ER26-3515-000 · 2026-09-03 · FirstEnergy Service Company, Ohio Edison Company and 6 others

Limited Protest and Comments of FirstEnergy Service Company et al. in response to PJM Interconnection, L.L.C.’s 08/13/2026 filing to establish Interim…

Text extracted from the eLibrary original (SHA-256 9c13eea24f1e3d9e…). Download the original from the official source.

Contents · 14 sections
  1. I. PJM is unlawfully attempting to set retail rates by proposing that new data centers that p. 3
  2. II. The IRAS Proposal includes no justification for requiring BYONC generation p. 5
  3. III. PJM is discriminating against new generation that aligns itself with a new data p. 6
  4. IV. PJM fails to align the timing of the IRAS Proposal with applicable Commission p. 7
  5. V. Various of the implementing details are beyond the scope of the Statement of p. 9
  6. A. The definition of “Large Load” should be adjusted, either to take the minimum p. 10
  7. B. The criteria for the Large Load registry must match the criteria that are to be set p. 11
  8. C. PJM should clarify that the Data Center, and not the Load-Serving Entity, is p. 12
  9. D. PJM should clarify that “Energy Resources” can be “new” Capacity Resources for p. 13
  10. E. There is no justification for dropping the IRAS rules if PJM has sufficient capacity p. 14
  11. F. There is no justification for requiring BYONC generation resources to participate p. 15
  12. G. PJM must provide additional clarification regarding the new data centers that p. 15
  13. H. IRAS obligations must be allocated to data centers that did not agree to be p. 16
  14. III. CONCLUSION p. 17

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Retail and wholesale authority · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

ER26-3515, PJM, Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability (“PJM IRAS Proposal”). 4 Statement of Principles Regarding PJM, 1st and 3rd bullets (1/16/26), available…
Read this passage Filed comments: Reliability and curtailment

I. PJM is unlawfully attempting to set retail rates by proposing that new data centers that

printed heading · Topic match: Retail and wholesale authority

The unlawful nature of PJM’s proposal is demonstrated by PJM’s implicit recognition that the jurisdictional state authority must set the amount of the final payment.14 That PJM is calling for states and LSEs to identify the other retail customers that are to fund such payments again reflects the…
Read this passage Filed comments: Retail and wholesale authority

II. The IRAS Proposal includes no justification for requiring BYONC generation

printed heading

The IRAS Proposal includes no justification for requiring BYONC generation resources to participate in RPM for 10 years, and the Commission should require PJM to drop this requirement.
Read this passage

III. PJM is discriminating against new generation that aligns itself with a new data

printed heading · Topic match: Reliability and curtailment

Section B of Schedule 8.1 of the PJM Reliability Assurance Agreement (RAA) sets forth the terms under which a certain load may “opt out” of the RPM program by demonstrating that it is eligible for the FRR program.19 An eligible LSE must demonstrate that all or part of its load falls within the…
Read this passage Filed comments: Reliability and curtailment

IV. PJM fails to align the timing of the IRAS Proposal with applicable Commission

printed heading

PJM fails to align the timing of the IRAS Proposal with applicable Commission guidance.
Read this passage

V. Various of the implementing details are beyond the scope of the Statement of

printed heading

Various of the implementing details are beyond the scope of the Statement of Principles and are unnecessary and/or inconsistent with other elements of the Commission’s developing data center policies and directives, and thus must be dropped from PJM’s eventual compliance filing.
Read this passage

A. The definition of “Large Load” should be adjusted, either to take the minimum

printed heading

As relevant here, PJM proposes to define Large Loads as an end-use customer that has a cumulative peak of 50MW or greater.26 This definition will capture new data centers.
Read this passage

B. The criteria for the Large Load registry must match the criteria that are to be set

printed heading · Topic match: Registry access

R.R., 263 U.S. at 524). 12 service.29 Importantly, PJM and the Transmission Owners are to submit a compliance filing that, among other things, provides the pro forma agreement anticipated in the Order to Show Cause.30 In the IRAS Proposal, PJM outlines the data that data centers must submit to be…
Read this passage Filed comments: Registry access

C. PJM should clarify that the Data Center, and not the Load-Serving Entity, is

printed heading

For example, the IRAS Proposal provides that LSEs must bring new capacity or be subject to load reductions.32 PJM, no doubt, intended confusion concerning this aspect of the IRAS Proposal.
Read this passage

D. PJM should clarify that “Energy Resources” can be “new” Capacity Resources for

printed heading

PJM proposes that new data centers can remove themselves – in whole or part – from the IRAS if the new data center brings new capacity.
Read this passage

E. There is no justification for dropping the IRAS rules if PJM has sufficient capacity

printed heading

PJM proposes that the IRAS rules will not apply if PJM has sufficient capacity to meet the RPM requirement for three consecutive years.36 This proposal, however, is unjust and unreasonable as it would allow data center loads that are “new” after the termination of the IRAS rules to enter with the…
Read this passage

F. There is no justification for requiring BYONC generation resources to participate

printed heading

There is no justification for requiring BYONC generation resources to participate in RPM for 10 years, and the Commission should require PJM to drop this requirement.
Read this passage

G. PJM must provide additional clarification regarding the new data centers that

printed heading · Topic match: Cost allocation

PJM must provide additional clarification regarding the new data centers that qualify for reduced IRAS due to being allocated a share of the Reliability Backstop Procurement megawatts.
Read this passage Filed comments: Cost allocation

H. IRAS obligations must be allocated to data centers that did not agree to be

printed heading · Topic match: Reliability and curtailment

PJM proposes to reallocate IRAS curtailment obligations annually.45 That is, PJM proposes to reallocate curtailment obligations annually based on the level of the capacity shortfall for a given region.
Read this passage Filed comments: Reliability and curtailment

III. CONCLUSION

printed heading

CONCLUSION FirstEnergy respectfully requests that the Commission consider the foregoing comments and protest in its consideration of PJM’s IRAS Proposal, and direct PJM to amend its proposal in a manner that corrects the issues as discussed above and to submit a compliance filing within a…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dean Managing Counsel edean@firstenergycorp.com Counsel for FirstEnergy Service Company Date: September 3, 2026