Comments of Voltus, Inc. on PJM Interconnection LLC’s Federal Power Act Section 205 filing requesting the approval of tariff amendments to establish an…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Proposal Of Pjm Interconnection, L.L.C. To
Establish Interim Resource Adequacy Service
And A Large Load Registry To Address
System Reliability
Docket No. RM26-3515-000
COMMENTS OF VOLTUS
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“FERC’s” or “Commission’s”) Rules of Practice and Procedure, and the August 13 “Combined Notice of Filings #2” setting a comment date of September 3, Voltus respectfully submits comments on PJM Interconnection LLC’s (“PJM’s”) Federal Power Act Section 205 filing requesting the approval of tariff amendments to establish an Interim Resource Adequacy Service (“IRAS”) and Large Load Registry.
1
PDF page 2
TABLE OF CONTENTS
I. INTRODUCTION … 3
II. CLARIFYING THE BYONC CRITERIA FOR DEMAND-SIDE RESOURCES IS
NECESSARY TO PREVENT UNDUE DISCRIMINATION, SUPPORT PRIVATE
MARKET CONTRACTING, AND PROVIDE A JUST AND REASONABLE RATE … 5
A. For DR/DER Resources, New Assets and Reactivations May Be Ineligible to Support
BYONC in the New Tariff Language As Drafted … 6
B. New BTM Assets and Site Reactivations Are a Genuine and Substantial Potential Source
of Additive System Capacity … 9
1. New BTM assets at existing DR/DER sites increase system capacity much like new
assets at existing generators/storage projects … 9
2. GW of capacity capability lie dormant at sites that once participated in DR … 10
C. Excluding New BTM Assets and Site Reactivations is Undue Discrimination … 11
1. Treatment of new BTM assets at existing sites versus new capability at existing
generators/storage projects … 11
2. Treatment of DR/DER site reactivations versus generator repowering … 12
D. In a Context in Which the Private Market Has Been Asked to Proceed Expeditiously with
Bilateral Negotiations Before Tariff Language Has Been Finalized, the Exclusion of New
BTM Assets and DR/DER Site Reactivations Raises “Notice” Concerns … 13
1. The exclusion of demand-side reactivations contravenes the alignment reached during
the CIFP process … 13
2. Meanwhile, contracting parties made commercial decisions on a reasonable
expectation that reactivations would be included … 14
E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and
Reactivations as Eligible to Support BYONC DR/DER in Both the Upcoming and Any
Future IRAS Periods … 15
1. This definition is designed to mirror the structure and specificity of the
generation/storage eligibility criteria in VI(b)(i) … 16
2. Line item (2) within this definition straightforwardly covers new asset capacity … 17
3. Line item (3) employs the language and logic of the reactivation definition for FTM
generation in VI(b)(i)(4) … 17
F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable Resulting in a
Just and Reasonable Definition of BYONC-Eligible DR/DER Reactivations … 17
1. What makes an effective deactivation test? … 17
2. Voltus’s test delivers against the standards just described … 18
3. Voltus’s test solves for other potential concerns … 20
4. The test’s timeline matches the deactivation timeline on the generator side … 21
G. The Proposed Test Provides a Concrete Delineation of Potential Reactivations and Is
Administratively Viable … 21
H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations Eligible to
2
PDF page 3
Reactivate for BYONC … 22
III. PJM’S INCLUSION OF PEAK SHAVING ADJUSTMENTS IN THE LARGE LOAD
REGISTRY IS LAUDABLE, BUT TO ALIGN INCENTIVES, THE MECHANISM
SHOULD ALSO BE CREDITED IN THE CALCULATION OF IRAS-ELIGIBLE LOAD
AMOUNTS … 23
IV. VOLTUS SUGGESTS MINOR REDLINES TO ALIGN BYONC REPORTING
TIMELINES AS TARIFFED WITH UNDERLYING INTENT … 24
A. Adjusting RPM Auctions that Capacity Can Have Cleared Prior to Becoming BYONC..24
B. Enabling PJM to Verify DER/DR BYONC … 25
1. Extension of resource owner certification in VII(a)(ii) to apply to section VI, as well as the existing VIII … 26
2. Enabling PJM review of DR/DER BYONC after registrations have been completed in
a Delivery Year … 26
3. Clarification that deficiency charges will apply under VIII(d), in the event that the review finds the BYONC arrangement does not meet the requirements of VI(b) … 26
V. CONCLUSION … 27
I.
INTRODUCTION
Voltus, Inc., (“Voltus”) is a distributed energy resource (“DER”) aggregator operating in all nine North American wholesale electricity markets. Voltus is a registered curtailment service provider (“CSP”) with PJM Interconnection, L.L.C., (“PJM”) aggregating the flexible attributes of retail load across the footprint and offering capacity, energy, and ancillary services products into PJM markets. Relevant to the provision of capacity, Voltus has participated in all Reliability Pricing Model (“RPM”) since the Base Residual Auction (“BRA”) for 2022/2023 (held in early 2021) and has delivered its capacity commitments as Demand Resources in the associated delivery years. Voltus also has experience transacting PJM-accredited capacity bilaterally, including to support “Bring Your Own Capacity
TM” arrangements1. Voltus’s commercial
experience developing demand-side capacity resources closely informs these comments.
