ER26-3515-000 · 2026-09-03 · Corporate Energy Buyers Association

Motion to Intervene and Protest of Corporate Energy Buyers Association urging Commission to reject PJM Interconnection, L.L.C.'s proposal to revise the…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000

MOTION TO INTERVENE AND PROTEST OF
CORPORATE ENERGY BUYERS ASSOCIATION

Pursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission’s (FERC or Commission) Rules of Practice and Procedure,1 Corporate Energy Buyers Association (CEBA) respectfully submits this motion to intervene and protest. CEBA urges the Commission to reject the proposal by PJM Interconnection, L.L.C. (PJM) to revise the Reliability Assurance Agreement Among Load Serving Entities (RAA) and the PJM Open Access Transmission Tariff (Tariff) to establish Interim Resource Adequacy Service (IRAS). In the alternative, and as detailed below, if the Commission accepts PJM’s proposal, it should: (1) condition that acceptance on a minor modification needed to fully recognize customer-sponsored Peak Shaving Adjustments as incremental new capacity within the IRAS construct; and (2) encourage PJM to work with stakeholders on reforms that unlock the full potential of Surplus Interconnection Service to bring incremental capacity to the region quickly and cost-effectively.

I. MOTION TO INTERVENE
CEBA is a business association that activates energy buyers and their partners to drive low-cost, reliable, carbon emissions-free global energy systems. Our members represent $40 trillion in market value, including energy customers of all sizes, suppliers, and service

1 18 C.F.R. §§ 385.211, 385.214.

PDF page 2

2

providers.2 CEBA members support millions of jobs, drive trillions in GDP, and anchor global supply chains. Their investments are powering U.S. leadership in artificial intelligence, manufacturing, retail, and economic growth.

The rules at issue in this docket implicate the terms and conditions of transmission service connected to the provision of retail electricity to CEBA members who are bringing, or plan to bring, new loads to the PJM region. PJM’s proposal thus directly impacts the ability of our members to procure and access the affordable, reliable energy they need to power operations as they grow and innovate in the region. For these reasons, CEBA has a substantial interest in this proceeding that cannot be adequately represented by another party, and its participation is in the public interest. Good cause exists to grant CEBA’s motion to intervene.

II. COMMENTS
CEBA supports the broader policy objectives underlying PJM’s proposal: large customers that are driving significant load growth should be encouraged to support solutions that help solve regional resource adequacy challenges. However, PJM’s proposal is fatally flawed in three ways. First, IRAS fails to promote the certainty needed for large load customers to support investment in new capacity because PJM promises a benefit—exemption from curtailment during IRAS Actions—for which it lacks authority. Second, IRAS impermissibly conditions access to transmission service based on attributes of retail customers and, in so doing, blurs the line between Federal and state jurisdiction. Third, IRAS unduly preferences Capacity Resources over investments that reduce the underlying capacity need, such as customer-sponsored Peak

2 A list of current CEBA members is accessible at: https://www.ceba.org/members/.

PDF page 3

3

Shaving Adjustments, when both approaches have the same practical effect as bringing new capacity to the region. For these reasons, the Commission should reject PJM’s proposal. In the alternative, as discussed infra §§ II.C and II.D, if the Commission chooses to accept PJM’s proposal, it should: (1) condition that acceptance on PJM making minor modifications to ensure that customer-sponsored Peak Shaving Adjustments can help a large load customer avoid taking IRAS just the same as a Capacity Resource can; and (2) urge PJM to advance reforms to Surplus Interconnection Service to, in relevant part, enable New Large Loads to procure incremental capacity at scale through this pathway.

A. IRAS FAILS TO PROMOTE THE CERTAINTY NEEDED TO SUPPORT
INVESTMENT IN NEW CAPACITY IN THE PJM REGION
PJM asserts that IRAS will incent large load customers to help underwrite the cost of new capacity in the PJM region—either through long-term bilateral contracts or through the allocation of capacity costs from the Reliability Backstop Procurement (RBP).3 CEBA agrees that large energy customers can play an important role in advancing resource development through long-term contractual commitments that help make new generation projects financeable. Indeed, our members have a well-documented track record of doing that across markets nationwide.4 However, such commitments are only viable when the customer has a clear

3 PJM Filing, Transmittal at 50.
4 CEBA and REsurety, Corporate Demand Drives Clean Energy (Sept. 2025), https://ceba.org/wp- content/uploads/2025/09/CEBA-Report-Corporate-Demand-Drives-Clean-Energy.pdf (empirical evidence shows that corporate procurement through long-term contracts plays a critical role in getting clean energy projects financed and built, including in PJM); CEBA, Deal Tracker (2025), https://ceba.org/programs/deal-tracker/ (from 2014 to 2025, CEBA members have contracted for at least 21.0 GW of new capacity in PJM. PJM is also a target market for member deals involving clean firm technologies).

