ER26-3515-000 · 2026-09-03 · Old Dominion Electric Cooperative

Comments of Old Dominion Electric Cooperative re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
COMMENTS OF OLD DOMINION ELECTRIC COOPERATIVE
I. INTRODUCTION
On August 13, 2026, PJM Interconnection, L.L.C. (“PJM”) submitted revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) for a proposed Interim Resource Adequacy Service (“IRAS”). IRAS, as described by PJM, is a “new supplemental capacity product”1 through which certain New Large Loads may be directed to reduce their load when PJM determines necessary to address potential capacity emergencies or Interconnection Reliability Operating Limits (“IROL”) violations. New Large Loads that do not have sufficient capacity of their own will qualify as Eligible New Large Loads under IRAS.

The IRAS filing also includes the following “foundational revisions”2 in order to facilitate IRAS: (1) clarification in the RAA that load serving entities (“LSEs”) are obligated to bring sufficient new capacity to cover New Large Loads or be subject to load reductions during Emergencies;3 (2) establishment of a Large Load Registry that PJM will maintain based on information to be provided by LSEs and Electric Distributors;4 and (3) revisions to the Tariff and RAA to include definitions for Large Load and New Large Load. Finally, PJM proposes, beginning with the 2029/20230 Delivery Year, to exclude certain New Large Loads from the Variable

1 PJM Transmittal Letter at 22.
2 Id. at 3.
3 Id. at 3-4.
4 Id. at 3; 36-37.

PDF page 2

2
Resource Requirement (“VRR”) Curve in PJM’s Reliability Pricing Model (“RPM”) capacity market.5

PJM requests that the Commission accept the IRAS filing effective October 12, 2026.6 In order to facilitate Commission acceptance as requested, PJM consents to the Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under section 205 of the FPA and NRG Power Marketing, LLC v. FERC,7 where such modification or severance is consistent with the objectives of PJM’s filing.8

ODEC appreciates PJM’s efforts to address the impending reliability problem of insufficient capacity as New Large Loads continue to connect to the PJM system. The IRAS filing is one component of PJM’s plan to address resource adequacy issues, that includes the recent Reliability Backstop Procurement (“RBP”) proposal currently pending before the Commission in Docket No. ER26-3380-000. ODEC is generally supportive of the IRAS proposal. However, as discussed in these comments, certain elements of PJM’s IRAS proposal raise concerns for ODEC

– namely certain aspects of the Large Load Registry and the IRAS load reduction proposal. Other elements of the IRAS proposal require further clarification or explanation, including the definition of New Large Load, compensation for IRAS load reductions, and the treatment of Bring Your Own New Capacity (“BYONC”).

Pursuant to the Combined Notice of Filings #1 issued August 13, 2026, ODEC submits these comments on PJM’s IRAS proposal. In support of its request for the Commission to direct PJM to address ODEC’s concerns, ODEC states as follows:

5 Id. at 5. 6 Id. at 8.
7 Id. at 9, citing NRG Power Marketing, LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017).
8 Id. at 9.

PDF page 3

3
II. COMMENTS
A. PJM’s proposed Large Load Registry requires LSEs to provide information they might not be able to obtain and might warrant enhanced confidentiality

protection.
PJM proposes to establish a Large Load Registry that will be used to facilitate implementation of IRAS, among other purposes.9 The Large Load Registry is a key component of PJM’s IRAS proposal, since the Large Load Registry will be used by PJM “to determine the quantity of New Large Loads by zone/area and allocate IRAS responsibility to each zone/area accordingly . . .”10 ODEC agrees with the concept of a Large Load Registry to provide transparency and consistent, verified information regarding New Large Loads. ODEC also agrees that the Large Load Registry is generally consistent with the Commission’s June 2026 Order to Show Cause regarding large loads, where the Commission determined that PJM’s Tariff appeared to be unjust and unreasonable absent provisions “that would require PJM and the Transmission Owners to publicly post and regularly update data that details (1) aggregate amounts of proposed large load additions in PJM’s footprint. . .”11

