ER26-3515-000 · 2026-09-03 · Vistra Corp.

Protest of Vistra Corp. regarding PJM Interconnection, L.L.C.’s proposed Interim Resource Adequacy Service filing

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
)
)

Docket No. ER26-3515-000

PROTEST OF VISTRA CORP.

Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Vistra Corp. (“Vistra”) submits this protest regarding PJM Interconnection, L.L.C.’s (“PJM”) proposed Interim Resource Adequacy Service (“IRAS”) proposal.  Although Vistra recognizes PJM’s concerns regarding the resource adequacy challenges facing the region, those concerns demand durable solutions that provide investors with the certainty they need to maintain and expand PJM’s generation fleet.2  That is not IRAS. IRAS is ill-conceived, inconsistent with the Federal Power Act (“FPA”), and will stymie investment in PJM.  With IRAS, PJM ignores the jurisdictional boundaries that Congress carefully crafted and proposes rules that are unjust, unreasonable, and unduly discriminatory—each of which is a sufficient basis for the Commission to reject the proposal and for a court to overturn an order accepting IRAS on appeal.  In rejecting IRAS, the Commission should order PJM to develop a durable solution that is faithful to sound market fundamentals to ensure that the region has the capacity resources needed to meet load growth.

1 18 C.F.R. § 385.211.
2 For instance, the Commission’s proposed measures to incentivize load flexibility could provide the types of durable solutions that bolster investor confidence, rather than undermine it.  See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at PP 85-87 (2026).

PDF page 2

-2-
Accepting IRAS would undermine the investor confidence that is critical to resource development because it would upset contracts negotiated in reliance on the rules in effect at the time.  That is a particularly concerning result now, in PJM, where the absence of predictable market rules in recent years has significantly undermined investment in the generation fleet needed to maintain resource adequacy.  If the Commission now casts doubt on the extent to which market participants, including both generation and load, can rely on already-executed or in-process bilateral contracts, it will only further impair PJM’s ability to meet its resource adequacy requirements at a time when the region can least afford it.3  To avoid that outcome, the Commission should reject IRAS altogether or clarify that new large loads that enter into contracts with existing capacity resources before the effective date of the IRAS reforms will not be subject to IRAS curtailments.

I. PROTEST
IRAS is both unlawful and counterproductive for the PJM region and the nation.  It will hinder investment in generation resources and data infrastructure unless and until the Commission rejects the proposal.  As explained below, IRAS runs afoul of the FPA in three distinct ways. First, as a threshold matter, IRAS oversteps the FPA’s jurisdictional boundaries because it targets retail customers that are outside of the Commission’s jurisdiction.  Under IRAS, PJM will make wholesale curtailment decisions based entirely on whether an Electric Distribution Company (“EDC”) has certain specific retail customers (i.e., new large loads that do utilize the Bring Your

3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 5 (“This proceeding is not intended to disrupt existing commercial arrangements[.]”); FERC, Chairman Laura Swett’s Comments at PJM’s Annual Meeting in Baltimore, MD (May 12, 2026), https://www.ferc.gov/news-events/news/chairman-laura-swetts-comments-pjms-annual- meeting-baltimore-md-0 (“[W]hatever happens, we cannot disrupt finalized commercial agreements.  At FERC, I have no appetite to compromise investor confidence when those investors are driving the buildout of the generation that PJM desperately needs.  However you get there PJM, you need to figure it out.  Fast.”).

PDF page 3

-3-
Own New Capacity (“BYONC”) pathway) in its footprint.  That cuts directly against Congress’s directive that retail service be regulated by the states, not by FERC.

Second, IRAS is unduly discriminatory or preferential in multiple ways.4  Most glaringly,
IRAS and BYONC unduly discriminate against existing capacity resources.  PJM proposes that
new large loads that contract with new capacity resources are not supposed to be exposed to the IRAS curtailment regime while new large loads that contract with otherwise identical existing capacity resources would be.  This is textbook undue discrimination, as one MW of capacity from a new resource provides the exact same resource adequacy benefits as one MW of capacity from an otherwise identical existing resource.5  After all, electrons don’t differ based on the age of the generation facility that produced them.6  To the extent proponents of IRAS assert that these MWs are not identical because PJM needs one new MW of capacity for every new MW of load to solve its resource adequacy concerns, they are wrong for two reasons.  For one, they have not actually demonstrated that the system cannot handle near-term load growth—and there are good reasons to

4 See, e.g., Ala. Power Co. v. FERC, 993 F.2d 1557, 1571 (D.C. Cir. 1993) (“[T]he party filing a rate adjustment with the Commission under § 205 bears the burden of proving the adjustment is lawful.”); ISO New England Inc., 136 FERC ¶ 61,221, at P 20 (2011) (“Where . . . a filing is made under section 205 of the FPA, the burden of proof is on the filing party to show that its proposal is just and reasonable.” (footnote omitted)).
5 PJM Interconnection, L.L.C., 128 FERC ¶ 61,157, at P 102 (2009) (“Both new entry and retention of existing efficient capacity are necessary to ensure reliability and both should receive the same price so that the price signals are not skewed in favor of new entry.”); see also Calpine Corp., 171 FERC ¶ 61,034 (2020) (Glick, Comm’r, Dissenting at P 84) (“[A] megawatt of capacity provided by a new resource is every bit as effective as a megawatt provided by an existing one.”).
6 To underscore this point, consider how generators impact the system as a matter of physics.  Electric energy is “transmitted through the propagation of an electromagnetic wave;” electrons themselves do not “flow” but rather “oscillate in place.”  North Dakota v. Heydinger, 825 F.3d 912, 924 (8th Cir. 2016) (Murphy, J., concurring in part and concurring in the judgment); see also Brief of Amicus Curiae of Electrical Engineers et al., New York v. FERC, 535 U.S. 1 (2002) (No. 00-568), 2001 WL 605124, at *7-8 (“The real energy transmission is accomplished through the propagation of an electromagnetic wave. Each electron is induced, under the effect of the electromagnetic wave generated at the power plant, to repel the electron in the next atom. Assume that energy is being transmitted left to right in a wire. Each electron repels its right-hand neighbor, because they are both negatively charged and similar charges repel each other. This ripple effect can be envisioned as each electron elbowing its neighbor toward the next right-hand neighboring electron, which in turn elbows the next electron, and so on down the power line. The electrons move very little, merely oscillating in place, but the energy – the electromagnetic wave – moves at the speed of light. The energized electrons making the lightbulb in a house glow are not the same electrons that were induced to oscillate in the generator at the generating plant.” (footnote omitted)).