1 See Voltus Blog, Voltus launches “Bring Your Own Capacity Product to Support Data Center Growth and Grid Resiliency” (Sept. 30, 2025), https://www.voltus.co/press/bring-your-own-capacity-data-centers. 3
PDF page 4
Voltus participated actively throughout the Critical Issue Fast Path (“CIFP”) RBP process and the Connect-and-Manage (“CAM” or “C&M”, IRAS’s predecessor) Senior Task Force (“CAMSTF”) as well as the merged “CIFP-RBP/CAM.”2 Voltus had earlier engaged in a limited manner in the preceding CIFP on Large Load Additions (“CIFP-LLA”), which had introduced several of the concepts carried into the January 17 CIFP-LLA Board Decisional Letter and same-day White House Energy Dominance Council and PJM State Governors’ Statement of Principles, which together set the goals and initial shape of the instant tariff filing and the sister RBP filing now before FERC. Voltus’s comments herein reflect a careful attention to the evolution of the IRAS (and RBP) frameworks; consideration of the intent of various design elements and their interactions; and a respect for the challenge of rapidly designing a complex solution that meaningfully meets an unprecedented moment, while under intense political scrutiny, and on largely-untested jurisdictional grounds. Voltus’s consistent interest throughout the stakeholder process has been to ensure a level playing-field for demand-side capacity, with rules designed to accommodate the differences between various resource classes without arbitrarily or unnecessarily limiting the ability of distributed resources to address the resource adequacy shortfall. These comments pick up certain issues Voltus raised during the CIFP process and seek clarification on new questions raised by the proposed tariff language. Voltus contends that incentivizing Bring Your Own New Capacity (“BYONC”) and
related frameworks is generally more effective and efficient at developing new capacity than central procurement, and better protects non-cost-causers. Voltus approves the IRAS proposal as a whole and supports PJM’s reintroduction of the RTO-wide CAM/IRAS incentive framework.
2 See CIFP-RBP/CAM record at https://www.pjm.com/committees-and-groups/cifp-rbp, and CIFP-LLA record at https://www.pjm.com/committees-and-groups/cifp-lla; and Executive Summary and proposals filed by Voltus in CIFP-RBP/CAM Stage 4, including Voltus RBP/C&M Package Executive Summary (June 2026), available at https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02l---voltus---c m-and-rbp---executive-summary.pdf. 4
PDF page 5
Voltus
further
appreciates
that
the
framework
includes
demand-side
capacity
resources—Demand Resources (“DR”) and Distributed Energy Resource (“DER”) Capacity Aggregation Resources—as eligible to support BYONC arrangements, and commends PJM for responding to broad stakeholder support to include the demand side. Demand-side resource additions minimize the risk of stranded assets in the face of an uncertain long-term load forecast, bring revenues directly to retail consumers to offset the increase in energy costs associated with large load growth, support grid resiliency, and promote the technological and operational modernization of the grid for more efficient utilization of existing infrastructure, in turn driving lower system costs and improving affordability. Demand-side resources by definition increase demand-side flexibility, crucial for absorbing the increasing renewables penetration that is a policy preference and legislative requirement for many states within the PJM footprint. Voltus’s primary concern herein is that by excluding certain critical categories of new, durable demand-side capacity, the IRAS tariff is unjust and unreasonable because it unnecessarily limits the volumes of capacity available to ease system constraints and provide ratepayer relief. This issue is addressed in Section II. Second, Voltus suggests an expansion of the inclusion of the Peak Shaving Adjustment mechanism to incentivize large load funding of the same (Section III). Third, Voltus offers minor redlines to clarify and align the required timelines for reporting and verifying BYONC arrangements (Section IV). A complete set of suggested redlines is provided in Attachment A.
II.
CLARIFYING
THE
BYONC
CRITERIA
FOR
DEMAND-SIDE
RESOURCES
IS
NECESSARY
TO
PREVENT
UNDUE
DISCRIMINATION, SUPPORT PRIVATE MARKET CONTRACTING,
AND PROVIDE A JUST AND REASONABLE RATE
The inclusion of new capacity from Demand Resources and DER Capacity Aggregation Resources naturally raises a question as to requirements on the sites underlying the aggregations. 5
PDF page 6
Stakeholders and PJM staff devoted significant energy to this question during the CIFP process and discussed the inclusion of several categories: (1) the capacity of sites providing wholesale capacity for the first time, (2) the added capacity associated with the installation of behind-the-meter (“BTM”) assets (generation, storage) to support DR/DER participation, and (3) the potential “reactivation” capacity of sites that supported a capacity resource at some point in the past, under different conditions, but no longer participate. PJM’s last several proposals on BYONC eligibility included all three categories, consistent with the analogous allowance of new-build, incremental, and repowered front-of-the-meter (“FTM”) generation and storage capacity.
However, the proposed Tariff language on DR/DER resource eligibility only
unambiguously includes the first category: sites providing wholesale capacity for the first time. Voltus understands—and there is evidence in the Tariff’s drafting—that excluding both categories was not the intent: PJM intended preserve the eligibility of new capacity associated with the installation of BTM generation/storage (“new asset capacity”), but chose to exclude the “reactivation” of any portion of a site’s capacity not associated with a new asset.3 Given this understanding of intent, several of the following subsections focus specifically on site reactivations rather than new asset capacity. Voltus contends that both categories must be added back to the final tariff and provides a redline to effectuate this change in Section II.E.
