ER26-3515-000 · 2026-09-03 · American Electric Power Corporation

Comments and Request for Clarification of American Electric Power Service Corporation re PJM Interconnection, LLC’s proposed revisions to the PJM Open…

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000

COMMENTS AND REQUEST FOR CLARIFICATION
OF AMERICAN ELECTRIC POWER SERVICE CORPORATION

American Electric Power Service Corporation, on behalf of its affiliates
Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power
Company, Kingsport Power Company, Ohio Power Company, and Wheeling Power
Company (collectively, “AEP”), submits the following comments to and request for clarification of PJM Interconnection, LLC’s (“PJM’s”) proposed tariff revisions to the PJM Open Access Transmission Tariff (“PJM Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) proposed in the above-captioned docket to establish Interim Resource Adequacy Service (“IRAS”) effective October 12, 2026 (the “IRAS Proposal”).1

I. EXECUTIVE SUMMARY
AEP recognizes that PJM faces a significant tightening of its Reliability Pricing Model (“RPM”) capacity market in recent years and subsequent resource adequacy shortfalls, and supports PJM taking action to mitigate the associated reliability risks.  AEP seeks narrow clarifications on certain aspects of the IRAS Proposal that impose

1 PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim Res. Adequacy Serv. and A Large Load Registry to Address Sys. Reliability, Docket No. ER26-3515 (filed Aug. 13, 2026) (“IRAS Proposal”).  AEP filed a doc-less motion to intervene in the captioned docket on August 17, 2026.

PDF page 2

2
requirements on entities that utilize the Fixed Resource Requirement Alternative (“FRR”) to satisfy their obligations under the RAA to commit Unforced Capacity to ensure reliable service to FRR loads in the PJM Region.2

Most of AEP’s affiliate load serving entities (“LSEs”) in the PJM Region use the FRR Alternative.  While IRAS itself does not apply to loads in FRR service areas, the IRAS Proposal includes a rule that restricts FRR Entities from utilizing Existing Generation Capacity Resources to meet the capacity obligations of New Large Load within FRR service areas unless the Existing Generation Capacity Resource is procured prior to a set date.3  The goal of this restriction is to ensure that FRR Entities cannot poach capacity from the RPM market during periods of capacity shortfall.4

Consistent with that goal, AEP requests a few points of clarification to ensure that the IRAS Proposal does not discriminate between FRR load and RPM load in its efforts to mitigate reliability risk during capacity shortfall periods in the RPM market.  First, as described in section III.B, the IRAS Proposal allows for IRAS to be active during periods of RPM capacity shortfall and to go dormant during periods of sufficient capacity in RPM.5 AEP seeks clarification that when IRAS goes dormant, the IRAS Proposal’s restrictions on FRR entities also go inactive.6  Second, the IRAS Proposal allows for IRAS to reactivate

2 Proposed RAA, Schedule 8.1, section D.1.  These comments solely address the aspects of the IRAS Proposal that affect FRR Entities and should not be construed as an endorsement of any specific provision of the IRAS Proposal applicable to RPM load.
3 Id. section D.1.1.
4 PJM Transmittal Letter at 73-74.
5 See infra section III.B.
6 See infra section IV.A.

PDF page 3

3
after a dormant period when PJM is again facing an RPM capacity shortfall.7  When IRAS reactivates, it redefines the load that IRAS can restrict based on a new in-service date— only Large Loads that go into service after the new in-service date will be subject to IRAS.8 AEP seeks clarification that when IRAS reactivates, the restrictions on using Existing Generation Capacity Resources also reset to an updated cutoff date.9  Finally, when IRAS reactivates, the reactivation determination is made just a few months before the service becomes active again.10  For FRR Entities, the effect is an extremely short timeline to comply with the IRAS Proposal’s restrictions on FRR Capacity Plans.11  AEP seeks clarification that there will be a buffer period for FRR Entities to develop compliant FRR Capacity Plans upon IRAS reactivation.12  If these clarifications are not made and the IRAS Proposal is implemented, the proposal will be unjust, unreasonable, and unduly discriminatory.  Accordingly, absent the clarifications that AEP seeks, the Commission should condition any approval of the IRAS on fixing these issues consistent with the comments below.13

7 See infra section III.B.
8 Id.
9 See infra section IV.B.
10 See infra section III.C; section IV.C.
11 See infra section IV.C.
12 Id.
13 Id.

