ER26-3515-000 · 2026-09-03 · FirstEnergy Service Company, Ohio Edison Company and 6 others
Limited Protest and Comments of FirstEnergy Service Company et al. in response to PJM Interconnection, L.L.C.’s 08/13/2026 filing to establish Interim…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
LIMITED PROTEST AND COMMENTS OF
FIRSTENERGY SERVICE COMPANY
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),1 FirstEnergy Service Company, as agent for its affiliates (“FirstEnergy”),2 respectfully submits this Limited Protest and Comments in response to PJM Interconnection, L.L.C.’s (“PJM”) August 13, 2026 filing, proposing to establish an Interim Resource Adequacy Service (“IRAS”) mechanism.3
In the Statement of Principles Regarding PJM (“Statement of Principles”), the National Energy Dominance Council and 13 of the Governors of the PJM States joined together and identified that there would be a class of new data centers that have not self-procured capacity or agreed to be curtailable.4 Under the Statement of Principles, this class of new data centers was to be excluded from PJM’s procurement of new Capacity Resources. PJM’s IRAS Proposal purports to outline how service is to be provided at the wholesale level to this class of data centers; the headline being that these new data centers either must bring their own new capacity (“BYONC”) or be curtailable.
1 18 C.F.R. § 385.211 (2025).2 FirstEnergy’s affiliates include Ohio Edison Company, The Cleveland Electric Illuminating Company, The Toledo Edison Company, FirstEnergy Pennsylvania Electric Company, Jersey Central Power & Light Company, Monongahela Power Company, and The Potomac Edison Company.3 Docket No. ER26-3515, PJM, Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability (“PJM IRAS Proposal”).4 Statement of Principles Regarding PJM, 1st and 3rd bullets (1/16/26), available https://www.energy.gov/documents/statement-principles-regarding-pjm.
PDF page 2
2
FirstEnergy agrees that new data centers that are not included within the scope of a PJM capacity procurement must either bring their own new capacity or be curtailable. Unfortunately, fundamental elements of PJM’s IRAS Proposal are fatally flawed and as a result these elements cannot be approved consistent with section 205 of the Federal Power Act (“FPA”). Section 205 of the FPA provides that the Commission can accept PJM’s RPM proposal only if it is just and reasonable and not unduly discriminatory or preferential.5 The filing utility— PJM—bears the burden of proof to demonstrate its proposal meets these FPA requirements.6 The Commission may accept PJM’s proposal only if there is sufficient evidence in the record to show PJM has carried its section 205 burden of proof.7 The Commission will reject any proposal that falls outside the zone of reasonableness—i.e., does not result in just and reasonable rates in accordance with section 205.8 Moreover, even if a rate falls within the zone of reasonableness, it may nevertheless violate section 205 due to being unduly discriminatory or preferential.9 In these comments, FirstEnergy demonstrates that PJM’s IRAS Proposal does not meet the FPA section 205 “just and reasonable” standard because:
1. PJM unlawfully is attempting to set retail rates by proposing that new data centers that are to be curtailable under the IRAS Proposal are to be paid to curtail;
2. PJM is discriminating against new generation that aligns itself with a new data center by requiring such new generation to participate in the RPM auctions for 10 years;
5 16 U.S.C. § 824d(a)-(b).6 Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022); NorthWestern Corp. v. FERC, 884 F.3d 1176, 1182-83 (D.C. Cir. 2018); Midcontinent Indep. Sys. Operator, Inc., 194 FERC ¶ 61,050, at P 23 (2026); Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC ¶ 61,236, at P 7 (2018).7 884 F.3d at 1182-84; Winnfield v. FERC, 744 F.2d 871, 876-77 (D.C. Cir. 1984); NorthWestern Corp., 147 FERC ¶ 61,049, at P 48 (2014). 8 Indep. Power Producers of N.Y., Inc. v. FERC, 2022 U.S. App. LEXIS 22081, at * 6, 2022 WL 3210362 (D.C. Cir. Aug. 9, 2022) (citing Me. Pub. Utils. Comm'n v. FERC, 520 F.3d 464, 471 (D.C. Cir. 2008), rev'd on other grounds, 558 U.S. 165 (2010); FCC v. Prometheus Radio Project, 141 S. Ct. 1150, 1158 (2021)).9 Ala. Elec. Coop, Inc. v. FERC, 684 F.2d 20, 27 (D.C. Cir. 1982) (citing U.S. v. Cent. Ill. R.R., 263 U.S. 515, 524 (1924)).