3 FERC precedent strongly supports the non-discriminatory treatment of demand-side resources. See FERC Order No. 2222: Fact Sheet (Sept. 28, 2020) (“FERC Order No. 2222 will help usher in the electric grid of the future and promote competition in electric markets by removing the barriers preventing distributed energy resources (DERs) from competing on a level playing field in the organized capacity, energy and ancillary services markets run by regional grid operators.”). 6
PDF page 7
A. For DR/DER Resources, New Assets and Reactivations May Be Ineligible to Support BYONC in the New Tariff Language As Drafted
DR/DER resource eligibility is delineated in proposed Tariff, Attachment DD-4, section VI(b):
(ii) For Demand Resources or DER Capacity Aggregation Resources, the resource must qualify as a Planned Demand Resource or DER Capacity Aggregation Resource, as described in the RAA, Schedule 6 and Schedule 6.2 and:
(1) be composed of, or reliant on, any location not registered in or prior to the 2026/2027 Delivery Year at which an incremental amount at that location is the result of the registration of new generation or storage assets at the location. However, to the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then will be composed of, or reliant on, any location registered in the Delivery Year prior to the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met; and/or
(2) be composed of, or reliant on, locations that were not previously supported Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand for or prior to the 2026/2027 Delivery Year. However, to the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then will be composed of, or reliant on, locations that were not previously supported a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand for the Delivery Year prior to the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met.
(The orange reflects text that was included in PJM’s redlined tariff in a different color than the surrounding text, and may indicate late-stage edits.) The second sentences in both VI(b)(ii)(1) and VI(b)(ii)(2) above address the composition of eligible BYONC in a future state in which the system has left and then returned to the BYONC posture. Putting these aside for now, DR/DER BYONC resources for the IRAS period beginning June 1, 2027, must
7
PDF page 8
be composed of, or reliant on, any location not registered in or prior to the 2026/2027 Delivery Year at which an incremental amount at that location is the result of the registration of new generation or storage assets . . . and/or . . . locations that were not previously supported [sic] a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand for or prior to the 2026/2027 Delivery Year.
The first clause allows new asset capacity but seemingly only at sites with no past DR/DER participation; the second allows new sites in general. Since sites supporting Capacity Resources, Peak Shaving Adjustments, and Price Responsive Demand must all be registered in PJM’s Demand Response Hub database tool (“DR Hub”), the qualification in the second clause is likely coincident with “not registered” in the first. Additionally, since a new site’s capacity nomination will count whether or not tied to a new asset, and since the capacity nomination will include the new asset’s capability, the first clause is redundant to the second. Fundamentally, this definition counts as new all of (but only the) capacity of never-before-registered sites. As to the future IRAS periods, as covered by the second sentences of VI(b)(ii)(1) and VI(b)(ii)(2), “to the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii),” DR/DER BYONC resources
will be composed of, or reliant on, any location registered in the Delivery Year prior to the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met; and/or . . . locations that were not previously supported a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand for the Delivery Year prior to the first Delivery Year for which the
requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met.
On a plain reading, the first clause above actually requires that a site was registered in the Delivery Year prior to the resumption of the IRAS posture (a requirement at odds with a plain meaning of “new”), which seems to be the opposite of the intent. Conversely, the second clause requires that the site was not supporting capacity (and therefore was not registered) in that same Delivery Year—a more plausible test of “new.” Reading these clauses literally would leave no path for any site to support BYONC in a future IRAS period. Voltus expects a simple drafting 8
PDF page 9
error: the exclusion of “not” before “registered” in the first clause. On that assumption, the tariff is intended to allow reactivations for BYONC in a future IRAS posture, since the test is on registration and/or support of a capacity product in the year prior to the resumption of IRAS only.
Thus the tariff drafting on plain reading allows only new sites today, and (assuming a one-word addition to resolve the apparent contradiction) both new sites and reactivations toward BYONC in future IRAS iterations.
B. New BTM Assets and Site Reactivations Are a Genuine and Substantial
Potential Source of Additive System Capacity
It is worth considering concretely the assets excluded by PJM’s current definition. First, without Tariff clarification, new “steel-in-the-ground” physical BTM generation and storage investments may not support BYONC unless sited at locations that have never before touched a wholesale capacity product. In parallel, sites that have ever touched a wholesale capacity product are ineligible. Both exclusions carve away very significant sources of new capacity, and incentivizing investment in the excluded categories is manifestly good policy, as the following examples illustrate.
1. New BTM assets at existing DR/DER sites increase system capacity much
like new assets at existing generators/storage projects
Consider a site that has participated in demand response by changing air conditioning setpoints, where air conditioning is only 5% of site load at a 20 MW large industrial facility. Installing a battery on site, sized to meet 95-100% of the full site’s load, will increase the volume of potential site curtailment by 19 MW. The battery will also add the ability to participate in ancillary services, the Energy market, and to avoid transmission and distribution system peaks. Or consider a site already curtailing its full load when PJM’s Emergency Load Response Program (“ELRP”) is dispatched but with the square footage and appetite to install a solar and 9
PDF page 10
storage system, fuel cell, etc. that could be reflected as injection capacity under the DER Model. In both cases, the system gains durable physical infrastructure that is genuinely additive. New storage and generation installed alongside existing sources of capacity—whether behind the meter or in front—provide exactly the kind of efficient capacity expansion necessary to counteract the reliability impacts of unprecedented load growth.
The BTM placement of new assets provides additional community benefits. BTM assets improve local grid resiliency, may avoid network upgrades as compared to the generator case for the same volume of new capacity, and send revenues directly to retail customers. BTM generation and storage also carry less stranded asset risk than FTM assets because the BTM assets may have additional use cases, such as providing back-up in the case of a blackout. 2. GW of capacity capability lie dormant at sites that once participated in DR Consider next a location that once did DR but has gone dormant. Perhaps curtailment proved operationally more disruptive than anticipated, or the facility lost the on-site staff required to execute a manual reduction when called. As such, the opportunity cost in terms of production, throughput, or other foregone benefits (e.g. HVAC access) simply exceeded the compensation the capacity market had to offer. In each case the underlying capability remains physically present but is “locked out” in absence of a business case sufficient to bring the capability to market.
