ER26-3515-000 · 2026-09-03 · American Electric Power Corporation

Comments and Request for Clarification of American Electric Power Service Corporation re PJM Interconnection, LLC’s proposed revisions to the PJM Open…

Text extracted from the eLibrary original (SHA-256 52564462eb456718…). Download the original from the official source.

Contents · 10 sections
  1. I. EXECUTIVE SUMMARY p. 1
  2. II. CORRESPONDENCE AND COMMUNICATIONS p. 4
  3. III. BACKGROUND p. 4
  4. B. IRAS p. 5
  5. C. AEP’s Comments Focus on Three Proposed Amendments in the IRAS p. 8
  6. IV. COMMENTS p. 9
  7. A. PJM Should Clarify that FRR Requirements Are Intended to Mirror p. 9
  8. B. PJM Should Clarify that When the Relevant In-Service Date for the p. 11
  9. C. PJM Should Clarify How FRR Entities Can Comply with Their p. 13
  10. V. CONCLUSION p. 17

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Registry access · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.
Read this passage Filed comments: Reliability and curtailment

I. EXECUTIVE SUMMARY

printed heading · Topic match: Registry access

EXECUTIVE SUMMARY AEP recognizes that PJM faces a significant tightening of its Reliability Pricing Model (“RPM”) capacity market in recent years and subsequent resource adequacy shortfalls, and supports PJM taking action to mitigate the associated reliability risks.
Read this passage Filed comments: Registry access

II. CORRESPONDENCE AND COMMUNICATIONS

printed heading

CORRESPONDENCE AND COMMUNICATIONS Correspondence regarding this filing should be sent to the following individuals, who should be placed on the official service list in this proceeding:14 John C.
Read this passage

III. BACKGROUND

printed heading

Accordingly, American Electric Power Service Corporation is a party 14 AEP respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) (2026) to allow more than two individuals to be designated for service on the official service list in this proceeding. 5 to PJM’s Reliability Assurance Agreement on…
Read this passage

B. IRAS

printed heading · Topic match: Reliability and curtailment

IRAS will apply to New Large Loads that satisfy their capacity requirements via the RPM auction process and PJM is not proposing to extend IRAS to New Large Loads located in FRR Service Areas.26 However, the IRAS Proposal does require that in an FRR Entity’s FRR Capacity Plan, any capacity planned…
Read this passage Filed comments: Reliability and curtailment

C. AEP’s Comments Focus on Three Proposed Amendments in the IRAS

printed heading · Topic match: Reliability and curtailment

PJM Tariff Definitions, Definition of New Large Load “New Large Load” shall mean end-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in- service after June 1, 2027, that increases the existing end-use customer load at a single…
Read this passage Filed comments: Reliability and curtailment

IV. COMMENTS

printed heading

IV.
Read this passage

A. PJM Should Clarify that FRR Requirements Are Intended to Mirror

printed heading · Topic match: Connecting load and generation

A Generation Capacity Resource shall be deemed to be in service if interconnection service has ever commenced (for resources located in the PJM Region), or if it is physically and electrically interconnected to an external Control Area and is in full commercial operation (for resources not located…
Read this passage Filed comments: Connecting load and generation

B. PJM Should Clarify that When the Relevant In-Service Date for the

printed heading · Topic match: Reliability and curtailment

PJM Should Clarify that When the Relevant In-Service Date for the Definition of New Large Load Resets, the Capacity Procurement Deadline under the FRR Capacity Rule Also Resets.
Read this passage Filed comments: Reliability and curtailment

C. PJM Should Clarify How FRR Entities Can Comply with Their

printed heading

This will provide approximately sixteen months for FRR Entities to develop a compliant capacity plan for 35 This statement assumes the requested clarification in section IV.B is accepted and the cutoff date becomes flexible, no longer fixed at June 1, 2027, but that the cutoff date is the same date…
Read this passage

V. CONCLUSION

printed heading

CONCLUSION AEP respectfully requests that PJM clarify under its IRAS Proposal: (1) that the FRR Capacity Rule will go dormant when IRAS goes dormant, (2) that the cutoff for procuring Existing Generation Capacity Resources under the FRR Capacity Rule will reset when the New Large Load in-service…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. on this 3rd day of September, 2026. /s/ Jeannette Crooks Jeannette Crooks Steptoe LLP 1330 Connecticut Avenue, NW Washington, DC 20036