As an initial matter, PJM should clarify whether its proposed RAA revisions would require LSEs to provide the Large Load Registry information. The IRAS transmittal letter states that “PJM is proposing that LSEs submit information to PJM about the Large Loads they serve”12 and that PJM may obtain information from Electric Distributors and Transmission Owners. PJM also states that it proposes to hold LSEs primarily responsible for providing information for the Large Load

9 See Proposed RAA Schedule 11, section B.3. (“The information provided . . . will be used . . . for purposes including but not limited to implementation of [IRAS] . . .”).
10 PJM Transmittal Letter at 28-29.
11 Id. at 48, citing PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 76
12 PJM Transmittal Letter at 36.

PDF page 4

4
Registry beginning as early as next March.13 The proposed RAA would require that “[e]ach Party shall submit, or cause to be submitted” the information related to each Large Load Served by the Party.14 The RAA defines “Party” as “an entity bound by the terms of the Operating Agreement.”15 The PJM Operating Agreement is binding on entities that are Members,16 and Members are defined as those who satisfy the Membership Requirements at Operating Agreement section 11.6.17 Operating Agreement section 11.6, in turn, provides, in part, that to qualify as a Member, an Applicant shall be a Transmission Owner, Generation Owner, an Other Supplier, an Electric Distributor, or an End-Use Customer.18 Thus, it is not clear that the IRAS provisions obligate LSEs to provide the Load Registry information. PJM should clarify the proposed RAA as necessary. Notwithstanding support for the concept of the Large Load Registry, ODEC is concerned that PJM’s proposal will at least create obligations that LSEs cannot satisfy and could subject LSEs like ODEC to enforcement actions. PJM states in its filing that “each piece of information is a necessary component to the Large Load Registry . . .”19 The proposed RAA revisions obligate LSEs to provide the information, without any provision for an LSE to notify PJM if the LSE cannot obtain the information in the time period required or at all. ODEC has reviewed the list of information that PJM proposes to require from each LSE and ODEC has identified certain information that ODEC does not have access to at this time nor is ODEC certain it can obtain.

13 PJM’s proposed RAA, Schedule 11, section B.2, requires that the Large Load Registry information be provided by “[e]ach Party serving or contracted to serve a Large Load . . .”
14 PJM’s proposed Tariff Attachment RAA, Schedule 11, section B.1(a).
15 PJM RAA, Article 1 – Definitions.
16 See Operating Agreement, section 17.1.3 (providing that the Operating Agreement “constitutes the legal, valid and binding obligation” of Members who execute the Operating Agreement.). 17 Id., Definitions M-N.
18 PJM Operating Agreement, section 11.6(a)(i). Operating Agreement section 11.6(b) also provides that “[c]ertain Members that are Load Serving Entities are parties to the Reliability Assurance Agreement.”
19 PJM Transmittal Letter at 37 (emphasis added).

PDF page 5

5
Below is the list of information that PJM proposes to require LSEs to provide. 20 Information that ODEC is uncertain that it will be able to obtain is indicated in bold font, with explanation as warranted:

1. Description of Large Load;
2. Location(s) (Control Zone, Electric Distributor zone/area, where a zone/area is an area within a Zone for which the relevant Electric Distributor specifies a separate Obligation Peak Load MW value. A zone/area is a service area of an Electric Distributor that is a separately identifiable, geographic area bounded by wholesale metering)

3. In-service date for each increment of load;
4. Peak shaving adjustment value pursuant to a state program codified in state law and whether and how it meets the requirements of Tariff, Attachment DD-2;

5. Delivery point / Point(s) of interconnection (include all if more than one);
6. Peak load quantity (MW) and ramp schedule, if applicable;
7. Telemetry specifications - ;
8. BYONC quantity (MW) and ramp schedule, if applicable – As discussed above, ODEC might not have timely information regarding the end-use customer and in those instances, ODEC might not be able to obtain information regarding BYONC;

9. Allocated RBP UCAP MW quantity (MW), if applicable - As discussed above, ODEC might not have timely information regarding the end-use customer and in those instances, ODEC might not be able to obtain information regarding allocated RBP UCAP MW quantities;