PDF page 4

4
II. CORRESPONDENCE AND COMMUNICATIONS
Correspondence regarding this filing should be sent to the following individuals, who should be placed on the official service list in this proceeding:14 John C. Crespo

Senior Legal Counsel
American Electric Power Service
Corporation
1 Riverside Plaza
Columbus, OH  43215
(614) 716-3727
jccrespo@aep.com

William M. Keyser
Megan McDowell
Steptoe LLP
1330 Connecticut Avenue, NW
Washington, DC  20036
202-429-8186
wkeyser@steptoe.com
mmcdowell@steptoe.com

III. BACKGROUND
A. AEP
American Electric Power Company, Inc. is one of the largest investor-owned electric public utility holding companies in the United States.  Its electric utility companies provide generation, transmission, and distribution services to more than five million customers in Arkansas, Indiana, Kentucky, Louisiana, Michigan, Ohio, Oklahoma, Tennessee, Texas, Virginia, and West Virginia.  It also partially owns entities that own transmission facilities in states outside of its service territories. American Electric Power Company, Inc.’s affiliates Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, and Wheeling Power Company are load serving entities (“LSEs”) in PJM.  Accordingly, American Electric Power Service Corporation is a party

14 AEP respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) (2026) to allow more than two individuals to be designated for service on the official service list in this proceeding.

PDF page 5

5
to PJM’s Reliability Assurance Agreement on behalf of these LSE affiliates.  Of these operating companies, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, and Wheeling Power Company are FRR Entities, meaning they utilize the FRR Alternative under the RAA to satisfy their RAA obligations to commit Unforced Capacity to ensure reliable service to loads in the PJM Region.  Thus, as FRR Entities, these companies do not satisfy their capacity obligations through the RPM and its auctions.  Rather, they supply their capacity needs from owned or contracted capacity resources and provide FRR Capacity Plans in advance of each Delivery Year demonstrating that they have sufficient Unforced Capacity to serve their load obligations, including satisfying the applicable reserve margin requirements.

B. IRAS
IRAS is a proposed service that will allow for Large Loads15 to interconnect in PJM without bringing their own capacity, on the condition that “they must reduce their load or switch to on-site backup resources under specific, limited emergency conditions.”16  New Large Loads17 can avoid being subject to IRAS reductions by bringing their own new capacity or procuring capacity through the Reliability Backstop Procurement.

15 Proposed RAA, Article 1 – Definitions (defining Large Load): “Large Load” shall mean end-use customer(s) load that has a cumulative peak load of 50 megawatts or greater at a single electrical site behind one or more points of interconnection, where for configurations involving multiple affiliated load facilities or multiple points of interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-mile radius will be considered a single electrical site as further described in the PJM Manuals.
16 PJM Transmittal Letter at 39 (footnote omitted).
17 See infra section III.C.1, reproducing proposed definition of New Large Load in the Proposed PJM Tariff.

PDF page 6

6
IRAS will only apply during multi-year periods where there are insufficient resources to reliably meet demand in real time operations, as defined in the proposed tariff changes.18  During those periods, IRAS will enable PJM to reduce loads in zones/areas where New Large Loads have not otherwise covered their capacity needs (the New Large Loads that can be reduced under IRAS are considered “Eligible New Large Loads”19).  The IRAS Proposal sets these “active” IRAS periods based on RPM auction results:  (1) IRAS begins as active in the coming 2027/2028 delivery year, (2) if three consecutive years pass where the RPM auction clears sufficient capacity to meet the capacity requirement,20 IRAS goes dormant, (3) then, if the RPM auction fails to clear sufficient capacity for the third incremental auction in advance of a delivery year,21 IRAS reactivates for the upcoming delivery year.  Upon reactivation, IRAS stays active until the capacity market meets conditions to go dormant, as set forth in proposed Attachment DD-4, section IV(b)(iii). The IRAS Proposal uses the proposed definition of New Large Load as the

mechanism to deactivate and reactivate IRAS.  IRAS obligations can only apply to eligible New Large Load.22  New Large Load is initially defined as Large Load with an in-service

