Protest of Google LLC regarding PJM Interconnection, L.L.C.’s Interim Resource Adequacy Service and Large Load Registry proposal
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
Docket No. ER26-3515-000
PROTEST OF GOOGLE LLC
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Google LLC (“Google”) hereby submits this protest regarding PJM Interconnection, L.L.C.’s (“PJM”) Interim Resource Adequacy Service (“IRAS”) and Large Load Registry proposal.
Google’s concerns with IRAS center on the proposed mechanism, not the underlying objectives. Specifically, Google agrees that New Large Loads that do not bring sufficient new capacity to offset their expected demand should be subject to curtailment prior to other firm wholesale customers during tight system conditions, ensuring service to residential and other commercial customers remains reliable. Consistent with this principle, a longstanding and foundational pillar of Google’s energy procurement philosophy has been that Google should enable sufficient new capacity to meet its energy demand.
IRAS would stymie that goal. It would inject fresh uncertainty into PJM, threatening desperately needed investments to build out the region’s generation fleet. The fundamental flaw in IRAS is PJM’s proposal to assign general curtailment obligations to Electric Distributors (“EDs”) with New Large Loads that do not bring new capacity, despite lacking jurisdiction over how EDs execute those curtailments.. Consequently, in the event of a shortage, New Large Loads
1 18 C.F.R. § 385.211 (2026).
PDF page 2
-2-
that bring new capacity—and spend billions of dollars doing so—could still be curtailed before those that do not. PJM cannot resolve this basic misalignment because curtailment priority among end users is a quintessential retail ratemaking question that only states have the authority to implement under the Federal Power Act (“FPA”).
Nevertheless, because of that misalignment, IRAS creates a clear risk that New Large Loads that invest billions of dollars to bring their own new capacity—i.e., the purported means of avoiding curtailment under IRAS——will, in fact, not avoid it. By penalizing the very behavior it seeks to incentivize, IRAS directly undercuts its own foundational premise. That regulatory disconnect makes it extremely risky for Google and similarly situated customers to invest in new PJM capacity unless and until states enact prompt laws or regulations establishing consistent curtailment protections. Ultimately, the result of IRAS will be less investment in new capacity in PJM—the exact opposite of what the region needs. Accordingly, the Commission should emphatically reject a proposal that would actively deter the capacity investments PJM so urgently needs.
In addition, IRAS violates the FPA in several different respects. It exceeds the Commission’s jurisdiction, it is unduly discriminatory, and it is unjust and unreasonable. Any of those significant shortcomings would be sufficient, on its own, to overturn a Commission approval on appeal. The long shadow of uncertainty caused by litigation over a program with such obvious shortcomings will further sap the confidence necessary for companies like Google to deploy the capital needed to develop the gigawatts (“GW”) of new generation that PJM demands. IRAS is a deeply flawed approach in light of the many, superior ways of addressing the concerns that motivated PJM to pursue IRAS in the first place. Specifically, because the curtailment issue is a quintessential question of state law, PJM should pursue an actual program
PDF page 3
-3-
of “cooperative federalism” through which it uses its position as operator of the wholesale market to empower the states to effectuate curtailment priorities that meet their public policy priorities, including, for example, a preference for New Large Loads that bring their own new capacity. This would avoid the legal risk and uncertainty that would throttle investment in new generation capacity while providing a clear path to pursuing the goals purportedly underlying this proceeding. Moreover, there are several additional options, such as demand response reforms, to unlock the flexibility that data centers and other large loads can provide under the appropriate circumstances that could further improve PJM’s capacity position without the problems that IRAS presents. Accordingly, for the reasons that follow, the Commission should accept the Large Load Registry (the only legally defensible part of PJM’s proposal), while rejecting IRAS and directing PJM onto a different, more sustainable path that will actually improve resource adequacy in the region to the benefit of all stakeholders, including retail customers.
I. WHO WE ARE
Google’s mission is to organize the world’s information and make it universally accessible and useful. AI is critical to that mission. Data centers are the infrastructure that make AI possible, and electricity is the fuel that powers them. To serve Google’s customers, data center infrastructure consumes a large amount of electricity and requires reliable electric service to operate. As Google’s business grows, so too does its demand for reliable, affordable, and clean electricity.
II. PROTEST
A. IRAS Will Not Incentivize New Large Loads to Bring Their Own New Capacity
Google agrees with the principle that ostensibly underlies IRAS. Namely, New Large Loads that connect to the transmission system should be incentivized to bring new capacity to the region to cure resource adequacy shortcomings; those that do not should be curtailed at the
PDF page 4
-4-
appropriate time. If the Commission agrees with that principle, it should reject IRAS. That is because PJM legally cannot ensure that New Large Loads that utilize the Bring Your Own New Capacity (“BYONC”) pathway will receive firm service and not be curtailed, as PJM itself acknowledges.2 Instead, it is the states that have “‘exclusive jurisdiction’ . . . to ensure that the appropriate retail customers, i.e., New Large Loads, including data centers—and not residential customers or small industrial customers—are reduced when system conditions call for PJM to require load reductions.”3 PJM is explicit that it has no authority to ensure that New Large Loads get the purported benefit of the IRAS “bargain” (firm service), explaining that it is “leaving it to [EDs], in coordination with the appropriate states and/or [Relevant Electric Retail Regulatory Authorities, (“RERRAs”)], [Load Serving Entities, (“LSEs”)], and LSE customers to determine which loads should ultimately reduce subject to IRAS.”4
States might curtail loads in the order that PJM envisions, but there is no guarantee. A state could create its own retail curtailment scheme that reflects entirely different considerations than IRAS. For example, a state could establish a curtailment priority that gives effect only to new capacity within the state or that meets certain other limiting characteristics. Or, alternatively, a state may curtail a New Large Load that brings new capacity in favor of other retail customers, including data centers, that are deemed too important to be curtailed. In short, it is impossible to
2 Compare PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515, at 2 (filed Aug. 13, 2026) (“Transmittal”)Transmittal at 2 (“New Large Loads can avoid this condition on taking transmission service by bringing new capacity to the system.”), with Transmittal at 87 (“[W]hile PJM will determine the quantity of MW that load in a zone/area will need to be reduced by to maintain system reliability in the PJM Region, states may determine—under their own laws, policies, and definition of what constitutes ‘large load’—which resources will be called on to reduce load.”). 3Id. at 90-914 Id. at 92.