PDF page 4

-4-
think that the system can, in fact, handle that load growth.7  For the other, they misdiagnose the problem: current resource adequacy concerns are caused by Load Serving Entities failing to procure enough capacity to cover the entirety of their load obligation, not the contracting decisions of individual retail customers.  And they ignore the fact that IRAS represents an unprecedented sea change in how customers’ service requests are viewed from a regulatory perspective.  Vistra is aware of no power market in history that has imposed a policy that says new customers are not eligible for the same service as existing customers unless they procure their own generation resources.8

Third, IRAS has not been shown to be just and reasonable in several more respects.  For
example, there is no assurance that new large loads will receive the purported benefit of BYONC because it is up to states and EDCs to decide curtailment orders and priorities.9  Thus, IRAS would impose a burden (BYONC) without any assurance that those bearing that burden would receive the purported benefits that are supposed to flow from it (firm service).  For that reason, IRAS is an illusory construct that is fundamentally unjust and unreasonable.  Further, IRAS violates cost causation principles, and is therefore unjust and unreasonable, because it allocates capacity costs to new large loads that do not bring new capacity even though it does not procure capacity to serve those loads.  It is also unjust and unreasonable because new large loads that do not bring new

7 Ryan Hledik, Long Lam & Kate Peters, The Untapped Grid: How a Better Utilized Power System Can Improve Energy Affordability, The Brattle Grp., (Mar. 2026), https://www.brattle.com/wp-content/uploads/2026/03/The- Untapped-Grid-Mar-2026.pdf.
8 Vistra believes that such a policy, in addition to being unlawful, would be counterproductive for the PJM system because it will incentivize customers to pursue fully islanded systems to avoid system costs, thereby reducing the amount of load to which those costs can be spread.
9 PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515-000, at 92 (filed Aug. 13, 2026) (“Transmittal”) (“[I]n recognition of the jurisdictional divide between PJM and the states and/or RERRAs, PJM will not direct reductions to specific New Large Loads pursuant to IRAS.  Rather, PJM is leaving it to Electric Distributors, in coordination with the appropriate states and/or RERRAs, LSEs, and LSE customers to determine which loads should ultimately reduce subject to IRAS.”).

PDF page 5

-5-
capacity would be subject to curtailment before demand response resources despite the fact that demand response resources volunteer to be curtailed and are compensated as a result.  Finally, IRAS is unjust and unreasonable because, by removing from the Variable Resource Reliability (“VRR”) Curve new large loads that do not bring new capacity, it would undermine capacity market fundamentals, thereby further eroding resource adequacy in PJM.

A. IRAS Violates the FPA’s Division of Jurisdiction
The Commission is a creature of statute and can act only within the scope of authority conveyed by Congress.10  IRAS exceeds the scope of the authority conveyed to the Commission under the FPA because the entire scheme is based on and triggered by the characteristics and behavior of retail customers (i.e., new large loads), which are within the states’ exclusive sphere to regulate.  In this way, IRAS explicitly “aims” at or “target[s]” specific retail customers, in violation of the FPA.11

The FPA gives the states exclusive authority over retail sales.12  This means that the Commission is prohibited from specifying the rates, terms, and conditions of retail sales “no matter how direct, or dramatic, [their] impact on wholesale rates” as that “is a job for the States alone.”13 Nevertheless, “[w]holesale and retail markets in electricity . . . are not hermetically sealed from each other,” so to determine whether an action that affects both wholesale and retail spheres oversteps the FPA’s bright jurisdictional line, the Supreme Court has considered “the target at

10 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir. 2002).
11 FERC v. Elect. Power Supply Ass’n, 577 U.S. 260, 282 (“EPSA”) (quoting Oneok, Inc. v. Learjet Inc., 575 U.S. 373, 385 (2015) (“Oneok”))).
12 16 U.S.C. § 824(b); Niagara Mohawk Power Corp. v. FERC, 452 F.3d 822, 824 (D.C. Cir. 2006) (“Under section 201(b)(1) of the Federal Power Act, 16 U.S.C. § 824(b)(1), FERC has jurisdiction over both the interstate transmission of electricity and the sale of electricity at wholesale in interstate commerce. States retain jurisdiction over retail sales of electricity and over local distribution facilities.”).
13 EPSA, 577 U.S. at 279-80.