The incentives related to BYONC allow aggregators to overcome these obstacles in several ways. The aggregator may invest in new systems and equipment—building controls, automatic load control—that address operational infeasibility. Higher revenues may be sufficient in themselves to incent participation, and the extended term and revenue certainty associated with BYONC arrangements may have independent value. In short, BYONC provides the financial incentive to make the participation of dormant sites feasible and economic. 10
PDF page 11
There are potentially GW of capacity at long-dormant sites. DR, which has been an eligible RPM resource class since the first auction, in 2007, peaked at just shy of 11 GW Installed Capacity (“ICAP”) registered Demand Resources in Delivery Year 2015/2016, but was only 6.76 GW in 2024/20254 (with erosion due to increasing dispatch frequency and other factors). The delta provides an indication of the volume of existing but “dormant” capability. Allowing the market to discover these missing GW and their appropriate price is good policy. Note also that site control upgrades and other investments that may be required to “unlock” the capability of dormant sites may be accomplished much faster than utility-scale uprates, much like BTM generation and storage development timelines are shorter than new generator or FTM storage development timelines. “Modular” distributed investments offer a significant advantage in terms of Commercial Operation Date (“COD”).
C. Excluding New BTM Assets and Site Reactivations is Undue Discrimination
Because an assessment of the differential treatment of DR/DER versus generation/storage resources for BYONC eligibility may be informed by consideration of RBP and Qualifying RBP Offset (“QRBPO”) criteria, this section notes the resource eligibility criteria for these other two products as defined in PJM’s companion RBP filing in Docket No. ER26-3380. The same underlying resources should be able to support both BYONC and QRBPO if tied to load growth in the 2027/2028 and 2028/2029 Delivery Years; this alignment ensures that a zone may receive QRBPO credit for the capacity investments that are decreasing the zone’s Eligible Large Load Amount, thus avoiding double procurement.
4 See Monitoring Analytics, 2024 State of the Market Report for PJM, Table 5-12 (2025), available at https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-pjm-sec5.pdf. 11
PDF page 12
1. Treatment of new BTM assets at existing sites versus new capability at
existing generators/storage projects
Unlike the increase of capacity within an existing generation or storage facility, achieved in proposed Tariff, Attachment DD-4, section VI(a) through either an uprate, the utilization of additional interconnection rights, or a change to fuel type, all of which are incremental capacity for an existing physical asset, the addition of new BTM assets involves the addition of completely new physical assets at an existing site. For this reason, and for those outlined in section B.1 supra, Voltus’ suggested wording for proposed Tariff, Attachment DD-4, section VI(b)(ii)(2) captures the capacity related to those new physical assets.
2. Treatment of DR/DER site reactivations versus generator repowering
While the "repowering of a deactivated generation resource that deactivated prior to April 10, 2026" is eligible to back BYONC, QRBPO, and even sell offers into RBP itself, a site that has ever participated as DR in the past is ineligible to support aggregations toward any of the three products. The proposed Tariff language just quoted applies both to BYONC5 and QRBPO6 resource eligibility. The language on RBP resource eligibility is even more inclusive, allowing “repowering of a generation resource that had deactivated, or announced deactivation, on or before April 10, 2026” (emphasis added).7 Given the availability of tests to effectively identify what DR/DER should be considered eligible to reactivate as new, including the test suggested by Voltus later in these comments, there is no justification for this discriminatory treatment. The exclusion discriminates unduly between rate classes and results in a perverse policy outcome: native load that constituted the vanguard of DR participation but was subsequently unable or uninterested in sustaining that participation are blocked from accessing the new large load incentives that would make market reentry feasible. This will disproportionately affect DR’s
7 Proposed Tariff, Attachment DD, section 18.5(b) (RBP filing). 6 Proposed Tariff, Attachment DD, section 18.2(b) (RBP filing). 5 Proposed Tariff, Attachment DD-4, section VI(b). 12
PDF page 13
traditional early adopters, namely commercial and industrial (“C&I”) customers previously considered “large loads.” Meanwhile, new load can meet its IRAS obligation using on-site load flexibility backed by storage and generation. The distinction siphons expected BYONC revenues from veteran to new large loads and promotes on-site asset build-out at data center complexes at the expense of investment in the efficient utilization of dormant C&I capacity. Early DR adopters should not be penalized for the long-ago capacity benefits they provided under different market conditions and DR program designs.
D. In a Context in Which the Private Market Has Been Asked to Proceed
Expeditiously with Bilateral Negotiations Before Tariff Language Has Been
Finalized, the Exclusion of New BTM Assets and DR/DER Site Reactivations
Raises “Notice” Concerns
This section primarily traces the evolution of the CIFP conversation on DR/DER reactivation eligibility rather than new BTM asset eligibility, because this is the category that PJM excluded from both BYONC and QRBPO in its tariff filings. The apparent exclusion from BYONC of new BTM asset capacity may be a misreading on Voltus’s part or the result of a drafting error. However, to the extent the category has been excluded, very similar notice concerns as delineated below apply.