PDF page 3
3
3. PJM fails to align the timing of its IRAS Proposal with applicable Commission guidance; and
4. Various of the implementing details are beyond the scope of the Statement of Principles and are unnecessary and/or inconsistent with other elements of the Commission’s
developing data center policies and directives, and thus must be dropped from PJM’s eventual compliance filing.
LIMITED PROTEST AND COMMENTS
I. PJM is unlawfully attempting to set retail rates by proposing that new data centers that are to be curtailable under the IRAS Proposal are to be paid to curtail.
As the Commission is aware, its ratemaking jurisdiction is limited to interstate transmission and wholesale power sales.10 States regulate retail rates for retail customers. And new data centers are retail customers.
These broad principles notwithstanding, PJM has filed a tariff that calls for retail payments to be made when new data centers are curtailed.11 PJM even goes so far as to propose a retail rate that is to be paid to the curtailing data center; although PJM leaves final determination of the payment amount in the hands of the jurisdictional state.12
There is no basis under federal law for PJM to propose this rate. PJM’s IRAS Proposal is careful to exclude curtailable new data centers from its “Reliability Pricing Model” capacity procurement.13 In fact, such loads are not participating directly in any PJM power market. This is because they are retail loads. It is true that Load-Serving Entities may buy power at wholesale for resale for end-use consumption by a new data center. But this does not mean that a curtailable new data center is participating directly in PJM’s power markets. As such, these loads do not
10 16 U.S.C. §§ 824, 824d, 824e.11 PJM IRAS Proposal, Filing Letter, pp. 101, et seq., and the proposed tariff amendments described therein.12 Id., p. 102.13 Id., p. 55.
PDF page 4
4
resemble “demand response” as that product is defined in the PJM tariffs or in applicable state retail programs.
There is no policy guidance that calls PJM to create a Commission-jurisdictional compensation mechanism for new data center loads that are to be curtailable. As noted above, the Statement of Principles contemplates that certain new data centers will be curtailable. But the Statement of Principles does not call for PJM to create a compensation mechanism to pay for such resources during periods of curtailment. And PJM points to no other policy guidance that compels creation of a rate that provides payments to the new data centers – that are retail customers – that are required to curtail during periods of capacity shortfalls.
The unlawful nature of PJM’s proposal is demonstrated by PJM’s implicit recognition that the jurisdictional state authority must set the amount of the final payment.14 That PJM is calling for states and LSEs to identify the other retail customers that are to fund such payments again reflects the fact that PJM’s proposal is about retail rates, even if it is dressed up as purported amendments to a Commission-jurisdictional tariff.
The tariff amendments that are embodied in PJM’s IRAS Proposal do not reflect the jurisdictional boundary between the Commission and the states. Indeed, the states must retain control over determining the need for new power generation facilities, the economic feasibility of such facilities, and the rates and services to be provided by suppliers of the same.15 The Commission’s role is limited to regulating wholesale power sales.16 That is, the Commission can regulate a wholesale power market, as it does with PJM and the other RTOs. But the Commission cannot direct a utility to build new generation, and it cannot establish retail rate recovery that can
14 PJM IRAS Proposal, Filing Letter, p. 104.15 See, e.g., Hughes v Talen, 136 S.Ct. 1288 at 1292 (US 2016).16 16 U.S.C. 824(b)(1).
