Comments and Limited Protests of Ohio Energy Leadership Council in response to the Interim Resource Adequacy Service and Large Load Registry proposed by PJM…
Text extracted from the eLibrary original (SHA-256 c11081e82db91eda…). Download the original from the official source.
Contents · 6 sections
- I. SUMMARY OF COMMENTS AND LIMITED PROTESTS.
- II. OELC’S INTEREST AND EXPERIENCE.
- III. PJM SHOULD ADOPT A SEPARATE 150 MW THRESHOLD FOR NON-DATA-
- IV. THE SEQUENTIAL LOAD-REDUCTION STACK PROPOSED BY PJM SHOULD
- V. THE COMMISSION SHOULD ENSURE ANY IRAS COMPENSATION IS JUST
- VI. CONCLUSION AND REQUEST FOR RELIEF.
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Cost allocation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
ER26-3515-000 COMMENTS AND LIMITED PROTESTS OF OHIO ENERGY LEADERSHIP COUNCIL Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (the “Commission”), Ohio Energy Leadership Council (“OELC”) respectfully submits these comments and limited protests…Read this passage Filed comments: Registry access
I. SUMMARY OF COMMENTS AND LIMITED PROTESTS.
printed heading · Topic match: Reliability and curtailment
Accordingly, OELC respectfully requests that the Commission condition any acceptance of PJM’s IRAS proposal on the following: 1.Read this passage Filed comments: Reliability and curtailment
II. OELC’S INTEREST AND EXPERIENCE.
printed heading · Topic match: Reliability and curtailment
OELC and its members have direct, long-standing experience with the practical effects of utility tariffs, rate design, energy legislation, and regulatory policy on Ohio businesses that must manage significant energy consumption and exposure to volatile energy costs.Read this passage Filed comments: Reliability and curtailment
III. PJM SHOULD ADOPT A SEPARATE 150 MW THRESHOLD FOR NON-DATA-
printed heading · Topic match: Cost allocation
PJM proposes to define a Large Load as an end-use customer load with a cumulative peak load of 50 MW or greater at a single electrical site.1 OELC does not oppose a definition that identifies the extraordinary new load additions producing the resource-adequacy concerns underlying IRAS.Read this passage Filed comments: Cost allocation
IV. THE SEQUENTIAL LOAD-REDUCTION STACK PROPOSED BY PJM SHOULD
printed heading · Topic match: Reliability and curtailment
PJM proposes to add IRAS as a category of load reduction that precedes Demand Resources and DER Capacity Aggregation Resources in that sequence.6 That sequencing is integral to the proposed incentive structure.Read this passage Filed comments: Reliability and curtailment
V. THE COMMISSION SHOULD ENSURE ANY IRAS COMPENSATION IS JUST
printed heading · Topic match: Reliability and curtailment
PJM’s own framework is premised on allowing qualifying large loads to connect subject to operational controls, including curtailment during specified system conditions, in order to protect customers from potential outages.9 The Commission should carefully evaluate the appropriate compensation…Read this passage Filed comments: Reliability and curtailment
VI. CONCLUSION AND REQUEST FOR RELIEF.
printed heading
OELC’s concern is that the IRAS framework must not threaten domestic manufacturing and should preserve an appropriate allocation of responsibility.Read this passage
CERTIFICATE OF SERVICE
printed heading
ER26-3515-000. chum@wrightlaw.com; collins@wrightlaw.com; craig.glazer@pjm.com; mark.stanisz@pjm.com; jesse.jacobe@pjm.com; neil@persistenceanalyticsgroup.com; Suzette.Krausen@monitoringanalytics.com; jeffrey.mayes@monitoringanalytics.com; Joseph.Bowring@monitoringanalytics.com; dmabry@mwn.com;…Read this passage