ER26-3515-000 · 2026-09-03 · Ohio Energy Leadership Council
Comments and Limited Protests of Ohio Energy Leadership Council in response to the Interim Resource Adequacy Service and Large Load Registry proposed by PJM…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
Docket No. ER26-3515-000
COMMENTS AND LIMITED PROTESTS OF OHIO ENERGY LEADERSHIP COUNCIL
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (the “Commission”), Ohio Energy Leadership Council (“OELC”) respectfully submits these comments and limited protests in response to the Interim Resource Adequacy Service (“IRAS”) and Large Load Registry proposed in this proceeding by PJM Interconnection, L.L.C. (“PJM”).
I. SUMMARY OF COMMENTS AND LIMITED PROTESTS.
OELC supports the objective of maintaining resource adequacy and recognizes that new large loads should bear responsibility for the incremental resource-adequacy needs their additions create. OELC also recognizes the value of an interim conditional service option that allows qualifying new large loads to connect subject to curtailment when system conditions require it. But the Commission should not allow PJM’s proposal to shift to existing customers the risks and costs associated with its proposal in this case. Accordingly, OELC respectfully requests that the Commission condition any acceptance of PJM’s IRAS proposal on the following:
1. Establish a separate, protective threshold for non-data-center customers. A non-data- center customer—including but not limited to traditional manufacturing, steelmaking, chemical, industrial, educational, institutional, and retail customers—should be treated as a Large Load only if its Peak Load Contribution (“PLC”) is at least 150 MW. The lower 50 MW threshold should not apply to non-data-center customers.
2. Preserve the intended sequential load-reduction order if PJM accepts New Large Load demand response as BYONC. PJM’s proposal may permit New Large Load to
PDF page 2
2
reduce its IRAS responsibility by registering its own load as a new Demand Resource or as part of a new DER Capacity Aggregation Resource. OELC does not oppose this proposal provided that curtailment sequencing should be preserved such that such new demand resources offered by the New Large Load should be curtailed before PJM calls on existing Demand Resources and existing DER Capacity Aggregation Resources as part of Pre- Emergency and Emergency Load Management Reduction Actions.
3. Ensure IRAS compensation is reasonable and just while preserving cost recovery questions to the appropriate state commissions. While OELC does not oppose
appropriate compensation for IRAS curtailments, the Commission should ensure the compensation regime is just and reasonable and that the framework leaves to the appropriate state commissions how such costs are recovered from the local utilities and their customers.
These protections are necessary for the proposal to satisfy the Federal Power Act’s just- and-reasonable standard. Section 205 requires that all Commission-jurisdictional rates, charges, practices, and classifications be just and reasonable. PJM bears the burden to demonstrate that each proposed IRAS condition, including its BYONC eligibility, load-reduction sequencing, and compensation provisions, satisfies that standard.
II. OELC’S INTEREST AND EXPERIENCE.
OELC is a not-for-profit trade association that represents its members’ interests in utility and ratemaking matters in Ohio. Managing the cost and availability of energy is a crucial component of success for many businesses, and OELC advocates for competitive, reasonable, and transparent laws, policies, and utility rates through effective lobbying and legal advocacy. OELC’s work is directed to ensuring Ohio remains an attractive place for businesses and enterprises to remain, grow, invest, and create jobs.
For more than 30 years, OELC has helped its members understand and manage their electric and natural gas supply costs. OELC and its members have direct, long-standing experience with the practical effects of utility tariffs, rate design, energy legislation, and regulatory policy on Ohio businesses that must manage significant energy consumption and exposure to volatile energy costs. OELC’s members include energy-intensive manufacturing, industrial, educational,
PDF page 3
3
institutional, and retail business customers in Ohio. Collectively, OELC’s members annually consume many billions of kilowatt-hours of electricity and are major contributors to Ohio’s economy and employment sector. For OELC’s members, electricity is not a discretionary purchase; it is a material production input, a prerequisite to continuous operations, and a major component of the delivered cost of goods and services.
