ER26-3515-000 · 2026-09-03 · Southern Maryland Electric Cooperative, Inc.

Comments and Limited Protest of Southern Maryland Electric Cooperative, Inc. regarding PJM Interconnection, L.L.C.’s 08/13/2026 filing

Text extracted from the eLibrary original (SHA-256 18555bdf4e3ab059…). Download the original from the official source.

Contents · 9 sections
  1. I. INTRODUCTION AND SUMMARY p. 2
  2. II. BACKGROUND p. 3
  3. III. COMMENTS. p. 6
  4. A. PJM’s IRAS Proposal Assigns Significant New Electric Distributor Responsibilities. p. 6
  5. IV. LIMITED PROTEST. p. 7
  6. B. PJM’s Real-Time Interim Resource Adequacy Service Action Mechanism Does Not p. 7
  7. C. The IRAS Filing’s Billing Indemnification Provision Shifts Compensation Default Risk p. 10
  8. D. The Large Load Registry Rests on Key Details That PJM Proposes to Develop Only p. 11
  9. V. CONCLUSION p. 14

Read topic-matched comments in ER26-3515

Topics in the text: Registry access · Reliability and curtailment · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (the “Commission”)1 and in accordance with the Commission’s Combined Notice of Filings notice issued August 13, 2026, Southern Maryland Electric Cooperative, Inc. (“SMECO”)2 respectfully submits…
Read this passage Filed comments: Reliability and curtailment

I. INTRODUCTION AND SUMMARY

printed heading · Topic match: Reliability and curtailment

SMECO focuses on the following issues: • New duties that proposed Tariff, Attachment DD-4 impose on Electric Distributors, certain of go beyond the metering, data-reporting, and physical emergency-response functions historically assigned to Electric Distributors under the PJM Operating Agreement…
Read this passage Filed comments: Reliability and curtailment

II. BACKGROUND

printed heading · Topic match: Registry access

IRAS itself would not become available until the 2027/2028 Delivery Year, beginning June 1, 2027.9 PJM proposes to define “Large Load” as end-use customer load with a cumulative peak of 50 MW or greater at a single electrical site, including affiliated load facilities within a one-mile radius under…
Read this passage Filed comments: Registry access

III. COMMENTS.

printed heading

III.
Read this passage

A. PJM’s IRAS Proposal Assigns Significant New Electric Distributor Responsibilities.

printed heading · Topic match: Registry access

An Electric Distributor must “execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions.”22 SMECO does not object to this task, which is a natural extension of the Electric Distributor’s existing Emergency-response role. 2.
Read this passage Filed comments: Registry access

IV. LIMITED PROTEST.

printed heading

IV.
Read this passage

B. PJM’s Real-Time Interim Resource Adequacy Service Action Mechanism Does Not

printed heading · Topic match: Reliability and curtailment

SMECO respectfully requests that the Commission direct PJM to clarify: 1.
Read this passage Filed comments: Reliability and curtailment

C. The IRAS Filing’s Billing Indemnification Provision Shifts Compensation Default Risk

printed heading · Topic match: Credit and exit

The PJM Filing proposes “IRAS Compensation”, in which “Electric Distributors bear the responsibility to implement the compensation scheme for New Large Loads that provide the IRAS load reduction service.”37 As noted above, PJM is proposing a rate for IRAS that is equal to 50% of the Non-Performance…
Read this passage

D. The Large Load Registry Rests on Key Details That PJM Proposes to Develop Only

printed heading · Topic match: Registry access

SMECO respectfully requests that the Commission direct PJM to (i) file the Manual provisions implementing the Large Load Registry’s data formats, one-mile-site methodology, and confidentiality safeguards for review before -- not after -- the Large Load Registry becomes effective; (ii) clarify the…
Read this passage Filed comments: Registry access

V. CONCLUSION

printed heading

CONCLUSION SMECO respectfully requests that the Commission consider SMECO’s Comments and Limited Protest in acting on PJM’s IRAS Filing.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated: September 3, 2026. /s/ _____ John S.