketing, LLC v. FERC.239  Modifications are acceptable if (1) the public utility has consented to the modification, and (2) the modification does not transform the proposal into an entirely new rate scheme.240  Those preconditions are satisfied here because PJM has expressly “consent[ed] to the Commission’s exercise of authority to modify” the Proposal consistent with the principles above,241 and the specified modifications are technical issues that do not transform the proposal or undermine “PJM’s overarching objectives.”242

A. If Accepted, The Proposal Should Be Modified To Allow Any Qualifying New Capacity To Serve As A Bridge To Other New Capacity

If the Commission were to accept the Proposal, it should modify the Proposal to allow any qualifying BYONC to be replaced by other qualifying BYONC.  The proposed tariff revisions state a rule that “BYONC that is in an arrangement with a New Large Load must remain in such arrangement with that New Large Load unless and until the New Large Load is permanently out- of-service.”243  The Proposal specifies, however, that “the seller of the BYONC may replace its

238 PJM Proposal 122.
239 862 F.3d 108 (D.C. Cir. 2017); see PJM Proposal 122.
240 NRG Power Marketing, 862 F.3d at 115.
241 PJM Proposal 122.
242 Id.
243 Proposed Tariff, Attachment DD-4, § VII(e).

PDF page 54

54

BYONC obligation with a different BYONC” during the ten-year commitment period—but only for “BYONC supported by a Demand Resource or DER Capacity Aggregation Resource.”244 Distinguishing between DR and other qualifying BYONC by failing to extend that replacement provision to all qualifying BYONC, not just DR and DER Capacity Aggregation Resources, is not just and reasonable in this context.

PJM’s own justification for allowing replacement of DR and DER Capacity Aggregation Resources with other qualifying BYONC supports modifying the Proposal to allow replacement of any qualifying BYONC.  PJM explains that the replacement approach “provides New Large Loads a ‘bridge to power’ of near-term demand-supported capacity that is eventually replaced with new generation as that supply comes online.” 245  It “increases commercial opportunities for BYONC without adversely affecting the region’s ability to address its capacity needs,” and it allows New Large Loads to “spur the development of additional capacity in a few years” while relying on existing or different capacity in the meantime.246

The same rationales would be equally served by allowing another type of BYONC to supply the bridge.  For example, if a new generating facility was intended to support a New Large Load but was delayed by two years, that load should be able to rely on an arrangement with other qualifying BYONC during those two years, with the intended facility later substituted for the remaining eight years.  That approach would provide a bridge to longer-term generation and increase commercial flexibility, while still conforming to the IRAS premise that the New Large Load’s capacity needs be supported by BYONC throughout the relevant timeframe.  It also would

244 PJM Proposal 56-57. 245 Id. at 57.
246 Id.

PDF page 55

55

conform with the general RPM principle that serves flexibility and reliability by allowing substitution of replacement capacity when intended resources are unavailable.247

B. If Accepted, The Proposal Should Be Modified To Specify That BYONC
Includes Otherwise Qualifying Capacity Resources That Clear Any RPM
Auction For 27/28, 28/29, And 29/30
If the Commission were to accept the Proposal, it also should modify the Proposal to clarify that qualifying BYONC is not limited to capacity resources that clear a Base Residual Auction for 27/28, 28/29, or 29/30, but rather includes capacity resources that clear additional incremental auctions for those Delivery Years.

Section VI(a)(i) of the proposed tariff states that “Capacity Resources that cleared an RPM Auction for the first time in the Base Residual Auction for the 2027/2028, 2028/2029, and 2029/2030 Delivery Years may qualify as BYONC.”248  But the Base Residual Auction is not the only auction that will occur for those Delivery Years; there also will be incremental auctions between a Base Residual Auction and the moment when the electrons begin to flow.249  There is no reason why Capacity Resources that cleared an incremental auction in the relevant time period should not be treated the same way as Capacity Resources that cleared a Base Residual Auction in the relevant time period for purposes of deciding whether those resources qualify as BYONC.  In fact, the Proposal itself seems to recognize the wisdom of that approach, as it describes the

247 For example, PJM’s tariff allows sellers to submit buy bids for replacement capacity resource in the event of “resource retirement, resource cancellation or construction delay,” or “any reason” causing the “need to purchase replacement Capacity Resources.”  Proposed Tariff, Attachment A, § 5.4(d); see also Proposed Tariff, Attachment A, “Definitions – L-M-N” (defining “Locational UCAP” as unforced capacity sold to a Member “that previously committed capacity through an RPM Auction but now requires replacement capacity to fulfill its RPM Auction commitment”).
248 Proposed Tariff, Attachment DD-4, § VI(a)(i).
249 PJM Proposal 113 n.300 (acknowledging existence of incremental auctions); see PJM Capacity Auction Calendar, available at https://www.esaipower.com/capacity-market-auction-calendar/pjm-capacity- auction-calendar/ (calendar of base residual and incremental auctions).

PDF page 56

56

Capacity Resources that may qualify as BYONC in general terms, referring only to “RPM Auctions” and not specifically to the Base Residual Auction, and notes that multiple “Auctions” take place:  “Given that New Large Loads are included in the RPM Auctions through the 2028/2029 Delivery Year and eligible BYONC that previously cleared an RPM Auction through the 2028/2029 Delivery Year was not on notice of this limitation, any eligible BYONC that is offered in RPM Auctions through the 2028/2029 Delivery Year can be procured by New Large Loads to avoid IRAS.”250  This point could easily be clarified by simply striking the words “the Base Residual Auction for” from Section VI(a)(i) of the proposed tariff, so that the provision instead stated that “Capacity Resources that cleared an RPM Auction for the first time in the 2027/2028, 2028/2029, and 2029/2030 Delivery Years may qualify as BYONC.”

C. If Accepted, The Proposal Should Be Modified To Include Incremental
Capacity Created By An Energy Resource In The Definition Of BYONC
PJM’s Proposal requires that generation and storage resources must meet certain “eligibility requirements” to qualify as BYONC, which are specified in the Proposed Tariff at Section VI(b).  Resources “must be supported by one of the following”:  (1) a new-build generation resource; (2) “incremental capacity created through an uprate of Existing Generation Capacity Resources”; (3) incremental capacity created by utilization of Surplus Interconnection Service; (4) repowering of a deactivated generation resource that deactivated prior to April 10, 2026; or (5) incremental capacity created by an Existing Generation Capacity Resource’s change to a more efficient fuel type.251  If the Commission were to accept the Proposal, it should modify requirement

(2) above to include incremental capacity created by an Energy Resource that acquires Capacity Interconnection Rights through an Interconnection Request.

250 PJM Proposal 115 n.302.
251 Proposed Tariff, Attachment DD-4, § VI(b)(i).

PDF page 57

57

The current language of the BYONC criteria covers “incremental capacity created by an uprate of Existing Generation Capacity Resources, but only to the extent such incremental capacity is created through an increase in such Generation Capacity Resource’s installed capacity and increase in Capacity Interconnection Rights associated with that Generation Capacity Resource.”252  As drafted, that language could be interpreted to exclude an energy-only resource seeking new capacity rights, because an energy-only resource would not yet be considered an “Existing Generation Capacity Resource.”

Such exclusion would be unreasonable and inconsistent with PJM’s objectives.  An Energy Resource that wishes to acquire Capacity Interconnection Rights, like a resource pursuing an uprate, must submit an Interconnection Request, proceed through PJM’s interconnection study process, and pay for any required network upgrades to accommodate its request.253  An Energy Resource that requests capacity rights also provides incremental capacity in a manner materially indistinguishable from a Generation Capacity Resource that uprates its capacity.  Accordingly, the BYONC criteria should be expanded to encompass incremental capacity created by an Energy Resource that acquires Capacity Interconnection Rights through an Interconnection Request.

V. Conclusion
The Commission should reject all portions of PJM’s Proposal other than the proposal to create the Large Load Registry and, in the alternative, should condition acceptance on the modifications described in this filing.

252 Proposed Tariff, Attachment DD-4, § VI(b)(i)(2).
253 See PJM Tariff, Part VIII, Subpart B, § 403(A)(1) (Generation Interconnection Request Requirements).