PDF page 6

-6-
which [a] law aims.”14  FERC cannot approve a proposal where retail customers are the “target at which [the proposal] aims.”15

That is IRAS to a T.  Under IRAS, PJM decides which wholesale transmission customers
are subject to curtailment based on the characteristics of individual retail customers—that is the central feature of IRAS.16  Specifically, PJM will curtail EDCs with new large loads (i.e., retail customers) in their footprints that do not bring sufficient new capacity to offset their demand.17 That makes IRAS all about the retail customer: when it comes online (before or after June 1, 2027), its size (more or less than 50 MW), and whether it brings offsetting new capacity (i.e., BYONC).18 Under IRAS, retail customers and their characteristics are far more than “the mechanism through which [IRAS] operates,”19 they are lynchpin of the entire scheme and the determining factor for whether IRAS applies.  Moreover, PJM is clear, again and again, that the purpose of IRAS is to shape the behavior of retail customers and to “solve” the resource adequacy challenge that PJM posits, a task that should be reserved for the PJM capacity market.20

14 Id. at 282 (quoting Oneok, 575 U.S. at 385) (alterations in original).
15 Oneok, 575 U.S. at 385.
16 See, e.g., Transmittal at 85-86.
17 Id. at 83-84.
18 Id. at 6, 86; see also id. at 1 n.2 (proposing to define “New Large Load” as: either: (a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June 1, 2027, that increases the existing end- use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load; id. at 32-33 (proposing to define Large Load as a load that (1) has a peak load of 50 MW or greater;
(2) is located at a single site; and (3) is behind one or more points of interconnection.”); id. at 69 (“All New Large Loads shall be eligible to provide IRAS and considered Eligible New Large Loads to the extent the combination of their BYONC arrangements and Allocated RBP UCAP MW does not meet their capacity needs.”).

19 EPSA. 577 U.S. at 283.
20 See, e.g., Transmittal at 7 (“IRAS would facilitate a decision by an Electric Distributor in conjunction with relevant state entities, as applicable, to decide that specific Eligible New Large Loads may be reduced during a Delivery Year when IRAS applies, because such loads are not arranged with sufficient new capacity.”); id. at 50 (“To incentivize Large Loads to address the capacity shortfall caused by their rapid growth, in both speed to interconnection and volume of capacity needed, PJM is proposing to allow New Large Loads to remove themselves—in whole or in part—from the MW eligible for IRAS where such loads bring new capacity to the PJM Region.”); id. at 124 (“The

PDF page 7

-7-
Contrast IRAS with the Supreme Court’s decision in EPSA, where the Court upheld Order No. 745 because (i) it did not literally regulate retail rates and (ii) the regulation did not target the retail customer.21  There, the demand response rule was “only about[] improving the wholesale market,” and FERC “focused wholly on the benefits that demand response participation (in the wholesale market) could bring to the wholesale market.”22  Any effects on the retail market were incidental at most and beside the point.  The same cannot be said of IRAS, which, as noted, is all about specific retail loads and tailoring wholesale services to address the decisions and actions of those retail loads.  Whereas EPSA upheld a FERC decision that accommodated retail customers by requiring RTOs/ISOs to enable them—if permitted by their state—to participate in FERC- jurisdictional wholesale markets through a FERC-jurisdictional product, IRAS would, through EDCs, regulate the nature and conditions of service that retail customers receive. It is obvious from how IRAS operates that PJM is targeting retail customers.  Recall that PJM proposes to assign wholesale curtailment obligation to an EDC based on the size (i.e., more than 50 MW) and vintage (i.e., interconnection date and ramp rate) of the relevant retail customers.23  PJM’s characterization of IRAS confirms the target, despite its veneer of regulating EDCs rather than retail load.  First, the PJM board directed PJM to file a proposal that “will be applicable to ‘[N]ew Large Loads that, as of June 1, 2027, do not bring sufficient capacity to serve their resource adequacy needs and cannot otherwise be served at the 1-in-10 reliability

elements of this proposal were developed together and designed to work in lockstep and provide complementary pieces to a multi-prong approach to incent New Large Loads to bring their own capacity to meet their resource adequacy needs and avoid imposing costs on ratepayers.”).

21 EPSA, 577 U.S. at 282-83.
22 Id. at 282-83.
23 Transmittal at 6.

PDF page 8

-8-
standard.’”24  Next, PJM defined IRAS as “a new supplemental capacity product through which New Large Loads provide a load reduction service that is a tool available to PJM to manage resource adequacy shortfalls.”25  At every turn, PJM has made clear that it designed IRAS as a way to curtail specific retail customers.  That these curtailments would be carried out by EDCs does not change the fact that the trigger for the curtailments is the characteristics of the retail customer—or that the curtailment directive is pursuant to a FERC-jurisdictional tariff.  Indeed, that type of formalistic argument is why the Supreme Court has repeatedly emphasized the target at which the regulation aims.26  Finally, as yet another piece of evidence, the wholesale transmission curtailments will mirror “a MW quantity equal to or less than the Electric Distributor’s Eligible New Large Load.”27  In other words, PJM plans to call for curtailments not based on the real-time transmission conditions in an EDC’s zone, which is how PJM sheds loads today, but based on whether a zone has retail customers that have certain characteristics.  It is easy to see that this is not a regulation where “every aspect of the regulatory plan happens exclusively on the wholesale market and governs exclusively that market’s rules.”28

In trying to defend IRAS as jurisdictionally permissible, PJM hangs its hat on the fact that “‘exclusive jurisdiction’ rests with the states to ensure that the appropriate retail customers, i.e., New Large Loads, including data centers—and not residential customers or small industrial

24 Transmittal at 17 (alteration in original).
25 Id. at 22.
26 EPSA, 577 U.S. at 282 (looking at the Commission’s justification for regulating demand response and quoting from the Court’s decision in Oneok, which “consider[ed] ‘the target at which [a] law aims’ in determining whether a State [was] properly regulating retail or, instead, improperly regulating wholesale sales.” (quoting Oneok, 575 U.S. at 385) (emphasis and alteration in original)); cf. Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 166 (2016) (state’s scheme to encourage development of generation resources overstepped its authority because it was tethered to the resource’s wholesale market participation).
27 Transmittal at 86.
28 EPSA, 577 U.S. at 282.