PDF page 5
-5-
know whether the states will implement IRAS as PJM expects because “the curtailment protocol was not developed with [relevant state actors’] input.”5
As a result, IRAS severely undermines any incentive to invest in new generation. If entities are going to spend billions of dollars to offset curtailment risk by bringing their own new capacity, and improve the region’s resource adequacy shortfall, they need some assurance that they will, in fact, receive firm service and will not be curtailed whenever conditions are tight. To be clear: Google is prepared to invest the billions of dollars necessary to ensure that its New Large Loads bring adequate new capacity. Maintaining regional resource adequacy has been and remains a longstanding and foundational pillar of Google’s energy procurement philosophy. 6 But Google cannot responsibly do so without some assurance that it will receive firm retail service in exchange for those investments, particularly where PJM’s proposal threatens to unwind firm service for facilities that have already executed firm Energy Service Agreements (“ESAs”). Without that assurance—which, again, PJM is legally precluded from providing—BYONC is a gamble, not an investment.
And that is not the only source of uncertainty inherent in IRAS. As explained below, IRAS has several glaring legal flaws. As PJM’s own staff recognized when it recommended against pursuing the previous—albeit substantially similar—iteration of IRAS, the inevitable litigation that follows such a legally infirm proposal will be significant and ultimately undermine the
5 PJM Interconnection, L.L.C., Answer of the Pennsylvania Public Utility Commission in support of the Organization of PJM States, Inc.’s motion for extension of time, Docket No. ER26-3515-000, at 2 (filed on Sep. 1, 2026). 6 See, e.g., Google, The Clean Transition Tariff, https://www.gstatic.com/marketing- cms/1f/d3/00f64e2c4f4f92e8e34ed8ef1e2c/clean-transition-tariff-ctt.pdf (last visited Sept. 1, 2026).
PDF page 6
-6-
program’s ability to achieve its purported objectives.7 Inevitable litigation coupled with IRAS’s obvious legal flaws will cast a pall of uncertainty over the contracting for and development of new capacity in PJM for as long as this proceeding and the resulting appeals continue. The best thing that the Commission could do to create certainty and facilitate investment in new long-term capacity is to reject IRAS emphatically (while accepting the Large Load Registry) and have PJM promptly produce a proposal that complies with the FPA. Anything short of that will only deepen the current resource adequacy insecurity in PJM.
PJM’s attempt to justify IRAS with analogies to various constructs that the Commission has accepted cannot bear the weight PJM puts on them. For example, the Southwest Power Pool’s (“SPP”) “large load integration construct”—which includes SPP’s High Impact Large Load Generation Assessment (“HILLGA”)8—is an inapt comparison that only highlights IRAS’s faulty premise. Under HILLGA, new generation paired with an electrically proximate large load can opt to interconnect to SPP’s system on an expedited basis in exchange for interconnection service that is limited in ways explicitly spelled out in the SPP tariff.9 And because SPP has authority over generator interconnection in the region, it can actually deliver the promised benefits of HILLGA. In this way, entities considering deploying capital in SPP know exactly what they are getting if they participate in HILLGA, which is essential for unlocking investment on the scale needed to bolster resource adequacy. IRAS does not offer comparable predictability because PJM has no authority over which retail loads are curtailed.10 As noted above, this means that large loads in
7 See PJM Interconnection, L.L.C., CIFP Connect & Manage: PJM Stage 4 Proposal Executive Summary (June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630- item-02a---pjm-stage-4-proposal---connect-and-manage---executive-summary.pdf. 8 Transmittal at 21-22 n. 64 (citing Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026)).9 Sw. Power Pool, Inc., 194 FERC ¶ 61,031 at P 8.10 See Transmittal at 85 (“[T]oday Electric Distributors select, consistent with their state programs, which loads to reduce in response to a PJM load reduction directive. . . . PJM is not looking to change any existing approach.
PDF page 7
-7-
PJM could invest billions of dollars to develop new generation only to be curtailed by an ED that has no obligation to prioritize service to New Large Loads that bring their own new capacity. Google has already committed to “build, bring, or buy the new generation resources and electricity needed to satisfy their new energy demands, paying the full cost of those resources whether by building, or buying from, new or otherwise additive power plants.”11 And it is not alone. Indeed, there is no shortage of offtakers willing to enter long-term contracts for new capacity, provided that they have certainty over the benefits that they will receive in return. PJM should focus on providing that certainty rather than undermining the otherwise favorable investment conditions for companies that stand ready to make the commitments that will actually bring new capacity to the region.