PDF page 58

58

       Respectfully submitted,
By:  /s/ Elaine J. Goldenberg
Carrie Hill Allen
Sr. Vice President & Deputy General
  Counsel
John M. White
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
john.white@constellation.com
Christopher A. Wilson
Vice President, Federal Regulatory Affairs Constellation Energy Generation, LLC

250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Elaine J. Goldenberg
MUNGER, TOLLES & OLSON LLP
601 Massachusetts Avenue NW
  Suite 500 E
Washington, DC 20001
(202) 220-1100
Elaine.Goldenberg@mto.com

Henry Weissmann
MUNGER, TOLLES & OLSON LLP
350 South Grand Avenue, 50th Floor
Los Angeles, CA 90071-3426
(213) 683-9100
Henry.Weissmann@mto.com

Teresa Reed Dippo
MUNGER, TOLLES & OLSON LLP
560 Mission Street, 27th Floor
San Francisco, CA 94105
(415) 512-4000
Teresa.ReedDippo@mto.com
Counsel for Constellation Energy Generation, LLC

Dated:  September 3, 2026

PDF page 59

59
CERTIFICATE OF SERVICE
I hereby certify that I have on this 3rd day of September 2026 served a copy of the foregoing upon all parties on the service list in this proceeding in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.

By: /s/ Elaine J. Goldenberg
Elaine J. Goldenberg
MUNGER, TOLLES & OLSON LLP
601 Massachusetts Avenue NW
   Suite 500 E
Washington, DC 20001
(202) 220-1100
Elaine.Goldenberg@mto.com

PDF page 60

Appendix A

PDF page 61

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

 PJM Interconnection, L.L.C.:
205(d) Rate Filing: Proposal to Establish Interim Resource Adequacy Service & a Large Load Registry to be effective 10/12/2026

)
)
)
)
)
)

Docket No. ER26-3515-000

AFFIDAVIT OF
AARON T. PATTERSON
ON BEHALF OF
CONSTELLATION ENERGY GENERATION, LLC

September 3, 2026

PDF page 62

1

I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT
A. QUALIFICATIONS
1. My name is Aaron T. Patterson.  I am a partner of The NorthBridge Group, Inc (“NorthBridge”).  NorthBridge is a consulting firm that provides economic and strategic advice to the electric and natural gas industries.  My business address is 30 Monument Square, Concord MA 01742.

2. I joined NorthBridge in 2001.  Before that, I was an analyst at Lexecon, Inc. which I joined in 1996.  I have over 25 years of experience working with clients in the electric and natural gas industries.  My electric industry business consulting work has focused on market design, environmental policy, finance, and mergers and acquisitions.  I received a Bachelor of Arts in Environmental Science and Public Policy from Harvard University, and a Master of Business Administration from the Tuck School of Business at Dartmouth.  I have previously testified before the Commission and have also submitted expert testimony and/or expert reports in proceedings before the U.S. Department of the Treasury, the Illinois Commerce Commission, the Public Utility Commission of Texas and the New York State Public Service Commission.

3. A list of my past prepared testimony is provided as Attachment A.
B. BACKGROUND AND PURPOSE OF AFFIDAVIT
4. On August 13th, 2026, PJM Interconnection L.L.C (“PJM”) filed a set of proposed revisions to its tariff (“PJM’s Proposal”) at the Commission to establish a new Interim Resource Adequacy Service (“IRAS”) that would be applicable to certain loads seeking to interconnect with the PJM system.1  PJM’s Proposal would require end-use loads with a peak load in excess of 50 Megawatts (“Large Loads”) that come online or add incremental demand on or after June 1, 2027 (“New Large Loads”) to establish a “Bring Your Own New Capacity” (“BYONC”) arrangement with new entrant capacity or be allocated new entrant capacity from PJM’s proposed Reliability Backstop Procurement (“RBP”) in an amount equal to their load; or be required to provide IRAS during delivery years where the PJM Reliability Pricing Model (“RPM”) clears short of its reliability

1 PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability to be effective 10/12/2026, Docket No. ER26-3515- 000 (filed August 13, 2026) (the “PJM Proposal”).

PDF page 63

2

requirement.  Loads required to provide IRAS would be subject to curtailment by their local Electric Distribution Company (“EDC”) when PJM issues a zonal instruction to curtail IRAS load under North American Reliability Corporation (“NERC”) Energy Emergency Alert (“EEA”) 1 conditions, prior to any other emergency actions other than the curtailment of load taking non-firm transmission service and the curtailment of non-firm interchange transactions.  PJM also proposes that New Large Loads entering the market in the 2029/30 delivery year or later that do not enter into BYONC arrangements or receive allocations of RBP supply sufficient to cover their load be excluded from RPM demand unless and until they make sufficient BYONC arrangements, regardless of whether IRAS is triggered for a given delivery year or not.

5. The purpose of my affidavit is to assist the Commission in its decision-making process in evaluating and ultimately taking action on PJM’s Proposal by approving, not approving, or modifying it.  My analysis focuses on four aspects of PJM’s Proposal: 1) the placement of IRAS curtailments within the overall priority order of actions taken by PJM under emergency operating conditions, 2) the impact of IRAS curtailments on price formation in the PJM energy market, 3) the exclusion of New Large Loads which do not bring new capacity from RPM demand, and 4) the overall effect of the proposal on the viability of PJM Markets going forward coupled with its long-term impacts on reliability and consumer costs.

C. SUMMARY OF CONCLUSIONS
6. I reach four primary conclusions in my assessment of PJM’s Proposal:
7. First, PJM’s proposed placement of IRAS load curtailments near the front of the emergency action priority order and prior to calling upon Demand Response is economically inefficient and also is likely to drive increased reliability risk during operations.  The Large Loads which are ultimately forced to provide IRAS are likely to be those Large Loads for whom curtailment is relatively costly and difficult.  Relying on such loads as the initial line of defense under emergency conditions will raise production costs, decrease total social surplus, and increase reliability risk.  If the Commission accepts PJM’s IRAS proposal, it should require PJM to move IRAS curtailments back in the emergency action priority order to just in front of general manual load shed under EEA3 conditions.

8. Second, PJM’s Proposal does not include any provisions addressing energy price formation when IRAS load curtailments occur.  In order to maintain proper incentives to deploy all less costly

PDF page 64

3

resources and to invest in lower-cost resources that can provide energy (or demand response) under emergency conditions, energy prices during IRAS load curtailments should reflect the economic cost associated with the curtailment of IRAS loads.  The Commission should require PJM to develop and implement measures that effectuate this treatment.

9. Third, PJM’s proposed exclusion from RPM demand of New Large Loads that do not offset their load with new capacity will compromise reliability and greatly limit the ability of the RPM to attract new supply going forward.  Excluding this load unless it has secured its own new capacity creates a disconnect between the level of resource adequacy signaled by the RPM and the level of physical resource adequacy that exists in reality.  As a result, new resources will not be provided with a signal to enter via the RPM to serve the New Large Load, and existing resources will not be provided with a similar signal to remain in the market.  This disconnect harms reliability because it effectively treats IRAS curtailment as a full substitute for capacity when in reality its performance is likely to be different than and less visible or directly controllable than actual accredited capacity resources, and in any event will not even exist at all in delivery years where IRAS is not triggered.  The Commission should require PJM to include all New Large Load in RPM demand, regardless of whether it brings new capacity or not.

10. Fourth, the BYONC mechanism of PJM’s IRAS Proposal along with the other issues discussed above and other recent and pending actions affecting the RPM will greatly reduce investor confidence in the RPM to the point where it will likely become non-viable as a pathway for new entry and the retention of existing resources.  This outcome will force PJM to contend with recurring resource adequacy shortfalls that cannot be resolved via the operation of the RPM but rather must be resolved via further ad-hoc intervention.  The result, ultimately, will be reduced reliability and increased costs for consumers.  While this problem is deep-seated and multi-causal, as documented in PJM’s recent white paper “Powering Reliability Through Market Design” (the “PJM White Paper”),2 the Commission can help PJM avoid this more costly and less reliable path by requiring PJM to remove or at least mitigate the BYONC mechanism.

2 Power Reliability Through Market Design:  Addressing Rising Demand and Constrained Supply, and Stimulating Investment to Support Durable Reliability, PJM (May 6, 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf (“PJM White Paper”).

