ER26-3515-000 · 2026-09-04 · Organization of PJM States, Inc.

Comments, Request for Clarification, and in the Alternative, Request to Sever of the Organization of PJM States, Inc. re PJM Interconnection, L.L.C.’s…

Text extracted from the eLibrary original (SHA-256 ca5f1ac293fbb533…). Download the original from the official source.

Contents · 8 sections
  1. I. COMMENTS p. 2
  2. A. OPSI SUPPORTS THE BYONC INCENTIVE, BUT PJM SHOULD p. 2
  3. B. OPSI SUPPORTS CURTAILING NEW LARGE LOADS WITHOUT p. 3
  4. C. OPSI SUPPORTS EXCLUDING NEW LARGE LOADS WITHOUT p. 5
  5. D. OPSI SUPPORTS THE LARGE LOAD REGISTRY TO INFORM RETAIL p. 7
  6. II. PJM SHOULD CLARIFY THE PROPOSED IRAS COMPENSATION RATE AND p. 7
  7. III. IF THE COMMISSION REACHES THE MERITS ON THE EXISTING p. 9
  8. IV. CONCLUSION p. 10

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Registry access · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

The Organization of PJM States, Inc. (“OPSI”) files these comments and request for clarification in response to PJM’s August 13, 2026, filing proposing revisions to the Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to…
Read this passage Filed comments: Registry access

I. COMMENTS

printed heading · Topic match: Cost allocation

COMMENTS Recognizing the 2027/2028 Base Residual Auction (“BRA”) cleared short of the PJM Region Reliability Requirement, PJM now proposes several measures intended to improve regional resource adequacy, including the creation and maintenance of an NLL Registry, establishment of IRAS, requiring new…
Read this passage Filed comments: Cost allocation

A. OPSI SUPPORTS THE BYONC INCENTIVE, BUT PJM SHOULD

printed heading · Topic match: Cost allocation

One of the very purposes of IRAS is “for New Large Loads to bring new capacity to address their capacity needs instead of relying on PJM’s capacity market” and eliminate resource adequacy shortfalls.8 OPSI is supportive of the primary objectives of this proposal.
Read this passage Filed comments: Cost allocation

B. OPSI SUPPORTS CURTAILING NEW LARGE LOADS WITHOUT

printed heading · Topic match: Reliability and curtailment

More importantly, the proposal functionally eliminates the incentive for NLL to bring new capacity.”11 PJM now proposes to implement an IRAS Action before calling on Pre-Emergency Load Management when available economic real-time supply may be insufficient to maintain required reserves or…
Read this passage Filed comments: Reliability and curtailment

C. OPSI SUPPORTS EXCLUDING NEW LARGE LOADS WITHOUT

printed heading

OPSI SUPPORTS EXCLUDING NEW LARGE LOADS WITHOUT BYONC FROM THE VRR CURVE UNTIL THEY BRING THEIR OWN CAPACITY Beginning with the 2029/2030 BRA, PJM proposes to exclude NLLs without sufficient BYONC or Allocated RBP Unforced Capacity (“UCAP”) MW from the Variable Resource Requirement (“VRR”) Curve.14…
Read this passage

D. OPSI SUPPORTS THE LARGE LOAD REGISTRY TO INFORM RETAIL

printed heading · Topic match: Registry access

The Registry will include information such as location, in- service date, peak load, backup generation, peak-shaving adjustments, BYONC, and other relevant characteristics, and PJM will use that information to identify and allocate IRAS obligations by zone/area.21 PJM also recognizes that this…
Read this passage Filed comments: Registry access

II. PJM SHOULD CLARIFY THE PROPOSED IRAS COMPENSATION RATE AND

printed heading · Topic match: Registry access

PJM describes the IRAS framework as squarely within the Commission’s established transmission jurisdiction and proposes that “[t]he rate for the provision of Interim Resource Adequacy Service shall be 50% of the Non-Performance Charge Rate” unless an Eligible NLL elects to accept less in its retail…
Read this passage Filed comments: Registry access

III. IF THE COMMISSION REACHES THE MERITS ON THE EXISTING

printed heading · Topic match: Reliability and curtailment

By PJM’s own account, rapid large-load growth has outpaced new supply, tightened the capacity market, and produced resource-adequacy shortfalls.28 PJM attributes the current shortfall particularly to the “unprecedented surge in data center load” occurring faster than new supply can come online,…
Read this passage Filed comments: Reliability and curtailment

IV. CONCLUSION

printed heading · Topic match: Reliability and curtailment

CONCLUSION The rapid influx of NLLs appearing in the PJM region presents a real threat to regional resource adequacy and reliability, and the status quo is not an option.
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated at Newark, Delaware this September 3, 2026.