Protest and Comments of Constellation Energy Generation, LLC addressing PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service…
Text extracted from the eLibrary original (SHA-256 46dab5860d3a164e…). Download the original from the official source.
Contents · 28 sections
- BACKGROUND
- I. PJM’s Proposal Is Beyond The Commission’s Jurisdictional Reach
- A. The Commission’s Jurisdiction Is Subject To Strict Statutory Limits
- B. The Proposal Exceeds The Statutory Limits On The Commission’s
- C. The Proposal Exceeds The Statutory Limits On The Commission’s
- D. The Authorities On Which PJM Relies Do Not Support Jurisdiction Here
- II. The Commission Would Unduly Discriminate Based On Load Size, Load Date, And
- A. The Commission Must Reject The Proposal Unless PJM Shows That The
- B. PJM’s Proposal Unduly Discriminates Based On Load Size And Load Date
- C. PJM’s Proposal Unduly Discriminates Based On Resource Vintage
- III. The Commission Must Reject PJM’s Proposal Because Market Design Flaws Make
- A. PJM’s Proposal To Curtail New Large Load Prior To Calling On Emergency
- B. PJM’s Proposal To Exclude New Large Load Without Sufficient BYONC
- IV. If the Commission Nonetheless Were To Accept PJM’s Unlawful Proposal, It Should
- A. If Accepted, The Proposal Should Be Modified To Allow Any Qualifying New
- B. If Accepted, The Proposal Should Be Modified To Specify That BYONC
- C. If Accepted, The Proposal Should Be Modified To Include Incremental
- V. Conclusion
- I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT
- A. QUALIFICATIONS
- B. BACKGROUND AND PURPOSE OF AFFIDAVIT
- C. SUMMARY OF CONCLUSIONS
- II. IRAS LOAD SHOULD BE CURTAILED AFTER DEPLOYMENT OF DEMAND RESPONSE AND OTHER
- A. DURING EMERGENCY OPERATIONS, RTOS SHOULD DEPLOY THE
- B. CURTAILMENT OF IRAS LOAD IS LIKELY TO BE MORE EXPENSIVE THAN
- C. THE COST OF CURTAILING IRAS LOAD SHOULD BE REFLECTED IN
- III. PJM’S PROPOSAL TO EXCLUDE NEW LARGE LOADS FROM RPM DEMAND UNLESS THEY
- IV. IRAS IS THE LATEST IN A SERIES OF RECENTLY-IMPLEMENTED OR PENDING ACTIONS BY
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 87.
Opening text
opening text · Topic match: Reliability and curtailment
The Commission cannot accept a Proposal that asks it to regulate based on retail characteristics and force a change in retail rules.Read this passage Filed comments: Reliability and curtailment
BACKGROUND
printed heading · Topic match: Reliability and curtailment
PJM proposes to define New Large Load based on size and in-service date.Read this passage Filed comments: Reliability and curtailment
I. PJM’s Proposal Is Beyond The Commission’s Jurisdictional Reach
printed heading
PJM’s Proposal Is Beyond The Commission’s Jurisdictional ReachRead this passage
A. The Commission’s Jurisdiction Is Subject To Strict Statutory Limits
printed heading · Topic match: Registry access
Such a registry does not involve interference with the retail market; it is merely an information-gathering exercise that, in and of itself, does not affect retail prices or the service provided to Large Loads or any other category of retail customer.Read this passage Filed comments: Registry access
B. The Proposal Exceeds The Statutory Limits On The Commission’s
printed heading · Topic match: Reliability and curtailment
Following an Interim Resource Adequacy Event, unless the Electric Distributor informs the Office of the Interconnection otherwise in accordance with Tariff, Attachment DD-4, section X(b)(ii), the Electric Distributor shall be responsible for compensating all Eligible New Large Loads that provided…Read this passage Filed comments: Reliability and curtailment
C. The Proposal Exceeds The Statutory Limits On The Commission’s
printed heading
The Proposal Exceeds The Statutory Limits On The Commission’s Jurisdiction Because The Proposal Does Not Directly Affect Wholesale Rates Finally, insofar as PJM’s Proposal is tied to specific retail-customer characteristics, it fails the first part of EPSA’s jurisdictional test: it does not…Read this passage
D. The Authorities On Which PJM Relies Do Not Support Jurisdiction Here
printed heading · Topic match: Reliability and curtailment
There, the challenged wholesale rule regulated participation in a wholesale market, as a retail customer voluntarily offered a demand reduction into a FERC-jurisdictional wholesale market and received wholesale-market compensation.112 That rule affected retail sales, but the nature of the retail…Read this passage Filed comments: Reliability and curtailment