PDF page 5
5
pay for new generation. And, just as FERC cannot establish a retail rate to pay for new generation, FERC cannot establish a retail rate that pays a new data center to curtail when there is not sufficient generation capacity available to serve that customer. These functions are reserved for the states. Moreover, beyond the jurisdictional issues, the concept of compensating new large loads to curtail in the IRAS Proposal is deficient from a policy perspective and is contrary to the intent of the Statement of Principles which is to protect customers from the costs associated with integrating large loads. However, the IRAS Proposal, as designed, will in fact unjustly raise costs to retail customers with no corresponding benefits, and rewards imprudent owners of new large load facilities for their failure to procure new capacity to serve their own load. PJM attempts to smooth over this dynamic by pointing to the Ratepayer Protection Pledge as a mechanism to avoid passing costs associated with the IRAS Proposal on to retail customers. The Ratepayer Protection Pledge, however, is not a binding legal document and would not prevent new large loads from seeking compensation pursuant to the IRAS Proposal mechanisms.
Thus, for these reasons, the Commission must reject PJM’s attempt to create a retail rate as part of the IRAS Proposal.
II. The IRAS Proposal includes no justification for requiring BYONC generation
resources to participate in RPM for 10 years, and the Commission should require
PJM to drop this requirement.
There is no basis for PJM to create a minimum 10-year term for participation in the annual RPM auction for new BYONC resources.17 Although it is not spelled out, if a data center aligns itself with a new generation resource, it is reasonable to assume that the data center has signed a contract that is the basis for financing the new resources. That is, the funding for a new
17 PJM IRAS Proposal, Filing Letter, p. 55 and et seq. (and the tariff amendments described therein).
PDF page 6
6
BYONC generation resource should be understood to come from the commercial arrangements between the new data center and the generation resource.
It is axiomatic that marginal-price market models do not pay for new capital investment in high cost-of-capital fields; an outcome that is reflected by the fact that marginal-price design RPM has brought very little significant new dispatchable generation in PJM. The new data center, and not PJM’s RPM program, will be funding the capital investment in the new resource. As such, there is no need, or reason, to compel the new generation resources to be in the RPM auction for 10 years.
III. PJM is discriminating against new generation that aligns itself with a new data center by proscribing the opportunity for that resource to serve as a Fixed Resource Requirement generator.
PJM proposes that new BYONC resources must participate in RPM.18 That is, PJM is forcing new Capacity Resources that are aligned with new data centers into the RPM market. This is unduly discriminatory and preferential as it treats data centers and data center- aligned new resources differently from new loads and generation that otherwise have the option to opt into a full or partial Fixed Resource Requirement (FRR).
Section B of Schedule 8.1 of the PJM Reliability Assurance Agreement (RAA) sets forth the terms under which a certain load may “opt out” of the RPM program by demonstrating that it is eligible for the FRR program.19 An eligible LSE must demonstrate that all or part of its load falls within the RAA’s FRR Service Area definition (capable of being metered separately from other load), and that it has procured eligible Capacity Resources to cover that load and the FRR- defined associated resource adequacy reserve requirement. Importantly, because they are in an
18 PJM IRAS Proposal, Filing Letter, p. 55 and et seq. (and the tariff amendments described therein).19 PJM Reliability Assurance Agreement, Schedule 8.1, B.
PDF page 7
7
FRR “alternative,” eligible loads, and the associated generation, are not subject to the annual RPM auction.
FirstEnergy agrees with PJM that new data centers can be established as a new class of customers that are subject to different capacity rules than other loads.20 However, there is no basis to obligate a new data center, and the new generation resources that have been procured to supply that data center, to participate in the annual RPM auctions. On the contrary, PJM’s IRAS proposal contemplates that new data centers with associated new Capacity Resources in existing FRR areas will be excluded from the RPM auction. But PJM does not afford the opportunity for a new load with associated new generation that is not in an existing FRR area to take advantage of the FRR opportunity.
If new data centers and associated new Capacity Resources in existing FRR areas are exempted from the RPM auction, then there is no basis to force new Capacity Resources that are not in an existing FRR area to participate in the RPM auction. On the contrary, given the vagaries of the RPM construct, prudent data center developers and associated developers of generation resources have every reason to demand that they be allowed to take advantage of the FRR alternative, and be afforded the opportunity to do so. Requiring participation in the RPM auction, as PJM so proposes, is unduly discriminatory and preferential. 21
IV. PJM fails to align the timing of the IRAS Proposal with applicable Commission guidance.
The Statement of Principles provides policy guidance about the timing of the programs contemplated therein. Specifically, the Statement of Principles provides that PJM is to conduct a
20 See PJM IRAS Proposal, Filing Letter, p. 94 and et seq. (and the tariff amendments described therein). 21 16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., 263 U.S. at 524).
