ER26-3515-000 · 2026-09-03 · Southern Maryland Electric Cooperative, Inc.
Comments and Limited Protest of Southern Maryland Electric Cooperative, Inc. regarding PJM Interconnection, L.L.C.’s 08/13/2026 filing
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
)
COMMENTS AND LIMITED PROTEST OF
SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC.
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (the “Commission”)1 and in accordance with the Commission’s Combined Notice of Filings notice issued August 13, 2026, Southern Maryland Electric Cooperative, Inc. (“SMECO”)2 respectfully submits this Comments and Limited Protest regarding the filing that PJM Interconnection, L.L.C. (“PJM”) submitted in the above-captioned docket on August 13, 2026 (the “IRAS Filing”).3
PJM proposes revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a new “Interim Resource Adequacy Service” (“IRAS”) and an associated “Large Load Registry.” As proposed by PJM, IRAS is a supplemental capacity product through which Eligible New Large Loads may be directed by the Electric Distributor to reduce their load in response to an Interim Resource Adequacy Service Action called by PJM.41 18 C.F.R. § 385.211 (2025).2SMECO is an electric distribution cooperative organized under the laws of the State of Maryland and is an “Electric Distributor,” as that term is defined in the PJM Amended and Restated Operating Agreement (“Operating Agreement” or “OA”), serving retail customers in Southern Maryland. In this proceeding, SMECO submitted, and the Commission accepted a (doc-less) motion to intervene on August 25, 2026.3Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Transmittal Letter of PJM Interconnection, L.L.C., Docket No. ER26-3515-000 (August 13, 2026) (“IRAS Filing”).4IRAS Filing at 74.
PDF page 2
2
Specifically, beginning with the 2027/2028 Delivery Year, IRAS would allow New Large Loads to interconnect without first securing capacity to cover their full demand, subject to a condition: PJM may direct the Electric Distributor serving such a load to reduce an aggregate quantity of that load -- ahead of PJM’s existing Pre-Emergency Load Management Reductions -- when PJM determines that available real-time supply may be insufficient to maintain required reserves.5
SMECO’s comments and limited protest address certain aspects of the IRAS Filing, including whether the real-time Interim Resource Adequacy Service Action mechanism that Mr. Christopher Pilong’s affidavit describes will operate as PJM intends without exposing Electric Distributors’ core native load to curtailment, and further aspects in which Electric Distributors are assigned new operational, data-reporting, compensation-administration responsibilities and exposure to payments and default allocations for payments owed by other entities under PJM’s proposed billing indemnification provision.
I. INTRODUCTION AND SUMMARY
PJM’s IRAS proposal responds to the same capacity shortfall underlying PJM’s separate Reliability Backstop Procurement (“RBP”) filing in Docket No. ER26-3380 – namely, that the 2028/2029 Delivery Year Base Residual Auction cleared 6,831.3 MW short of the PJM Region Reliability Requirement, a shortfall PJM attributes in substantial part to the rapid interconnection of large loads, including data centers.6 Where the RBP is a one-time capacity procurement, IRAS is a standing framework – i.e., it permits New Large Loads to connect to the PJM system ahead of
5IRAS Filing at 74–77.6IRAS Filing at 21 (describing the 2028/2029 Delivery Year Base Residual Auction shortfall); see also Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26- 3380-000, PJM Transmittal Letter at 2 (July 31, 2026).
PDF page 3
3
securing their own capacity, in exchange for exposing the uncovered portion of that load to curtailment before PJM calls on Pre-Emergency Load Management Reductions.7 However, the IRAS Filing assigns Electric Distributors a series of new duties -- to execute IRAS Action directives, to help build and validate a data registry, to coordinate retail deployment of load reductions, and to implement a wholesale compensation program -- while leaving several design questions either unresolved or deferred to future PJM Manual revisions. SMECO focuses on the following issues:
• New duties that proposed Tariff, Attachment DD-4 impose on Electric Distributors, certain of go beyond the metering, data-reporting, and physical emergency-response functions historically assigned to Electric Distributors under the PJM Operating Agreement (“OA”).