1. The exclusion of demand-side reactivations contravenes the alignment
reached during the CIFP process
During the CIFP-RBP process and later CIFP-RBP/CAM,Voltus and other stakeholders advocated that DR/DER site reactivations should be treated as new capacity equivalently with the generation side. On the BYONC side, Staff included reactivations in its very first proposal that specified what counted as new DR/DER, presented May 15, 2026.8 All versions of PJM’s Stage 3 package included reactivations, and PJM staff verbally acknowledged the reasonableness 8 Tim Horger, PJM, Connect and Manage PJM Proposal, at slide 8 (May 15, 2026), available at https://www.pjm.com/-/media/DotCom/committees-groups/task-forces/camstf/2026/20260515/20260515-item-03a-- -connect--manage-pjm-package---presentation.pdf.
13
PDF page 14
of providing a market for dormant sites to reactivate as new on the basis of large load price incentives, given that existing incentives had proven insufficient for such sites. Contemporaneously, BYONC was proposed as eligible to decrement the RBP procurement target, implying reactivations’ eligibility for this function as well. The tight linkage between BYONC and the RBP target was maintained until the day before the CIFP Stage 4 meeting.9 2. Meanwhile, contracting parties made commercial decisions on a
reasonable expectation that reactivations would be included
Thus, for the final six weeks of the stakeholder process, and up until the RBP and IRAS tariff filings four to six weeks later, stakeholders expected that DR/DER reactivations would be eligible both to reduce a large load’s IRAS exposure (the BYONC function) and to decrement the RBP procurement target (the QRBPO function). Given the very short timeframe to finalize bilaterals, especially for QRBPO purposes, the industry made investments based on the latest and best understanding of resource eligibility. This meant reactivations on both the generation and DR sides.
Pursuing, under conditions of regulatory uncertainty, both the large load bilaterals and the contracts with the underlying sites that would serve those bilaterals aligned with the best interests of the system and the provided incentives. Political actors had expressed urgency, and PJM was actively matching potential buyers and sellers through RBP’s “matchmaking” service. BYONC arrangements with potentially very large companies as buyers imply complex contracting for a product (IRAS protection) never before sold. Parties required time to develop shared understanding and design agreements addressing risk allocation for unknowns beyond just present regulatory uncertainty. With IRAS beginning in less than a year and large loads
9 See PJM, CIFP - Reliability Backstop Procurement - Options and Packages Matrix - Updated (June 29, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-cifp---reliability-bac kstop-procurement---options-and-packages-matrix---updated.xls. 14
PDF page 15
seeking to lock in protection, bilateral discussions needed to begin prior to final tariff approval, in October or later. PJM has requested effective dates for both 205 filings of just after tariff approval, to meet political urgency and accommodate interdependencies with the December BRA.
Parties were thus encouraged, if not required, to make commercial investments and pursue commercial arrangements on the basis of evidence-backed assessments as to the range of final tariff outcomes. As explained above, the DR/DER industry’s defensible expectation was that site reactivations and new BTM assets would be eligible to supply BYONC.
PJM has publicly explained neither the reasoning behind the change from the CIFP conclusion nor the justification for discriminatory treatment compared to generators. Neither the Board CIFP decisional letter10 nor the Board Executive Summaries on RBP11 and IRAS12 mentioned the specific definitions of new DR/DER, and there was no reference to a change in these definitions or to considerations that would have led to such a change.
12 PJM Board, CIFP Framework for Service During Periods of Insufficient Resource Adequacy Executive Summary (July 27, 2026), available at
https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-cifp-framework-f or-service-during-periods-of-insufficient-resource-adequacy-executive-summary.pdf 11 PJM Board, CIFP Reliability Backstop Procurement Executive Summary (July 27, 2026), available at https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-cifp-reliability-ba ckstop-procurement-pjm-board-decision.pdf
10 PJM Board, Board Decisional Letter on CIFP Reliability Backstop Procurement and Connect and Manage (July 27, 2026), available at https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-board-decisional- letter-on-cifp-reliability-backstop-procurement-and-connect-and-manage.pdf 15
PDF page 16
E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and
Reactivations as Eligible to Support BYONC DR/DER in Both the Upcoming
and Any Future IRAS Periods
Voltus suggested language (in italics below) replaces proposed Tariff, Attachment DD-4,
sections VI(b)(ii)(1)-(2):
(ii) For Demand Resources or DER Capacity Aggregation Resources, the resource
must qualify as a Planned Demand Resource or DER Capacity Aggregation
Resource, as described in the RAA, Schedule 6 and Schedule 6.2, and must be
supported by any combination of the following:
(1)sites never previously registered nor otherwise previously supporting a
Capacity Resource, a Peak Shaving Adjustment, or Price Responsive
Demand;
(2)new-build behind-the-meter generation or storage assets;
(3)reactivations of locations previously registered or otherwise supporting a
Capacity Resource, a Peak Shaving Adjustment, or Price Responsive
Demand that deactivated prior to, and were not registered in or since, the
2025/2026 Delivery Year.
1. This definition is designed to mirror the structure and specificity of the
generation/storage eligibility criteria in VI(b)(i)
This recommended definition parallels the structure PJM has used to define resource
eligibility on the FTM generation/storage side: first providing for resources that are fully new to the system, then accommodating new capacity tied to specific investments, and finally providing for the repowering of dormant resources. Like the generation and storage criteria, the suggested definition handles the current and future IRAS periods together, collapsing the additional clauses.13 And, wherever possible, the above definition borrows the wording of the
13 The urgent imperative is to define BYONC eligibility for the first IRAS period, beginning next June. This will provide much-needed clarity for contracting. If the system moves out of and then back into an IRAS posture as contemplated by proposed Tariff, Attachment DD-4, section IV(b) in combination with the proposed definition of New Large Load tariff terms, at a possibly far-future date, it is likely that certain elements of Attachment DD-4 will need to be revisited to account for changing conditions and lessons learned. PJM’s proposed BYONC-eligibility language on the generation/storage side accomplishes the tariff’s goal of capturing the policy determinations hashed out in the stakeholder process as to the kinds of capabilities that should be incentivized by large load investments. Voltus’s amendments attempt to do the same on the DR/DER side. Further specifications needed to accommodate a future IRAS period, if not requiring tariff revisions, may be appropriately determined in the manuals. 16
PDF page 17
generation/storage eligibility criteria. This consistency supports interpretive ease and unambiguously provides for non-discriminatory treatment of distributed demand-side capacity. The suggested language supplies fundamentally the same level of specificity as PJM's language on the underlying sites that may contribute to an aggregation. Voltus does not propose that the tariff resolve every question of measurement and verification for each category. Many such determinations are properly developed in the PJM manuals.