B. IRAS Violates the FPA
IRAS is also illegal for three independent reasons. First, it aims at and targets the retail sphere, in violation of the FPA’s division of jurisdiction. Second, it is unduly discriminatory because it treats entities that are functionally identical for the purposes of the wholesale market differently without any legally relevant basis for doing so. Suffice it to say, discrimination on the basis of legally irrelevant characteristics can never be “due.” Finally, it is unjust and unreasonable because PJM would charge customers for capacity that it never intends to procure or that those customers, by design, can never use.
Currently, the manner in which an Electric Distributor reduces load is a function of their state-approved contracts and state-approved curtailment and load reduction plans.”).
11 The White House, Ratepayer Protection Pledge (Mar. 4, 2026), https://www.whitehouse.gov/releases/20 26/03/ratepayer-protection-pledge/.
PDF page 8
-8-
1. IRAS Exceeds the Commission’s Jurisdiction
IRAS exceeds the Commission’s jurisdiction because it targets particular retail customers: “New Large Loads.” FPA Section 201(b) “‘limit[s] FERC’s sale jurisdiction to that at wholesale,’ reserving regulatory authority over retail sales (as well as intrastate wholesale sales) to the States.”12 “FERC cannot take an action transgressing that limit no matter how direct, or dramatic, its impact on wholesale rates.”13 To respect that limit, FERC and entities like PJM are prohibited from taking actions that “aim[]” at or “target” particular retail consumers or the retail market generally.14 Instead, as relevant here, a Commission order adheres to the FPA’s jurisdictional divide only where “every aspect of the regulatory plan happens exclusively on the wholesale market and governs exclusively that market’s rules.”15
IRAS violates that principle. FERC cannot approve tariff provisions where retail consumers are the “target at which [those tariff provisions] aim.” 16 IRAS breaks that rule because it targets retail customers by assigning the wholesale curtailment obligation based on the size (i.e., more than 50 MW) and vintage (i.e., in-service date and ramp rate) of the relevant retail customers.17 In so doing, the proposal makes the characteristics of the retail customer, not that of the ED, LSE, or Eligible Customer, or any other Commission-jurisdictional entity or transaction, the basis for imposing a curtailment obligation. It thus explicitly determines the
12 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 279 (2016) (“EPSA”) (quoting New York v. FERC, 535 U.S. 1, 6 (2002)).13 Id. at 280.14 Id. at 282 (quoting Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015) “Oneok”)).15 Id. 16 Oneok, 575 U.S. at 385; see EPSA, 577 U.S. at 282.17 Transmittal at 6.
PDF page 9
-9-
quality of wholesale service based on the characteristics of retail customers, and, as explained below, that is no accident or side effect of IRAS; it is the entire reason we are here. 18 Compare that “target[ing]” of individual retail customers to what PJM is not doing.
Although PJM suggests that the policy problem it is trying to solve is capacity shortages driven by new load growth,19 under IRAS, PJM would not determine an ED’s curtailment obligations based on its rate of load growth. Consider a hypothetical where one ED’s annual load grows by 200 MW through ten separate 20 MW industrial facilities, while another ED’s load grows by only 100 MW driven by one single data center. Assume none of the loads bring their own new capacity. The first ED would not be subject to curtailment while the second ED would, despite having half the load growth of the first. That differential treatment confirms that it is not the ED’s load growth that is the focus of IRAS, but rather the specific retail customers that make up that load growth that matters. To put it mildly, this is not a regulation where “every aspect of the regulatory plan happens exclusively on the wholesale market and governs exclusively that market’s rules.” 20 Rather, IRAS is unlawfully “tethered” to the retail markets and specific retail consumers21—most prominently, new data centers.22
18 Cf. Corner Post, Inc. v. Bd. of Governors of Fed. Rsrv. Sys., 603 U.S. 799, 815 (2024) (“As this Court has repeatedly stated, the text of a law controls over purported legislative intentions unmoored from any statutory text.”); Keister v. AARP Benefits Comm., 410 F. Supp. 3d 244, 257 (D.D.C. 2019) (“[I]t is well established that extrinsic evidence may not be relied upon to show the subjective intent of the parties absent ambiguity in the contract’s language.” (cleaned up)).
19 See, e.g., Transmittal at 99, 124. 20 EPSA, 577 U.S. at 282. 21 Cf. Hughes v. Talen Energy, Mktg. LLC, 578 U.S. 150, 166 (2016) (state’s action to encourage development of certain generation resources cannot be tethered to the resource’s wholesale market participation).22 PJM’s own transmittal letter confirms that the target of IRAS is specific retail customers. See, e.g., Transmittal at 17 (explaining that, as directed by the PJM Board, one of the elements of PJM’s proposal is that “IRAS will be applicable to ‘[N]ew Large Loads that, as of June 1, 2027, do not bring sufficient capacity to serve their resource adequacy needs and cannot otherwise be served at the 1-in-10 reliability standard[.]”).
