Protest of Google LLC regarding PJM Interconnection, L.L.C.’s Interim Resource Adequacy Service and Large Load Registry proposal
Text extracted from the eLibrary original (SHA-256 81292f60c4a218be…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Specifically, because the curtailment issue is a quintessential question of state law, PJM should pursue an actual program -3- of “cooperative federalism” through which it uses its position as operator of the wholesale market to empower the states to effectuate curtailment priorities that meet…Read this passage Filed comments: Reliability and curtailment
I. WHO WE ARE
printed heading
WHO WE ARE Google’s mission is to organize the world’s information and make it universally accessible and useful.Read this passage
II. PROTEST
printed heading
II.Read this passage
A. IRAS Will Not Incentivize New Large Loads to Bring Their Own New Capacity
printed heading · Topic match: Reliability and curtailment
If entities are going to spend billions of dollars to offset curtailment risk by bringing their own new capacity, and improve the region’s resource adequacy shortfall, they need some assurance that they will, in fact, receive firm service and will not be curtailed whenever conditions are tight.Read this passage Filed comments: Reliability and curtailment
B. IRAS Violates the FPA
printed heading · Topic match: Reliability and curtailment
Most obviously, it violates the FPA’s cost causation principle, which provides that the costs allocated to an entity must be “roughly commensurate” to the benefits it receives.35 Cost causation and the statutory requirement to roughly equate benefits and costs does not permit PJM to assign costs to…Read this passage Filed comments: Reliability and curtailment
III. CONCLUSION
printed heading · Topic match: Reliability and curtailment
Instead of enhancing resource adequacy, it would perpetuate uncertainty and stymie the investment necessary to develop new capacity in PJM.Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated: September 3, 2026 Washington, DC /s/ Bryan Shpall Bryan Shpall Wilson Sonsini Goodrich & Rosati1700 K Street NW Fifth Floor Washington, DC 20006 bshpall@wsgr.comRead this passage