18 PJM Transmittal Letter at 1, 39-40. 19 “Eligible New Large Loads shall mean a New Large Load eligible to provide Interim Resource Adequacy Service in accordance with Tariff, Attachment DD-4, section V.”  Proposed PJM Tariff, Definitions (defining Eligible New Large Loads); see Proposed PJM Tariff, Attachment DD-4, section V(b).
20 The IRAS Proposal details the conditions for IRAS dormancy in proposed Attachment DD-4, section IV(b)(iii).
21 The IRAS Proposal details the conditions for IRAS reactivation in proposed Attachment DD-4, section IV(b)(iii).
22 See infra section III.C.1, reproducing proposed definition of New Large Load in the Proposed PJM Tariff; see PJM Transmittal Letter at 40-41, 69 (footnotes omitted).

PDF page 7

7
date after June 1, 2027.23  After three consecutive years of sufficient capacity clearing the RPM auction,24 the relevant in-service date for the definition of New Large Load resets.  It becomes June 1 of the next delivery year where sufficient capacity does not clear the RPM auction.25  Thus, there can be a time period where there is no load that meets the definition of New Large Load, because the relevant in-service date for the definition of New Large Load is not June 1, 2027, and has not yet reset to a new date.  Under these circumstances, IRAS is effectively dormant because there is no defined load for the service to apply to. IRAS will apply to New Large Loads that satisfy their capacity requirements via the RPM auction process and PJM is not proposing to extend IRAS to New Large Loads located in FRR Service Areas.26  However, the IRAS Proposal does require that in an FRR Entity’s FRR Capacity Plan, any capacity planned to serve New Large Load must be owned or contracted by the FRR Entity prior to a specified date:  June 1, 2027.  For ease of reference, these comments will refer to this rule, which the IRAS Proposal proposes to effectuate via revisions to the RAA Schedule 8.1, section D.1.1, as the “FRR Capacity Rule.”

23 Id. at 38-40, 72 (footnotes omitted).
24 As detailed in proposed Attachment DD-4, section IV(b)(iii).
25 See section III.C.1, reproducing proposed definition of New Large Load in the Proposed PJM Tariff; see Proposed PJM Tariff, Attachment DD-4, section IV(b)(iii).
26 PJM Transmittal Letter at 73.

PDF page 8

8
C. AEP’s Comments Focus on Three Proposed Amendments in the IRAS Proposal

AEP’s comments and request for clarification of the IRAS Proposal focus on three specific proposed amendments to PJM’s governing documents:  the definition of New Large Load to be included in the PJM Tariff, section IV(b)(iii) of the new Attachment DD-4 to the PJM Tariff (which is referenced by the New Large Load definition and regulates when that definition is dormant and active), and the revised language in the RAA, Schedule 8.1, section D.1.1., which forms the FRR Capacity Rule.  These proposed amendments are reproduced below for ease of reference:

1. PJM Tariff Definitions, Definition of New Large Load
“New Large Load” shall mean end-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in- service after June 1, 2027, that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load.  However, to the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD- 4, section IV(b)(iii), then New Large Load shall mean end-use customer load that is either (a) a Large Load that goes into service after June 1 of the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met or (b) incremental load in-service after June 1 of the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load.

2. PJM Tariff Attachment DD-4, section IV(b)(iii)
In the event ([the amount of Capacity Resources committed for a given Delivery Year (as determined after the Third Incremental Auction) equals or exceeds the PJM Region Reliability Requirement determined prior to the Third Incremental Auction] divided by the Pool-wide Accredited UCAP Factor), then the Office of the Interconnection does not need any Eligible New Large Loads to be available to provide Interim Resource Adequacy Service for that Delivery Year.