PDF page 9

-9-
customers—are reduced when system conditions call for PJM to require load reductions,”29 but the fact that PJM is not the party that physically “flips the switch” to curtail specific retail loads does not save IRAS.  Creating the conditions by which a state must take the final step of curtailing retail customers that PJM has already singled out for curtailment does not retroactively cure the jurisdictional defects inherent in IRAS.

IRAS also exceeds the Commission’s authority for the related reason that PJM seeks to regulate retail customers and their rates—albeit indirectly—which the FPA and EPSA prohibit.  It bears repeating that the Commission cannot regulate retail customers, even indirectly, in ways that target the retail customer.30  But that is IRAS in a nutshell.  The whole point of IRAS is to have certain retail loads curtailed under PJM-defined conditions.31  Deciding when certain large loads should be curtailed is a condition of retail distribution service, not something to be decided by an RTO, as PJM would be doing here.

PJM also proposes to overstep its jurisdictional limits by setting forth how retail customers are compensated when they are curtailed under IRAS.32  Under IRAS, PJM would compensate EDCs for IRAS curtailments at a rate that is equal to 50% of the Non-Performance Charge Rate.33 Specifically, PJM proposes to pay a wholesale rate to EDCs that curtail under IRAS, but if a new large load waives curtailment compensation at the retail level, the wholesale IRAS rate will be

29 Transmittal at 90-91.
30 EPSA, 577 U.S. at 282-83.
31 See Transmittal at 22 (defining IRAS as “a new supplemental capacity product through which New Large Loads provide a load reduction service that is a tool available to PJM to manage resource adequacy shortfalls.”).
32 PJM indicates that the ultimate wholesale rate for IRAS would not be reviewed under FPA section 205.  See id. at 102.  To the extent that PJM is proposing to charge rates that differ from what is on file with the Commission, this would violate the filed rate doctrine.
33 Id.

PDF page 10

-10-
reduced to zero dollars.34  In other words, PJM is creating a mechanism within the wholesale rate that determines retail compensation, namely the waiver election on the part of the new large load, which controls whether a payment is made to an end-use customer.  That is a direct regulation of the retail customer.

Thus, IRAS regulates the retail customer, which is why it differs from other issues involving large loads that lie at the confluence of federal and state jurisdiction.  For example, in the PJM Large Load Order to Show Cause,35 the Commission has asserted jurisdiction over discrete aspects of the interconnection of large loads to the transmission system based on the Commission’s jurisdiction over the interstate transmission of electricity.  That regulation does not come close to touching the ultimate sale of electricity to the retail customer, whereas IRAS directly regulates it.  Instead, the Large Load Order to Show Cause is all about “ensur[ing] that transmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions governing how transmission service to Eligible Customers”—i.e., the entity taking wholesale transmission service—“on behalf of large loads interconnecting to the transmission system will be studied.”36  To the extent that the regulation affects retail customers, such effects are incidental to the purpose of the Large Load Order to Show Cause.  Further, as Vistra has previously explained, the Commission’s jurisdiction over the transmission of electricity in interstate commerce—the basis for Commission action in the Large Load Order to Show Cause—is plenary and therefore broader than its jurisdiction with respect to sales wholesale sales of electricity—the basis for IRAS,

34 Id. at 105; Proposed Tariff, attach. DD-4, § X(a) (“The rate for the provision of Interim Resource Adequacy Service shall be 50% of the Non-Performance Charge Rate specified in Tariff, Attachment DD, section 10A(e), unless any Eligible New Large Load elects to (i) accept in its retail rates a sum less than 50% of the Non-Performance Charge Rate as compensation for the provision of wholesale Interim Resource Adequacy Service, or (ii) waive receipt in its retail rates any compensation for the provision of wholesale Interim Resource Adequacy Service . . . . ”).
35 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211.
36 Id. P 45 (emphasis added).

PDF page 11

-11-
which operates through PJM’s wholesale capacity market and is all about the supply of electricity in the region.37

B. IRAS Is Unduly Discriminatory
IRAS is also unduly discriminatory because it treats similarly situated entities differently.38 “Similarly situated” does not mean that there are no differences between the two entities, but rather that there are no differences “that are material to the inquiry at hand.”39  PJM bears the burden to explain how its proposal to treat entities differently is justified by factors that render those entities not “similarly situated.”  PJM fails to meet that standard for several reasons.

1. IRAS Unduly Discriminates Between EDCs
To start, IRAS would unduly discriminate among EDCs based on the characteristics of
retail customers within those EDCs’ footprints.  Specifically, IRAS would subject EDCs to curtailment based on the size, timing, and contracting decisions of its retail customers.  Those retail customers are outside the Commission’s jurisdiction to consider and therefore cannot be “material to the inquiry at hand.”40  Providing differing levels of wholesale market treatment depending on legally irrelevant characteristics of entities sitting outside the Commission’s jurisdiction is, by definition, unduly discriminatory.