Through its dedicated lobbying and regulatory advisors, OELC actively participates in legislative matters affecting Ohio energy and utility policy and participates in matters before the Public Utilities Commission of Ohio (“PUCO”). That work includes electric distribution-rate proceedings for Ohio electric utilities and other PUCO proceedings affecting member utility rates and issues. OELC is therefore well positioned to explain how PJM’s IRAS proposal will affect Ohio end-use customers and the competitiveness of Ohio’s industrial economy.
A reliable and reasonably priced electric system is essential to OELC’s members. OELC therefore supports measures that maintain system reliability and allocate the responsibility for new load fairly. The Commission should ensure that the IRAS construct does not allow new load to obtain preferential treatment in emergency curtailment or to impose on existing customers the cost of compensating that new load for complying with the conditions of its earlier, conditional service.
III. PJM SHOULD ADOPT A SEPARATE 150 MW THRESHOLD FOR NON-DATA-
CENTER CUSTOMERS BASED ON PLC VALUES.
PJM proposes to define a Large Load as an end-use customer load with a cumulative peak load of 50 MW or greater at a single electrical site.1 OELC does not oppose a definition that identifies the extraordinary new load additions producing the resource-adequacy concerns underlying IRAS. But PJM should not apply a uniform 50 MW threshold that treats traditional,
1 Application, FERC Docket No. ER26-3515-000 (August 13, 2026) at 31-32.
PDF page 4
4
energy-intensive, non-data-center customers as similarly situated to data centers or apply that threshold without considering the materially different characteristics of these customer classes. Large non-data center loads include manufacturers, steel mills, chemical facilities, universities, and retailers, among others. Traditional industrial facilities are foundational to domestic supply chains. They supply critical domestically produced materials and products used in infrastructure, transportation, construction, energy systems, agriculture, health care, and national-defense-related production. A durable national-security and national economic strategy require that these industries have access to reliable and reasonably priced power. Reliability and affordability are complementary objectives, not competing ones.
The Commission need not choose between supporting data-center growth and supporting domestic industry. It can do both by applying a definition that targets the new load that creates the IRAS regime requirement while maintaining reliable service to the traditional industrial base. The Application itself describes specific characteristics of new data-center load that support differentiated treatment. PJM states that an “unprecedented surge in data center load” has arrived faster than new supply can come online; the speed of connecting these loads has created a “fundamental misalignment between demand and supply cycles,” resulting in significant resource- adequacy stress.2 PJM likewise cites data centers’ incomparably large energy demands, rapid energization, and unique collective potential to affect grid reliability and raise rates for other customers.3 PJM’s Application also identifies data-center growth as the predominant source of the near-term load-growth problem. PJM forecasts 32 GW of peak-load growth between 2024 and 2030, of which 30 GW is projected to come from data centers.42 Application at 21.3 Application at 96-97.4 Application at 13.
PDF page 5
5
In this context, penalizing existing manufacturers for energy intensity simply weakens the very industrial capacity on which the nation depends, while doing little to improve the signal sent to the new load that drives the need for additional capacity. Energy prices are already a decisive component of manufacturing competitiveness. Capacity charges and other demand-related costs are not absorbed in a vacuum. They increase the delivered energy cost of production, reduce operating margins, constrain capital spending, and affect decisions about production volumes, facility expansions, and employment. OELC’s members compete not only with other domestic facilities but with international producers that may operate under materially different energy, regulatory, labor, and capital-cost conditions.
The Commission should not introduce a new cost burden on domestic manufacturing at this critical time in our nation’s economy. The likely effect of an overbroad 50 MW threshold is not confined to the affected bill. Energy-intensive manufacturers transmit higher production costs through supply chains, or they absorb them by reducing investment, output, or employment. Neither outcome advances reliability, affordability, or economic resilience. Moreover, traditional energy-intensive customers often operate equipment and facilities with which utilities are familiar, promoting more accurate load forecasting and system planning for traditional loads. In the current inflation-sensitive environment, the Commission should avoid a tariff design that may add avoidable cost pressure to domestically produced materials and the goods made from them. A tailored distinction between data center and non-data center load is neither unduly discriminatory nor preferential. That distinction has already been implemented in Ohio where the Public Utilities Commission of Ohio has found a reasonable basis for treating data centers differently where their unique, concentrated load characteristics and system impacts distinguish
PDF page 6
6
them from other large-load customers.5 The Federal Power Act does not require PJM to disregard material differences among load categories. Rather, a just-and-reasonable tariff should recognize the materially different characteristics of data centers and avoid placing traditional manufacturing and industrial customers in the IRAS category solely because they exceed an undifferentiated 50 MW threshold.
