ER26-3515-000 · 2026-09-03 · Corporate Energy Buyers Association

Motion to Intervene and Protest of Corporate Energy Buyers Association urging Commission to reject PJM Interconnection, L.L.C.'s proposal to revise the…

Text extracted from the eLibrary original (SHA-256 58ba0ae4c63bcdfe…). Download the original from the official source.

Contents · 7 sections
  1. I. MOTION TO INTERVENE p. 1
  2. II. COMMENTS p. 2
  3. A. IRAS FAILS TO PROMOTE THE CERTAINTY NEEDED TO SUPPORT p. 3
  4. B. IRAS IMPROPERLY CONDITIONS ACCESS TO TRANSMISSION p. 5
  5. C. IRAS UNDULY PREFERENCES CAPACITY RESOURCES OVER p. 8
  6. D. PJM APPROPRIATELY RECOGNIZES INCREMENTAL CAPACITY p. 11
  7. III. CONCLUSION p. 13

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Retail and wholesale authority · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

CEBA urges the Commission to reject the proposal by PJM Interconnection, L.L.C. (PJM) to revise the Reliability Assurance Agreement Among Load Serving Entities (RAA) and the PJM Open Access Transmission Tariff (Tariff) to establish Interim Resource Adequacy Service (IRAS).
Read this passage Filed comments: Reliability and curtailment

I. MOTION TO INTERVENE

printed heading

MOTION TO INTERVENE CEBA is a business association that activates energy buyers and their partners to drive low-cost, reliable, carbon emissions-free global energy systems.
Read this passage

II. COMMENTS

printed heading · Topic match: Reliability and curtailment

COMMENTS CEBA supports the broader policy objectives underlying PJM’s proposal: large customers that are driving significant load growth should be encouraged to support solutions that help solve regional resource adequacy challenges.
Read this passage Filed comments: Reliability and curtailment

A. IRAS FAILS TO PROMOTE THE CERTAINTY NEEDED TO SUPPORT

printed heading · Topic match: Reliability and curtailment

It is the states that each must decide the specific benefits available to customers that make qualifying investments, including the extent of any curtailment protection or service rights associated with those investments.
Read this passage Filed comments: Reliability and curtailment

B. IRAS IMPROPERLY CONDITIONS ACCESS TO TRANSMISSION

printed heading · Topic match: Retail and wholesale authority

Likewise, Hughes and Oneok caution that regulators must 7 In this pleading, “Electric Distributor zone/area” has the same meaning as PJM uses it in its IRAS filing and associated tariff revisions.
Read this passage Filed comments: Retail and wholesale authority

C. IRAS UNDULY PREFERENCES CAPACITY RESOURCES OVER

printed heading · Topic match: Reliability and curtailment

PJM’s rules expressly recognize qualifying Peak Shaving Adjustments as reductions to forecast peak demand and, therefore, to the capacity requirement PJM must satisfy.13 Indeed, PJM recognizes this resource adequacy benefit in its RBP proposal, where qualifying Peak Shaving Adjustments reduce the…
Read this passage Filed comments: Reliability and curtailment

D. PJM APPROPRIATELY RECOGNIZES INCREMENTAL CAPACITY

printed heading · Topic match: Connecting load and generation

CEBA is not asking the Commission to resolve these issues in this proceeding, but instead respectfully requests that it encourage PJM to pursue these reforms diligently and 20 Several parties have highlighted these limitations in this docket and in the RBP docket.
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, CEBA respectfully requests that the Commission reject PJM’s IRAS proposal as unjust, unreasonable, and unduly preferential.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 3rd day of September 2026. /s/ John Miller___________________ John Miller Director, Transmission Policy CEBA 1501 M Street, N.W., Suite 900 Washington, D.C. 20005 (240) 630-2201 jmiller@ceba.org