PDF page 8
8
Reliability Backstop [Procurement] to procure new Capacity Resources for new data centers that have not self-procured or agreed to be curtailable.22 Importantly, the policy guidance issued to PJM is to make changes for “new” data centers. Existing data centers implicitly are grandfathered. PJM’s IRAS Proposal purports to apply to new data centers that go into service after June 1, 2027.23 However, there could be a difference between “new” data centers and data centers that go into service after June 1, 2027. Specifically, it is possible that a developer of a data center may have signed a construction agreement for new transmission network facilities before January 16, 2026 and that due to the process of construction the data center may not go into service until after June 1, 2027. This customer is not “new” within the scope of the Statement of Principles and should be grandfathered. Importantly, the fact that these customers are not “new” within the contemplated scope of the agreement could mean that attempting to apply the IRAS Proposal to them could violate the filed rate doctrine because to do so would undermine preexisting commercial relationships by attempting to allocate capacity market outcomes to data centers who possibly have already signed FERC-jurisdictional contracts based on a pre-IRAS Proposal understanding of the market.
Relevant here is that PJM makes no effort to demonstrate that its proposal, at least for the customers described in the prior paragraph, is consistent with relevant Commission guidance. Specifically, in its June 18, 2026 Order to Show Cause, the Commission identified that certain data centers were, as of the date of the Order, working with transmission owners and other relevant entities to take service from the transmission system.24 The Commission further identified that there is a need to protect existing commercial arrangements, that stakeholders needed to ensure
22 Statement of Principles, 3rd bullet. 23 PJM IRAS Proposal, Filing Letter, p. 38 (and the tariff amendments described therein).24 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 105.
PDF page 9
9
minimal disruption to existing commercial arrangements, and that stakeholders were to thoughtfully develop proposals to establish a reasonable amount of time to finalize agreements that are nearing completion as of the date when tariff amendments were filed for Commission approval.25
PJM’s “one size fits all” IRAS Proposal does not protect against disruption to existing commercial arrangements, and it makes no effort to establish a reasonable time to finalize agreements that are nearing completion as of the date when the IRAS Proposal was filed. That is, PJM failed to align the timing of the IRAS Proposal with the Commission’s guidance about existing and nearly final commercial arrangements. As such, the Commission should reject PJM’s “one size fits all” date of “enters service after June 1, 2027,” and instead direct PJM to develop an IRAS Proposal effective date that does not disrupt existing commercial arrangements and that provides sufficient notice so that stakeholders can complete contracting processes that are “in flight” as to the date of PJM’s future compliance filing.
V. Various of the implementing details are beyond the scope of the Statement of Principles and are unnecessary and/or inconsistent with other elements of the Commission’s developing data center policies and directives, and thus must be dropped from PJM’s eventual compliance filing.
Certain aspects of PJM’s IRAS Proposal are not consistent with the express or implied policy guidance that is provided in the Statement of Principles or other applicable Commission guidance. As such, these details do not clear the “just and reasonable” legal standard for evaluating tariff amendments. As outlined in the following sections, the Commission should require PJM to address these instances by submitting further amendments in order to bring these instances into harmony with the Statement of Principles and the other applicable Commission guidance.
25 Id.
PDF page 10
10
A. The definition of “Large Load” should be adjusted, either to take the minimum megawatt threshold to 200 MW, or to limit the definition to new data centers.
As relevant here, PJM proposes to define Large Loads as an end-use customer that has a cumulative peak of 50MW or greater.26 This definition will capture new data centers. But it will also capture small and medium-sized manufacturing facilities.
The scope of the Statement of Principles document, which is the policy guidance that should control for review of PJM’s IRAS proposal, is limited to new data centers.27 And for good cause. It is true that similar energy infrastructure must be constructed without regard to whether the new facility is a data center or a manufacturing facility. But that is where the similarity ends. Manufacturing facilities generate numerous upstream, local and downstream investment and jobs; whereas data centers do not. That is, manufacturing facilities generate significant upstream, local and downstream benefits for workers, their communities, and the states that comprise PJM; whereas the economic benefits of data centers are different and more limited.