PDF page 65

4

II. IRAS LOAD SHOULD BE CURTAILED AFTER DEPLOYMENT OF DEMAND RESPONSE AND OTHER
LOWER-COST ACTIONS, AND THE COST OF IRAS CURTAILMENT SHOULD BE REFLECTED IN
ENERGY MARKET PRICES
A. DURING EMERGENCY OPERATIONS, RTOS SHOULD DEPLOY THE
LOWEST-COST EMERGENCY ACTIONS FIRST WHEN POSSIBLE IN ORDER
TO MAXIMIZE TOTAL SOCIAL SURPLUS
11. A bedrock principle underlying organized power markets since their inception in PJM and elsewhere is that resources should be deployed and load served in a manner that maximizes the total social surplus for all participants on both the supply and demand side of the market, subject to all physical and operational constraints.  Under normal operating conditions in PJM’s energy market, this is achieved by dispatching resources in increasing order of their marginal cost and serving all load which has expressed a willingness to pay that is equal to or higher than the marginal cost of serving the final increment of load (or which has expressed a lack of demand elasticity, as is the case for most loads, which is treated as a willingness to pay in excess of administrative market price caps under normal operating conditions).  The market clearing energy price under this design is effectively3 determined by the intersection of the supply and demand curves, where the marginal cost of serving load is equal to the marginal benefit that the final increment of load derives from consumption.  This market organization maximizes social surplus because the sum of the benefits that load derives from the consumption of electricity minus the production cost of electricity (effectively the area between the supply and demand curves) is maximized.  Simply put, the maximum amount of load that can be economically served is served, and the production cost of serving that load is minimized.  The Commission has stated that a primary goal, or objective function, of organized power markets is to maximize total surplus,4 and has approved numerous

3 In technical terms, the market clearing price is the incremental cost of serving the next increment of load at a given location, whether that is achieved through the incremental dispatch of supply resources or the curtailment of price- sensitive demand resources.  The supply and demand intersection provides a useful heuristic for visualizing the formation of market prices that is sufficient for this discussion but in actual operation the determination of prices is more complex.
4 Price Formation in Energy and Ancillary Services Markets Operated by Regional Transmission Organizations and Independent System Operators, Notice Inviting Post-Technical Workshop Comments, Docket No. AD14-14-000 (Jan 16, 2015) at 1: “The goals of proper price formation are to: maximize market surplus for consumers and suppliers…” In Order 2000 (1999) the Commission broadly articulated a goal of utilizing organized power markets to increase market efficiency to the greatest extent possible.  See 89 FERC ¶ 61,285, 32-71.

PDF page 66

5

market designs, such as PJM’s energy and capacity markets, that explicitly seek to maximize total surplus through their operation.5

12. The benefits of maximizing total surplus remain when the system is operating under emergency conditions, although such maximization can be more challenging to fully achieve. When PJM is operating under emergency conditions the amount of available excess generation supply will typically approach zero, and PJM thus must rely on other actions, such as the curtailment of load, in order to maintain reliable operations.  All of the actions PJM may take under emergency operations have a cost, however, and these costs should be considered when deciding which emergency actions to take at any particular point in time.  For instance, curtailing load, whether it occurs through the deployment of demand response resources, through the curtailment of IRAS loads under PJM’s IRAS proposal, or via manual load shed actions, has an economic cost because the load in question is deprived of the benefits it derives from the consumption of electricity, whether that be through business disruption, damage to assets, or other problems.  The cost of curtailment is commonly referred to as the Value of Lost Load or “VOLL.”  Similarly, other emergency actions such as ordering generation to produce at emergency levels also result in incremental costs.  When operating under emergency conditions PJM does not take emergency actions based on a surplus-maximizing market optimization algorithm like it does under normal conditions.  Rather PJM utilizes a combination of an established deployment order coupled with operator judgement to decide which actions to take and when.6  Nonetheless, actions that PJM takes under emergency conditions still have economic costs, which are often very high.  To the extent that PJM deploys high-cost emergency actions while lower-cost actions which can also help the market maintain reliable operations remain available and unutilized, that choice unnecessarily increases the total costs borne by market participants and reduces total surplus.  Thus, to remain in alignment with the overall goal of maximizing market surplus, during emergency conditions PJM should seek to take lower cost actions before it takes higher cost actions if possible and should design its emergency action protocols and emergency action deployment order accordingly.

5 Any market that determines price by equalizing the marginal cost of supply with the marginal benefit of consumption, as both the PJM energy and capacity markets do, seeks to maximize total surplus by construction.
6 PJM Proposal, Attachment C, Affidavit of Christopher Pilong on Behalf of PJM Interconnection, L.L.C. (“Pilong Affidavit”), PP 14-16.

PDF page 67

6

B. CURTAILMENT OF IRAS LOAD IS LIKELY TO BE MORE EXPENSIVE THAN
DEPLOYMENT OF DEMAND RESPONSE, AND SHOULD THUS BE
CURTAILED AFTER DEMAND RESPONSE IN THE EMERGENCY ACTION
ORDER
13. Under its IRAS proposal, during emergency operations PJM proposes to locate curtailment of IRAS loads at a very early point in its emergency action deployment priority order.  Specifically, PJM proposes to curtail IRAS loads after it curtails loads operating under non-firm transmission service and curtails non-firm interchange transactions, but before all other emergency actions, including the deployment of Demand Response, maximum emergency generation actions, voltage reduction, and general manual load shed.7

14. While there is little data on the relative costs of the various emergency actions at PJM’s disposal, curtailment of IRAS loads is almost certainly significantly more costly than many of the other actions that PJM proposes to deploy after IRAS in the emergency action priority order.  In particular, as I discuss below, curtailment of IRAS load is highly likely to be significantly more costly than Demand Response.  Thus, curtailment of IRAS in favor of deployment of Demand Response almost certainly will lead to higher-than-necessary loss of consumer benefits from consumption and a corresponding reduction in total surplus.

15. The predominant types of Demand Response in PJM, Emergency and Pre-Emergency Load Management service, are voluntary services where loads are voluntarily certified as capacity resources, offer into and clear the RPM on a purely voluntary basis without a capacity must-offer obligation, and, if cleared as a capacity resource, agree to curtail load in response to PJM instruction under emergency conditions.  In exchange for this service, loads providing Demand Response are compensated as capacity resources via the RPM and are also paid a minimum dispatch price per MW-hour of curtailment when deployed.8  Implicitly, loads which choose to provide Demand Response will weigh the compensation they receive (the combination of capacity

7 Pilong Affidavit PP 44-46.
8 Loads which elect the capacity-only option for the Pre-Emergency and Emergency Demand Response are not paid the minimum dispatch price.  As of 2025/26 loads electing the capacity-only option comprise 1.3 percent of total nominated Demand Response capacity.  See 2025 Quarterly State of the Market Report for PJM: January Through June, Monitoring Analytics, LLC (August 14, 2025), 399. https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2025/2025q2-som-pjm.pdf

PDF page 68

7

revenues and minimum dispatch payments) against their private estimate of their own VOLL in the form of business disruption costs or similar.  If projected demand response compensation exceeds the load-specific VOLL for a given load, it will be economically advantageous to them to provide Demand Response services to PJM.

16. Given these economics, the population of loads that voluntarily provide Demand Response to PJM will generally represent a self-selected population of loads with relatively low VOLL because only those loads with a VOLL below the projected total Demand Response compensation can economically provide the service.  As an example, I estimate that the total compensation to a representative demand response resource in 2025/26 receiving the RPM Base Residual Auction clearing price of $270 per MW-Day and deploying for a total of 22.7 hours consistent with actual deployments of demand response in eastern PJM over 2025/26 was on the order of $5,000 per Megawatt-hour of curtailment, comprised of the capacity payment of about $3,350 per MWh and a per-MWh deployment payment (the Minimum Dispatch Price) of between $1,100 and  $1,849 per MWh depending on the notice time.9  Thus, in this example only loads with a VOLL of about $5,000 per MWh or less would be likely to be willing to offer and supply demand response at that level of compensation.

17. Unlike Demand Response, however, IRAS is not a voluntary service, despite PJM putting “service” in the name.  New Large Loads that cannot render themselves exempt from IRAS by bringing new capacity via BYONC arrangements or RBP allocations are involuntarily placed on IRAS if they enter the market and the conditions to trigger IRAS  are in effect.  New Large Loads have the option to provide Demand Response if they are willing and able, just like other loads. For New Large Loads that are able to economically curtail, providing Demand Response and utilizing Demand Response to qualify for the BYONC exemption is a categorically superior option to not providing Demand Response and instead being forced to provide IRAS.  As discussed above, Demand Response receives both a capacity payment and a per-MWh payment for actual deployments.  IRAS, by contrast, receives no capacity payment at all and receives a maximum

9 The curtailment hours are for Pre-Emergency Load Management with a 120-minute response time in the PECO Zone.

According
to
PJM’s
Active
Load
Management
history
data
(https://www.pjm.com/-
/media/DotCom/planning/res-adeq/load-forecast/alm-history.xlsx), demand response in this category was deployed for 7 hours on 6/23/2025, 7 hours on 6/24/2025, 3.2 hours on 7/25/2025, and 5.5 hours on 7/29/2025 for a total of 22.7 hours.  Given the RTO clearing price of $270/MWD and demand response ELCC of 77% for the 2025/26 delivery year, this translates to a capacity payment per deployment megawatt-hours of $3,342.