PDF page 4

4

understanding of the benefits they will receive in exchange for undertaking those substantial obligations.

IRAS fails that test. Under PJM’s proposal, a large load customer could enter into decade-plus commitments to support the development of new capacity resources that satisfy the requirements necessary to avoid taking IRAS. Yet, PJM cannot ensure that those commitments will result in any defined level of curtailment protection or service reliability for that customer. As PJM itself acknowledges, those are fundamentally terms and conditions of retail service, which are not governed by PJM’s tariffs but instead fall squarely within state jurisdiction.5 More specifically, PJM issues load curtailment directives to Electric Distributors. Individual Electric Distributors then determine which retail customers, such as Large Loads, are curtailed in response to any PJM directive based on the specific conditions at the time, consistent with state laws and regulations. Under this split construct, PJM has no authority or ability to ensure that an individual New Large Load that brings its own new capacity and/or is allocated capacity through the RBP can avoid curtailment when PJM initiates an IRAS Action. That is because policies and procedures regarding curtailment of retail customers sit within each Electric Distributor’s retail tariff, which are subject to exclusive state jurisdiction. As a result, PJM’s proposal attempts to induce investment by promising a benefit that PJM itself lacks the legal authority to offer. In other words, a large load customer could secure new capacity to avoid curtailment under IRAS, have that new capacity recognized appropriately in the Large Load Registry, and yet the customer could still be curtailed during an IRAS Action

5 PJM Filing, Transmittal at 86–88, 90–92.

PDF page 5

5

because of policy choices made by state regulators with respect to curtailment priority among retail customers.

This deficiency undermines PJM’s central premise that IRAS will stimulate investment in new generation resources. Customers considering long-term commitments to support new capacity require confidence that the benefits associated with those commitments are clearly defined, enforceable, and durable over the life of the investment. Where the principal benefit remains uncertain and dependent on decisions outside PJM’s authority, customers face diminished incentives to undertake the long-term obligations necessary to finance and develop new generation resources.

If policymakers wish to encourage large customers to support the development of new generation resources through long-term contractual commitments, the foundation for such a framework should instead be established at the retail level, where curtailment rights and service obligations are determined. It is the states that each must decide the specific benefits available to customers that make qualifying investments, including the extent of any curtailment protection or service rights associated with those investments.

B. IRAS IMPROPERLY CONDITIONS ACCESS TO TRANSMISSION
SERVICE BASED ON ATTRIBUTES OF RETAIL CUSTOMERS
PJM’s proposal, if accepted, would also set troubling precedent for gatekeeping access to transmission service6 based on attributes of individual retail customers. To implement IRAS,

6 In this case, full Network Integration Transmission Service (NITS) taken by a load-serving entity acting on behalf of a large load customer.

PDF page 6

6

PJM would classify a retail customer based on its size, location, affiliation, in-service date, ramp schedule, capacity arrangements, backup generation, and contracts or service agreements. That information would be used to determine whether the customer is an Eligible New Large Load (i.e., eligible to provide IRAS) and the amount of its load that may be subject to curtailment. PJM’s assertion that it is merely directing load reductions in the aggregate by Electric Distributor zone/area7 is a misdirection from the fact that those directives are calculated based on the identities and retail service characteristics of individual customers.8 This approach risks blurring the Federal Power Act’s division between Commission-jurisdictional transmission and wholesale service and state-jurisdictional retail service.

The Supreme Court has repeatedly emphasized that the Federal Power Act preserves a meaningful jurisdictional distinction between regulation of wholesale markets and regulation of retail service. In EPSA, the Court upheld the Commission’s demand response rules because they “address[] only transactions occurring on the wholesale market” and were directed at “enhancing the wholesale, not retail, electricity market.”9 By contrast, IRAS conditions wholesale treatment on customer-specific retail characteristics, raising the question whether the proposed tariff revisions remain targeted at wholesale market regulation or instead reach into matters traditionally reserved to the states. Likewise, Hughes and Oneok caution that regulators must

7 In this pleading, “Electric Distributor zone/area” has the same meaning as PJM uses it in its IRAS filing and associated tariff revisions. PJM Filing, Transmittal at 26, n.73; PJM Filing, Attach. A, Proposed Tariff, Attach. DD- 4, § III(a).
8 PJM Filing, Transmittal at 36–44, 82.
9 FERC v. Elec. Power Supply Ass’n., 577 U.S. 260, 282, 287 (2016) (upholding Commission action because it “addresses—and addresses only—transactions occurring on the wholesale market” and is directed at “enhancing the wholesale, not retail, electricity market”).