There are material differences between a new data center and a manufacturing facility. First, a new data center will generate many jobs during initial construction; but very few full-time jobs post construction, whereas a new manufacturing facility will generate many permanent full- time jobs. Next, once it is up and running, the new data center will consume enormous amounts of energy, and that’s it. In contrast, a new manufacturing facility will consume raw and somewhat processed materials; the extraction/processing/supply of such also will generate many full-time jobs. Importantly, each full-time job that is supported directly or indirectly by a manufacturing facility will support a family. And families own homes, pay taxes, and participate in communities.
26 PJM IRAS Proposal, Filing Letter, p. 31, and the proposed tariff amendments described therein.27 Statement of Principles, 3rd bullet.
PDF page 11
11
The differences are not limited to jobs. For example, data centers likely can be curtailed on short notice with little consequence. But there are consequences for curtailing manufacturing facilities on short notice, including at least: upstream and downstream supply chain disruption; work stoppages for affected workers; lost inventory that is stranded in the manufacturing process; damage to manufacturing equipment; and cleaning and restarting of manufacturing equipment.
PJM is unable to demonstrate that it clears the FPA section 205 hurdle for including manufacturing facilities within the scope of the IRAS proposal. This is because it is unjust and unreasonable to include manufacturing facilities within scope. Manufacturing facilities are not like data centers, and they also are not within the scope of the Statement of Principles guidance. And imposing what amounts to a “tax” on future operations will likely have the unintended consequence of driving investment and jobs out of PJM and into regions of the country that are more welcoming; that is, including manufacturing facilities within the scope of the IRAS proposal is unduly discriminatory and preferential28 against manufacturing facilities that are attempting to locate or expand in PJM as compared to other regions. As such, the Commission should direct PJM to either raise the MW threshold for IRAS applicability (to 200 MW) or refine the Large Load definition to limit the rule to new data centers.
B. The criteria for the Large Load registry must match the criteria that are to be set forth in the pro forma agreement that is described in the Commission’s June 18, 2026 Order to Show Cause.
The Commission’s June 18, 2026 Order to Show Cause included a preliminary finding that PJM’s tariff appears to be unjust and unreasonable because it lacks a pro forma agreement that itemizes the terms and requirements under which a new data center would take transmission
28 16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., 263 U.S. at 524).
PDF page 12
12
service.29 Importantly, PJM and the Transmission Owners are to submit a compliance filing that, among other things, provides the pro forma agreement anticipated in the Order to Show Cause.30
In the IRAS Proposal, PJM outlines the data that data centers must submit to be included in a contemplated “Registry.”31 FirstEnergy does not object to many of these criteria, but notes that the criteria should not be finalized until the pro forma agreement and “registry” that are contemplated in the Order to Show Cause are finalized.
C. PJM should clarify that the Data Center, and not the Load-Serving Entity, is responsible for certain compliance obligations.
PJM’s IRAS Proposal is filled with terms, requirements, obligations, and conditions that attach to data centers under the IRAS. But, from time to time, PJM attempts to place some of these conditions on Load-Serving Entities. For example, the IRAS Proposal provides that LSEs must bring new capacity or be subject to load reductions.32
PJM, no doubt, intended confusion concerning this aspect of the IRAS Proposal. However, PJM’s language is confusing. Sometimes the terms, requirements, obligations, and conditions are described as pertaining to the new data center. And, as noted, at other times, PJM suggests that they pertain to the LSE.
Assuming that at some future time some form of PJM’s IRAS Proposal is approved, the Commission can remedy this deficiency by directing PJM to clarify which entity holds the obligations. For example, PJM could create new classes of LSEs and Electric Distribution
29 Supra, n. 24 at P 65.30 FERC Docket No. EL26-67, PJM, Motion of PJM, fn 28 (PJM working with Transmission Owners on compliance filing) (July 28, 2026); id., Letter Order, 196 FERC ¶ 61,129 (2026).31 PJM IRAS Proposal, Filing Letter, pp. 36 and et seq. (and the proposed tariff amendments described therein).32 PJM IRAS Proposal, Filing Letter, pp. 49 and et seq. (and the proposed tariff amendments described therein).