PDF page 10
-10-
PJM’s arguments to the contrary are barred by governing Supreme Court precedent. PJM briefly claims that, as in EPSA, the policy question at issue is one the FPA’s drafters “could not have anticipated.”23 But novel circumstances are not an excuse to rewrite a statute.24 PJM does not and cannot even assert that it satisfies EPSA’s requirement that the regulation “addresses—and addresses only—transactions occurring on the wholesale market.”25 Nor does it help that, after determining that an ED must “reduce load by a certain MW quantity” based on the characteristics of its retail customers, PJM then leaves it to the ED and state to implement the reduction across its customers.26 Although PJM attempting to direct reductions on a customer-by-customer basis would provide another reason why IRAS is unlawful, the fact that things could be more jurisdictionally infirm does not immunize PJM’s already-unlawful proposal to condition curtailment obligations on retail customer characteristics, rather than consumer-neutral load and capacity considerations. The plan still targets and is tethered to specific retail consumers and thus exceeds PJM’s jurisdiction.27
Similarly, it is no answer for PJM to assert that IRAS’s targeting of data centers is justified because they make up the vast majority of load growth. While that is true, the fact that certain retail customers are having an outsized effect on the wholesale market does not give the Commission license to target those customers any more than it gives it license to target “markets in all electricity’s inputs—steel, fuel, and labor most prominent among them—[based on how they]
23 Transmittal at 91.24 Cf. Oklahoma v. Castro-Huerta, 597 U.S. 629, 649 (2022) (refusing to “rewrite a constitutionally valid statutory text under the banner of speculation about what Congress might have done had it faced a question that ... it never faced”).25 EPSA, 577 U.S. at 282; see Transmittal at 91 (drawing comparison to EPSA as to whether the policy need was anticipated, but not whether the regulation only addresses wholesale transactions).26 Transmittal at 92.27 Oneok, 575 U.S. at 385; see EPSA, 577 U.S. at 282.
PDF page 11
-11-
affect generators’ supply of power.”28 Rather, as discussed above, the Commission must restrict its program of regulation to the wholesale market, no matter how significantly certain retail customers’ demand might affect that market and make retail regulation a tempting target for the Commission.
Finally, although PJM characterizes its proposal as “a product of cooperative federalism,” it is, in fact, quite the opposite. Cooperative federalism is rooted in the concept that the federal entity need not, and should not, exercise the full extent of its authority when addressing issues that affect both federal and state interests. For example, in EPSA, while the Commission claimed that it could negate state decisions prohibiting retail consumers from making wholesale demand response bids, it “chose not to do so in recognition of the linkage between wholesale and retail markets and the States’ role in overseeing retail sales.” That was a scheme of cooperative federalism in “which the States retain[ed] the last word.” Here, by contrast, PJM has created a scheme that it lacks the authority to carry out and so it has, instead, unilaterally foisted onto the states the responsibility for implementing IRAS without consulting with them on the program’s design.29 The principle of cooperative federalism does not describe a program that would have the federal government exceed its authority and then leave it to the states to resolve the resulting complexities.
2. IRAS Is Unduly Discriminatory
IRAS is unduly discriminatory for similar reasons. The FPA categorically prohibits undue discrimination, which occurs when similarly situated entities are treated differently
28 EPSA, 577 U.S. at 277-78.29 See PJM Interconnection, Answer of the Pennsylvania Public Utility Commission in support of the Organization of PJM States, Inc.’s motion for extension of time, Docket No. ER26-3515-000, at 2 (filed on Sep. 1, 2026) (“The curtailment protocol was not developed with PA PUC’s input, and it may impinge upon our jurisdiction over retail rates.”).
PDF page 12
-12-
without good reason.30 When evaluating whether resources are similarly situated, it is not enough for those resources to be different in any respect; rather, they must be different with respect to the inquiry at hand.31 As explained above, the only differences between EDs that receive curtailment orders under IRAS and those that do not are the characteristics of their retail customers, which are outside Commission jurisdiction and thus legally irrelevant to the question of whether two entities are similarly situated for the purposes of the FPA. Receiving differing levels of Commission-jurisdictional service based on legally irrelevant differences is unduly discriminatory.
But even if PJM could consider the characteristics of retail customers when making curtailment decisions, IRAS would still be unduly discriminatory because it discriminates amongst EDs for reasons that have nothing to do with the resource adequacy concerns PJM is trying to address.
First, under IRAS, PJM would issue curtailment directives to EDs based on the size of individual new loads rather than the aggregate amount of new demand in a zone. It is the aggregate growth that causes a resource adequacy challenge, not the load growth of only a subset of customers. To slightly revise the example from the previous section, if a hypothetical ED’s load grows by 200 MW due to ten 20 MW loads, it would have no curtailment exposure under IRAS. If another hypothetical ED’s load grows by 200 MW based on a single data center, all the incremental load would be subject to IRAS despite having identical load growth to the first ED. PJM has not explained how such disparate treatment can be justified under the FPA.
30 Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th 265, 282 (D.C. Cir. 2022).31 See Xcel Energy Servs., Inc. v. FERC, 41 F.4th 548, 559-60 (D.C. Cir. 2022).
PDF page 13
-13-
In addition, IRAS is unduly discriminatory because of the manner in which it treats New Large Loads differently than existing large loads. One MW of load contributes identically to a reliability requirement shortfall regardless of its in-service date. Analogous D.C. Circuit and FERC precedent calls for treating new and continuing customers alike.32 Nevertheless, PJM defines a “New Large Load” as having an in-service (or incremental-ramp) date after June 1, 2027. This means that a 500 MW load interconnected in the first half of 2027 would not trigger a curtailment directive to its ED, but a 500 MW load interconnected in the second half of the year would. This would be true even though the earlier-in-time load contributes equally to any resource adequacy shortfall as the later-in-time load. PJM, which bears the burden for justifying its section 205 proposal, has not explained why large loads that interconnect after June 1, 2027, warrant differential treatment from those that interconnect before that date, which is reason alone to reject PJM’s filing.