Even if the characteristics of the retail customers within an EDC’s territory could, in theory, be a lawful basis to discriminate among wholesale customers, the retail characteristics on which

37 See Interconnection of Large Loads to the Transmission Sys., Docket No. RM26-4-000, Initial Comments of Vistra Corp., at 7 (filed Nov. 21, 2025).
38 16 U.S.C. § 824d(b); see also Transmission Agency of N. California v. FERC, 628 F.3d 538, 551 (D.C. Cir. 2010) (citing Sacramento Mun. Util. Dist. v. FERC, 474 F.3d 797, 802 (D.C. Cir. 2007)).
39 See N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at PP 10, 14 (2018) (“To say that entities are similarly situated does not mean that there are no differences between them; rather, it means that there are no differences that are material to the inquiry at hand”); see also Ala. Elec. Coop. v. FERC, 684 F.2d 20, 27 (D.C. Cir. 1982) (explaining that if the costs of providing service to two groups are different, the two classes are differently situated in that “important respect” for cost-of-service ratemaking).
40 N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124 at P 10.

PDF page 12

-12-
PJM proposes to discriminate are irrelevant to the resource adequacy issues that IRAS purports to solve, and therefore do not render the EDCs differently situated.  PJM has misdiagnosed the cause of the resource adequacy problem.  The regional resource adequacy problem is not caused by the individual contracting decisions of each retail customer.  The resource adequacy problem is that some EDCs have agreed to serve more load than they have generation.  Were PJM to continue to assign load shed to EDCs that are short, it is likely that EDCs that interconnect large loads without the generation to serve it would be exposed to curtailment.  The current method aims at generation deficient zones, with the potential they are short due to additional large loads.  PJM skips past the question of whether an EDC is generation deficient and aims simply at EDCs that have large loads that do not bring their own new capacity.

2. IRAS Unduly Discriminates Against Existing Resources
When determining whether new large loads are subject to IRAS, PJM would value identical new and existing capacity resources differently even though they provide the same resource adequacy benefits to the system.  PJM has not explained why large loads that contract with new generation resources should be non-curtailable while those that contract with existing generation resource with the same capacity value should be curtailed when system conditions warrant.  Nor could it.  One MW of accredited capacity from a new resource provides the same resource adequacy benefits as one MW of capacity from an otherwise identical existing resource.  Whether the otherwise identical resources are bilaterally contracted or selling exclusively in the PJM capacity market does not change the resource adequacy value to the PJM system as a matter of physics.

Indeed, the D.C. Circuit has held that is arbitrary and capricious for the Commission to treat new and existing customers differently where both contribute equally to the need in

PDF page 13

-13-
question.41  So too, the Commission has previously rejected efforts by PJM to treat new and existing capacity resources differently, even when the avowed purpose was to incentivize new resource entry.42  In that case, PJM proposed to lock in capacity prices for new capacity resources for seven years, which would guarantee higher prices to new entrants that were not available to existing suppliers.  The Commission rejected the proposal, explaining that both new and existing capacity are necessary to ensure reliability and that both should receive the same price so that the price signals are not skewed in favor of new entry.43  That logic applies with force here because IRAS gives preferential treatment to one MW of new capacity even though one MW of existing capacity is equally as effective when it comes to ensuring resource adequacy.

3. IRAS Unduly Discriminates Based on Vintage of Load Addition
Next, IRAS also unduly discriminates between new and existing large loads given that curtailment obligations would be assigned to the EDC based on when the large loads in question began operating, a characteristic that is entirely irrelevant to reliability and resource adequacy concerns.  As already discussed, the D.C. Circuit has rejected similar efforts to treat existing and marginal customers differently based on the principal that, because every user of a system is economically marginal, increases in demand can be attributed to every user, both new and existing.44  That principle forecloses IRAS, which would treat EDCs with large loads that begin operations on May 31, 2027 differently than those with large loads that begin operations the next

41 See BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014) (“[T]he cost causation principle generally calls for giving the same treatment to new and continuing customers, based on a straightforward economic rationale.  Where ‘all customers cause the incurrence of the costs . . . , whether by adding or merely continuing their usage assignment of the costs to all customers (both continuing and new) forces each set to weigh the marginal benefits of the capacity to them against the marginal costs they impose on society by continuing to make demands.” (internal citations and quotation marks omitted)).
42 PJM Interconnection, L.L.C., 128 FERC ¶ 61,157 at PP 101-102.
43 Id.; see also id. P 103 (“A market should be designed correctly so that the contribution to reliability from both new entrants and existing suppliers is compensated comparably.”).
44 See BNP Paribas Energy Trading GP v. FERC, 743 F.3d at 268-69.

PDF page 14

-14-
day, even though it is the load’s size, not the date that it started operating, that determines its effect on resource adequacy.