PDF page 9

9
3. The FRR Capacity Rule:  RAA Schedule 8.1, section D.1.1
An FRR Entity may not include in its FRR Capacity Plan any MW quantity
of Existing Generation Capacity Resource27 in excess of what such FRR
Entity owned or contracted by such FRR Entity prior to June 1, 2027, to serve New Large Load.

IV. COMMENTS
A. PJM Should Clarify that FRR Requirements Are Intended to Mirror
the RPM Requirement Such That When IRAS is Dormant, the FRR
Capacity Rule is Also Dormant.
The IRAS Proposal provides a mechanism for IRAS to deactivate after three consecutive years of sufficient capacity clearing the RPM auction, as described above in section III.B.  PJM should clarify that the FRR Capacity Rule likewise deactivates when IRAS deactivates.  Since both the IRAS deactivation mechanism and the FRR Capacity Rule hinge on the definition of New Large Load, it should be evident that the FRR Capacity Rule is inactive when IRAS is inactive.  Nonetheless, an explicit clarification will ensure that no future FRR load is subject to capacity restrictions above and beyond those for RPM load.

27 See RAA, Article 1 – Definitions (defining Existing Generation Capacity Resource): “Existing Generation Capacity Resource” shall mean, for purposes of the must-offer requirement and mitigation of offers for any RPM Auction for a Delivery Year, a Generation Capacity Resource that, as of the date on which bidding commences for such auction:  (a) is in service; or (b) is not yet in service, but has cleared any RPM Auction for any prior Delivery Year.  A Generation Capacity Resource shall be deemed to be in service if interconnection service has ever commenced (for resources located in the PJM Region), or if it is physically and electrically interconnected to an external Control Area and is in full commercial operation (for resources not located in the PJM Region).  The additional megawatts of a Generation Capacity Resource that is being, or has been, modified to increase the number of megawatts of available installed capacity thereof shall not be deemed to be an Existing Generation Capacity Resource until such time as those megawatts
(a) are in service; or (b) are not yet in service, but have cleared any RPM Auction for any prior Delivery Year.

PDF page 10

10
The IRAS Proposal defines New Large Load as Large Load that goes into service after June 1, 2027.  However, once system conditions are met such that IRAS is no longer necessary, IRAS is deactivated.  When this happens, the definition of New Large Load becomes Large Load that goes into service after June 1 of the next Delivery Year that PJM faces capacity scarcity and IRAS must be reactivated.28

Under the proposed FRR Capacity Rule, “An FRR Entity may not include in its FRR Capacity Plan any MW quantity of Existing Generation Capacity Resource in excess of what such FRR Entity owned or contracted by such FRR Entity prior to June 1, 2027, to serve New Large Load.”  The final clause “to serve New Large Load” clearly modifies the entire sentence.  The inclusion of this phrase demonstrates that the FRR Capacity Rule should be read to only apply to New Large Load as it is defined at that time.  Accordingly, when IRAS is inactive, no new load will meet the definition of New Large Load.  In this circumstance, the FRR Capacity Rule would also effectively be inactive because there would be no identifiable New Large Load for the rule to apply to.

Although it is possible to determine via the proposed PJM Tariff and RAA amendment language that the FRR Capacity Rule is effectively dormant at the same time that IRAS is dormant, the Commission should clarify that this is the case to avoid any confusion in the future.  Without clarification that the FRR Capacity Rule goes dormant simultaneous with IRAS, this aspect of the IRAS Proposal is unjust, unreasonable, and unduly discriminatory because it could be used to treat RPM load and FRR load differently

28 See proposed definition of New Large Load; see proposed PJM Tariff, Attachment DD-4, section IV(b)(iii).

PDF page 11

11
without justification.  The FRR Capacity Rule, as described further below in section IV.B, is aimed at protecting the RPM market during periods of capacity scarcity in that market. PJM does not explain why the rule would continue to apply to FRR when capacity is not scarce.  Accordingly, PJM should clarify that AEP’s understanding of the rule is correct or the Commission should find the rule unjust and unreasonable and require PJM to modify it on compliance.

