Protest of Vistra Corp. regarding PJM Interconnection, L.L.C.’s proposed Interim Resource Adequacy Service filing
Text extracted from the eLibrary original (SHA-256 0db4237f10ede37e…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
With IRAS, PJM ignores the jurisdictional boundaries that Congress carefully crafted and proposes rules that are unjust, unreasonable, and unduly discriminatory—each of which is a sufficient basis for the Commission to reject the proposal and for a court to overturn an order accepting IRAS on…Read this passage Filed comments: Reliability and curtailment
I. PROTEST
printed heading · Topic match: Reliability and curtailment
PJM proposes that new large loads that contract with new capacity resources are not supposed to be exposed to the IRAS curtailment regime while new large loads that contract with otherwise identical existing capacity resources would be.Read this passage Filed comments: Reliability and curtailment
A. IRAS Violates the FPA’s Division of Jurisdiction
printed heading · Topic match: Reliability and curtailment
DD-4, § X(a) (“The rate for the provision of Interim Resource Adequacy Service shall be 50% of the Non-Performance Charge Rate specified in Tariff, Attachment DD, section 10A(e), unless any Eligible New Large Load elects to (i) accept in its retail rates a sum less than 50% of the Non-Performance…Read this passage Filed comments: Reliability and curtailment
B. IRAS Is Unduly Discriminatory
printed heading · Topic match: Reliability and curtailment
Operator, Inc., 162 FERC ¶ 61,124 at P 10. -12- PJM proposes to discriminate are irrelevant to the resource adequacy issues that IRAS purports to solve, and therefore do not render the EDCs differently situated.Read this passage Filed comments: Reliability and curtailment
C. IRAS Is Unjust and Unreasonable
printed heading · Topic match: Reliability and curtailment
PJM proposes to call for an IRAS curtailment “prior to calling on Pre-Emergency Load Management Reduction Actions” when it determines that system conditions warrant such action.57 In practice, this means that new large loads that depend on firm service to operate but have not brought new capacity…Read this passage Filed comments: Reliability and curtailment
D. IRAS Should Not Apply to Behind the Meter Load
printed heading · Topic match: Connecting load and generation
The Commission must direct PJM to provide this confirmation to ensure that this proceeding does not undermine the Commission’s parallel efforts to facilitate co-location.Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, the Commission should promptly reject PJM’s filing.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated: September 3, 2026 Washington, D.C. /s/ Bryan Shpall Bryan Shpall Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006Read this passage