PDF page 7

7

respect the line between federal and state spheres of authority and focus on the field at which a regulatory regime is aimed, rather than using one jurisdictional domain as a vehicle to regulate the other.10 While the Court has recognized that Federal and state jurisdiction are not

“hermetically sealed from each other,”11 overlap is permissible only where the regulation remains genuinely directed at a wholesale-market function. The more PJM’s tariffs condition wholesale treatment on customer-specific retail characteristics, the more difficult it is to characterize those rules as merely incidental to wholesale regulation.

Simply stated, because curtailment of retail customers is not a practice affecting
wholesale rates, the Commission is likely barred under this precedent from approving tariffs that attempt to regulate which retail customers are curtailed. Commission acceptance of PJM’s proposal would thus introduce unnecessary legal risk at precisely the wrong moment given the resource adequacy challenges facing the region. To the extent that the Commission supports the policy objectives underlying IRAS, those instead could be addressed in a more legally durable manner by calling on the PJM states to make the necessary reforms to retail tariffs.12 PJM could then work to recognize those retail arrangements in its own tariffs.

10 See Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 165 (2016) (reaffirming that the Federal Power Act leaves retail regulation to the states and prohibiting state action that fails to “give effect” to federally regulated wholesale rates); Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385–86 (2015) (examining the “target at which [a] law aims” and distinguishing measures aimed at matters within state jurisdiction from those aimed directly at the federal field). 11 EPSA, 577 U.S. at 276–77 (quoting FERC v. Mississippi, 456 U.S. 742, 759 (1982)).
12 For example, the Virginia State Corporation Commission (VA SCC) is already working in partnership with the Data Center Coalition (DCC) to develop model retail tariff structures and regulatory frameworks that state regulators across PJM could consider as they craft large load tariffs that target similar policy objectives as those underlying PJM’s proposal. VA SCC and DCC, Letter to the PJM Board (June 30, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-written-comments---va-scc-and-data-center- coalition.pdf.

PDF page 8

8

C. IRAS UNDULY PREFERENCES CAPACITY RESOURCES OVER
INVESTMENTS THAT REDUCE THE UNDERLYING CAPACITY NEED
CEBA supports PJM’s objective of ensuring that significant new load growth does not exacerbate existing resource adequacy challenges. But a framework intended to encourage large customers to support solutions should not unnecessarily dictate the form those solutions must take. Customers should be able to address the incremental resource adequacy needs associated with their growth through the most efficient available means—whether by supporting new generation, reducing the underlying capacity requirement through qualifying demand-side investments, or making efficient use of existing interconnection capability. Under IRAS, a New Large Load can seek to reduce its curtailment exposure by securing new Capacity Resources that qualify as Bring Your Own New Capacity (BYONC) or through an allocation of capacity procured through the RBP. But PJM provides no comparable credit for investments that directly reduce the amount of capacity the system needs.

That distinction is difficult to justify within PJM’s existing framework. PJM’s rules expressly recognize qualifying Peak Shaving Adjustments as reductions to forecast peak demand and, therefore, to the capacity requirement PJM must satisfy.13 Indeed, PJM recognizes this resource adequacy benefit in its RBP proposal, where qualifying Peak Shaving Adjustments reduce the capacity need to be addressed through the centralized procurement.14 Both incremental Capacity Resources and incremental qualifying Peak Shaving Adjustments can

13 PJM, Intra-PJM Tariffs, Open Access Transmission Tariff, Attach. DD-2 (1.0.0); PJM, Manual 19, Load Forecasting and Analysis, § 3.2, https://www.pjm.com/-/media/DotCom/documents/manuals/m19.pdf.
14 PJM Filing, Docket No. ER26-3380-000, Transmittal at 45–46; PJM Filing, Docket No. ER26-3380-000, Attach. A, Proposed Tariff, Attach. DD, § 18.1(d).

PDF page 9

9

address the resource adequacy need associated with load growth—one by increasing available supply and the other by reducing the capacity requirement.