• A real-time Interim Resource Adequacy Service Action that directs an Electric Distributor to reduce its full, pre-assigned aggregate MW quantity without regard to whether the underlying New Large Load is actually energized and taking service, risking curtailment of the Electric Distributor’s existing, non-Large-Load native customers.
• A billing indemnification provision8 that assigns Electric Distributors all of the risk that another entity -- potentially an LSE with which the Electric Distributor has no affiliation -- fails to pay IRAS compensation it owes, with no PJM-level credit support of any kind.
• Mechanics of the proposed Large Load Registry’s data-reporting mandate on Electric Distributors, that PJM proposes to defer to PJM Manual revisions that have not yet been drafted; PJM’s proposal also identifies no mechanism for Electric Distributors to recover the costs of Large Load Registry compliance.
II. BACKGROUND
PJM submitted the IRAS Filing on August 13, 2026, requesting that the Commission act by no later than October 12, 2026, so that PJM may begin implementing the Large Load Registry
7IRAS Filing at 74–77.8 Proposed Tariff, Attachment DD-4, section X(b)(iii)
PDF page 4
4
and the other proposed Tariff and RAA revisions on that date. IRAS itself would not become available until the 2027/2028 Delivery Year, beginning June 1, 2027.9
PJM proposes to define “Large Load” as end-use customer load with a cumulative peak of 50 MW or greater at a single electrical site, including affiliated load facilities within a one-mile radius under specified configurations.10 A “New Large Load” is a Large Load (or incremental load at an existing site) that enters service after June 1, 2027,11 and an “Eligible New Large Load” is a New Large Load that has not entered into a “Bring Your Own New Capacity” (“BYONC”) arrangement or has not been allocated UCAP MW through the RBP.12
IRAS is triggered when PJM determines that available economic real-time supply may not be sufficient to maintain required reserves or applicable Interconnection Reliability Operating Limits.13 In that circumstance, PJM may issue an “Interim Resource Adequacy Service Action” directing the affected Electric Distributor to reduce an aggregate MW quantity of load -- based on the zone/area’s pre-Delivery Year IRAS obligation -- before calling on existing Pre-Emergency Load Management Reduction Actions.14
Notably, PJM will not itself identify which specific New Large Loads must reduce load; that determination is left to the Electric Distributor, who in coordination with the relevant state and/or Electric Retail Regulatory Authority (“RERRA”), LSEs, and LSE customers, make that
9IRAS Filing at 121-122.
10IRAS Filing at 31 (quoting proposed RAA, Definitions — Large Load). 11IRAS Filing at 1, FN 2 (quoting proposed Tariff, Definitions — New Large Load): New Large Load shall mean end-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June 1, 2027, that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load.12IRAS Filing at 38–41.13IRAS Filing at 74–75 (quoting proposed Tariff, Attachment DD-4, section I(b)).14IRAS Filing at 81-84; Affidavit of Christopher Pilong at para 52.
PDF page 5
5
determination.15 PJM emphasizes that “an Interim Resource Adequacy Service Action will not be specific as to which New Large Loads would need to be reduced; rather, it will be based on the aggregate MW of reduction available from the Eligible New Large Loads in the zone/area.” 16 Compensation for IRAS load reductions is set at a wholesale rate of up to 50% of the existing Non-Performance Charge Rate, but the rate can be reduced -- including to zero -- if the Eligible New Large Load elects a lower or no payment in its retail rate.17 How that wholesale rate reaches an Eligible New Large Load, and how (or whether) it is funded at the retail level, is left to the Electric Distributor, in conjunction with the applicable state authority or RERRA.18 To administer both IRAS and the Large Load Registry, PJM’s proposal assigns Electric Distributors four (4) duties under proposed Tariff, Attachment DD-4, section III:
• Executing PJM’s Interim Resource Adequacy Service Action directives;
• Coordinating with PJM on Large Load Registry development, including by providing “any information or data the Electric Distributor believes appropriate to facilitate an accurate Large Load Registry;”19
• Coordinating with the relevant state(s) or RERRA(s), LSEs, and LSE customers to support “transparent, effective, and orderly deployment” of IRAS;20 and
• Implementing the IRAS compensation program.21
Remainder of Page Intentionally Blank
15IRAS Filing at 83. 16IRAS Filing at 83-84.17IRAS Filing at 101-102.18IRAS Filing at 104–107. 19IRAS Filing at 26 (quoting proposed Tariff, Attachment DD-4, section III(b)).20IRAS Filing at 27 (quoting proposed Tariff, Attachment DD-4, section III(c)).21IRAS Filing at 27 (quoting proposed Tariff, Attachment DD-4, section III(d)).
