ER26-3515-000 · 2026-09-03 · North Carolina Electric Membership Corporation

Limited Comments of North Carolina Electric Membership Corporation on PJM Interconnection, L.L.C.’s filing proposing revisions to the Open Access…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-3515-000
LIMITED COMMENTS OF NORTH CAROLINA ELECTRIC
MEMBERSHIP CORPORATION
Pursuant to Rule 211 of the Commission’s Rules of Practice and Procedure1 and the Commission’s Combined Notice of Filings #2 of August 13, 2026, North Carolina Electric Membership Corporation (“NCEMC”)2 submits the following comments on the filing by PJM Interconnection, L.L.C. (“PJM”) proposing revisions to its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish Interim Resource Adequacy Service (“IRAS”).3 PJM states that it will implement IRAS only when there are insufficient resources to reliably meet demand in real-time operations, and, when implanted, IRAS will enable PJM “to prioritize load reductions in zones/areas where New Large Loads have not brought their own new capacity or had their capacity needs covered through the Reliability Backstop Procurement (‘RBP’).”4

1 18 C.F.R. § 385.211 (2025).
2 NCEMC filed a (doc-less) motion to intervene in this proceeding on August 17, 2026, which, unopposed within 15 days, makes NCEMC a party to this proceeding by rule. See 18 C.F.R. § 385.214(c)(1).
3 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, “Proposal of PJM Interconnection, L.L.C. To Establish  Interim Resource Adequacy Service and a Large Load Registry To Address System Reliability” (filed Aug. 13, 2026).
4 PJM IRAS Transmittal Letter at 1-2. See PJM Interconnection, L.L.C., Docket No. ER26-3380- 000, “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads” (filed July 31, 2026).

PDF page 2

2
Thus, PJM is proposing IRAS as an operational tool to address the reality that New Large Loads, which are developing more quickly than generation and transmission can be built to provide them firm service, may want to connect to the grid in a provisional manner on an interim basis. Practically speaking, PJM seeks to create an optional path forward for New Large Loads that choose to be curtailable in the interim in exchange for quicker interconnection to the grid. As PJM notes, “the IRAS framework is not motivated by any desire to single out New Large Loads for reduction because of their size or vintage, but rather for the valid and legitimate reason that New Large Loads have led to periods of insufficient resource adequacy and should, justifiably, play a significant role in the remedy.”5 The IRAS framework is intended to allow PJM to identify the megawatt (MW) amount of New Large Load that exceeds new generation to ensure that in emergency conditions the New Large Load can be shut off before existing load is impacted. In order to avoid perceived jurisdictional limitations, PJM proposes that it would issue an IRAS Action directive to the Electric Distributor, who will then, in coordination with the relevant Load-Serving Entities (LSEs) in the zone/area and the appropriate state and/or Relevant Electric Retail Regulatory Authority (“RERRA”), determine which loads will be shut off.

I. NCEMC
NCEMC is a generation and transmission cooperative responsible for the full or partial power supply requirements of its 25 members throughout the state of North Carolina. Those 25 distribution cooperatives, in turn, supply electricity to approximately one million homes, farms, and businesses in which more than 2.5 million North

5 PJM IRAS Transmittal Letter at 100.

PDF page 3

3
Carolinians live and work. NCEMC distribution cooperative loads are located throughout the service areas of three investor-owned public utilities: Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, both subsidiaries of Duke Energy Corporation, and Virginia Electric and Power Company, doing business as Dominion Energy Virginia in Virginia and as Dominion Energy North Carolina in North Carolina (hereinafter, Dominion).

NCEMC is a member of PJM, which operates transmission facilities owned by Dominion and other electric utilities. NCEMC purchases transmission services from PJM over Dominion’s transmission facilities to serve the loads of its six member cooperatives that distribute power at retail in the Dominion transmission zone of the PJM region. NCEMC is a member of PJM’s Electric Distributor sector, a load-serving entity, and a participant in PJM’s energy, ancillary services, capacity, and financial transmission rights markets.

II. The Commission should direct PJM to clarify that an IRAS Action
directive applies only to New Large Loads provisionally interconnected to the grid and only to the extent of a provisionally interconnected New Large Load’s load at the time of the IRAS Action directive.