2. Line item (2) within this definition straightforwardly covers new asset
capacity
The capacity associated with a new investment and installation of a physical asset should be included as new regardless of the history of the host site. There is no need to link the allowance of this type of capacity to only those locations that do not otherwise “host” eligible BYONC capacity. Doing so creates potential ambiguity as to whether new assets at new or reactivated sites may support BYONC.
3. Line item (3) employs the language and logic of the reactivation definition for FTM generation in VI(b)(i)(4)
On the generation/storage side, PJM proposes that the “repowering of a deactivated generation resource that deactivated prior to April 10, 2026” may support a BYONC arrangement.14 Voltus’s proposed allowance of DR/DER reactivations parallels this structure by permitting the reactivation of sites deactivated by a certain date. The primary test is on whether the site has been registered in the Delivery Years since that date. A site could be registered, indicating availability, but never dispatched. Thus registration is a stricter and cleaner check than a criteria based only on “support” of a capacity resource or "participation" in DR/DER.
14 Proposed Tariff, Attachment DD-4, section VI(b)(i)(4). 17
PDF page 18
F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable
Resulting in a Just and Reasonable Definition of BYONC-Eligible DR/DER
Reactivations
1. What makes an effective deactivation test?
The inclusion of new sites and new assets as providing new capacity is largely self-justifying. These resources are providing capacity incremental to the system’s total capacity today. On the other hand, reactivations—whether of generators and FTM storage or sites underlying an aggregation—invite further consideration. It is not self-evident that a generator or site that previously provided system capacity should be counted as new.
Rather, reactivations provide additive capacity against the counterfactual that the relevant resource remains out of commission. If a large load incentivizes the resurrection of a resource that would otherwise stay out of market, that large load may be legitimately credited for offsetting the impact of its addition. Thus dormant capacity may be considered new again, if the BYONC arrangement is the cause-in-fact of the repowering. This is the logic supporting generator repowerings is section VI(b)(i)(4).
Thus the appropriate definition of DR/DER reactivations must assess whether a site now out of market would stay out in the normal course of business; in other words, whether it should be considered actually deactivated rather than temporarily unavailable. A deactivated site is one that is not out of market for exogenous, short-term reasons such as maintenance, but for reasons that will hold for the foreseeable future unless there is a material change in market conditions (such as a sizable increase in available incentives to participate). An effective test will capture true deactivations as so defined without sweeping in false positives; at the same time, the line-drawing exercise should not arbitrarily exclude a subset of true deactivations in its efforts to avoid false positives. Finally, the test should not be gameable. It should not allow for a site, by a 18
PDF page 19
change in behavior, to intentionally preserve or create the ability to qualify for the BYONC incentive.
2. Voltus’s test delivers against the standards just described
Voltus’s test meets the mark because it calibrates the start of the lookback period to the specific market conditions of the pre-IRAS Delivery Years. BRAs for both 2025/2026 and 2026/2027 cleared at the administratively-imposed price cap, resulting in unprecedented capacity value that aggregators could pass on to sites willing to register and perform in these Delivery Years. BRA results were known well in advance of registration decisions; a retail energy customer deciding not to participate for those Delivery Years did so with full knowledge of the high compensation on offer—substantially diminishing the possibility that could have been incentivized to reenter the market under the non-IRAS status quo. A retail customer with past experience of DR but that registered in neither of these years has signalled that participation is uneconomic or otherwise infeasible absent significant changes at the site or with respect to market conditions. Simply put, if a site that once participated would have come back anyway absent the BYONC incentive, it would have done so in 2025/2026 or 2026/2027. If a site is temporarily unavailable due to maintenance or other ordinary, temporary conditions, under high pricing conditions, customers and their aggregators are incentivized to resolve the condition and become available as quickly as possible. Thus, while a single-year lookback risks sweeping in locations that happened to be unavailable for an ordinary reason but that would have returned the following year by default, checking for non-registration in consecutive Delivery Years substantially avoids this risk: a location out for maintenance in 2025/2026 would be expected to return in 2026/2027, and a location out in 2026/2027 would ordinarily have participated in 2025/2026. Nonparticipation in both years despite the highest pricing PJM’s capacity market has thus far produced is not readily explained by transient, 19
PDF page 20
addressable circumstances, but instead indicates a permanent choice or necessity to “deactivate” the site.