PDF page 6
6
III. COMMENTS.
A. PJM’s IRAS Proposal Assigns Significant New Electric Distributor Responsibilities. In its IRAS Filing, Proposed Tariff, Attachment DD-4, section III requires that Electric Distributors “shall” fulfill four tasks:
1. Execute IRAS Load Reductions. An Electric Distributor must “execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions.”22 SMECO does not object to this task, which is a natural extension of the Electric Distributor’s existing Emergency-response role.
2. Build and validate the Large Load Registry. An Electric Distributor must “provide PJM with any information or data the Electric Distributor believes appropriate to facilitate an accurate Large Load Registry, including applicable state or RERRA retail tariff or contractual obligations,” and coordinate with PJM and the applicable Transmission Owner to “check the validity of the information provided.”23
This task goes beyond OA section 11.3.3(h)’s data-reporting obligation, which speaks to data “necessary or appropriate to implement or administer” the OA and RAA themselves -- not to serving as a validation source for a registry whose contents is built on information originating with LSEs or Large Loads that the Electric Distributor does not necessarily control.24
3. Identify which retail customers to curtail. An Electric Distributor must “coordinate, as appropriate, with the relevant state(s) or RERRA(s), individual [LSEs], and customers served by the [LSEs] in its zone/area to support transparent, effective, and orderly deployment” of IRAS.25 PJM characterizes this function as “memorializing” existing practice, under which Electric Distributors already determine, consistent with state programs, which loads to reduce in response to a PJM directive.26
While PJM OA sections 11.3.3(c) and (e) require an Electric Distributor to maintain load- shedding capability and to “[s]hed connected load … and take such other coordination actions as may be necessary in accordance with the directions of the Office of the Interconnection in Emergencies” -- an operational, physical-curtailment obligation27, PJM’s description of the coordination duty as a “memorialization” of past practice does not change that Electric
22IRAS Filing at 26 (quoting proposed Tariff, Attachment DD-4, section III(a)).23IRAS Filing at 26, 43 (quoting proposed Tariff, Attachment DD-4, section III(b); proposed RAA, Schedule 11, section B.1(c)).24IRAS Filing at 36–37 (describing the LSE as the party with the initial obligation to submit Large Load Registry data, with the Electric Distributor providing supplemental information).25IRAS Filing at 27 (quoting proposed Tariff, Attachment DD-4, section III(c)).26IRAS Filing at 27. 27OA sections 11.3.3(c), (e).
PDF page 7
7
Distributors are, for the first time, being asked to administer eligibility and curtailment-priority determinations under an entirely new service category.
4. Implement the IRAS compensation program. An Electric Distributor must “implement [a] compensation program consistent with Tariff, Attachment DD-4, section X.”28 It requires the Electric Distributor to administer, collect for, and disburse a PJM wholesale-rate-linked payment obligation.
IV. LIMITED PROTEST.
B. PJM’s Real-Time Interim Resource Adequacy Service Action Mechanism Does Not Confirm That the New Large Load Underlying an Electric Distributor’s Assigned Obligation Is Actually Energized or Online, Risking Curtailment of Core Native Load. The Affidavit of Christopher Pilong, submitted in support of the IRAS Filing, confirms that the “[i]dentification of an IRAS requirement for each Electric Distributor’s zone/area establishes the reliability obligation applicable to affected load,”29 and that “the IRAS requirement establishes an operational reliability resource available to PJM, which can be called upon when actual system conditions indicate that the reliability need addressed by the IRAS requirement is materializing.”30
Nothing in Mr. Pilong’s affidavit, however, ties PJM’s actual exercise of that authority in real time to whether the New Large Load generating the obligation, in fact, is energized and taking service. To the contrary, Mr. Pilong describes an Interim Resource Adequacy Service Action as a directive to reduce a fixed, pre-set quantity of load at the Electric Distributor zone/area level, determined without regard to real-time large-load operating status.