PDF page 69

8

per-deployment payment equal to 50% of the capacity Non-Performance Charge Rate, which will be about $1,500 per MWh for the first year in which IRAS is proposed to be in effect (rising to about $2,000/MWh for the following year).10  Thus, for the representative resource discussed above, Demand Response is compensated at about $5,000 per MWh of curtailment, while the same resource placed on IRAS would be compensated at most at about $1,500 per MWh of curtailment. The net effect of these starkly different economics is that New Large Loads that can economically curtail and meet the physical and notice requirements needed to supply Demand Response will provide Demand Response and avoid IRAS via the BYONC exemption (where the Demand Response is the new capacity).  The loads that actually end up being placed on IRAS will be the leftovers: those New Large Loads that cannot easily curtail either because their VOLL is too high to make Demand Response economic or because their physical operating characteristics preclude them from meeting the notice and response time required to provide Demand Response or even from curtailing at all.  These loads will thus typically have a VOLL which is much higher than the loads that are able to provide Demand Response.  EDC compliance with a NERC instruction to curtail these loads will likely require curtailment via utility-controlled breakers rather than reductions implemented by the load itself, which is a particularly costly and disruptive form of curtailment.  A recent study on the VOLL of different classes of load in the Electric Reliability Council of Texas indicates that the VOLL of typical large loads is generally between $6,500 and $23,000 per MWh.11  I expect that a typical load placed on IRAS would have a VOLL at least in this approximate range.

18. Thus, by prioritizing the curtailment of IRAS loads over those providing Demand Response within its proposed new emergency action priority order, PJM is affirmatively choosing to undertake high-cost actions while lower-cost actions that provide at least the same level, if not more, of relief against emergency conditions remain unused.  As discussed above, this

10 PJM Proposal 101-108.  The Non-Performance Charge Rate for the 2027/28 delivery year based on the published RTO Net CONE is $2,951/MWh, which translates to an IRAS Credit Rate of $1,475/MWh.  For 2028/29 these values will rise to $3,963/MWh and $1,981/MWh, respectively. 11 Value of Lost Load Study for the ERCOT Region, The Brattle Group (Charles Gibbons and Sanem Sergici), August 19th, 2024, Table ES-1. https://www.brattle.com/wp-content/uploads/2024/09/Value-of-Lost-Load-Study-for-the- ERCOT-Region.pdf Table ES-1 provides estimated VOLL for Medium/Large Commercial and Industrial customers as a function of interruption duration ranging between $22,721/MWh for a 1-hour interruption and $6,507/MWh for a 8-hour interruption.

PDF page 70

9

unnecessarily reduces total market surplus and runs counter to the basic design principles underlying PJM markets.

19. Further, it is likely that other emergency actions that PJM proposes to prioritize below the curtailment of IRAS loads have incremental costs that are lower than the VOLL of IRAS loads. Specifically, PJM proposes that IRAS loads be curtailed before it takes a Maximum Generation Emergency Action (including curtailment of firm exports), before Emergency Voluntary Energy- Only Demand Response Reductions, Curtailment of Non-Essential Building Load, and the Deploy All Resources Action.12  While PJM has not provided data on the cost of these actions, they are all deployed under EEA1 or EEA2 conditions and in advance of involuntary manual load shed and thus may have costs that are generally lower than the cost of involuntary load shed including load shed due to IRAS curtailment.  For example, the Maximum Emergency Generation and Deploy All Resources actions will typically have costs consistent with the marginal cost of high-cost thermal generation with some additional accrued operations and maintenance costs due to operating outside of normal economic limits but nonetheless will typically be far below most VOLL levels under most types of emergency conditions.  Voluntary Emergency Energy-Only Demand Response Reductions and Curtailment of Non-Essential Building Load are a form of load shed but as discussed above, are likely to be less costly than curtailment of IRAS load.

20. In addition to the economic cost implications, placing IRAS load curtailments at the front of the curtailment order carries the risk of adverse reliability consequences in actual operations.  PJM proposes that it issue instructions to curtail IRAS loads to EDCs up to the amount of IRAS service that PJM has allocated to an EDC’s zone.  This will be a NERC instruction that EDCs must comply with if they are physically able, but PJM will not directly control the curtailment, nor will it have real-time operating insight or real-time enforcement capability to ensure that the curtailment produces the expected relief, and nor can it require a specific method of curtailment.   Given the uncertainties and frictions inherent in emergency operations, this creates real reliability risk.  As an example, assume an EDC is allocated 1,000 MW of IRAS service due to the presence of a large load with projected peak demand of 1,000 MW (without BYONC) on its system.  In real-time, PJM issues an instruction to the EDC to curtail 1,000 MW of IRAS load, but the particular large load in question is operating at a lower-than-expected level of 600 MW.  In this instance, even if

12 Pilong Affidavit Figure 3.

PDF page 71

10

the EDC has installed a utility-controlled breaker at the large load, it will likely not be able to fully comply with the IRAS instruction.  More generally, PJM will not have the ability to mandate a particular method of compliance with IRAS instructions, so it is possible that EDCs may implement compliance methods that perform differently than expected by PJM with respect to implementation time, certainty of curtailment level, and so on.  While capacity resources face performance uncertainty as well, PJM directly interfaces with capacity resources in real-time, subjects them to rigorous qualification and testing, and measures, quantifies, updates their expected performance based on actual physical performance over time and has stringent penalties it can enforce to incent performance.  These mechanisms will not be in place for IRAS.  In other words, capacity is a standardized, tested product whereas IRAS, as proposed, is not.    Thus, PJM could be faced with a situation where it calls on IRAS load to curtail in anticipation of system stress, but the IRAS load does not perform as expected, even if EDCs comply with the instruction to the extent they are physically able.  PJM then will have an unanticipated need to deploy Demand Response or other actions, but may not be able to do so quickly enough to avoid a more serious physical reliability problem.  Thus, by placing a high degree of reliance in real-time operations on what is likely to be a less visible, non-standardized, and less controllable group of resources in the form of IRAS curtailments, PJM creates material reliability risk.  Moving IRAS back in the emergency operation order will not make it more reliable, but it will reduce PJM’s reliance on it and reduce the risk of unanticipated performance shortfalls.

21. Given these economic and reliability problems, I recommend that if the Commission accepts IRAS, it should require PJM to revise its proposed emergency order to move IRAS curtailment back in the order of emergency actions to behind all actions that take place under EEA1 or EEA2 conditions and just before actions which are only deployed under EEA3 conditions, such as manual load shed.  Further, I recommend that the Commission require PJM to designate IRAS curtailment as an EEA3 action (rather than EEA1 as PJM proposes) and place it first in the order of EEA3 actions.

22. To the extent that existing voluntary Demand Response would experience an increase in curtailment risk with an appropriate deployment prioritization, resulting in fewer or higher-priced offers for such service, that is the nature of providing the capacity product: suppliers should offer only those demand response services and at the prices they are comfortable providing.  In addition, to the extent demand response providers are not comfortable providing unlimited Demand

PDF page 72

11

Response capacity but PJM still believes there is benefit available, PJM can develop other more limited Demand Response products that Demand Response providers are comfortable providing. Limited Demand Response could limit the total number of curtailment hours per year, daily curtailment hours, or curtailment time window in a similar fashion to the limits that existed prior to the transition to the current unlimited Demand Response Product and consistent with proposals put forth by stakeholders in the process leading up to PJM’s Proposal. 13  Limited Demand Response would receive a lower Effective Load Carrying Capacity to reflect its lower availability, but would allow Demand Response providers to better tailor their product choice to their unique curtailment economics, allowing for Demand Response participation to be maintained or even grown despite potentially increased deployment frequency.  PJM may be better served pursuing such new, voluntary Demand Response products instead of forcing certain load to curtail involuntarily

C. THE COST OF CURTAILING IRAS LOAD SHOULD BE REFLECTED IN
ENERGY PRICES WHEN IT OCCURS
23. As discussed above, a core feature of PJM’s energy market design is that the market clearing price for energy under normal operating conditions is set by the incremental cost of serving the next increment of load (or of curtailing the final increment of load, if it is price-responsive). Setting the market price in this manner ensures that all potential lower-cost resources have an incentive to offer and provide energy during operations, and that the market sends a price signal for lower-cost resources to invest in their assets and enter the market.  This market design is commonly referred to as “marginal cost pricing.”