PJM’s proposal to reset the IRAS curtailment regime if the region has sufficient capacity to meet the reliability requirement for three consecutive delivery years further underscores the unduly discriminatory nature of IRAS.  Consider a hypothetical in which a new large load is subject to IRAS for the first two years it is in operation, after which the resource adequacy picture in the region improves for three years and there are no shortfalls during that time.  At that point— five years after it began operating—the new large load would no longer be subject to IRAS curtailments going forward even if a shortfall returns in year six.45  But a new load coming online in year six that does not BYONC would be subject to curtailment.  Toggling IRAS’s curtailment scheme in this way makes no sense, as the demand that the large load puts on PJM’s system (i.e., its effect on resource adequacy) remains constant in all six years.  As this example shows, IRAS would subject large loads to discriminatory treatment based solely on the resource adequacy picture in PJM at the time those loads begin operating rather than on the loads’ effects on resource adequacy—a principle that is inconsistent with the D.C. Circuit’s BNP Paribas decision.46

C. IRAS Is Unjust and Unreasonable
IRAS is unjust and unreasonable for at least five reasons.  First, it is designed to require new large loads to bring new capacity to avoid being curtailed even though PJM lacks the authority to ensure that such loads will not, in fact, be curtailed.  Second, under IRAS, new large loads that do not bring new capacity are allocated costs for capacity that PJM never procures.  Third, IRAS

45 Transmittal at 58.
46 Even if the Commission were to order PJM to apply IRAS and BYONC to a wider range of large loads (putting aside the filed-rate doctrine issues this would raise), any scheme in which preferential treatment would turn on the vintage of loads in an EDC’s footprint would be patently illegal, as the D.C. Circuit has made clear.  BNP Paribas Energy Trading GP v. FERC, 743 F.3d at 268-69.

PDF page 15

-15-
fails to respect existing contracts because new large loads that contract with existing capacity resources prior to the effective date of IRAS are nevertheless subject to the IRAS curtailment regime.  Fourth, it curtails loads seeking firm service before those that have volunteered to be curtailed.  Finally, PJM’s proposal to remove from the VRR Curve large loads that do not bring their own capacity distorts market fundamentals and could lock in any resource adequacy gap that remains after the backstop auction.  Each of these flaws is a sufficient basis to reject the filing.

1. IRAS Does Not Ensure That BYONC Loads Get the Benefit of the
Bargain
IRAS is unjust and unreasonable because it imposes costs on new large loads without commensurate benefits.  As PJM implicitly concedes, new large loads that that seek to acquire firm service via BYONC could still be curtailed under IRAS before pre-emergency load management reductions.47  To see why, recall how IRAS is designed to work.  When called upon by PJM, an EDC must curtail load in an amount equal to the sum of Eligible New Large Load Amounts in the EDC’s footprint—i.e., the sum of new large loads that do not BYONC.48  A new large load that brings sufficient new capacity to offset its demand is not considered eligible to be curtailed under IRAS.49  Nevertheless, as PJM itself concedes, “while PJM will determine the quantity of MW that load in a zone/area will need to be reduced by to maintain system reliability in the PJM Region, states may determine—under their own laws, policies, and definition of what constitutes ‘large load’—which resources will be called on to reduce load.”50

47 See Transmittal at 92 (“PJM will not direct reductions to specific New Large Loads pursuant to IRAS.  Rather, PJM is leaving it to Electric Distributors, in coordination with the appropriate states and/or RERRAs, LSEs, and LSE customers to determine which loads should ultimately reduce subject to IRAS.”).
48 Id.at 71-72.
49 Id. at 69.
50 Id. at 87.

PDF page 16

-16-
This means that even though BYONC large loads are not considered eligible for
curtailment by PJM, EDCs will decide which loads to shed according to retail tariffs and state policy priorities, which could include BYONC large loads.  In other words, PJM has designed a scheme in which it purports to protect certain loads from being curtailed, even though PJM has no way to ensure that those loads are not, in fact, curtailed.  As a result, new large loads that spend billions of dollars contracting with new capacity resources may be curtailed before ones that do not bring new capacity because PJM has no authority to determine which retail customers to shed. The fact that the ultimate curtailment decision is a retail question does not excuse this result.  The Commission must determine whether the construct proposed by PJM is just and reasonable—a conclusion it cannot make for a program, like IRAS, that creates a burden but does not deliver the benefit that it is purportedly premised on.

2. IRAS Is Unjust and Unreasonable Because It Allocates RPM Costs to
Loads for Capacity that They Never Procure
IRAS is also unjust and unreasonable because it flagrantly violates bedrock cost causation and beneficiary pays principles.  Under IRAS, PJM would exclude from the VRR Curve new large loads that fail to bring new capacity while still allocating capacity charges to them.51  By design, PJM’s proposal would meddle with capacity market fundamentals to avoid procuring capacity to serve new large loads that fail to bring new capacity and yet turn around and allocate capacity costs to those very same loads.  This scheme is inconsistent with the requirement that costs assigned to a party must be “roughly commensurate” with the benefit it receives in exchange for

51 See Proposed Tariff, attach. DD, § 5.10(a) (deducting Excluded New Large Load Amounts from the Reliability Requirement used to establish the VRR Curve).  PJM does not propose to change how it calculates and allocates capacity charges.

PDF page 17

-17-
paying those costs.52  It would be impossible for new large loads to get a benefit from capacity they are paying for when that capacity is never acquired for them in the first place. As discussed further below,53 this aspect of PJM’s proposal is not just unlawful, it is also dangerously short-sighted as a matter of policy.  In the short term, administratively suppressing demand in the capacity market might help insulate existing retail customers from price increases due to large loads. But it is not a lasting solution.  Instead, by removing from the VRR Curve loads that will come online in the region, PJM is further eroding capacity market fundamentals, which will undermine investment in the region’s generation fleet, thereby harming resource adequacy in the long-term and ultimately increasing costs for the region.