Specifically, the MW quantity of IRAS assigned to a given zone/area is fixed “prior to the start of each Delivery Year,” and thereafter is simply the figure “utilized by PJM Dispatch in their
28IRAS Filing at 27 (quoting proposed Tariff, Attachment DD-4, section III(d)). 29 Affidavit of Christopher Pilong para 21.
30Affidavit of Christopher Pilong para 22.
PDF page 8
8
system projections, alerts and actions.”31 When PJM later calls an actual Interim Resource Adequacy Service Action, Mr. Pilong explains that PJM Dispatchers “will direct Electric Distributors to implement reductions in load up to, and capped at, the pre-Delivery Year IRAS obligations they were assigned” -- the pre-set figure, not a real-time measure of the underlying load’s actual consumption -- and that PJM “will not direct specific New Large Loads to reduce load” but instead “will only direct load reduction of an aggregate MW IRAS within the zone or area.”32 The affidavit describes PJM Dispatchers calling, in an RTO-wide emergency, “for some or all Electric Distributors to reduce load across the PJM RTO Region” based on “the maximum IRAS amounts assigned to each Electric Distributor zone/area” -- again with no reference to whether the New Large Load behind that assignment is actually in service.33 This is not a remote hypothetical. The New Large Loads whose lack of BYONC makes them “Eligible” for IRAS treatment in the first place -- because, as described above, they have not secured a BYONC arrangement and have not been allocated sufficient RBP UCAP MW34 -- are, as a structural matter, disproportionately likely to be projects still working through interconnection, construction, or commissioning, rather than loads already drawing their full expected demand, if any demand at all based upon the state of project development. Mr. Pilong’s affidavit also confirms that an Interim Resource Adequacy Service Action “prioritizes load reduction from those Electric Distributor zones/areas where New Large Loads have not brought their own new capacity and do not have Allocated Reliability Backstop
31Affidavit of Christopher Pilong para 28.32Affidavit of Christopher Pilong para 42.33Affidavit of Christopher Pilong para 43. 34IRAS Filing at 38–41, 69.
PDF page 9
9
Procurement Unforced Capacity Megawatts … sufficient to cover their capacity needs” -- the same under-covered load that defines Eligible New Large Load status in the first place.35 And, because an Interim Resource Adequacy Service Action need not be preceded by any day-ahead alert -- Mr. Pilong acknowledges that “it is not a requirement that an Interim Resource Adequacy Service Alert be issued prior to an Interim Resource Adequacy Service Action”36 -- an Electric Distributor may have no advance opportunity to flag that its assigned New Large Load is not yet in service before PJM’s Action issues.
If an Electric Distributor’s assigned New Large Load has not yet been energized -- or has only begun a ramp or testing period well short of its expected draw -- at the time PJM issues an Interim Resource Adequacy Service Action, the Electric Distributor will nonetheless receive a directive to reduce its full pre-Delivery Year MW quantity. Because that New Large Load is not consuming power to reduce, and because the Interim Resource Adequacy Service Action is directed to the Electric Distributor’s zone/area as a whole rather than to any specific load, the Electric Distributor’s only means of complying would be to curtail its core, non-Large-Load native customers.
That outcome is the opposite of what IRAS is meant to achieve and would adversely impact SMECO’s ability to provide safe and reliable service on its electric distribution system to its customer-members. SMECO respectfully requests that the Commission direct PJM to clarify:
1. Whether an Electric Distributor’s obligation under an Interim Resource Adequacy Service Action is capped by the New Large Load MW actually energized and taking
35Affidavit of Christopher Pilong para 41.36Affidavit of Christopher Pilong para 34.