The test is also immune to strategic behavior: when the registration decision for 2025/2026 was made (in May 2025), the IRAS and BYONC frameworks did not exist and were not reasonably foreseeable in their current form. No location would have withheld itself from the market in order to preserve or manufacture eligibility for a construct that had not yet been socialized or developed. The suggested test identifies revealed preference under conditions that could not have been influenced by the eligibility rule the Commission is now asked to approve. Note that pushing back the start of the lookback period does not improve the test but instead disqualifies true deactivations from 2025/2026. A site whose departure from the market exactly coincided with a step-change in pricing—an order of magnitude—and which did not return the following year despite the 2025/2026 price signal and the equally high pricing realized and available for 2026/2027, should be considered intentionally dormant. Beginning the lookback with Delivery Year 2025/2026 is a well-justified rather than arbitrary choice. 3. Voltus’s test solves for other potential concerns
In conversations with PJM, Voltus has heard another concern that may have informed the exclusion of reactivations: that Curtailment Service Providers routinely nominate more locations, and more UCAP, than is strictly necessary to fill a cleared RPM commitment, to build a performance buffer into the portfolio. Individual locations may effectively cycle in and out of the resource from year to year or from dispatch to dispatch, such that a location's apparent absence in a given period does not reflect genuine unavailability. PJM’s concern, as Voltus understands, is that this “cycling” invites or enables gaming of the “reactivation” category. Voltus first observes that there is nothing undesirable about the performance buffer / cycling dynamic. Aggregators should be encouraged to build redundancy into their portfolios so 20
PDF page 21
they may perform fully against their commitments. Reliable performance across the range of conditions during dispatch requires portfolio diversification as well as judgment about how to sequence and manage the participation of individual locations during an event. These activities are core to an aggregator’s function and comprise the layer converting distributed resources into a product legible to and usable by the system operator: individually variable end-use customers may function as a firm capacity resource.
However, Voltus understands and agrees with the premise of the concern with “cycling” in the context of reactivation: a location that was available in a given year to contribute to any test or dispatch, but for whatever reason did not end up doing so, has not deactivated and should not be counted as new capacity.
Voltus's recommended test addresses the concern by disqualifying sites that were in any way available to provide capacity: the test is on registrations, not just participation. Only a location registered by the start of the Delivery Year may have its actions measured and settled toward DR/DER performance. Whether the CSP in fact calls upon such location in response to a PJM dispatch instruction is immaterial: the location was registered, and it therefore fails Voltus’s reactivation test. The test avoids any “cycling” concerns (as does, incidentally, PJM’s own proposed wording which defines DR/DER eligibility in terms of registration and/or support of a capacity resource).
4. The test’s timeline matches the deactivation timeline on the generator side Finally, the proposed test neatly aligns DR/DER reactivation with generator/storage reactivation, defined as “repowering of a deactivated generation resource that deactivated prior to April 10, 2026.”15 The process to complete deactivation following the decision or announcement takes time, perhaps about a year per Voltus’s understanding. Deactivation by 15 Proposed Tariff, Attachment DD-4, section VI(b)(i)(4).
21
PDF page 22
April 2026 implies a deactivation decision by sometime in 2025. Similarly, a site not registered in DY25/26 has made the “deactivation” decision by May 2025 at latest.
G. The Proposed Test Provides a Concrete Delineation of Potential Reactivations and Is Administratively Viable
Crucially, Voltus’s test is administratively workable. A time-limited lookback involves a straightforward, well-defined, and efficient database search against the relevant years’ historical registrations, with Electric Distribution Company (“EDC”) account number as the identifier. For PJM verification, lengthier lookback periods introduce data fidelity challenges, the complexity of changes to the data model over time, and uncertainty as to stability of EDC account numbers: a given location’s account number may change for a variety of reasons, disrupting database history for that site. On the customer/aggregator side, there may be insufficient information available to check eligibility against a longer lookback: a site’s residents, owners, and/or operators may have no recollection or knowledge of long-past DR participation, or may confuse participation in a utility DR program carrying no resource adequacy benefits with support of a wholesale capacity product. A discrete and limited lookback enables customers and aggregators to confidently assess whether a given site satisfies criteria, providing clarity for bilateral contracting purposes and greatly reducing the risk that a resource shows up to the Delivery Year partially “unavailable” for BYONC purposes due to site ineligibility discovered during registrations. In this situation, large load MW avoided curtailment risk and have been added back to RPM on the basis of capacity that PJM does not consider to be new. For internal coherence of the IRAS/BYONC framework, the reactivation test should provide high confidence to all parties as to a site’s eligibility, so that large loads contracted with DR/DER resources may bring to the system the expected volume of new capacity as defined.
22
PDF page 23
H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations
Eligible to Reactivate for BYONC
Note that in comments in Docket No. ER26-3380, Voltus recommended a test of site deactivation for purposes of Qualified Reliability Backstop Procurement Offset (“QRBPO”) DR/DER resource eligibility that was linked to the 2026/2027 Delivery Year only. That recommendation had reflected Voltus's supposition that an allowance of reactivations under a one-year lookback may have been what PJM originally planned to file for BYONC eligibility (see section II.A supra, interpreting the tariff drafting). Voltus has no objection to a two-year test which aligns with the formulation PJM had advanced in the stakeholder process. Voltus's interest is in a defined and administrable lookback applied consistently across the QRBPO and BYONC constructs and future IRAS iterations.
Voltus welcomes feedback on its proposed test and is not averse to discussing further criteria PJM or the Commission may propose to appropriately identify the set of DR/DER sites eligible for BYONC reactivation.
III.