24. Adhering to a marginal cost pricing design is more challenging under emergency conditions because the marginal costs of many emergency actions are not well defined but nonetheless becomes even more important under such conditions.  During emergency conditions, PJM needs every potential resource to provide energy to serve load, and the costs of emergency actions that it would otherwise take if load cannot be served using conventional resources are very high. Therefore, it is imperative that the energy market clearing price during emergency conditions be

13 See Joint Stakeholder Package PJM CIFP – Large Load Additions, Presentation from Joint Stakeholders (Amazon, Calpine, Constellation, Google, Microsoft, Talen) at the Nov. 7th, 2025 Meeting of the Critical Issue Fast Path – Large Load Additions stakeholder process, Slide 4. https://www.pjm.com/-/media/DotCom/committees-groups/cifp- lla/2025/20251107/20251107-item-03c---joint-stakeholders-proposal.pdf

PDF page 73

12

set high enough such that it provides a clear signal for all potential lower-cost resources to make their energy available to the market.  In a situation where PJM must curtail load in order to maintain reliable operations (through Demand Response deployment, IRAS curtailment, or manual load shed), the appropriate energy clearing price is the VOLL of the load that PJM must curtail.  Setting the price at this level sends a clear signal for all resources with economic costs that are lower than the cost of curtailment to provide their energy to the market and provides a longer-term signal encouraging market entry of resources that can provide energy under emergency conditions.

25. PJM’s real-time economic dispatch software (specifically the Real-Time Security Constrained Economic Dispatch and Locational Price Calculator tools), which it utilizes to determine real-time energy market dispatch and prices, cannot without specific, special intervention reflect the cost of load curtailment, such as the curtailment of IRAS loads, in market prices.  PJM’s Proposal is completely silent as to how it proposes to handle energy price formation when IRAS loads are curtailed.  Absent specific changes to its economic dispatch software, which PJM does not indicate any plans to implement, a load curtailment is simply treated as a drop in demand, and market prices will adjust accordingly, with the energy clearing price set based on the energy offers of whatever dispatchable resources move in response to the load reduction.  Under high-stress conditions this price-setting resource will usually be some type of thermal generation resource with a marginal cost far below the VOLL of IRAS load, which as discussed above are likely to be well in excess of $5,000 per MWh.  Thus, without intervention, the prevailing price signal that PJM’s economic dispatch software will produce when IRAS is deployed will be far below the VOLL of IRAS load, and thus far below the level needed to send the appropriate economic signals.  Put simply, absent changes to PJM’s economic dispatch software, curtailment of IRAS loads will suppress prices despite the existence of emergency conditions serious enough to warrant involuntary load curtailment, completely inconsistent with marginal cost pricing principles.

26. PJM does make Demand Response eligible to set the energy price when it is deployed.14 PJM utilizes a workaround mechanism in its economic dispatch software called “closed-loop interfaces” to implement this, despite its economic dispatch software ordinarily being unable to reflect load reductions in energy prices.  Specifically, PJM defines constraints around the potential

14 PJM Open Access Transmission Tariff Attachment K Appendix Section 8.5.

PDF page 74

13

zones in which Demand Response may be deployed, which allows Demand Response to set the price at its minimum dispatch price (that is, up to $1,849 per MWh) when it is deployed.15  While this provides a potential model for allowing IRAS resources to set price when curtailed, PJM’s Proposal does not contain any proposed tariff revisions that would allow IRAS curtailments to set price in a manner similar to Demand Response.

27. In order to ensure that proper market price incentives are maintained when PJM curtails IRAS loads, if the Commission accepts PJM’s IRAS proposal, it should require PJM to make changes to its real-time economic dispatch software to allow IRAS to set the energy clearing price when it is curtailed.  This modification could take the form of a closed-loop interface workaround similar to that used for Demand Response or a more fundamental modification that treats IRAS (and potentially Demand Response as well) as a dispatchable resource.  The Commission should direct PJM to set the dispatch cost of IRAS at a level that is consistent with its VOLL ($5,000 per MWh or more) or at the least, at the level of the proposed IRAS credit payment (about $1,500 per MWh) which is parallel with the approach taken with Demand Response even if it is well below the likely VOLL of IRAS loads.

28. Because capacity supply offers and the reference resource cost used to calibrate the capacity demand curve are based on “missing money,” or the additional revenue that resources need to enter or stay in the market in excess of their expected energy and ancillary services revenue, properly reflecting IRAS deployment costs in energy prices during emergency operations will increase expected energy revenues and decrease capacity offers and ultimately decrease capacity prices. Given that most of the damaging interventions that have led to the problems in attracting new entry identified in the PJM White Paper have targeted the capacity market, moving overall market compensation from the capacity market to the energy market via improved price formation can generally be expected to have a positive effect on overall market performance in attracting and retaining capacity.

15 PJM Manual 11 at 12-13 and 2018 State of the Market Report for PJM, Monitoring Analytics, LLC (March 14, 2019), 238-240.  https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2018/2018-som-pjm- sec4.pdf

PDF page 75

14

III. PJM’S PROPOSAL TO EXCLUDE NEW LARGE LOADS FROM RPM DEMAND UNLESS THEY
BRING THEIR OWN NEW CAPACITY WILL COMPROMISE RELIABILITY INCREASE COSTS,AND
GREATLY LIMIT THE ABILITY OF THE RPM TO ATTRACT NEW SUPPLY GOING FORWARD
29. PJM proposes that new large loads that enter starting in the 2029/30 delivery year and do not bring an equivalent amount of new capacity in UCAP terms be excluded from the RPM demand curve until and unless they bring such capacity.  PJM proposes that this exclusion apply regardless of whether IRAS service is triggered in a given delivery year.  New large loads “bring” new capacity under PJM’s proposal either by being allocated capacity procured in the one-time Reliability Backstop Procurement or by forming bilateral “BYONC arrangements” whereby new capacity is attributed to new large loads that would otherwise be subject to IRAS and would otherwise be excluded from RPM demand.16  This new capacity that is tied to new large loads must subsequently be offered into the RPM at a price of $0 per MW-day (that is, as a price-taker) for a period of 10 years.17

30. This proposed structure effectively creates a new source of value for new capacity only that is generally referred to as “BYONC” in PJM’s filing.  BYONC is tied to new entrant resources that are able to provide capacity that is otherwise the same as standard RPM capacity provided by other capacity resources on a UCAP MW-for-MW basis.  However, under PJM’s IRAS proposal, resources that qualify to supply BYONC would be also uniquely able to provide new large loads that seek to enter PJM with a means of avoiding IRAS and its associated curtailment risk if the large load is able to amass sufficient BYONC MWs to offset its load.18  Thus, BYONC as proposed represents a new source of value only available to new entrant capacity supply resources that is separate from and additional to standard RPM capacity.  Resources qualifying to supply BYONC will monetize this new, discriminatory source of value by effectively selling their “newness” to new large loads via bilateral BYONC arrangements that will be made outside of the RPM.  The value of the “newness” feature of BYONC capacity is likely to be quite high in the coming years

– supply of new entrant capacity supply resources is limited and demand is likely to be high – and because BYONC contracting occurs outside the RPM on a bilateral basis there are no limits on

16 PJM Proposal 109-117.
17 PJM Proposal 55-58.
18 PJM Proposal 49-54, 69-72.

PDF page 76

15

price.  But because capacity providing BYONC must subsequently be offered into the RPM as a price-taker, the bilateral price paid to BYONC resources will be completely disconnected from and external to the RPM.  While BYONC resources may be able to command very high bilateral prices via bilateral BYONC arrangements with new large loads, these high prices cannot be reflected in the RPM offers associated with these resources.  Rather, resources providing BYONC on a bilateral basis will be offered into the RPM as price-takers and thus will provide no RPM price signal with regards to the need for or cost of new entry.

31. Large loads that are unable to make BYONC arrangements or receive RBP allocations sufficient to cover their load may still interconnect with the PJM system, but PJM proposes that, starting with loads entering in the 2029/30 Delivery Year, these new large loads be excluded from RPM demand.  Under normal circumstances, when load grows or enters the system, it will be included in the RPM demand curve which in turn will send a signal to the market that additional supply is needed and existing supply should remain in the market.  This signal occurs through the demand parameters that PJM makes available to market participants prior to each auction, as well as through auction results themselves, including market clearing prices and quantities.  But under PJM’s Proposal, this will not occur because the load is excluded from the demand curve.  Despite this, the load in question will still be physically present when it comes to real-world operations, will be taking Network Integration Transmission Service on the same basis as other loads, and but- for the IRAS curtailments will have the same right to be served as any other load.