II. The Commission Would Unduly Discriminate Based On Load Size, Load Date, And
printed heading
The Commission Would Unduly Discriminate Based On Load Size, Load Date, And Resource Vintage If It Accepted PJM’s Proposal PJM’s Proposal unduly discriminates in at least two respects: (1) against certain load, based on load size and load in-service date, and (2) against certain generation, based…Read this passage
A. The Commission Must Reject The Proposal Unless PJM Shows That The
printed heading · Topic match: Reliability and curtailment
The Commission Must Reject The Proposal Unless PJM Shows That The Proposal Is Not Unduly Discriminatory And Preferential The FPA prohibits undue discrimination in utility rates and dealings.Read this passage Filed comments: Reliability and curtailment
B. PJM’s Proposal Unduly Discriminates Based On Load Size And Load Date
printed heading · Topic match: Reliability and curtailment
Yet PJM proposes that only New Large Loads would be prioritized for service interruptions.Read this passage Filed comments: Reliability and curtailment
C. PJM’s Proposal Unduly Discriminates Based On Resource Vintage
printed heading · Topic match: Reliability and curtailment
Circuit has explained, any proposal that differentiates between new and existing generators must demonstrate “how” new and existing suppliers “are not similarly situated and in what respects the reasons are material” to the proposal.165 Thus, the Commission has rejected a PJM proposal to provide…Read this passage Filed comments: Reliability and curtailment
III. The Commission Must Reject PJM’s Proposal Because Market Design Flaws Make
printed heading
The Commission Must Reject PJM’s Proposal Because Market Design Flaws Make The Proposal Unjust And Unreasonable Under Section 205 of the FPA, PJM bears the burden to demonstrate both that its proposed tariff revisions are not unduly discriminatory and that they are “just and reasonable.” 180 To…Read this passage
A. PJM’s Proposal To Curtail New Large Load Prior To Calling On Emergency
printed heading · Topic match: Reliability and curtailment
PJM proposes to revise its Tariff to define an Interim Resource Adequacy Service Action as an Operating Instruction “to reduce load prior to calling on Pre-Emergency Load Management Reductions after determining that economic real-time supply may not be sufficient to maintain reserves to meet…Read this passage Filed comments: Reliability and curtailment
B. PJM’s Proposal To Exclude New Large Load Without Sufficient BYONC
printed heading · Topic match: Reliability and curtailment
Doing so would erode the investor confidence necessary to ensure resource adequacy at just and reasonable rates224 by blunting the signal for existing resources to remain in and new resources to enter the capacity markets, thus intensifying the market stagnation 219 Patterson Affidavit ¶¶ 36-37.…Read this passage Filed comments: Reliability and curtailment
IV. If the Commission Nonetheless Were To Accept PJM’s Unlawful Proposal, It Should
printed heading
If the Commission Nonetheless Were To Accept PJM’s Unlawful Proposal, It Should Condition Acceptance On Certain Small Modifications The Commission should reject the Proposal due to the defects described above.Read this passage
A. If Accepted, The Proposal Should Be Modified To Allow Any Qualifying New
printed heading
The proposed tariff revisions state a rule that “BYONC that is in an arrangement with a New Large Load must remain in such arrangement with that New Large Load unless and until the New Large Load is permanently out- of-service.”243 The Proposal specifies, however, that “the seller of the BYONC may…Read this passage
B. If Accepted, The Proposal Should Be Modified To Specify That BYONC
printed heading
If Accepted, The Proposal Should Be Modified To Specify That BYONC Includes Otherwise Qualifying Capacity Resources That Clear Any RPM Auction For 27/28, 28/29, And 29/30 If the Commission were to accept the Proposal, it also should modify the Proposal to clarify that qualifying BYONC is not…Read this passage
C. If Accepted, The Proposal Should Be Modified To Include Incremental
printed heading · Topic match: Connecting load and generation