IRAS, however, does not provide equivalent recognition for these two means of addressing resource adequacy. A New Large Load may be able to make a long-term contractual commitment to finance distributed storage or other demand-side capability across an Electric Distributor zone/area. If those investments support a qualifying Peak Shaving Adjustment and produce an incremental, measurable reduction in PJM’s peak forecast, they reduce the amount of capacity that PJM must procure. Yet, IRAS provides no mechanism for the sponsoring New Large Load to receive recognition for that contribution comparable to the credit available for BYONC. More precisely, PJM’s calculation of Eligible New Large Load Amount—which determines the IRAS curtailment exposure of an individual New Large Load—does not explicitly account for Peak Shaving Adjustments associated with that load.15 The proposed Large Load Registry does not cure this problem. PJM proposes to identify Peak Shaving Adjustments associated with the New Large Load itself, which may permit PJM to account for peak shaving occurring at the individual customer’s site.16 But even assuming such on-site peak shaving is appropriately reflected in the New Large Load’s Registered Peak Load, the proposal provides no mechanism for a New Large Load to sponsor incremental peak-shaving capability elsewhere in the relevant Electric Distributor zone/area and receive credit for the resulting reduction in PJM’s capacity need. The distinction matters because some of the most

15 PJM Filing, Attach. A, Proposed Tariff, Attach. DD-4, § V(b).
16 PJM Filing, Transmittal at 37; PJM Filing, Attach. A, Proposed RAA, Sched. 11, § B.1(a).

PDF page 10

10

scalable near-term demand-size investments may occur across a broader portfolio of customers or facilities rather than behind the meter of the sponsoring New Large Load.

PJM has offered no explanation for this limitation, despite this limitation appearing to be an intentional design choice by PJM.17 If a New Large Load finances new generation that qualifies as BYONC, IRAS recognizes that investment in determining the load’s curtailment exposure. But if the same customer finances incremental distributed storage or other qualifying peak-shaving capability that reduces PJM’s forecast capacity requirement, IRAS provides no corresponding recognition. That distinction turns on the form of investment rather than its demonstrated contribution to resource adequacy.

If the Commission chooses to accept the IRAS proposal, at a minimum the Commission
should require PJM to amend its proposal to provide a clear tariff-based mechanism for New Large Loads to receive recognition for incremental, customer-sponsored Peak Shaving

Adjustments that reduce PJM’s capacity requirement, including qualifying investments located elsewhere within the relevant Electric Distributor zone/area. Such a directive would be precisely the kind of permissible, minor modification that the NRG court contemplated.18 Here, directing PJM to recognize customer-sponsored Peak Shaving Adjustments in the calculation of a New Large Load’s Eligible New Large Load Amount would not alter the fundamental IRAS

17 PJM explains in its RBP filing that “even if the Electric Distributor zone/area qualifies for and receives an opt-out from the RBP, the load in that zone/area may be subject to load reduction under the forthcoming proposal to implement an IRAS.” PJM, Filing, Docket No. ER26-3380-000, at 46 (filed July 31, 2026). CEBA member Equinix highlighted that this disparate treatment between the RBP and IRAS risks undermining the use case of customer- sponsored Peak Shaving Adjustments. Equinix, Comments, Docket No. ER26-3380-000, at 12 (filed Aug. 21, 2026).
18 NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 115–16 (D.C. Cir. 2017) (recognizing that the Commission may require modifications to a utility’s FPA section 205 filing where the utility consents, while cautioning only against modifications that result in an “entirely different rate design” or “eviscerate[] the terms of the bargain” embodied in the original proposal).

PDF page 11

11

framework. Rather, it would simply permit New Large Loads to address the resource adequacy consequences of their growth through either incremental supply or an incremental reduction in the capacity requirement. This clarity in the tariff is necessary to give prospective New Large Loads the confidence they need to make investments in Peak Shaving Adjustments with the understanding those demand-side reductions serve to reduce the sponsoring large load customer’s IRAS curtailment risk.

Absent this change, the Commission should reject PJM’s proposal because it is unjust and unreasonable insofar as PJM recognizes the capacity benefit of customer-sponsored Peak Shaving Adjustments at the system level (through reductions to the RBP Initial Procurement Target) while providing no apparent pathway for the customer whose investment creates incremental peak-shaving capability to receive corresponding recognition. When compared with PJM’s treatment of BYONC and capacity procured through the RBP, there is a clear undue preference for Capacity Resources over investments that reduce the underlying need for new capacity.