3. IRAS Is Unjust and Unreasonable Because It Disrupts Existing
Commercial Arrangements
Furthermore, IRAS is unjust and unreasonable because it fails to respect existing contracts. Specifically, new large loads that contract with existing capacity resources prior to the effective date of IRAS will be subject to the IRAS curtailment regime.  Despite PJM’s claim that its proposal will not disrupt existing contracts, IRAS will force large loads that have already paid for capacity by contracting with existing generation to pay for capacity price twice by BYONC to try to avoid curtailment.  Requiring an entity to pay twice for the same product or service is unjust and unreasonable.54

Subjecting new large loads that have executed contracts with existing generators to IRAS will disrupt settled expectations and compound uncertainty in the PJM region, chilling investment in energy infrastructure when it is most needed.  Some new loads that will not come online until

52 See Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1256 (D.C. Cir. 2018).
53 See Infra § I.C.5.
54 See N.Y. Indep. Sys. Operator, Inc., 155 FERC ¶ 61,076, at P 82 (2016) (rejecting proposal that would have required ratepayers to pay twice for the same capacity).

PDF page 18

-18-
after June 1, 2027 have already entered into bilateral contracts to purchase capacity from existing generators or are currently in the process of negotiating such contracts that will be executed prior to the IRAS effective date.  If those contracts are not honored, the Commission and PJM will only reinforce investors’ fears that the ground in PJM can shift beneath them at any point.  That will throttle investment into the region and jeopardize resource adequacy.

For example, Vistra previously entered into power purchase agreements for the sale of nuclear power from Vistra’s operating nuclear facilities in Ohio with a data center customer.55  As proposed, IRAS would not extend curtailment protection to capacity procured under agreements of this kind, notwithstanding that these agreements were executed prior to the effectiveness of IRAS.  That result would create the prospect of duplicative capacity procurement and would unsettle the expectations of underlying agreements that were negotiated within the existing regulatory framework.  The Commission must not adopt IRAS in a form that operates retroactively on existing agreements.

Even if the Commission were otherwise inclined to accept IRAS, it must reject the proposal solely for its failure to exempt contracts with existing resources.  In so doing, the Commission should provide guidance that, in any future filing, PJM must grandfather contracts between new large loads and existing capacity resources negotiated according to the rules in effect at the time. This would be consistent with PJM’s own statement and FERC’s approach to honoring existing contracts and reliance interests.56  Without such grandfathering, new large loads will have paid

55 Vistra, Vistra and Meta Announce Agreements to Support Nuclear Plants in PJM and Add New Nuclear Generation to the Grid (Jan. 9, 2026), https://investor.vistracorp.com/2026-01-09-Vistra-and-Meta-Announce- Agreements-to-Support-Nuclear-Plants-in-PJM-and-Add-New-Nuclear-Generation-to-the-Grid.
56 See, e.g., PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at PP 222-224 (2025); N.Y. Indep. Sys. Operator, Inc., 122 FERC ¶ 61,267, at P 65 (2008); ISO New England Inc., 194 FERC ¶ 61,249, at P 34 (2026); see also FERC, Chairman Laura Swett’s Comments at PJM’s Annual Meeting in Baltimore, MD (May 12, 2026),

PDF page 19

-19-
billions of dollars for capacity only to then be subjected to curtailment risk and double-charged for capacity from the PJM market which they do not need.  That type of regulatory framework is a sure recipe for scaring off investment not only in PJM but any market regulated by FERC that might follow PJM’s lead.

4. IRAS Is Unjust and Unreasonable Because it Creates a Scheme to Curtail
Loads Seeking Firm Service Before Those That Volunteer to Be
Curtailable
Further, under IRAS’s tortured curtailment scheme, new large loads that are seeking firm service could be curtailed before loads that have volunteered to participate as demand response resources.  PJM proposes to call for an IRAS curtailment “prior to calling on Pre-Emergency Load Management Reduction Actions” when it determines that system conditions warrant such action.57 In practice, this means that new large loads that depend on firm service to operate but have not brought new capacity for any number of reasons (e.g., because the paired generation cannot clear the backlogged interconnection queue) could be curtailed before loads that have elected to be curtailed whenever called upon by PJM to do so.  And to make matters worse, demand response resources will receive capacity payments and be curtailed after new large loads subject to IRAS. Curtailing loads that have paid for firm service before those that have raised their hand to be curtailable is unjust and unreasonable.

5. IRAS Will Undermine PJM’s Capacity Market Fundamentals, Which
Will Further Harm Resource Adequacy in PJM
IRAS’s design flaws are also unjust and unreasonable because they will deter investment needed to bolster resource adequacy in the region at a time when that investment is desperately

https://www.ferc.gov/news-events/news/chairman-laura-swetts-comments-pjms-annual-meeting-baltimore-md-0 (“[W]hatever happens, we cannot disrupt finalized commercial agreements.  At FERC, I have no appetite to compromise investor confidence when those investors are driving the buildout of the generation that PJM desperately needs.  However you get there PJM, you need to figure it out.  Fast.”).

57 Transmittal at 75.

PDF page 20

-20-
needed.  PJM asserts that it is proposing to remove large load that does not BYONC from the demand curve to protect other customers from high costs.58  This is counterproductive because it will lock in any reliability gap that exists after the reliability backstop auction is run. Dr. Carl Coscia’s affidavit on behalf of P3 illustrates the sensitivity of the capacity price when load is removed from the capacity market.59  When demand growth is removed from the auction, even a modest amount of resource entry will drive the capacity price below the cost of new entry.60  Consistent and predictable demand growth can mitigate the disincentive to enter based on a single year’s capacity price because entry is less likely to reduce future capacity prices below the level that made the entry rational.  Thus, PJM’s proposal to remove load growth associated with large loads that do not BYONC will likely disincentivize the entry needed to close any reliability gap remaining after the backstop auction.