32. The implicit logic underlying PJM’s proposal is that because the excluded large loads can be called on to provide IRAS, the provision of IRAS offsets the resource adequacy need created by the physical entry of the excluded large load.  Thus, within the RPM framework, PJM’s proposal to remove large loads without BYONC arrangements or RBP allocations is effectively equivalent to incorporating the excluded large loads into the demand curve while also entering an equivalent amount of price-taker capacity supply that serves as a proxy for the IRAS curtailments that the excluded large load may be forced to provide.19

19 The amount of megawatts PJM proposes to remove from the RPM demand curve will vary slightly at different points along the curve because PJM will deduct the excluded load from the reliability requirement before multiplying by the relevant percentages at that define each point on the demand curve (99% for point A, 101.5% for point B, 106% for point C) (see PJM Proposal 117-118).  For this reason, PJM’s proposal is not exactly equivalent to retaining the excluded load in the supply curve and adding an equivalent amount of price-taker supply because the price-taker supply is not multiplied by the relevant percentages, but the difference is very minor.

PDF page 77

16

33. This implicit logic fails badly, for two reasons.  First, in any given delivery year IRAS will not exist at all if it is not triggered.    In this scenario, the excluded new large load will be physically present and will have the same service priority as other loads, but for RPM purposes PJM will simply pretend it is not there.  Furthermore, it will be uncertain whether or not IRAS will be in effect for a given delivery year until less than three months before the start of the delivery year because PJM proposes that the triggering conditions for the provision of IRAS are not to be finalized until the conclusion of the third Incremental Auction.  This lack of forward certainty as to whether IRAS will even be present at all further complicates PJM’s ability to plan for reliable operations both with respect to resource adequacy specifically as well as general transmission security in operations.

34. Second, even when it is in effect, IRAS is not capacity.  Unlike its nearest capacity analogue, Demand Response, IRAS is not subject to any sort of rigorous accreditation process to verify that it can perform as required; it does not receive an Effective Load Carrying Capacity or UCAP award quantifying its capability; it is not subject to testing or performance measurement; and it is not subject to capacity performance incentives or penalties.  Instead, IRAS is implemented as a NERC Instruction to EDCs, which carries the weight of NERC oversight and potential enforcement, but is nonetheless far different from capacity.  Specifically, PJM will lack the same level of visibility and control it has with capacity resources because it cannot issue direct curtailment instructions to IRAS loads, because it cannot subject IRAS to the same precise, rigorous testing regime it places on capacity, because it cannot quantify expected IRAS performance via ICAP and UCAP ratings, and because it cannot assess or credit Non-Performance incentive payments to IRAS resources. But PJM’s proposed treatment of loads that are eligible to provide IRAS in the RPM effectively assumes that IRAS is equivalent to capacity resources that offset the incremental reliability requirement of the load in question on a one-for-one UCAP basis.  In mechanical terms, this is equivalent to assuming IRAS is a capacity resource with an ELCC equal to the forecast pool requirement, or about 92% in the upcoming 2029/30 BRA, which is better than Demand Response and most Generation Capacity Resource types.

35. In addition to the reliability aspects, deployment of IRAS is likely to be very costly, and thus as a resource adequacy product it is likely to be much more costly than Demand Response or other capacity resources.  Excluding IRAS-eligible large load from RPM demand removes any pathway

PDF page 78

17

to express these economic differences and replace costly IRAS with less costly capacity resources over time, but rather effectively treats IRAS as if it is a zero-cost resource.

36. The consequence of PJM’s exclusion of non-BYONC large loads from the RPM is that regardless of whether or not IRAS is triggered, the RPM will reflect a fictional reliability outcome that will be materially different from the real physical resource adequacy situation.  This is at odds with the purpose of the RPM, which is to conduct a competitive procurement for physical capacity supply sufficient to achieve PJM’s resource adequacy standard at the level of the RTO and Local Delivery Areas based on forecasted demand.  The amount of capacity procured, and the price paid for that capacity, will be inconsistent with the real underlying resource adequacy situation.

37. This mismatch will be particularly stark in delivery years where IRAS is not triggered.  For example, consider the following illustrative example depicted below in Figure 1: Figure 1

In this example, there is 5 GW of IRAS-eligible demand on the system which is excluded from the RPM demand curve, but the RPM just barely clears enough supply to avoid triggering IRAS.  As a result, there is a sharp divergence between the apparent “on-paper” outcome of the BRA and the actual, physical reliability situation.  On paper the market clears at a low price with an apparent excess - 103.8% in this example - when compared to the fictional, reduced amount of demand embedded in the demand curve.   If, instead, actual physical fundamentals were properly reflected in the RPM, it would show a quantity cleared just barely in excess of the reliability requirement – 100.3% in this example – and a clearing price greater than the actual clearing price.  The clearing price thus signals a large amount of excess while in reality the market is dangerously close to falling short of the reliability requirement.  There is no signal to retain the resources needed to RPM Supply Curve

UCAP MW
5 GW of IRAS-Eligible Load
Excluded from Demand
“On-Paper” Cleared
outcome: 103.8% of
Reliability Requirement;
Price
($/MWD)
Outcome Consistent with Physical Reality:
100.3% of Reliability Requirement;
RPM Demand Curve

PDF page 79

18

maintain resource adequacy and address potential future shortfalls, nor is there a signal for new resources to begin the often-lengthy process of entering the market in anticipation of further tightening of the resource adequacy situation.  And if the market were actually short of the reliability requirement and IRAS were triggered, there would be no signal for the procurement of actual, accredited capacity resources to replace the reliance on IRAS as a resource adequacy product, which as discussed above is both costly and subject to uncertainty.  This raises the risk that PJM’s proposal will trap it in a kind of reliability purgatory: the RPM will paint a better resource adequacy picture than exists in reality and thus fail to signal the need for new resource entry or resource retention consistent with the actual underlying physical resource adequacy situation, leaving PJM stuck.  But actual physical operations will unforgivingly expose these shortcomings. When actual system stress occurs in real operations, and IRAS was never triggered in the first place or does not perform as expected, PJM will be faced with a real, physical emergency.  Fundamentally, excluding demand from the RPM that will nonetheless ultimately be physically present undermines the ability of PJM to achieve its resource adequacy standard or even to know where it stands relative to its resource adequacy standard at any given point in time.  Going forward over time as more load is excluded under PJM’s proposal, the wedge between the fictional RPM and underlying physical reality will widen, and the risk that it will lead to real physical load shed will multiply, with no endpoint because PJM’s proposal to exclude load that does not bring new capacity is permanent.

38. Thus, when PJM faces a need for new capacity (or retention of existing capacity) to support new demand from large load, there is no avenue for the RPM to reflect this need.  New large loads will either contract with new supply outside the RPM via BYONC arrangements whose economics cannot be reflected in the RPM, or they may enter without BYONC arrangements but will not be included in RPM demand.  In either case, no signal is sent to the RPM that incremental supply or retention of existing supply is needed to support the new demand, despite there being a very clear fundamental need in reality.  PJM’s proposal creates the illusion within the RPM that no net new large load demand exists on the system, even if there is substantial need for new supply to serve new large load.

39. The overall result of PJM’s proposed treatment of new large loads is that the only viable pathway to attract new supply when faced with new demand from large load is through the BYONC mechanism, which as discussed above occurs outside the RPM and does not result in a

PDF page 80

19

new entry price signal being sent to the RPM.  When large load enters without the BYONC mechanism in place, it will be excluded from the RPM and a price signal for new entry and/or retention of existing supply to support this new demand will not be sent.  Rather, the new demand will be effectively assumed to be served via the deployment of IRAS, which is both much more costly than actual capacity and subject to considerable uncertainty around its availability and performance.

40. If it accepts the PJM Proposal, the Commission should order PJM to modify its proposal to include new large load in RPM demand under all circumstances, regardless of whether or not the new large load brings new capacity through a BYONC arrangement.  This treatment ensures that the RPM parameters and market clearing outcomes will be consistent with the actual underlying resource adequacy situation and will provide an accurate market price signal for resources to enter and/or remain in the market to support this incremental demand.

