ER26-3515-000 · 2026-09-03 · North Carolina Electric Membership Corporation

Limited Comments of North Carolina Electric Membership Corporation on PJM Interconnection, L.L.C.’s filing proposing revisions to the Open Access…

Text extracted from the eLibrary original (SHA-256 0be499787b311848…). Download the original from the official source.

Contents · 4 sections
  1. I. NCEMC p. 2
  2. II. The Commission should direct PJM to clarify that an IRAS Action p. 3
  3. III. Conclusion p. 5
  4. F. Alvin Taylor p. 5

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

In order to avoid perceived jurisdictional limitations, PJM proposes that it would issue an IRAS Action directive to the Electric Distributor, who will then, in coordination with the relevant Load-Serving Entities (LSEs) in the zone/area and the appropriate state and/or Relevant Electric Retail…
Read this passage Filed comments: Reliability and curtailment

I. NCEMC

printed heading

NCEMC NCEMC is a generation and transmission cooperative responsible for the full or partial power supply requirements of its 25 members throughout the state of North Carolina.
Read this passage

II. The Commission should direct PJM to clarify that an IRAS Action

printed heading · Topic match: Registry access

If PJM were allowed to direct IRAS quantities in real-time that exceed the real-time demand of New Large Loads, this mismatch between the peak load reported by the New Large Load in the registry and the amount of load the Large Load is using in real-time could require the Electric Distributor to…
Read this passage Filed comments: Registry access

III. Conclusion

printed heading

Conclusion For the reasons stated above, the Commission should take these comments into consideration and direct PJM to make the requested clarification.
Read this passage

F. Alvin Taylor

printed heading

Alvin Taylor McCarter & English, LLP 1301 K Street NW, Suite 1000 West Washington, D.C. 20005 (202) 753-3400 sbeeny@mccarter.com relliott@mccarter.com ataylor@mccarter.com Attorneys for North Carolina Electric Membership Corporation 6
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 3rd day of September 2026. /s/ Randolph Elliott Randolph L.