3. IRAS Is Unjust and Unreasonable
Last but not least, IRAS is also unjust and unreasonable for two independent reasons. First, PJM is proposing to charge customers for a service that it never intends to procure. Specifically, PJM proposes to exclude from the Variable Resource Requirement Curve (i.e., the capacity market demand curve) New Large Loads that do not bring their own new capacity, meaning that it would, by definition, not procure capacity to serve them, even if that capacity is available. Nevertheless, PJM proposes to charge the LSEs that will service those same New Large Loads for a share of the capacity (even though none of that capacity will have been procured for them). Being forced to pay money for nothing is not just and reasonable or consistent with cost causation.
32 See BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).
PDF page 14
-14-
PJM justifies this novel intervention in the interaction of supply and demand by arguing that it would help ensure that residential and other existing commercial customers’ rates do not increase when New Large Loads connect to the grid.33 To be clear: Google supports that aim unequivocally. That is why Google signed the Ratepayer Protection Pledge and, as explained above, Google is firmly committed to procuring new capacity sufficient to cover its demand. 34 But breaking supply and demand fundamentals by ignoring the demand that PJM itself expects to materialize is not a reasonable way to further that critical goal. Most obviously, it violates the FPA’s cost causation principle, which provides that the costs allocated to an entity must be “roughly commensurate” to the benefits it receives.35 Cost causation and the statutory requirement to roughly equate benefits and costs does not permit PJM to assign costs to entities that are structurally precluded from receiving the corresponding benefits. The fact that New Large Loads that are curtailed under IRAS might36 receive a credit in their retail rates certainly cannot retroactively undo PJM’s decision to forgo procuring capacity, but then still charge customers as if it had, in fact, procured capacity to serve them.
In addition, ignoring demand to make the market clear is yet another significant intrusion into the market fundamentals and resulting price signals that, in theory, are the reason the
33 Transmittal at 23-24. 34Amanda Peterson Corio, Supporting the White House Ratepayer Protection Pledge: Google's Approach for Responsible Energy Growth, Google: The Keyword (Mar. 4, 2026), https://blog.google/innovation-and- ai/infrastructure-and-cloud/global-network/affordability-pledge-responsible-energy-growth/.35 See Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022); Long Island Power Auth. v. FERC, 27 F.4th 705, 714-15 (D.C. Cir. 2022); Neb. Pub. Power Dist. v. FERC, 957 F.3d 932, 939-41 (8th Cir. 2020); Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1260-62 (D.C. Cir. 2018); K N Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992).36 There is no guarantee that New Large Loads that are curtailed under IRAS will be compensated for those curtailments, because “how the compensation scheme will work in practice relies on application of state retail law. Whether a specific New Large Load may be entitled to compensation for provision of IRAS will be determined by state authorities under state law or [Relevant Electric Retail Regulatory Authorities] as may be applicable.” Transmittal at 106 (footnote omitted)).
PDF page 15
-15-
Reliability Pricing Model (“RPM”) exists.37 In the very short term, PJM’s proposed capacity market may help achieve the laudable goal of insulating residential and other existing retail customers from the price effects of large load additions—a goal that, as noted, Google firmly supports. But it does so only by further balkanizing the market and turning it into a construct that bears ever-less connection to the economic forces it is supposed to harness. Nominal reliance on a market-based construct that is in reality untethered to market forces is a recipe for prolonging PJM’s current resource adequacy crisis or ending up in another one in the future. And that is exactly what IRAS would do by removing known, forecasted demand from the RPM with the explicit goal of reducing resource procurement and resulting capacity prices. PJM would, once again, be muting the demand signal and forcing capacity prices to a level that is lower than what is needed to attract investment in new generation. That, in turn, threatens the region’s long-term resource adequacy and is inconsistent with PJM’s own statement that the RPM should “reflect actual supply and demand fundamentals.”38
Second, IRAS would require EDs with New Large Loads that do not bring their own new capacity to contribute to the cost of new demand response capacity resources, but curtail the associated EDs before those demand response resources are dispatched. In other words, under IRAS, New Large Loads would pay for demand response resources to serve as capacity and yet, when system conditions warrant it, those New Large Loads would be curtailed before demand response resources are ever dispatched. This defies basic logic: no one would buy an umbrella on the condition that it must be surrendered the moment it rains, yet that is precisely what PJM demands here.
37 Id. at 115 (indicating that the RPM should “reflect actual supply and demand fundamentals”).38 Id.
PDF page 16
-16-
Google reiterates that it is committed to bringing new capacity and supporting legal and durable solutions for ensuring that large loads do not raise rates or undermine service for residential customers and other existing customers. Google strongly supports competitive wholesale markets and believes that they are a highly effective means of developing new supply while protecting customers from unnecessary costs. But functioning markets require adherence to market fundamentals. A market design that, like IRAS, undermines the basic principles on which markets depend is neither just and reasonable nor a viable tool for ensuring resource adequacy, reliability and affordability.
C. A Lawful and Durable Framework Can Protect Residential Customers While
Preserving Incentives for Large Loads to Bring New Capacity
Accepting IRAS would be an egregious misstep because there are ample alternative avenues through which PJM, in cooperation with the States, could facilitate the goals underlying IRAS, rather than impede them.
First, with the appropriate data management and confidentiality guarantees, the Commission should accept PJM’s proposed Large Load Registry as it would provide much needed transparency without the jurisdictional concerns inherent in IRAS. Second, PJM should reform its wholesale demand response rules39 to unlock the flexibility that large loads are capable of providing. As explained below, Google has been a pioneer in unlocking data centers’ latent flexibility. And Google has consistently advocated for demand response reforms at PJM to make data center-driven demand response a pillar of the solution to the resource adequacy challenges associated with rapid load growth. Breaking down the barriers to demand response supplied by data centers would go a long way to resolving the resource adequacy challenge that motivated PJM
39 Which, unlike the retail customers that are the target of IRAS, is a matter within the Commission’s exclusive jurisdiction. EPSA, 577 U.S. 260.