10. Backup generation (MW), including fuel type and relevant permitting limitations;
11. Contracts or service agreements between the Large Load and the LSE – Large Loads as end-use customers will likely have contracts or service agreements with ODEC’s member distribution cooperatives, not ODEC. Therefore, ODEC is uncertain that PJM or ODEC can require disclosure regarding these agreements;

12. Points of contact at the applicable Transmission Owner, Electric Distributor, and Load Serving Entity;

13. EMS B1/B2/B3 name (for the applicable Transmission Owner, Electric Distributor); and

14. Additional details and contents as necessary, in accordance with the PJM Manuals – ODEC and other LSEs should not be obligated to provide yet-to-be determined information, as part of the RAA. Instead, to the extent further information may be necessary, it should either be detailed in the RAA or, alternatively, requested on a “best efforts” basis through the Manuals. 20 Proposed RAA Schedule 11, Section B.1.(a).

PDF page 6

6
In addition to these requirements, PJM proposes to require LSEs to promptly inform PJM of any change in the above-mentioned information.21 Here again, LSEs may not receive such notification and may not have ready access to changes in the required information. The obligation and risk imposed on LSEs by PJM’s proposal is significant. Not only does PJM place the responsibility on LSEs to ensure aspects of PJM’s IRAS that are foundational to the success of IRAS,22 but PJM emphasizes in its filing that LSEs’ reporting of information for the Large Load Registry subjects LSEs to the full extent of the Commission’s enforcement authority for the duty of candor and the prohibition against false or misleading statements.23 To the extent LSEs are acting in good faith and simply unable to provide information that they cannot obtain, LSEs should not be subject to the threat of an enforcement action. While PJM’s need for complete and accurate information is justifiable, placing the full burden on LSEs to ensure access to information that they simply may not be able to obtain, under threat of enforcement actions, is not. Instead, PJM should change its RAA to (1) require LSEs to provide the information that they are able to obtain with reasonable efforts or due diligence; (2) require LSEs to promptly identify information that they are not able to obtain; and (3) change the provisions regarding PJM’s possible coordination with Transmission Owners and Electric Distributors as needed.24

21 Proposed RAA, Schedule 11, section B.2.(c).
22 PJM Transmittal Letter at 43-44 (“The information provided in the Large Load Registry will form the foundation for an accurate, complete, and reliable database that will inform, inter alia, decisions about the MW quantify of new Large Loads that is available to provide IRAS in a Delivery Year.”).
23 PJM Transmittal Letter at 44-45.
24 See PJM Transmittal Letter at 26-27 (“. . . the initial obligation to submit data to PJM is on the LSE serving the Large Load, but in order to increase the accuracy of the registry, PJM finds valuable—and needed—the information available to the Electric Distributors.”).

PDF page 7

7
B. PJM should revise its IRAS load reduction framework.
PJM proposes to require Electric Distributors to execute PJM’s directives to reduce load during Interim Resource Adequacy Service Actions.25 PJM’s IRAS does not consider how the load reductions will need to be carried out.26 Electric Distributors may not have the necessary equipment on site with all New Large Loads in order to require the load reductions and/or verify the load reductions are executed as directed. For example, where colocated loads are served behind a generator’s point of interconnection. Therefore, while having the Electric Distributor responsible might provide the necessary system stabilization, it will not be possible where the Electric Distributor does not have equipment to execute the load reduction. An alternative would be to require the assistance of Transmission Owners in executing IRAS load reductions. However, load reductions at the higher voltage levels (e.g., 230 kV) will result in larger MW reductions of load, which could destabilize the transmission system if multiple New Large Loads need to be reduced simultaneously.