B. PJM Should Clarify that When the Relevant In-Service Date for the
Definition of New Large Load Resets, the Capacity Procurement
Deadline under the FRR Capacity Rule Also Resets.
The fixed date of June 1, 2027 in the FRR Capacity Rule is inconsistent with the flexible in-service date in the proposed definition of New Large Load.  PJM should clarify that when the in-service date for New Large Load resets, the procurement deadline for Existing Generation Capacity Resources under the FRR Capacity Rule likewise resets. PJM’s transmittal letter describes that the FRR Capacity Rule is proposed to ensure that “FRR Entities (or their New Large Loads) bring new capacity to the system to meet the New Large Loads’ resource adequacy needs, and precludes FRR Entities from satisfying load growth from New Large Loads with existing Capacity Resources that could potentially be lured from the RPM Auctions (and further exacerbating the shortage conditions in the capacity market).”29  Thus, the rationale for the FRR Capacity Rule appears to be to establish an obligation for FRR Entities that parallels the IRAS Proposal’s incentives for RPM load to bring its own new capacity.

29 PJM Transmittal Letter at 73-74 (alteration in original).

PDF page 12

12
Under the FRR Capacity Rule as drafted, however, an FRR Entity cannot use Existing Generation Capacity Resources that were procured after June 1, 2027 to serve New Large Load even when IRAS goes dormant and then reactivates.  Thus, as written, the FRR Capacity Rule creates a likely scenario where in future years, if IRAS reactivates after a period of dormancy and the relevant in-service date for the definition of New Large Load has been reset, FRR Entities are still restricted from using Existing Generation Capacity Resources to satisfy New Large Load capacity requirements unless those Existing Generation Capacity Resources were procured prior to June 1, 2027.  This outcome is inconsistent with the intent of the IRAS rule and, if left unclarified, would put FRR Entities at a clear disadvantage to entities participating in the RPM.

Accordingly, PJM should clarify that if the in-service date for New Large Load resets to June 1 of a future year, the cutoff date for procuring Existing Generation Capacity Resources under the FRR Capacity Rule also resets.  If the issue is not clarified, the IRAS Proposal will be unjust, unreasonable and unduly discriminatory with respect to the FRR Capacity Rule.  It will restrict FRR Entities to a greater extent than it would restrict RPM load.  Furthermore, such an inconsistent approach would thwart the aligned, parallel approach to FRR and RPM large load capacity that PJM describes in its transmittal letter as the justification for the novel restriction on the historic ability of FRR Entities to plan holistically for the capacity needs of their loads.

PDF page 13

13
C. PJM Should Clarify How FRR Entities Can Comply with Their
Obligations Under the FRR Capacity Rule After IRAS is Reactivated.
PJM should clarify that an FRR Entity can comply with the FRR Capacity Rule during years where IRAS is reactivated because the IRAS Proposal, as written, does not appear to provide sufficient notice for an FRR Entity to develop a compliant FRR Capacity Plan to provide for New Large Loads in reactivation years.

Under the IRAS Proposal, if IRAS goes dormant, the determination of whether IRAS reactivates in a future delivery year is made pursuant to outcome of the final RPM auction for that delivery year, the Third Incremental Auction.30  This auction occurs only three to four months before the start of the delivery year.31  As described above in section IV.A, the mechanism for IRAS to go dormant and to reactivate is the definition of New Large Load and, because the FRR Capacity Rule hinges on its applicability to New Large Load, the FRR Capacity Rule should go dormant and reactivate at the same time as IRAS.32 Thus, in a year where IRAS reactivates, the FRR Capacity Rule should also reactivate. However, as drafted, the FRR Capacity Rule appears to leave FRR Entities with only three to four months to ensure that their FRR Capacity Plan to serve New Large Load complies with the rule.  This timeline will be difficult, if not impossible, for FRR Entities to comply with because FRR Capacity Plans take years to develop.  FRR Entities must first submit their FRR Capacity Plan for a delivery year at least one month before the Base

30 Proposed PJM Tariff, Attachment DD-4, section IV(b)(iii).
31 PJM Interconnection, L.L.C., PJM Manual 18:  PJM Capacity Mkt., § 5.2, at 122 (rev. 62 Dec. 17, 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m18.ashx.
32 As explained in section IV.A, FERC should clarify that this is the correct interpretation of the IRAS Proposal.