PDF page 17
-17-
to pursue IRAS in the first place. Finally, PJM should (on its own or at the direction of the Commission) develop a method for facilitating state interruptible load tariffs. As explained above, the question of which retail customers should reduce their demand in the face of a resource adequacy shortfall is fundamentally a retail ratemaking question that only the states can address. 40 Rather than pursuing a convoluted methodology like IRAS in an effort to circumvent that basic jurisdictional fact, PJM should embrace it. In so doing, it could implement an actual “program of cooperative federalism” in which the states design the interruptible load tariffs and PJM provides the wholesale-market support that it is uniquely positioned to administer.
The Data Center Coalition has already presented PJM with such a durable State Opt-In framework coupled with immediate improvements to existing emergency load-shed procedures.41 Below, Google offers principles that should guide the Commission and PJM on the path to ensuring that the region maintains resource adequacy and reliability in the face of rising demand.
1. The Commission Should Accept the Large Load Registry, Which Will
Facilitate Cooperative Federalism
As a threshold matter, the Commission should accept the Large Load Registry. The Registry is a common-sense mechanism for providing both PJM and states with the information they need to carry out their respective responsibilities related to resource adequacy and reliability and, as it is informational in nature, it does not present the same jurisdictional concerns as the rest of the IRAS filing. For PJM in particular, the Large Load Registry would be an important step towards improving the region’s load forecast, which will help ensure that the region is procuring
40 Supra § II.B.1.
41 Letter from Kelsey Bagot, Chair, Va. State Corp. Comm’n & Josh Levi, President & CEO, Data Center Coal., to Paula Conboy, PJM Bd. of Managers & David Mills, President & CEO, PJM Interconnection, L.L.C. (June 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260630-va-scc- and-data-center-coalition-letter-re-cifp-connect-manage-reliability-backstop-procurement.pdf.
PDF page 18
-18-
the appropriate quantities of capacity and making the appropriate long-term investments in transmission infrastructure, including through PJM’s regional transmission planning process. Although PJM has taken steps over the last year to improve its load forecasting,42 more is needed, and the Large Load Registry would be a meaningful step in that regard. In addition, the transparency the Registry would provide aligns directly with the transparency measures that the Commission required in the PJM Show Cause Order, allowing states greater visibility into the large load matters affecting their jurisdictions.
The Commission has the authority to accept only the Large Load Registry. PJM has
consented to severing “any element of the proposed Tariff and RAA language to the extent necessary and permitted under FPA section 205 and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching objectives in this filing.”43 For the reasons explained above, accepting the Large Load Registry and severing the remainder of the proposal would be consistent with PJM’s goals of improving resource adequacy in the region while ensuring that service to existing residential customers remains reliable.44 And doing so is consistent with the Commission’s “passive and reactive” role under section 205 of the FPA45 and its authority to accept in part and reject in part a filing, provided that it does not create a whole new rate.4642 See, e.g., Reliability Technical Conference, Pre-Technical Conference Remarks of Jason Connell, Vice President, Planning, PJM Interconnection, L.L.C., Docket No. AD25-8-000 Attach. 1 (filed Oct. 17, 2025) (summarizing PJM’s recent load forecasting processes and enhancements).43 Transmittal at 9 (footnote omitted).44 Id. at 59 (“The purpose of the BYONC construct is to incent New Large Loads to facilitate the development of new capacity so that the PJM Region has sufficient capacity to maintain reliability without entering into a capacity shortage and/or having to shed existing native load customers.”). 45 NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114 (D.C. Cir. 2017).46 See, e.g., See El Paso Nat. Gas Co., L.L.C. v. FERC, 966 F.3d 842, 863 (D.C. Cir. 2020) (discussing the analogous Section 4 of the Natural Gas Act and explaining that “FERC can alter a proposed rate and remain in a
PDF page 19
-19-
2. PJM Should Reform Demand Response to Unlock the Resource Adequacy
Value of Large Loads and Other Flexible Demand
Before implementing unprecedented and unworkable new curtailment regimes like IRAS, PJM should focus on making the most of the flexibility that can be provided through more familiar and jurisdictionally sound avenues, such as wholesale market demand response.
PJM’s current demand response regime sidelines significant quantities of flexible load. That is because it presents them with a stark choice: either be available to curtail at any time, with no limits on how long curtailments can last or receive no capacity value for the more limited flexibility they can reliably provide. But demand response rules in PJM do not need to be an all- or-nothing proposition. Instead, PJM should establish bounded demand response products with defined availability parameters and accredit those products to reflect participating loads’ marginal contribution to reliability. Doing so could unlock substantial new demand-side capability. Reforming demand response is a commonsense path to ensuring that existing residential and other existing retail customers continue to receive reliable service. During the CIFP process, PJM expressed concern that dispatching demand response more frequently to address the reliability effects of load growth could lead to demand response attrition. But if some existing resources cannot perform under PJM’s current availability requirements when called upon, the answer is not to develop an unworkable and illegal curtailment scheme for involuntarily curtailing certain large loads—i.e., IRAS. Rather, PJM should create demand response products that require loads to curtail less frequently in exchange for a lower capacity value, which would facilitate voluntary curtailments and unlock the capacity needed to maintain resource adequacy.