If Accepted, The Proposal Should Be Modified To Include Incremental Capacity Created By An Energy Resource In The Definition Of BYONC PJM’s Proposal requires that generation and storage resources must meet certain “eligibility requirements” to qualify as BYONC, which are specified in the Proposed…Read this passage Filed comments: Connecting load and generation
V. Conclusion
printed heading · Topic match: Registry access
White Assistant General Counsel Constellation Energy Generation, LLC 250 Massachusetts Ave.Read this passage Filed comments: Registry access
CERTIFICATE OF SERVICE
printed heading · Topic match: Registry access
Goldenberg MUNGER, TOLLES & OLSON LLP 601 Massachusetts Avenue NW Suite 500 E Washington, DC 20001 (202) 220-1100 Elaine.Goldenberg@mto.com Appendix A UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.: 205(d) Rate Filing: Proposal to Establish…Read this passage Filed comments: Registry access
I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT
printed heading
QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVITRead this passage
A. QUALIFICATIONS
printed heading
I am a partner of The NorthBridge Group, Inc (“NorthBridge”).Read this passage
B. BACKGROUND AND PURPOSE OF AFFIDAVIT
printed heading · Topic match: Reliability and curtailment
Loads required to provide IRAS would be subject to curtailment by their local Electric Distribution Company (“EDC”) when PJM issues a zonal instruction to curtail IRAS load under North American Reliability Corporation (“NERC”) Energy Emergency Alert (“EEA”) 1 conditions, prior to any other…Read this passage Filed comments: Reliability and curtailment
C. SUMMARY OF CONCLUSIONS
printed heading · Topic match: Reliability and curtailment
This outcome will force PJM to contend with recurring resource adequacy shortfalls that cannot be resolved via the operation of the RPM but rather must be resolved via further ad-hoc intervention.Read this passage Filed comments: Reliability and curtailment
II. IRAS LOAD SHOULD BE CURTAILED AFTER DEPLOYMENT OF DEMAND RESPONSE AND OTHER
printed heading · Topic match: Reliability and curtailment
IRAS LOAD SHOULD BE CURTAILED AFTER DEPLOYMENT OF DEMAND RESPONSE AND OTHER LOWER-COST ACTIONS, AND THE COST OF IRAS CURTAILMENT SHOULD BE REFLECTED IN ENERGY MARKET PRICESRead this passage Filed comments: Reliability and curtailment
A. DURING EMERGENCY OPERATIONS, RTOS SHOULD DEPLOY THE
printed heading · Topic match: Reliability and curtailment
When PJM is operating under emergency conditions the amount of available excess generation supply will typically approach zero, and PJM thus must rely on other actions, such as the curtailment of load, in order to maintain reliable operations.Read this passage Filed comments: Reliability and curtailment
B. CURTAILMENT OF IRAS LOAD IS LIKELY TO BE MORE EXPENSIVE THAN
printed heading · Topic match: Reliability and curtailment
Specifically, PJM proposes that IRAS loads be curtailed before it takes a Maximum Generation Emergency Action (including curtailment of firm exports), before Emergency Voluntary Energy- Only Demand Response Reductions, Curtailment of Non-Essential Building Load, and the Deploy All Resources…Read this passage Filed comments: Reliability and curtailment
C. THE COST OF CURTAILING IRAS LOAD SHOULD BE REFLECTED IN
printed heading · Topic match: Reliability and curtailment
In a situation where PJM must curtail load in order to maintain reliable operations (through Demand Response deployment, IRAS curtailment, or manual load shed), the appropriate energy clearing price is the VOLL of the load that PJM must curtail.Read this passage Filed comments: Reliability and curtailment
III. PJM’S PROPOSAL TO EXCLUDE NEW LARGE LOADS FROM RPM DEMAND UNLESS THEY
printed heading · Topic match: Reliability and curtailment
PJM proposes that new large loads that enter starting in the 2029/30 delivery year and do not bring an equivalent amount of new capacity in UCAP terms be excluded from the RPM demand curve until and unless they bring such capacity.Read this passage Filed comments: Reliability and curtailment
IV. IRAS IS THE LATEST IN A SERIES OF RECENTLY-IMPLEMENTED OR PENDING ACTIONS BY
printed heading · Topic match: Reliability and curtailment
After that it becomes an existing resource that is forever locked out of the special, high- value discriminatory pathways and instead must rely on the ongoing compensation from RPM.Read this passage Filed comments: Reliability and curtailment