PDF page 10
10
service in its zone/area at the time of the Action, rather than by the full pre-Delivery Year assigned quantity;
2. If clarification point #1 above is not capped as described, what safeguard, if any, prevents an Electric Distributor from being directed to reduce more load than its interconnected, energized New Large Load represents, such that the Electric
Distributor would be required to curtail core native load to comply; and
3. Whether PJM will commit to adjusting/suspending an Electric Distributor’s assigned IRAS obligation when the underlying New Large Load’s in-service date is delayed beyond what PJM assumed in setting the zone/area’s pre-Delivery Year quantity.
C. The IRAS Filing’s Billing Indemnification Provision Shifts Compensation Default Risk to Electric Distributors, Including for Payments Owed by Other Entities.
The PJM Filing proposes “IRAS Compensation”, in which “Electric Distributors bear the responsibility to implement the compensation scheme for New Large Loads that provide the IRAS load reduction service.”37 As noted above, PJM is proposing a rate for IRAS that is equal to 50% of the Non-Performance Charge Rate. Given that the current RTO-wide Non-Performance Charge Rate is approximately $2,278/MWh (for the 2027/2028 Delivery Year), a new large load that did not arrange for new capacity would be compensated for curtailing at a rate of over $1,100/MWh. However, proposed Tariff, Attachment DD-4, section X(b)(iii) provides that “neither PJM nor the PJM membership, generally, is financially responsible for any potential defaults that may arise in association with the billing of” IRAS compensation.”38 Under this provision, if a state-approved rate requires collection of IRAS compensation from other LSEs, and an LSE does not pay as required -- “whether billed directly by the Electric Distributor or by PJM upon request of the Electric Distributor” -- “the default will not pass to the PJM membership,” and instead “any default shall be assessed to the Electric Distributor.”3937 IRAS Filing at 101.38IRAS Filing at 108 (quoting proposed Tariff, Attachment DD-4, section X(b)(iii)).39IRAS Filing at 108–109.
PDF page 11
11
PJM acknowledges that “in restructured states, the LSE may be an independent entity, not affiliated with the Electric Distributor.”40 Where that is so, an Electric Distributor directed to bill (or to request that PJM bill) another LSE for IRAS compensation would bear the full risk of that unaffiliated LSE’s non-payment, notwithstanding that the Electric Distributor has no ownership relationship, and potentially no pre-existing commercial or credit relationship, with the paying LSE. PJM’s proposal includes no mechanism -- no collateral requirement or no PJM-administered mutualization -- to protect the Electric Distributor against that exposure. SMECO respectfully requests that the Commission direct PJM to revise section X(b)(iii) to limit an Electric Distributor’s exposure to such circumstances.
D. The Large Load Registry Rests on Key Details That PJM Proposes to Develop Only After the Registry Takes Effect, With No Identified Cost-Recovery Mechanism. Proposed RAA, Schedule 11, section B.1(b) directs PJM to obtain Large Load Registry information from Electric Distributors, and proposed Tariff, Attachment DD-4, section III(b) requires an Electric Distributor to supply “any information or data the Electric Distributor believes appropriate to facilitate an accurate Large Load Registry, including applicable state or RERRA retail tariff or contractual obligations.”41 PJM’s proposes that its Large Load Registry will contain the following information about each Large Load in the PJM Region:
• Eligible Customer/Network Customer for Large Load;
• Description of Large Load;
• Location(s) (Control Zone, Electric Distributor zone/area, where a zone/area is an area within a Zone for which the relevant Electric Distributor specifies a separate Obligation Peak Load MW value. A zone/area is a service area of an Electric Distributor that is a separately identifiable, geographic area bounded by wholesale metering);
• In-service date for each increment of load;
• Peak shaving adjustment value pursuant to a state program codified in state law and whether and how it meets the requirements of Tariff, Attachment DD-2;
40IRAS Filing at 105, FN 281.41IRAS Filing at 26 (quoting proposed Tariff, Attachment DD-4, section III(b).