Section 4 proceeding as long as its change represents at least partial approval of the change for which the pipeline itself petitioned” (internal quotation marks omitted)).
PDF page 20
-20-
Google has been a pioneer among data centers in developing the capability to reduce demand, particularly for Artificial Intelligence (“AI”) and Machine Learning (“ML”) workloads, in response to stressed grid conditions.47 Earlier this year, Google announced 1 GW of executed contracts for demand response capability with utility partners across the United States, including PJM member utility Indiana Michigan Power.48 These executed agreements represent contractually obligated data center demand-side capacity commitments to reduce demand during defined stressed system conditions.
Yet PJM’s current rules regarding demand response make it difficult—and, in many cases, impossible—for entities that own and operate large loads to realize the potential flexibility that it can provide the grid. This problem is not unique to data centers. Many commercial and industrial customers can reduce demand for defined periods or under defined conditions but cannot commit to effectively unbounded interruptions without jeopardizing their underlying operations or customer commitments. For data centers, most capacity is used to support enterprise and other cloud-based functions that demand high up times and predictable compute availability. For those functions, suddenly dropping offline in response to high power prices simply is not an option. The prospect of unpredictable and uncapped curtailment events for data centers when the services they provide are most in demand is not a way to unlock the flexibility that they can provide. The same basic constraint applies across industries: flexibility can be valuable even if it is not unlimited. Demand response rules that require effectively unbounded availability risk leaving substantial
47 Michael Terrell, How We’re Making Data Centers More Flexible to Benefit Power Grids, Google: The Keyword (Aug. 4, 2025), https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/how-were- making-data-centers-more-flexible-to-benefit-power-grids/.48 Michael Terrell, A New Milestone for Smart, Affordable Electricity Growth, Google: The Keyword (Mar. 19, 2026), https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/demand-response-data- center-milestone/.
PDF page 21
-21-
flexibility on the sidelines rather than capturing the reliability value these customers can actually provide.
To unlock this flexibility, PJM should supplement its existing demand response offerings with a bounded product that allows loads to commit to defined availability parameters, such as maximum hours per year, maximum hours per event, and maximum event frequency. Existing Demand Resources that can meet PJM’s broader availability requirements should remain able to do so and receive the corresponding capacity value. But other loads may be able to provide substantial reliability value under more limited parameters. For Google, defined parameters would allow it to translate load-reduction obligations to PJM into predictable service-level commitments to customers that rely on its infrastructure, rather than exposing those customers to effectively unbounded interruption risk. Providing both bounded and unbounded options would allow PJM to capture a broader range of load flexibility, with each resource accredited based on the reliability value of the commitment it actually makes.
In addition, PJM should make a firm service level construct explicitly available as an option for resources participating in a bounded demand response product. A firm service level would allow a participating load to make a clear, measurable commitment to reduce consumption to a specified level when called upon, rather than measuring performance against a baseline established months or years in advance. This approach can be particularly valuable for rapidly growing loads undergoing multi-year ramps, for which historical or projected baselines may not accurately reflect actual consumption at the time of an event. PJM’s existing tariff and Business Practice Manuals already provide for a firm service level construct, but Google understands that its use has been limited to date. Google recognizes and agrees that resources electing more limited availability parameters, such as a cap on hours, should receive correspondingly lower accreditation than
PDF page 22
-22-
resources committing to broader availability. But within those defined parameters, the resource would make a firm capacity commitment and be fully accountable for performing when called. The result would be accreditation that reflects the reliability contribution the resource can actually and reliably provide, while expanding the pool of demand-side resources available to PJM. Google has pushed hard for rules that put these principles into practice in order to maximize the flexibility that data centers can provide to the grid. At the outset of the first Critical Issues Fast Path to address Large Load Additions (“CIFP”) in August of 2025, Google “encourage[d] the Board and PJM to pursue reforms to existing [demand response] rules that enable any flexible load, particularly from data center loads, to participate in PJM’s markets.”49 Similarly, Google subsequently joined Amazon, Calpine, Constellation, Microsoft, and Talen on a joint proposal that, among other things, would have created two new limited demand response products better aligned with the operational capabilities of data centers.50 And as a member of the Data Center Coalition, Google supported the CIFP proposal of the Data Center Coalition, Governors, Exelon, and PPL, which introduced a new, voluntary flexible demand response product that would allow load to offer to be flexible in a range of options for a limited number of hours each day, for a total of 24 to 240 total hours each year.51 Those approaches offered legally durable pathways for unlocking
49 PJM Interconnection, L.L.C., Critical Issue Fast Path – Large Load Additions: Stakeholder Comments (Aug. 28, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/postings/20250828-stakeholder- comments-cifp-lla.pdf.50 Amazon, Calpine, Constellation, Google, Microsoft & Talen, Joint Stakeholder Package: PJM CIFP – Large Load Additions, Stage 4 (Nov. 19, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/cifp- lla/2025/20251119/20251119-item-02c---joint-stakeholder-package--executive-summary.pdf.51 Governors, Data Center Coalition, Exelon Corp. & PPL Corp., Joint Proposal for CIFP LLA: Load Forecasting, Enhanced Demand Flexibility, BYOG (Nov. 19, 2025), https://www.pjm.com/- /media/DotCom/committees-groups/cifp-lla/2025/20251119/20251119-item-02d---data-center-coalition-governors- exelon-and-ppl-package---executive-summary.pdf.
PDF page 23
-23-
large quantities of additional capacity, especially from the data center driven load growth causing PJM to pursue measures like IRAS in the first place.