PDF page 14

14
Residual Auction for that delivery year, which occurs three years before the delivery year commences.33  The FRR Capacity Plan is then extended and updated annually.34  Compared to the usual multi-year timeline to develop an FRR Capacity Plan, three to four months is unrealistically short and would put FRR Entities at a severe disadvantage to RPM customers, who are able to comply with IRAS requirements on a shorter time frame. RPM load can comply with the IRAS Proposal requirements on a short time frame because they can comply either by (1) bringing their own new capacity or Reliability Backstop Procurement capacity, or by (2) being subject to IRAS reductions.  FRR load, however, can only comply with the IRAS proposal by providing sufficient capacity, because FRR load is not subject to IRAS.  FRR Entities are therefore disadvantaged by arbitrarily being placed in jeopardy of noncompliance as a result of the IRAS rules in reactivation years.

Also, if the issue described in section IV.B above is not clarified and the FRR Capacity Rule restricts the use of Existing Generation Capacity Resources to only the resources procured before June 1, 2027, this will exacerbate the detrimental effects of the unreasonably short timeline for FRR Entities to develop a compliant FRR Capacity Plan, because they will be further restricted as to which capacity resources can be used to meet the capacity requirements of New Large Load.

33 Proposed RAA, Schedule 8.1, section D.1; PJM Manual 18, § 5.2, at 121.
34 Proposed RAA, Schedule 8.1, section D.1.

PDF page 15

15
To address these time constraints, PJM should clarify that upon reactivation, there is a one-year delay for the FRR Capacity Rule.  For example:  assume the IRAS is dormant entering 2035 for the prior delivery year but the Third Incremental Auction that occurs in February 2035 does not meet the conditions of Attachment DD-4, section IV(b)(iii) (i.e., does not clear sufficient capacity).  Under the IRAS Proposal, this would reactivate IRAS for the upcoming 2035/2036 delivery year and the definition of New Large Load would employ an in-service date of June 1, 2035.  Accordingly, under the IRAS Proposal, the FRR Capacity Rule would apply to New Large Load—that is, Large Load that goes into service after June 1, 2035.  Thus, under the FRR Capacity Rule, an FRR Entity would not be able to include in its FRR Capacity Plan any MW quantity of Existing Generation Capacity Resource in excess of what such FRR Entity owned or contracted by such FRR Entity prior to June 1, 2035, to serve New Large Load.35  This essentially gives the FRR Entity a short, three to four month period to contract with necessary supply to serve New Large Load.  This is simply not a reasonable amount of time to do so and puts FRR at a significant disadvantage to the rest of the PJM market.  Accordingly, in this example, FRR Entities should not have to comply with the FRR Capacity Rule until the start of the 2036/2037 delivery year, and should have an additional year to procure the necessary Existing Generation Capacity Resources to serve New Large Load.  This will provide approximately sixteen months for FRR Entities to develop a compliant capacity plan for

35 This statement assumes the requested clarification in section IV.B is accepted and the cutoff date becomes flexible, no longer fixed at June 1, 2027, but that the cutoff date is the same date as the IRAS reactivation date instead of providing a one-year delay as this section requests.

PDF page 16

16
New Large Load (which would still, in this example, be Large Load with an in-service date of June 1, 2035 or later).  The FRR Capacity Rule would restrict FRR Entities from using Existing Generation Capacity Resources that the FRR Entity procured after June 1, 2036, and would still provide the safeguards contemplated by the IRAS proposal at that time. Thus, upon reactivation, the FRR Capacity Rule would recognize that compliance with the rule reasonably requires more time than compliance with IRAS.