PDF page 12
12
• Delivery point / Point(s) of interconnection (include all if more than one);
• Peak load quantity (MW) and ramp schedule, if applicable;
• Telemetry specifications;
• BYONC quantity (MW) and ramp schedule, if applicable;
• Allocated RBP UCAP MW quantity (MW), if applicable;
• Backup generation (MW), including fuel type and relevant permitting limitations;
• Contracts or service agreements between the Large Load and the LSE;
• Points of contact at the applicable Transmission Owner, Electric Distributor, and Load Serving Entity;
• EMS B1/B2/B3 name (for the applicable Transmission Owner, Electric Distributor); and Additional details and contents as necessary, in accordance with the PJM Manuals. 42 The IRAS Filing, however, defers the mechanics of this mandate to PJM Manual revisions that have not yet been reviewed. For example, among other items deferred to later development, PJM states that it “intends to develop provisions in its Manuals to implement the Large Load Registry, as needed, including details about who may access the information and specific safeguards in place to maintain the confidentiality of certain data.”43
Electric Distributors are thus asked to commit to an obligation whose scope, format, and confidentiality protections will not be defined until after the Tariff and RAA revisions PJM proposes in the IRAS filing take effect.44 This timing is compounded by a liability concern PJM raises. That is, submitters of Large Load Registry information are subject to the Commission’s prohibition on untrue statements or material omissions under FPA Section 222 and 18 C.F.R. Part 1c, backed by civil penalties that can exceed $1.5 million per violation per day, and that “Sellers” additionally owe a duty of candor to the Commission and to PJM under 18 C.F.R. § 35.41(b).45
42IRAS Filing at 37.
43IRAS Filing at 43.44IRAS Filing at 121–122 (requesting an October 12, 2026 effective date for the Large Load Registry rules).45IRAS Filing at 44–45, citing FPA section 222, 16 U.S.C. § 824v; 18 C.F.R. §§ 1c.1(a), 1c.2(a), 35.36(a)(1), 35.41(b); Civil Monetary Penalty Inflation Adjustments, Order No. 906, 190 FERC ¶ 61,006 (2025).
PDF page 13
13
However, much of the underlying data an Electric Distributor is asked to relay into the Large Load Registry (see list above), will originate with the LSE serving the Large Load or with the Large Load itself, neither of which the Electric Distributor necessarily controls or can independently verify.46 PJM’s IRAS Filing does not clarify the scope of an Electric Distributor’s potential exposure under the above-noted anti-fraud and candor provisions for registry information it receives from, and relays on behalf of, third parties.
Finally, the IRAS Filing identifies no mechanism through which an Electric Distributor may recover the costs (administrative and systems) of complying with the Large Load Registry’s data- supply, validation, and coordination duties. SMECO respectfully requests that the Commission direct PJM to (i) file the Manual provisions implementing the Large Load Registry’s data formats, one-mile-site methodology, and confidentiality safeguards for review before -- not after -- the Large Load Registry becomes effective; (ii) clarify the scope of an Electric Distributor’s potential liability for registry information sourced from LSEs or Large Loads; and (iii) identify a mechanism for Electric Distributors to recover the reasonable costs of Large Load Registry compliance.
Remainder of Page Intentionally Blank
46IRAS Filing at 36–41.
PDF page 14
14
V. CONCLUSION
SMECO respectfully requests that the Commission consider SMECO’s Comments and Limited Protest in acting on PJM’s IRAS Filing.
Respectfully submitted,
Damon L. Krieger
Senior Vice President, Legal and Strategy, and
General Counsel
Southern Maryland Electric Cooperative, Inc.
15035 Burnt Store Road
P.O. Box 1937
Hughesville, MD 20637-1937
301.274.4323
Damon.Krieger@SMECO.coop
Dated: September 3, 2026.
PDF page 15
15
CERTIFICATE OF SERVICE
I hereby certify that I have this day served a copy of the foregoing document upon each party on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.
Dated: September 3, 2026.
/s/ _____
John S. Rohrbach