OELC therefore requests that the Commission direct PJM to establish a separate 150 MW
threshold for non-data-center customers. A 50 MW threshold that indiscriminately includes every customer category is overinclusive. It risks imposing undue IRAS-related obligations on
traditional industries based on electricity intensity alone, rather than on a demonstrated causal nexus between incremental demand and the specific reliability concern the IRAS proposal is designed to address. Additionally, the non-data center 150 MW threshold should be calculated based on the customer’s system-peak PLC, rather than a non-data center customer’s highest
demand during any hour of the year. Capacity-related classifications should be based on capacity- related data—demand when the PJM system is under peak conditions—not an isolated
noncoincident operating maximum. A threshold must do more than identify customers that use a meaningful amount of electricity. It must identify customers whose incremental system-peak demand creates the need for the specific capacity procurement and associated charges.
5 See, e.g., Opinion & Order, PUCO Case No. 24-508-EL-ATA (July 9, 2025) at 76-78 (“unlike non-data center load, which comprises a diverse group of customer end uses, data center load cannot be naturally hedged by other industries in AEP Ohio’s service territory…Thus, we recognize that data center customers pose a different type of risk, as well as an increased amount of risk”); Opinion and Order, Case No. 25-392-EL-AIR (April 1, 2026) at 65-66 (approving settlement separating data centers into their own rate class in future case); Finding and Order, PUCO Case No. 26-113-EL-ATA (August 5, 2026) at 12 (“Limiting the Interim Relief to customers subject to the DCT is consistent with the existing regulatory framework in the state of Ohio and continues to be narrowly tailored for customers that present unique load characteristics and system impacts that distinguish them from other large load customers.”).
PDF page 7
7
That is because capacity procurement exists to ensure that sufficient resources are available when the PJM system faces its highest coincident peak demand. The relevant question, therefore, is not whether a particular customer ever reached a high demand level in an isolated hour. It is whether the customer materially contributes to the regional peak conditions that establish the system’s capacity need. A customer-specific annual maximum can occur in a season, hour, or operating condition that does not coincide with the PJM system peak. It may reflect a one-time production event, an outage recovery, a weather-related operational adjustment, commissioning activity, or another idiosyncratic event with no meaningful relationship to the capacity issues in PJM that its IRAS proposal attempts to address. Using that noncoincident maximum would overstate the customer’s capacity responsibility and produce classifications untethered from the need for incremental capacity.
By contrast, system-peak PLC is a familiar and objective planning construct used by PJM for many years. It measures demand when capacity is most needed by the region. PJM itself relies on load adjustments and capacity-obligation concepts that are intended to assign changes in forecasted load to the zone or area where they occur. The Large Load definition should employ the same fundamental principle: identify load by its contribution to the relevant system condition, rather than by an isolated and potentially unrepresentative maximum peak demand. If a customer can be classified as a Large Load based on its highest demand at any time in a year, a single non-coincident operating hour could trigger long-lived tariff consequences. That approach would be unpredictable, hard to audit, and unfair to customers with variable manufacturing processes. It could also perversely encourage customers to alter operations during individual high-demand hours without reducing their contribution to system peaks, thereby producing no genuine reliability benefit.
PDF page 8
8
The Commission should thus reject a methodology that conflates a facility’s maximum operating demand with its system-relevant contribution to capacity requirements. A capacity- related classification must be based on capacity-related data. Accordingly, the Commission should direct PJM to revise its proposed tariff language to resolve at a minimum the following issues:
1. Establish a separate, protective 150 MW threshold for non-data-center customers. A non-data-center customer—including but not limited to traditional manufacturing, steelmaking, chemical, industrial, educational, institutional, and retail customers—should be treated as a Large Load only if its PLC is at least 150 MW. The lower 50 MW threshold should not apply to non-data-center customers.