D. PJM APPROPRIATELY RECOGNIZES INCREMENTAL CAPACITY
UNLOCKED THROUGH SURPLUS INTERCONNECTION SERVICE,
BUT FURTHER REFORMS ARE NEEDED TO MAKE THIS PATHWAY
COMMERCIALLY VIABLE
CEBA supports PJM’s recognition that capacity enabled through Surplus Interconnection Service (SIS) may qualify as BYONC.19 SIS has the potential to facilitate incremental capacity

19 PJM Filing, Transmittal at 53; PJM Filing, Attach. A, Proposed Tariff, Attach. DD-4, § VI(b)(i)(3).

PDF page 12

12

additions, particularly storage, quickly and cost-effectively by allowing new resources to make more efficient use of existing interconnection capability and, in so doing, avoid the need for network upgrades. In practice, however, existing PJM rules can limit the ability of SIS to fulfill that potential. Among other things, these rules prevent new surplus resources from participating independently as a co-located Capacity Resource, despite this being the most commercially viable pathway for many developers and their offtakers to add a new resource behind an existing point of interconnection. The only available alternative—pursuing a hybrid configuration—is unworkable in most cases due to the complexities of unwinding existing ownership, financing, and offtake arrangements.20

These barriers are particularly relevant here because PJM is expressly relying on SIS as one pathway through which New Large Loads can secure new capacity necessary to qualify for BYONC. One relatively straightforward rule change would be to allow an existing resource with underutilized Capacity Interconnection Rights (CIRs) to allocate a portion of those rights to a new resource interconnecting through SIS. Doing so would maximize opportunities to repurpose underutilized interconnection capability to add incremental capacity resources in the near-term, all while preserving appropriate reliability, operational, and market-power safeguards. CEBA is not asking the Commission to resolve these issues in this proceeding, but instead respectfully requests that it encourage PJM to pursue these reforms diligently and

20 Several parties have highlighted these limitations in this docket and in the RBP docket. Google LLC, Comments, Docket No. ER26-3380-000, at 10–11 (filed Aug. 21, 2026); Solar Energy Industries Association, Comments, Docket No. ER26-3515-000 at 4–6 (filed Sept. 3, 2026); Solar Energy Industries Association, Comments, Docket No. ER26-3380-000, at 9–12 (filed Aug. 21, 2026); Advanced Energy United, Comments, Docket No. ER26-3380- 000, at 11–15 (filed Aug. 21, 2026).

PDF page 13

13

collaboratively with stakeholders.21 Particularly if the Commission accepts PJM’s proposal, doing so would help ensure that PJM’s recognition of SIS under the BYONC framework translates into a meaningful and commercially viable pathway for bringing incremental capacity online. If these barriers cannot be addressed expeditiously through the PJM stakeholder process, further Commission attention may be warranted to ensure that existing interconnection capability can be used efficiently to support needed incremental capacity.

III. CONCLUSION
For the foregoing reasons, CEBA respectfully requests that the Commission reject PJM’s IRAS proposal as unjust, unreasonable, and unduly preferential. CEBA members stand ready to make the long-term commitments necessary to support investment in new capacity in the PJM region. But those investments require a regulatory framework that provides investor certainty, reduces legal risk, and preserves the ability of large load customers to procure new capacity through arrangements that best align with their commercial needs. If the Commission nevertheless accepts PJM’s proposal, it should: (1) condition acceptance on the modifications described above, including revisions necessary to ensure that customer-sponsored Peak Shaving Adjustments receive appropriate recognition within the IRAS framework; and (2) encourage

21 PJM has introduced a Problem/Opportunity Statement and Issue Charge that seeks to address some of these practical barriers to using SIS to add incremental capacity. The proposed scope is a helpful first step but may be insufficient. CEBA intends to support stakeholder discussions on these issues. PJM, Problem/Opportunity Statement: Hybrid Resources Market Model Selection (Aug. 5, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-1---hybrid-resources- market-model-selection---problem-statement.pdf; PJM, Issue Charge: Hybrid Resources Market Model Selection (Aug. 5, 2026), https://www.pjm.com/-/media/DotCom/committees- groups/committees/mic/2026/20260805/20260805-item-04-2---hybrid-resources-market-model-selection---issue- charge.pdf.

PDF page 14

14

PJM to work with stakeholders on reforms that unlock the full potential of SIS to bring incremental capacity to the region quickly and cost-effectively.

PDF page 15

15

Respectfully submitted,

/s/ John Miller___________________
John Miller
Director, Transmission Policy
CEBA
1501 M Street, N.W., Suite 900
Washington, D.C. 20005
(240) 630-2201
jmiller@ceba.org

September 3, 2026

PDF page 16

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.

Dated at Washington, D.C., this 3rd day of September 2026.
/s/ John Miller___________________
John Miller
Director, Transmission Policy
CEBA