IV. IRAS IS THE LATEST IN A SERIES OF RECENTLY-IMPLEMENTED OR PENDING ACTIONS BY PJM THAT WILL COLLECTIVELY DESTROY THE ABILITY OF RPM TO MEET THE RESOURCE

ADEQUACY NEEDS OF PJM GOING FORWARD UNLESS CORRECTIVE ACTION IS TAKEN
41. PJM’s IRAS proposal is the latest in a series of actions and proposed actions that collectively depress market prices in the RPM for existing resources while providing higher, discriminatory prices for new resources under specific conditions.  Without corrective action by the Commission, the collective weight of these proposals, coupled with the specific problems created by the IRAS proposal, will act together to effectively make it impossible for the RPM to attract new entry to serve any type of new demand, Large Load or otherwise, or to forestall resource exit.

42. As discussed above, PJM’s proposal in this proceeding creates a special pathway for new resources to enter the market via bilateral BYONC arrangements with new large loads while requiring the capacity entering under such arrangements to offer into the RPM as price-takers and while excluding large loads that do not make BYONC arrangements from RPM altogether.  Both of these elements depress market prices in the RPM even when supply is needed to meet new demand.

43. In addition to PJM’s proposal in this proceeding, in recent years, actions taken by PJM which erode the ability of the RPM to attract and retain market-based supply include:

PDF page 81

20
•
Counting resources operating under Reliability-Must-Run contracts that do not provide
capacity as if they are nonetheless providing capacity and entering those resources into the RPM supply curve as price-takers, despite the resources receiving full cost-based

compensation.20
•
Enacting a temporary ad-hoc price cap (and non-binding price floor) that reduced the
normal standard price cap determined through Quadrennial VRR Review process by
approximately 35% when it became apparent that the 2026/27 and 2027/28 RPM auctions
would likely clear at the price cap.21
•
Extending the temporary ad-hoc price cap at the same nominal level to the 2028/29 and
2029/30 auctions when it became apparent that those auctions too were likely to
otherwise clear at the normal price cap.  This extension of the ad-hoc price cap occurred despite PJM filing and the Commission approving a new VRR Curve and normal price

cap through the 2025 Quadrennial Review process.22
•
Proposing to procure up to 6.8 Gigawatts of new build capacity outside of the RPM via
the Reliability Backstop Procurement process which would allow new resources to offer
and realize prices that are approximately 70% higher than those currently available to
existing resources in the RPM for up to 15 years while requiring that those high-cost new
20 PJM Interconnection, L.L.C., Revisions to Reliability Pricing Model, Docket No. ER25-682-000 (filed December 9, 2024) (PJM petition seeking to incorporate RMR resources into RPM capacity supply curve, among other changes). PJM Interconnection, L.L.C., 190 FERC ¶ 61,088 (2025) (Order approving PJM’s proposed treatment of RMR resources).
21 PJM Interconnection, L.L.C., Proposal for Revised Price Cap and Price Floor for the 2026/2027 and 2027/2028 Delivery Years, and Request for a Waiver of the 60-Days’ Notice Requirement to Allow for a March 31, 2025 Effective Date, Docket No. ER25-1357-000 (filed February 20, 2025) (PJM petition seeking a cap at $325/MWD and a floor at $175/MWD, as compared to the but-for price cap of approximately $500/MWD for the 2026/27 and 2027/28 Delivery Years).  Commonwealth of Pennsylvania v. PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 (2025) (Order approving the revised cap and floor).
22 PJM Interconnection, L.L.C., Proposal to Extend the Price Cap and Price Floor for the 2028/2029 and 2029/2030 Delivery Years, And Request for a Waiver of the 60-Days’ Notice Requirement to Allow for a March 31, 2026 Effective Date, Docket No. ER26-1556-000 (filed February 27, 2026) (PJM petition seeking to extend the cap at $325/MWD and floor at $175/MWD for the 2028/29 and 2029/30 Delivery Years).  PJM Interconnection, L.L.C., 195 FERC ¶ 61,076 (2026) (Order approving the extension of the revised cap and floor).

PDF page 82

21

resources offer into the RPM as price-takers for the full duration of their contracts regardless of whether the forecasted load that motivated the RBP ever shows up.23

44. PJM is well aware of the corrosive effect that these one-sided interventions have on the incentives for new resources to enter the market and for existing resources to remain in the market. The PJM White Paper eloquently describes this phenomenon as the “Credibility Trap.”  The Credibility Trap occurs when PJM seeks to utilize its markets to signal a need for capacity, but providers of capacity have little or no confidence that the market will provide the compensation necessary to support the entry or retention of that capacity due to the ongoing risk of politically- driven interventions similar to those taken by PJM in the recent past.  The PJM White Paper illustrated the credibility trap with the following graphic:

Source: PJM White Paper 26
45. When a resource enters via RPM, rather than via one of the special, discriminatory paths that PJM has proposed, such as via the RBP or a bilateral BYONC arrangement, it is “new” for only

23  PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (currently pending before the Commission).

PDF page 83

22

one year.  After that it becomes an existing resource that is forever locked out of the special, high- value discriminatory pathways and instead must rely on the ongoing compensation from RPM.  As such, it is subject to ongoing risk of further one-sided interventions such as further extension or re-imposition of “temporary” ad-hoc price caps or further infusions of price-taker new supply entering via new-only pathways.  To the extent that load growth does not materialize as forecast or materializes later than originally forecast, such resources are likely to endure an extended period of oversupply and extremely depressed prices driven by entry of new resources availing themselves of the RBP or BYONC arrangements.

46. PJM is well aware of the impact that low prices have on resource adequacy over time, particularly if the low prices are not consistent with physical fundamentals. In 2023, it published its Energy Transition in PJM: Resource Retirements, Replacements & Risks report (the “4R Report”) detailing how resource retirements and forecasted load growth were likely to result in a resource adequacy crunch.24 The 4R Report was published during a period of low capacity prices from 2021/22 through 2024/25 that sent a clear exit signal to many existing resources. Now that the predicted resource adequacy crunch is here, PJM is trying to incent replacement of these retired resources via new build capacity (or potentially re-activation of some of the retired resources) through more expensive RBP or BYONC contracts that, when entered into the market as price takers, will lead to the same price suppressing outcome for current existing resources that drove these deactivated resource to retire less than half a decade earlier.

47. Given this market landscape, the market stagnation identified in the PJM White Paper is likely to take hold.  No rational entrant will enter via the RPM, particularly when higher-priced, lower-risk pathways for new entry such as bilateral BYONC contracts, the proposed RBP, or a repeat of the proposed RBP at a later date are available or are likely to be available in the future, particularly if PJM further blunts the signal for new entry by removing new large load without associated new capacity from the RPM.  The rational approach for potential new entrant resources under these circumstances is to avoid entry via the RPM and instead enter via these special discriminatory new-only resource pathways.  And if these pathways are not available at a given point in time, investors in potential new entrant resources will prefer to wait until they do become

24 Energy Transition in PJM: Resource Retirements, Replacements & Risks, PJM (February 24, 2023). https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2023/energy-transition-in-pjm- resource-retirements-replacements-and-risks.ashx

PDF page 84

23

available rather than enter via the RPM.  Given PJM’s emerging track record in this area, waiting is likely to be a rational, winning bet.  The results of the 2028/29 Base Residual Auction provide an initial confirmatory datapoint of this phenomenon: despite clearing at the temporary price cap of $325 per MW-day and 6,831 MW short of the reliability requirement, only 525 MW of new resources (uprates and new build capacity) entered the market, the lowest level of new entry in 20 years.25  The likely reason is obvious: investors in new resources are holding out for the RBP and/or the prospect of bilateral BYONC arrangements.  If they enter via the RPM, they become an existing resource going forward that can never access those higher-value pathways.

48. Existing resources will also respond to these various one-sided interventions that cumulatively erode the ongoing revenues that they can expect to realize through the RPM.  Some resources may choose to retire if expected market revenues are insufficient to cover their ongoing operating costs and risks.  In addition to resources that simply retire, many existing resources have the capability to exit the RPM and instead sell into other markets.  Many generators can physically move their equipment to other regions of the country and effectively become a new generator in a different market.  Approximately 900 MW of gas-fired combustion turbine capacity in the ComEd zone of Illinois recently elected to leave the PJM market by physically moving their turbines to Texas and re-installing them there, effectively becoming a new resources in the Electric Reliability Council of Texas.26  Other existing resources have in recent years acquired firm transmission into neighboring markets such as MISO to export their capacity27 and can be expected to continue to do so in increasing numbers.  Finally, resources may relinquish their interconnection with PJM altogether and instead serve self-contained “islanded” networks.