2. Use of PLC Values. Identify the precise PJM peak-hour set and the period used to calculate the customer’s peak load for purposes of defining a “Large Load Customer,” including the process for publishing those hours and correcting data errors. OELC recommends that PJM be directed to use the existing PLC methodology; an annual maximum, an unannounced ad hoc interval, or a noncoincident peak should not be used.
3. Net-load treatment. Specify the treatment of behind-the-meter generation, demand response, energy storage, and other load-management arrangements, including the data necessary to verify net system contribution.
4. Customer notice and verification. Provide customers with advance notice of proposed classification, their underlying interval data and calculated PLC, a reasonable time to correct errors, and a transparent mechanism for challenging a classification before charges take effect.
5. Temporal nexus to new load. For purposes of the IRAS, require PJM and the relevant electric distributor to demonstrate that the customer’s qualifying PLC reflects new or incremental load relative to the forecast or baseline used to establish the relevant target. Existing load should not be reclassified solely because it is large.
These elements are indispensable. Without them, manufacturing customers cannot forecast their exposure, evaluate the accuracy of their bills, or meaningfully participate in any state retail- cost-allocation proceeding. Ambiguity in the definition and measurement of load invites inconsistent results, disputes, and cost shifting—the opposite of the transparent and reasonable tariff administration OELC seeks.
PDF page 9
9
IV. THE SEQUENTIAL LOAD-REDUCTION STACK PROPOSED BY PJM SHOULD
BE PRESERVED EVEN IF NEW LARGE LOAD USES DEMAND RESPONSE AS
BYONC.
PJM’s application explains that its emergency procedures use sequential load reduction. Sites registered in the PJM demand-response program as Demand Resources may be called to reduce load in Pre-Emergency and Emergency Load Management Reduction Actions before firm exports are reduced in a Maximum Generation Emergency. PJM proposes to add IRAS as a category of load reduction that precedes Demand Resources and DER Capacity Aggregation Resources in that sequence.6 That sequencing is integral to the proposed incentive structure. PJM explains that placing IRAS after Pre-Emergency Load Management would reduce the incentive for New Large Loads to bring new capacity because the new loads would instead be insulated by Demand Resource capacity products.7
OELC recommends that the Commission approve the curtailment sequencing proposed by PJM in this case. This is particularly important because PJM’s proposal may permit New Large Load to rely on demand response resources to meet BYONC requirements. A New Large Load that has not brought new generation could, in theory, register as a Demand Resource, avoid the earlier IRAS tranche, and move into the later Demand Resource tranche. It could improve its position in the sequential load-dump stack through a contractual arrangement rather than through the procurement of distinct incremental supply. The question is not whether Demand Resources provide reliability value. Properly structured and verifiable demand response can provide substantial benefits to the system, including demand resources offered by New Large Load. Rather, the question is whether a New Large Load’s participation in Demand Response should change the curtailment priority proposed by PJM under IRAS.
6 Application at 101.7 Application at 80.
PDF page 10
10
This tension can be resolved by creating a new category of Demand Resources consisting of New Large Load that elects to utilize its own curtailment capability as BYONC. The Commission should, therefore, direct PJM to revise its proposed tariff to provide that, to the extent New Large Load utilizes new Demand Resources or new DER Capacity Aggregation Resources to satisfy the BYONC requirements, for purposes of load-curtailment sequencing those resources should be curtailed before other PJM demand-response resources. This conditional acceptance of PJM’s proposal would help maintain power availability for traditional manufacturers and industrial customers as grid conditions become constrained by the increasing load brought about by increasing data center demand in PJM.
V. THE COMMISSION SHOULD ENSURE ANY IRAS COMPENSATION IS JUST
AND REASONABLE AND RESERVE RETAIL COST RECOVERY QUESTIONS
FOR THE STATE COMMISSIONS.