As a reasonable alternative to PJM’s proposal to hold Electric Distributors solely responsible for executing New Large Load reductions for an Interim Resource Adequacy Service Action, PJM should consider its role and authority to initiate Interim Resource Adequacy Service Actions, as such is “an ‘Operating Instruction, as defined by NERC.’”27 PJM should use its existing authority as defined by NERC, as well as authority that may be developed as part of NERC’s computational loads/large loads standard in development, to determine PJM’s ability to coordinate with Electric Distributors and/or relevant state entities (perhaps RERRAs) to execute Interim

25 PJM Proposed Tariff Attachment DD-4, Section III. (a).
26 See PJM Transmittal Letter at 75-76 (“The details as to how and when PJM may call an Interim Resource Adequacy Service Action will be set forth in PJM Manual 13.”) 27 PJM Transmittal Lettera t 75 (citation omitted).

PDF page 8

8
Resource Adequacy Service Action load reductions. The entirety of this obligation should not be left to Electric Distributors.

Further, PJM’s filing addresses the reliability and other benefits of load reductions. However, PJM has not addressed how Interim Resource Adequacy Service Action load reductions will be assessed and executed in a manner to minimize or avoid adverse transmission or distribution system conditions. PJM should provide clarification regarding how voltage stability impacts will be evaluated and which entity will be ultimately responsible for ensuring that Interim Resource Adequacy Service Action load reductions do not create adverse transmission or distribution system conditions.

C. PJM should provide additional clarifications regarding its proposed IRAS. In addition to the changes discussed above, certain elements of PJM’s IRAS should be further clarified so that the Commission can ensure the proposal is just and reasonable, and so that market participants have certainty regarding the IRAS.

First, the definition of Large Load should be clarified. PJM proposes to define Large Load as follows:

end-use customer(s) load that has a cumulative peak load of 50 megawatts or
greater at a single electrical site behind one or more points of interconnection, where for configurations involving multiple affiliated load facilities or multiple points of interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-mile radius will be considered a single electrical site as further described in the PJM Manuals.

ODEC agrees that the definition should include affiliated load facilities. However, PJM’s filing does not provide how affiliation will be determined for purposes of the one-mile radius measurement. For example, where facilities are owned by separate legal entities within the same corporate family, does common control deem the entities affiliates?

PDF page 9

9
Second, PJM’s Tariff provisions for IRAS compensation should clarify that such compensation will be limited to Eligible New Large Loads that are incurring capacity costs. PJM explains that its IRAS compensation will be implemented by Electric Distributors, in conjunction with applicable state authorities and New Large Loads.28 PJM further explains that “the IRAS rate is intended to be conjoined with retail rates and ultimately paid to Eligible New Large Loads that reflect a discount on capacity costs commensurate with the impact of Interim Resource Adequacy Service on addressing resource adequacy issues.”29 The proposed Tariff provisions, however, do not explicitly state this condition that compensation will only be paid to Eligible New Large Loads that are charged capacity costs. PJM should provide such clarification in its Tariff provisions. Third, PJM’s proposal for BYONC appears to allow a New Large Load in one zone to be supported by BYONC located in another zone. However, PJM has not explained how BYONC will impact RPM locational deliverability and market modeling assumptions, including CETL, CETO, LDA demand curves or capacity price separation. PJM should provide such clarification.

III. CONCLUSION
WHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider these comments in its determination of the PJM IRAS proposal and if the Commission accepts PJM’s filing, direct PJM to (1) modify the Large Load Registry as provided in section II.A. above;

(2) modify the IRAS load reduction framework as discussed in section II.B. above, and (3) clarify the definition of Large Load, IRAS compensation and treatment of BYONC, as discussed in section II.C. above.

28 PJM Transmittal Letter at 104 (emphasis added).
29 Id.

PDF page 10

10
Respectfully submitted,
 /s/ Adrienne E. Clair
Adrienne E. Clair
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C. 20006-1167
(202) 585-6900
(202) 585-6969 (fax)
aclair@thompsoncoburn.com
Attorney for Old Dominion Electric
Cooperative
Dated: September 3, 2026

PDF page 11

CERTIFICATE OF SERVICE
I hereby certify that on this 3rd day of September 2026, I have caused a copy of the foregoing to be served upon each party designated on the Commission’s Official Service List for this proceeding.

 /s/Adrienne E. Clair