3. The Commission Should Order PJM to Create a Program of Genuine
Cooperative Federalism that Relies Upon State-Approved Interruptible Load
Tariffs
As explained above, the question at the heart of this proceeding—which retail customers should be disconnected from the grid in the event demand exceeds supply—is one that is within exclusive state jurisdiction. On that point, Google agrees with PJM.52 Rather than fight that fact or attempt to bootstrap its way into regulating matters under exclusive state jurisdiction, PJM should embrace the limits of the FPA and develop an actual “program of cooperative federalism” that supports states in pursuing the goals that purportedly underlie IRAS. To do so, PJM should establish protocols pursuant to which it would send a signal under certain, defined conditions to disconnect retail customers that take service under state interruptible large load tariffs pursuant to the rules and priorities established under those tariffs.
Those tariffs could resemble the model state interruptible tariff that the Virginia State Corporation Commission and the Data Center Coalition have committed to develop.53 The key features should include customer eligibility and classification criteria, the circumstances and procedures for interruption, applicable service rights and obligations, and other associated tariff provisions. And, in particular, states could establish service arrangements under which New Large
52 Transmittal at 90-91 (“At bottom, ‘exclusive jurisdiction’ rests with the states to ensure that the appropriate retail customers, i.e., New Large Loads, including data centers—and not residential customers or small industrial customers—are reduced when system conditions call for PJM to require load reductions according to IRAS.” (footnote omitted)).53 Letter from Kelsey Bagot, Chair, Va. State Corp. Comm’n & Josh Levi, President & CEO, Data Center Coal., to Paula Conboy, Chair, PJM Bd. of Managers & David Mills, President & CEO, PJM Interconnection, L.L.C. (June 30, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260630- va-scc-and-data-center-coalition-letter-re-cifp-connect-manage-reliability-backstop-procurement.pdf.
PDF page 24
-24-
Loads that bring sufficient new capacity, consistent with PJM’s definition of BYONC, receive firm service while those that do not are subject to interruption.
A program structured in this way would provide a durable and effective path to realize the goals underlying IRAS without the self-defeating uncertainty that IRAS would create. PJM would determine whether and where load reductions are necessary to maintain bulk-system reliability; States and EDs would establish the rules determining which retail customers are subject to interruption and the priority among those customers. In that way, an approach along these lines could function similarly to IRAS with one notable exception: Because these state tariffs would actually establish the curtailment priority—something that IRAS cannot do, as explained above— they would provide the certainty needed for companies like Google to make the multi-billion dollar commitments necessary to develop needed new capacity. In addition, because an approach along these lines would rely on curtailment priorities memorialized by states, it would address the undue discrimination created by determining the quality of wholesale service based on the legally irrelevant characteristics of retail customers. By addressing these legal flaws, an approach along these lines would also help to address the uncertainty created by the considerable litigation risk that IRAS creates—i.e., the risk that led PJM’s own staff to recommend against it in the first place.54
In addition, to complement this approach, PJM could consider reforms to its manual load dump procedures to reflect the specific reliability challenges of certain large loads under stressed grid conditions. Today, under PJM’s emergency procedures, if it determines that load must be
54 See PJM Interconnection, L.L.C., CIFP Connect & Manage: PJM Stage 4 Proposal Executive Summary (June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630- item-02a---pjm-stage-4-proposal---connect-and-manage---executive-summary.pdf.
PDF page 25
-25-
shed for reliability reasons, it issues a broad load-shed directive that is allocated across all affected EDs.55 But, because large loads are concentrated in certain parts of PJM, that approach can require EDs with little or no large load to shed residential customers even when substantial large-load reductions are available elsewhere. Google believes that is an inequitable outcome and PJM should develop practices to avoid it, if at all possible. One potential approach is to establish a new phase of manual load dump whereby PJM would first call upon large loads enrolled in an initial load-shed phase before issuing a broader load shed directive. PJM would only issue its broader load-shed directive if the load reductions from the initial load shed phase were insufficient to mitigate system conditions. States, working with their EDs, would identify which customers to include as eligible for curtailment under this initial load dump phase. Customers could also be permitted to participate voluntarily under state law, and Google would commit to participating in such a process to identify those conditions and circumstances. An approach along these lines would insulate residential and other customers from reliability risk associated with large-load growth, while still respecting jurisdictional bounds.
III. CONCLUSION
IRAS would undermine its own aims. Instead of enhancing resource adequacy, it would perpetuate uncertainty and stymie the investment necessary to develop new capacity in PJM. The Commission must put PJM on a better course. It should focus on unlocking the flexibility that data centers can provide while developing an actual program of cooperative federalism that would create the conditions necessary for companies like Google to make the multi-billion investments needed to ensure resource adequacy, both in the near term and the long run.
[Signatures on next page]
55 See PJM Manual 13, section 5.
PDF page 26
-26-
Respectfully submitted,
/s/ Brian George
Brian George
Sr. Lead, US Energy Markets
Elizabeth Savage
Strategic Negotiator
Google LLC
655 New York Ave., NW
Washington, DC 20001
(202) 999-0990
briangeorge@google.com
eomsavage@google.com
Matthew Christiansen
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
mchristiansen@wsgr.com
bshpall@wsgr.com
Counsel for Google LLC
Dated: September 3, 2026
PDF page 27
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.
Dated: September 3, 2026
Washington, DC
/s/ Bryan Shpall
Bryan Shpall
Wilson Sonsini Goodrich & Rosati1700 K
Street NW
Fifth Floor
Washington, DC 20006
bshpall@wsgr.com