Finally, the Commission should fully evaluate whether PJM’s proposal to offer compensation at fifty (50) percent of the Non-Performance Charge Rate is just and reasonable.8 Under PJM’s IRAS proposal, a New Large Load’s obligation to curtail when required to protect reliability is a condition of receiving earlier service. PJM’s own framework is premised on allowing qualifying large loads to connect subject to operational controls, including curtailment during specified system conditions, in order to protect customers from potential outages.9 The Commission should carefully evaluate the appropriate compensation scheme for New Large Loads that are complying with an IRAS curtailment condition that permits such New Large Loads to connect and energize earlier than the grid may otherwise permit.
Further, OELC respectfully submits that the Commission should avoid approving a structure whereby existing industrial and manufacturing customers will subsidize any such
8 Proposed Tariff, Attachment DD-4, § X(a); Application at 102.9 Application at 15-16.
PDF page 11
11
curtailment credits or payments. Instead, the Commission should reserve for the relevant state authorities or commissions with jurisdiction over retail terms and conditions of service how such compensation obligations are ultimately recovered from retail customers.
VI. CONCLUSION AND REQUEST FOR RELIEF.
OELC does not oppose new load connecting to the PJM system or the development of mechanisms that protect reliability while such load is integrated. To the contrary, reliable service is essential to OELC’s members and to Ohio’s manufacturing and industrial economy. OELC’s concern is that the IRAS framework must not threaten domestic manufacturing and should preserve an appropriate allocation of responsibility. Accordingly, OELC respectfully requests that the Commission condition its approval of PJM’s tariff on the adoption of the recommendations set forth in these comments and limited protests.
Date: September 3, 2026
Respectfully submitted,
/s/ David F. Proaño
David F. Proaño (Counsel of Record)
Benjamin A. Kurtz
BAKER & HOSTETLER LLP
127 Public Square, Suite 2000
Cleveland, OH 44114
216-621-0200 / Fax 216-696-0740
Email: dproano@bakerlaw.com
Email: bkurtz@bakerlaw.com
*Willing to Accept Service by Email*
COUNSEL FOR OHIO ENERGY
LEADERSHIP COUNCIL
PDF page 12
CERTIFICATE OF SERVICE
I hereby certify that on this third day of September 2026, I served the foregoing document by electronic means on each person listed on the Federal Energy Regulatory Commission’s official service list in Docket No. ER26-3515-000.
chum@wrightlaw.com;
collins@wrightlaw.com;
craig.glazer@pjm.com;
mark.stanisz@pjm.com;
jesse.jacobe@pjm.com;
neil@persistenceanalyticsgroup.com;
Suzette.Krausen@monitoringanalytics.com;
jeffrey.mayes@monitoringanalytics.com;
Joseph.Bowring@monitoringanalytics.com;
dmabry@mwn.com;
sbruce@mcneeslaw.com;
lhuff@mwn.com;
NancyB@epsa.org;
blipman@rpa.nj.gov;
dwand@rpa.nj.gov;
rglover@rpa.nj.gov;
dlayugan@rpa.nj.gov;
morris.schreim@maryland.gov;
joey.chen@maryland.gov;
Ransom.Davis@Maryland.gov;
dslifer@gtpowergroup.com;
gthomas@gtpowergroup.com;
laurac@chappelleconsulting.net;
scott.metzger@ilag.gov;
kimberly.janas@ilag.gov;
andrew.obeso@ilag.gov;
susan.satter@ilag.gov;
aleksandar.mitreski@brookfieldrenewable.com;
nathalie.godard@brookfieldrenewable.com;
OBustami@mintz.com;
sshparber@mintz.com;
emily.starobin@huschblackwell.com;
linda.walsh@huschblackwell.com;
emmanix.simon@edf-re.com;
temujin.roach@edf-re.com;
paul.youchak@bpu.nj.gov;
steven.chaplar@law.njoag.gov;
8
john.decker@kirkland.com;
cassidy.hall@kirkland.com;
Jennifer.Mansh@talenenergy.com;
sco@vitol.com;
bja@vcrenewables.com;
enc@vitol.com;
enc@vitol.com;
sco@vitol.com;
/s/ David F. Proaño
David F. Proaño
Counsel of Record