PDF page 13
13
Companies – e.g., Data Center-Related LSEs/EDCs – and clarifying that the obligations attach to these classes of entities.
D. PJM should clarify that “Energy Resources” can be “new” Capacity Resources for purposes of evaluating a Data Center’s compliance with the proposed Bring Your Own New Capacity option for removal from IRAS.
PJM proposes that new data centers can remove themselves – in whole or part – from the IRAS if the new data center brings new capacity. PJM goes on, however, to clarify that a new Capacity Resource cannot be existing generation that is “repackaged.”33
It is clear that PJM is attempting to ensure that existing Capacity Resources are not removed from the Reliability Pricing Model markets and then paired with a new data center so that the new data center can be removed from the IRAS. However, there is a class of generating resources that currently are not Capacity Resources. Specifically, PJM’s Open Access Transmission Tariff defines an “Energy Resource” as a Generating Facility that is not a Capacity Resource.34 Energy Resources do not have RPM obligations, and receive no RPM revenues. Instead, Energy Resources typically limit their power market participation to selling energy and ancillary services into PJM’s day-ahead and real-time markets. Because such resources are not committed to the RPM market, they are not Capacity Resources.
The Commission should direct PJM to allow Energy Resources to qualify as “new capacity” for purposes of evaluating whether a data center can be removed from IRAS. There is no basis to exclude Energy Resources. Excluding such resources would be unduly discriminatory
33 Id. at p. 50 (and the tariff provisions described therein).34 PJM Open Access Transmission Tariff, definitions.
PDF page 14
14
and preferential35 in that it would prohibit Energy Resources from entering the capacity market as supply for the new data centers that wish to bring their own new capacity.
E. There is no justification for dropping the IRAS rules if PJM has sufficient capacity to meet the RPM requirement for three consecutive years.
PJM proposes that the IRAS rules will not apply if PJM has sufficient capacity to meet the RPM requirement for three consecutive years.36 This proposal, however, is unjust and unreasonable as it would allow data center loads that are “new” after the termination of the IRAS rules to enter with the expectation of firm capacity supply. There is no basis to expect that such firm supply will exist. PJM itself admits that its current capacity resource shortfall is at least 6,831 MW.37 And the Statement of Principles notes that PJM must procure new Capacity Resources to serve new data centers that do not self-supply or agree to be curtailable.38 The Statement of Principles does not authorize PJM to allow new data centers to enter the market when there is not sufficient supply. And new data centers now range from hundreds to more than a thousand megawatts of demand.39 This is not the incremental load growth for which the RPM construct was designed. The mere fact that the RPM market has cleared for three consecutive years does not mean that there is enough “headroom” to absorb hundreds or possibly thousands of new megawatts of new load. Moreover, this proposal is unjust and unreasonable in that it allows “new” data centers that enter the market after termination of the IRAS rules to ride on the capacity that is being
35 16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., 263 U.S. at 524).36 PJM IRAS Proposal, Filing Letter, p. 52 and et seq. (and the tariff amendments described therein)37 FERC Docket No. ER25-3380, PJM, RBP Filing Letter, p. 31.38 Statement of Principles, 3rd bullet.39 See Data Centers and Their Energy Consumption, Library of Congress (2026), available https://www.congress.gov/crs-product/R48646.
PDF page 15
15
paid for by other customers. In other words, this proposal is unduly discriminatory and preferential in favor of the new “free riding” data centers.40
F. There is no justification for requiring BYONC generation resources to participate in RPM for 10 years, and the Commission should require PJM to drop this
requirement.
There is no basis for PJM to create a minimum 10-year term for participation in the annual RPM auction for new BYONC resources.41 Although it is not spelled out, as the impetus for funding a new BYONC resource should be understood to come from the commercial arrangements between the new data center and the generation resource. It is axiomatic that marginal-price markets models do not pay for new capital investment in high cost-of-capital fields; an outcome that is reflected by the fact that marginal-price design RPM has brought very little significant new dispatchable generation in PJM. The new data center, and not PJM’s RPM program, will be funding the capital investment in the new resource. If there is to be a minimum term, it should be set at a minimum term for the new data center to be removed from the IRAS program, and not on the basis that the data center brought new generation.