Buckeye Power, Inc. (“Buckeye”), East Kentucky Power Cooperative, Inc. (“EKPC”), and Southern Maryland Electric Cooperative, Inc. (“SMECO”) are submitting filings responsive to PJM’s IRAS filing on even date herewith. NCEMC generally supports the need for greater clarity highlighted in the Buckeye, EKPC, and SMECO filings. NCEMC specifically supports a concern articulated by Buckeye in its filing. Buckeye, in its Comments filed contemporaneously with these NCEMC Comments, states as follows:

PJM’s filing is largely silent as to exactly how it will
determine the MW amount when issuing an IRAS Action. PJM

PDF page 4

4
states that the “IRAS reduction MW quantity … will be based on the IRAS quantity PJM determined for the Delivery Year.” PJM’s filing describes how it determines the yearly IRAS quantity based on Eligible New Large Load Amounts, which will be less than or equal to the Electric Distributor’s Eligible New Large Load Amount for that year. But PJM’s Filing does not explain how PJM will determine the IRAS quantity it directs an Electric Distributor to cause to be reduced in a given emergency event in real-time. …

Buckeye is concerned that directing the Electric Distributor to reduce a specific amount of MW quantity based on registered peak load of New Large Loads determined for the Delivery Year will not match the actual amount of load being used by the New Large Loads in real-time. If PJM were allowed to direct IRAS quantities in real-time that exceed the real-time demand of New Large Loads, this mismatch between the peak load reported by the New Large Load in the registry and the amount of load the Large Load is using in real-time could require the Electric Distributor to reduce existing customers, including residential loads, to make up the difference.

…
Buckeye asks that PJM clarify how the MW amounts Electric Distributors will be asked to curtail will be determined in a real- time IRAS Action, and whether this determination will consider the actual demand of the New Large Loads in real-time to avoid requiring impacts to existing customer load described above. Specifically, PJM should ensure that the amount of MWs the Electric Distributor is required to drop in response to an IRAS Action will not exceed the amount of MWs being used by the New Large Loads in real-time.  This clarification will still allow the Electric Distributors, working with its applicable state or RERRA, to determine how the MW drop will be assigned to individual loads, while at the same time ensuring that Electric Distributors are not put in the position of being forced to drop existing load (the action of last resort to maintain grid integrity) to comply with an IRAS Action.6

NCEMC shares Buckeye’s concern. An IRAS Action directive should in no way require any existing load that is not provisionally interconnected to be curtailed. Put

6 Limited Comments of Buckeye Power, Inc., Docket No. ER26-3515-000 at 4, 5, 6–7 (filed Sept. 3, 2026) (emphasis original; footnotes omitted).

PDF page 5

5
another way, under IRAS, it should be unambiguous that only a New Large Load that choose to be curtailable in the interim in exchange for quicker interconnection to the grid is subject to curtailment under an IRAS Action directive.

To the extent PJM does not make this important clarification on its own, the Commission should issue a deficiency letter directing PJM to make this clarification or explain how the existing proposal is just, reasonable, and not unduly discriminatory.

III. Conclusion
For the reasons stated above, the Commission should take these comments into consideration and direct PJM to make the requested clarification.

September 3, 2026
Respectfully submitted,
/s/ Michael D. Youth
Charles Bayless
Senior Vice President and General
Counsel
Michael D. Youth
Vice President and Deputy General Counsel
North Carolina Electric Membership
Corporation
3400 Sumner Blvd.
Raleigh, NC 27616
Charlie.Bayless@ncemcs.com
Michael.Youth@ncemcs.com
Sean T. Beeny
Randolph L. Elliott
F. Alvin Taylor
McCarter & English, LLP
1301 K Street NW, Suite 1000 West
Washington, D.C. 20005
(202) 753-3400
sbeeny@mccarter.com
relliott@mccarter.com
ataylor@mccarter.com
Attorneys for North Carolina Electric
Membership Corporation

PDF page 6

6
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C. this 3rd day of September 2026.

/s/ Randolph Elliott
Randolph L. Elliott
McCarter & English, LLP
1301 K Street NW, Suite 1000 West
Washington, D.C. 20005
(202) 753-3428