25 2028/29 Base Residual Auction Report, PJM Interconnection, L.L.C, Figure 2.  https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results-report.pdf 2019/20 Base Residual Auction Report, PJM Interconnection, L.L.C, Table 7. https://www.pjm.com/-/media/DotCom/markets- ops/rpm/rpm-auction-info/2019-2020-base-residual-auction-report.pdf
26 Editorial: Owner of Massive Elwood Energy Plant isn’t Waiting for Illinois Closure Deadlines.  They’re Literally Moving the Plant to Texas.  Chicago Tribune Editorial Board (April 17, 2026). https://www.chicagotribune.com/2026/04/17/editorial-elwood-will-county-jb-pritzker-ceja-clean-energy-law/
27 See, e.g., Cordova Energy Company LLC, 194 FERC 61,108 (2026) (authorizing a 611.2 MW natural-gas fueled, combined-cycle electric generating facility located in PJM to sell its capacity to an affiliate in MISO during the 2028/2029 Delivery Year after already receiving approvals for similar sales during the 2027/2028 Delivery Year); Dairyland Power Coop., 194 FERC ¶ 61,133, at P 5 (2026) (explaining that Dairyland acquired PJM units for the purpose of exporting energy and capacity to fulfill Dairyland’s capacity obligations to its distribution cooperative members located in MISO).

PDF page 85

24

49. To the extent that existing resources take these pathways out of the market in response to the erosion of the RPM, PJM risks additional resource adequacy shortfalls going forward caused by resource exit.  While PJM is proposing a discriminatory pathway for new resources to enter in response to large load growth, it does not have a similar discriminatory pathway for new resources to enter in response to resource adequacy needs caused by other reasons such as the exit of existing resources.  But due to the continued erosion in investor confidence in the RPM caused by its proposal in this proceeding coupled with the other recent and pending actions detailed above, PJM is likely to find the investors in new capacity to be unresponsive to signals for new entry via the RPM, with capital staying on the sideline and waiting for PJM to crack and implement some new discriminatory pathway for new entrants, such as a reprise of the RBP.

50. The endpoint for PJM is a market that is continually in a spiraling crisis.  Ongoing interventions drive resource exit and eliminate the RPM as a viable pathway for new resource entry, which drives new resource shortfalls which beget further intervention, further eroding confidence in the market.  This outcome will erode reliability over the long run.  It will erode reliability because ad hoc interventions are a poor solution to resolving resource adequacy shortfalls.  They are slow to implement, frequently involve substituting inferior alternatives (such as RMR resources or IRAS curtailment) for real capacity, carry the risk of unforeseen or unintended consequences compared to the tried-and-true design of the market, and are often subject to ongoing legal risk.  Repeated reliance on these measures raises the risk that something will go wrong – IRAS loads do not curtail as expected, non-Capacity Performance compliant RMR resources fail to perform as hoped, RBP resources are delayed, either or both is thrown out on legal review – with ongoing elevated physical resource adequacy risk for all customers being the ultimate consequence.

51. While repeated interventions to depress market prices for existing resources and restrict payment of prices at the level needed for new entry solely to new entrant resources may appear to lower consumer costs, over time as the need for such interventions continually repeats and existing resources exit the market, any apparent consumer cost savings will decline and ultimately reverse. A core feature of this type of world is ongoing market exit of relatively low-cost existing resources that are nonetheless needed for maintaining resource adequacy.  Under the emerging paradigm, the only viable way to replace these lost existing resources is to engage in further discriminatory

PDF page 86

25

interventions to procure additional new resources at high cost.  This is a bad trade for consumers, and one that will come to predominate in the world towards which PJM is trending.

52. The forces moving PJM in the direction of the Credibility Trap have been operating for several years now and some of the interventions driving it have already occurred.  And PJM’s credibility as a steward of a stable, non-discriminatory, investable market for capacity has already been badly damaged.  Put simply, PJM is already deeply mired in the Credibility Trap.  Without modification, the IRAS proposal will drive substantial further market erosion for the reasons discussed above which will further undermine resource adequacy and increase costs in PJM.  This is particularly the case because the IRAS proposal will become a permanent part of the tariff and even if its implementation is suspended due to changing market conditions it can be repeatedly re- activated later if market conditions again become tight.  Thus, the IRAS proposal is a permanent “heads I win, tails you lose” policy from the perspective of existing resources.

53. But strong, prompt intervention by the Commission in the proceeding could put PJM on a path to ultimately escaping the Credibility Trap.  The modifications I discuss in other sections of this affidavit – namely moving IRAS curtailments back in the curtailment order and reflecting them in energy prices and reflecting all new large load in demand – are necessary to this but not sufficient in my view.  As discussed above, the BYONC mechanism is ultimately highly corrosive to markets and is a major contributor to the confluence of factors driving PJM towards the spiral of crisis.  Ideally the Commission should direct PJM to remove the BYONC mechanism from its proposal.  If the Commission declines to recommend a full removal of the BYONC mechanism from PJM’s proposal, it should consider mechanisms that limit its impact on the broader market, such as requiring resources entering the market under BYONC arrangements to comply with the Minimum Offer Price Rule which would preserve a new entry price signal for the broader RPM market.  The issues discussed in the PJM White Paper are broad and not limited only to the IRAS proposal, but strong action by the Commission to preserve markets in this proceeding will send a strong signal to investors that markets remain viable over the long term.

54. This concludes my affidavit.

PDF page 87

[No extractable text on this page.]

PDF page 88

26

Attachment A to Patterson Affidavit

PDF page 89

27

Aaron T. Patterson Testimony and Expert Reports Date

On Behalf Of
Commission/Court
Subject Matter
Docket/Case Number
Dec-25
Constellation Energy FERC
Affidavit – Proposal for
Enhanced Reliability
Backstop Mechanism
RM26-4-000
EL25-49-000
AD24-11-000
EL25-20-000
Dec-25
Constellation Energy Illinois Commer
Commission
Rebuttal Testimony
Responding to Joint NGO
Bring Your Own Generation
Proposal
25-0680
Oct-25
Constellation Energy Illinois Commerce Commission

Rebuttal Testimony
Responding to Joint NGO
Bring Your Own Generation
Proposal
25-0679 and 25-0677
Apr-25
Constellation Energy FERC
Affidavit – Resource
Adequacy Issues in PJM
EL25-49-000
AD24-11-000
EL25-20-000
Jan-25
Constellation Energy FERC
Affidavit – Treatment of RMR
Resources in PJM Capacity
Market
ER25-682-000
Feb-24
Nuclear Energy
Institute
U.S. Department of
the Treasury
Expert Report (with Frank
Huntowski and John
Hutchinson) – “Assessing the
Incrementality Requirement
of Treasury’s Proposed 45V
Regulations”
REG-117631-23
Dec-23
Constellation Energy FERC
Reply Affidavit – PJM
Capacity Market Reforms
ER24-99-000 and ER24-98-000
Nov-23
Constellation Energy FERC
Affidavit – Market Monitor
Complaint regarding PJM
Capacity Market
EL24-12-000
Nov-23
Constellation Energy FERC
Affidavit – PJM Capacity
Market Reforms
ER24-99-000 and ER24-98-000
Nov-22
Constellation Energy FERC
Joint Affidavit (with Michael
M. Schnitzer) – New England
Winter Gas-Electric Forum
AD22-9-000
June-21
Exelon Corporation
and PSEG
Companies
FERC
Reply Affidavit – PJM
Capacity Market Seller Offer
Cap
EL-19-63-000
May-21
Exelon Corporation
and PSEG
Companies
FERC
Affidavit – PJM Capacity
Market Seller Offer Cap
EL19-63-000

PDF page 90

28

Aaron T. Patterson Testimony and Expert Reports Date

On Behalf Of
Commission/Court
Subject Matter
Docket/Case Number
Nov-20
Exelon Corporation
FERC
Declaration (with Michael M.
Schnitzer) – NYISO Capacity
Market Buyer Side Mitigation
EL21-07-000
Nov-19
Exelon Corporation
State of New York
Public Service
Commission
Expert Report – “Impact of
Carbon Pricing on Potential
Expanded Buyer-Side
Mitigation in the NYISO
Markets”
19-E-0530
Dec-17
Exelon Corporation
Public Utility
Commission of Texas
Expert Report (with David
Coleman) – “Economic
Equilibrium and Reliability in
ERCOT”
Project No. 47199