1. This Issue Compounds if the FRR Capacity Rule Cutoff Date for
Existing Generation Capacity Resources Remains Fixed at June
1, 2027.
If the issue described in section IV.B above is not clarified, and the FRR Capacity Rule restricts the use of Existing Generation Capacity Resources to only such resources procured before June 1, 2027—even far into the future after a period of IRAS dormancy— then an FRR Entity may have already included Existing Generation Capacity Resources in their FRR Capacity Plan before it is determined that IRAS is reactivating for the upcoming delivery year.  During IRAS dormancy, an FRR Capacity Plan may be submitted prior to the Base Residual Auction (three years prior to the delivery year),36 and such a plan may utilize Existing Generation Capacity Resource that the FRR Entity procured after June 1, 2027 to fulfill the capacity requirements of upcoming Large Load additions that will, if IRAS is reactivated after the Third Incremental Auction, be deemed New Large Load.37  In

36 PJM Manual 18 § 5.2, at 121.
37 This also raises a potential conflict with the Takings Clause of the Fifth Amendment, because FRR Entities would be restricted from utilizing their investment in the Existing Generation Capacity Resources they procured after June 1, 2027, with the reasonable expectation of using the procured capacity in their FRR Capacity Plan to serve upcoming large load additions.  The Takings Clause of the Fifth Amendment provides that “private property [shall not] be taken for public use, without just compensation.”  Regulatory takings occur where the government “imposes regulations that restrict an owner’s ability to use his own

PDF page 17

17
such a situation, the FRR Entity would be out of compliance with the FRR Capacity Rule as soon as IRAS (and the FRR Capacity Rule) is reactivated.  This is clearly not the intent of the IRAS proposal.  At a minimum, this issue should be addressed by clarifying the proposal is intended to operate as discussed in section IV.B and providing that FRR Capacity Rule’s cutoff date for procuring Existing Generation Capacity Resources resets along with the in-service date for New Large Load.

2. If PJM does not clarify this issue, the IRAS Proposal is unjust
and unreasonable.
If PJM does not clarify that FRR Entities can comply with the FRR Capacity Rule in delivery years where IRAS reactivates after a dormant period, the IRAS Proposal is unjust, unreasonable and unduly discriminatory because it places FRR Entities at a significant disadvantage, as discussed above.

V. CONCLUSION
AEP respectfully requests that PJM clarify under its IRAS Proposal:  (1) that the FRR Capacity Rule will go dormant when IRAS goes dormant, (2) that the cutoff for procuring Existing Generation Capacity Resources under the FRR Capacity Rule will reset when the New Large Load in-service date resets, and (3) that FRR Entities can comply with the FRR Capacity Rule in years when the rule “reactivates” following a period of IRAS being dormant.

property” but goes too far.  Cedar Point Nursery v. Hassid, 594 U.S. 139, 148 (2021).  A key consideration in evaluating whether a regulatory taking has occurred is the regulation’s interference with reasonable investment-backed expectations.  Penn Central Transportation Co. v. New York City, 438 U. S. 104, 124- 125 (1982).

PDF page 18

18

John C. Crespo
Senior Legal Counsel
American Electric Power Service
Corporation
1 Riverside Plaza
Columbus, OH  43215
(614) 716-3727
jccrespo@aep.com

Respectfully submitted,

/s/ William M. Keyser
William M. Keyser
Megan McDowell
Steptoe LLP
1330 Connecticut Avenue, NW
Washington, DC  20036
202-429-8186
wkeyser@steptoe.com
mmcdowell@steptoe.com

Counsel for AEP

Dated:  September 3, 2026

PDF page 19

19
CERTIFICATE OF SERVICE

Pursuant to Rule 2010, 18 C.F.R. § 385.2010, I hereby certify that I have this day caused the foregoing document to be served upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Washington, D.C. on this 3rd day of September, 2026.

/s/ Jeannette Crooks
Jeannette Crooks
Steptoe LLP
1330 Connecticut Avenue, NW
Washington, DC 20036