With the capacity market less able to attract entry based on PJM’s proposal, one is left to question what will motivate new entry.  PJM seems to be relying on the BYONC elements of its proposal.  As discussed above, IRAS leaves large loads in an impossible situation:  they can either contract with new capacity with nothing more than the hope that the state will honor BYONC, such that they will not be curtailed; or they can forgo BYONC, and hope that they are not curtailed, either because system conditions never warrant it or because states decide to curtail other loads first.  Further, removing load growth from the demand curve deepens the conundrum for any large load considering a costly bilateral contract for capacity.  While PJM’s proposal will likely disincentivize new generation, there remains a chance that enough new resources will enter so that

58 Transmittal at 109-119.
59 PJM Interconnection, L.L.C. Protest of PJM Power Providers (P3) Group, Docket No. ER26-3515-000, Aff. of Dr. Carl Coscia (to be filed Sep. 3, 2026).  P3 has informed Vistra that they intend to attach the affidavit of Dr. Coscia and has authorized us to represent that here.
60 Id.

PDF page 21

-21-
capacity prices will drop significantly.  A new large load that is not fully protected from IRAS curtailment must weigh the certainty of costly new generation against the chance for significantly less costly capacity.  PJM is asking large loads to take a gamble.  Under those circumstances, it would be entirely rational and predictable if new large loads choose the side of the wager that does not involve them making a potentially multi-billion-dollar commitment.  In practice, that means an exodus of capital from the region, or a flight to fully islanded configurations, which would be contrary to the stated goals of IRAS and the best interests of all PJM stakeholders. In short, PJM’s proposal will likely either disincentivize new entry into the PJM capacity market but encourage BYONC, thus locking in whatever reliability gap remains after PJM’s planned Reliability Backstop Procurement auction; or it will encourage new entry through the capacity market and discourage BYONC, thereby creating a permanent class of load subject to IRAS curtailment and driving capital away from the region.  Either result will work against the region’s needs, so whichever way the IRAS gamble plays out it is clear that the end state will harm PJM customers.

D. IRAS Should Not Apply to Behind the Meter Load
Finally, the Commission should require PJM to confirm that IRAS will not apply to new large loads that are co-located behind the meter of generation resources that are not capacity resources.  For loads in such a configuration, there is nothing to curtail because the load is not using PJM capacity.  The Commission must direct PJM to provide this confirmation to ensure that this proceeding does not undermine the Commission’s parallel efforts to facilitate co-location. PJM’s filing introduces significant ambiguity about whether it intends to subject co-located loads to IRAS because it deviates from the Commission’s proposed definitions concerning co- located configurations in the PJM Large Load Order to Show Cause in Docket No. EL26-67-000. There, the Commission defined a “large load” as “a new, commercial or industrial customer,

PDF page 22

-22-
located at a single site behind one or more points of interconnection, and that has a peak load of 50 MW or greater, interconnects to the transmission system at a voltage level of greater than 69 kV, and is not part of a co-location arrangement.”61  To contrast, PJM’s proposed definitions for “Large Load” and “New Large Load” specifically do not exclude load that is part of a co-location arrangement.62  PJM’s decision not to carve out co-located load in the manner the Commission intended indicates that co-located loads could be subject to IRAS.

PJM did not and cannot explain why IRAS should apply to co-located loads.  Instead, PJM attempted to justify its inclusion of co-located load in these definitions by stating that it “proposed rules that specifically address situations in which Large Load is co-located with their own generation.”63 It is not clear what rules PJM is referring to, as nothing in PJM’s proposal clarifies how IRAS will work for co-located load.64

It would be manifestly unjust and unreasonable to curtail a load that is co-located behind the meter of a generator that is not a capacity resource.  If PJM, in conjunction with EDCs, were to seek to curtail a new large load co-located with a non-capacity resource, it would need to direct the co-located generator to increase output to the grid because the co-located load is not a network load subject to EDC direction.  But the co-located generator is not paid to be a capacity resource so PJM has no claim to the generator’s output.  Further, the co-located generator may no longer be deliverable to all load as it is required to forfeit its capacity injection rights, and so it may not be

61 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 58 (emphasis added).
62 Transmittal at 31, 35-36, 38.  PJM’s proposed definition also fails to include a voltage threshold.  PJM also fails to justify this omission, stating only that its stakeholders “have not identified any need” to include a voltage threshold.  Id. at 36.  That is not a sufficient reason to ignore a Commission directive.
63 Id.
64 For example, because a co-located load is behind a generator’s point of interconnection, the only way to curtail that load may be to disconnect the generator.  Such an action would raise serious legal and operational issues—for both the generator, the load, and the PJM system—and ultimately would be counterproductive from a resource adequacy perspective.

PDF page 23

-23-
able to improve system conditions.  PJM has not, and cannot, justify including co-located new large loads in IRAS.  Accordingly, the Commission should order PJM to confirm that such loads are not subject to IRAS curtailments.

II. CONCLUSION
For the foregoing reasons, the Commission should promptly reject PJM’s filing.

Respectfully submitted,

/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy

Andrew Weinstein
Vice President, FERC Market Policy

Vistra Corp.
325 7th Street NW
Suite 520
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com

Nic Gladd
Sarah Greenberg
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com
bshpall@wsgr.com

Counsel for Vistra Corp.
Dated:  September 3, 2026

PDF page 24

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.

Dated:  September 3, 2026
Washington, D.C.

/s/ Bryan Shpall
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006