G. PJM must provide additional clarification regarding the new data centers that qualify for reduced IRAS due to being allocated a share of the Reliability Backstop Procurement megawatts.
PJM proposes that a new data center that could be subject to the IRAS can have its IRAS obligations reduced or eliminated by virtue of being allocated a share of the new Capacity Resources that are to be procured through PJM’s proposed “Reliability Backstop Procurement” (RBP).42 Given, however, that the RBP capacity is to be allocated to data center loads that were
40 16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., 263 U.S. at 524).41 PJM IRAS Proposal, Filing Letter, p. 55 and et seq. (and the tariff amendments described therein).42 PJM IRAS Proposal, Filing Letter, p. 67 and et seq. (and the tariff provisions described therein).
PDF page 16
16
included in forecasts from 2025 that are the basis for the RBP cost allocation,43 PJM should clarify that a new data center can have its IRAS obligation reduced or eliminated only if the data center was included in the 2025 forecast that is the basis of the RBP procurement. To do otherwise would be unduly discriminatory and preferential to other similarly situated data centers that retain IRAS obligations.44
H. IRAS obligations must be allocated to data centers that did not agree to be
curtailable.
PJM proposes to reallocate IRAS curtailment obligations annually.45 That is, PJM proposes to reallocate curtailment obligations annually based on the level of the capacity shortfall for a given region. As capacity shortfalls ebb and flow, PJM will reallocate curtailment obligations. The proposal is unduly discriminatory and preferential as it could allow new data centers that did not bring their own generation to avoid curtailment based on market activity of other market participants.
The Statement of Principles, which is the policy guidance that should control for review of PJM’s IRAS proposal, provides that new data centers either must participate in the RBP, or bring their own generation, or agree to be curtailable.46 It does not allow a data center to exit a curtailment obligation because, through the activity of some other market participant, the region in which the data center is not located no longer is net-short of capacity. And, under PJM’s proposal, the “net short” conditions will change because either other loads exited the region or because unaffiliated new Capacity Resources entered the region.
43 FERC Docket No. ER25-3380, PJM, Filing Letter, p. 103.44 16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., 263 U.S. at 524).45 PJM IRAS Proposal, Filing Letter, p. 70 and et seq. (and the tariff provisions described therein).46 Statement of Principles, 3rd bullet.
PDF page 17
17
In short, PJM is proposing to allow certain data centers to benefit from actions of unaffiliated third parties. This is the definition of undue discrimination and preferential treatment;47 especially as compared to the other new data centers that will remain subject to the IRAS requirement. The policy guidance provided in the Statement of Principles is clear - if a new data center is not subject to the RBP, and does not bring its own new capacity, then it is curtailable. The Commission should direct PJM to drop this unjust and unreasonable proposal as part of PJM’s compliance filing.
III. CONCLUSION
FirstEnergy respectfully requests that the Commission consider the foregoing comments and protest in its consideration of PJM’s IRAS Proposal, and direct PJM to amend its proposal in a manner that corrects the issues as discussed above and to submit a compliance filing within a reasonable timeframe.
Respectfully submitted,
/s/___Evan K. Dean_____________
Morgan Parke
Vice President - Associate General Counsel
Evan K. Dean
Managing Counsel
FirstEnergy Service Company
341 White Pond Drive
Akron, Ohio 44320
(330) 942-2519
edean@firstenergycorp.com
Counsel for FirstEnergy Service Company
47 16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., 263 U.S. at 524).
PDF page 18
CERTIFICATE OF SERVICE
I certify that I have served the foregoing document on each person designated on the official service list compiled by the Secretary of the Commission in this docket.
Respectfully submitted,
Evan K. Dean______________
Evan K. Dean
Managing Counsel
edean@firstenergycorp.com
Counsel for FirstEnergy Service Company
Date: September 3, 2026