PJM’S INCLUSION OF PEAK SHAVING ADJUSTMENTS IN THE
LARGE
LOAD
REGISTRY
IS
LAUDABLE,
BUT
TO
ALIGN
INCENTIVES, THE MECHANISM SHOULD ALSO BE CREDITED IN
THE CALCULATION OF IRAS-ELIGIBLE LOAD AMOUNTS
As currently drafted, Peak Shaving Adjustment values are to be separately tracked in the Large Load Registry for each New Large Load16 yet play no role in the calculation of the Eligible New Large Load Amount as written,17 with the potential effect that a Peak Shaving Adjustment does not reduce a Large Load's exposure to IRAS curtailment. This could mean that a load that invests in reducing demand could qualify its zone for an RBP opt-out and still be subject to IRAS curtailment. We support the points made by Advanced Energy United on this issue, that
17 Proposed Tariff, Attachment DD-4, section VII(h).16 Proposed Tariff, Schedule 11, section B.1(a). 23
PDF page 24
clear, unambiguous rules regarding PSA’s treatment are essential, to give those that do use a Peak Shaving Adjustment the confidence they will not face unexpected curtailment exposure once IRAS is filed. We support United’s recommendation that the Commission direct PJM to amend the Eligible New Large Load Amount formula to credit Peak Shaving Adjustment values on the same basis as BYONC and Allocated RBP UCAP MW, or to explain on the record why a load managing its footprint through a state-sponsored peak shaving program should be treated identically to one that has not.
IV.
VOLTUS
SUGGESTS
MINOR
REDLINES
TO
ALIGN
BYONC
REPORTING TIMELINES AS TARIFFED WITH UNDERLYING INTENT
A. Adjusting RPM Auctions that Capacity Can Have Cleared Prior to
Becoming BYONC
Voltus notes a minor inconsistency with the reporting timelines that must be met for BYONC to qualify and provide IRAS protection as recorded in the Large Load Registry. PJM’s transmittal letter and tariff design describe three functions enabled by reporting the BYONC arrangement to PJM, each with different timelines. At minimum, PJM needs to know about the arrangement prior to the relevant Delivery Year (more precisely, prior to determining the available IRAS amounts for each zone/area, as BYONC decreases these amounts). Additionally, PJM should be told about the arrangement prior to the commencement of the supply’s RPM participation, as insurance that the supply is coming online as a consequence of the BYONC arrangement. Finally, given that Eligible Large Load Amounts will be removed from the load forecast for RPM purposes beginning with Delivery Year 2029/2030, PJM needs to verify the matched load and supply amount prior to finalizing auction parameters for the auction in which the underlying supply first intends to clear (consistent with its ten-year RPM obligation). 24
PDF page 25
Given the non-applicability of this last deadline for the first two IRAS years as well as the interaction of tariff finalization with in-flight bilateral deals, the application of these deadlines varies for different years. Hence the nuanced delineation of reporting timelines in proposed Tariff, Attachment DD-4, sections VII(b)-(d) (setting reporting deadlines for RPM parameter adjustments) and VI(a). Section VI(a)(iii) provides the general rule that clearing an RPM auction before reporting the BYONC arrangement is disqualifying, with the exception that clearing auctions listed in section VI(a)(i) is not. Logically, the exempted auctions should include those that will have already cleared by the time the tariff is approved and which pertain to near-term IRAS years such that supply may be assumed to have cleared in anticipation of a BYONC arrangement; these are BRAs 27/28 and 28/29. It is consistent with this logic to additionally exempt the one near-term auction whose parameters will not be impacted by IRAS—the Third Incremental Auction (“3IA”) for 2027/2028—to allow parties additional time to finalize contracts given how recently the IRAS framework will have been finalized. Reflecting this logic but contradicting section VI(a)(i)’s current exemptions, section VII(b) sets a just-prior-to-Delivery Year reporting deadline for 27/28 and 28/29 BYONC. Thus, Voltus proposes replacing in section VI(a)(i) the reference to BRA 29/30 with a reference to 3IA 27/28, to clarify that 27/28 BYONC need not be reported until April 1, 2027, (well after the 3IA 27/28 auction), but that BYONC wishing to clear BRA 29/30 must obey the much earlier deadline provided in VII(c), because PJM needs BYONC inputs in time to adjust auction parameters. Expected 29/30 BYONC not able to meet this very near-term deadline may use a 29/30 Incremental Auction to satisfy the RPM obligation once the BYONC arrangement is finalized and reported. The effectuating redline, at proposed Tariff, Attachment DD-4, section VI(a), is as follows:
25
PDF page 26
(i) Capacity Resources that cleared an RPM Auction for the first time in the Base Residual Auction for the 2027/2028, or 2028/2029, and 2029/2030 Delivery Years or the Third Incremental Auction for the 2027/2028 Delivery Year may qualify as BYONC to the extent the underlying resource meets the criteria in subsection (b) below.
[. . .]
B. Enabling PJM to Verify DER/DR BYONC
As discussed above, sections VII(b)-(d) set out the timeframes for when BYONC arrangements need to be provided to PJM for verification. Following the initial two years, arrangements need to be provided prior to the commencement of the underlying supply’s RPM participation and, from Delivery Year 2029/2030, prior to finalizing auction parameters for the auction in which the underlying supply first intends to clear. Given that site-level registrations for DR/DER occur immediately prior to the start of a Delivery Year, Voltus proposes three amendments to ensure that this sequence enables DR/DER BYONC in practice. They are: 1. Extension of resource owner certification in VII(a)(ii) to apply to section VI, as well as the existing VIII
The process for BYONC to be in an arrangement with a New Large Load anticipates two key stages: (1) reporting of the arrangement; and (2) certification from the resource owner or contractual authority to PJM attesting to the arrangement and that the capacity will follow the requirements of section VIII. With this process occurring well ahead of the time at which DR/DER sites will be registered, it will not be possible to provide the level of detail needed to determine satisfaction of the section VI requirements. To address this, Voltus is suggesting to add to section VII the supplier’s certification that the capacity will follow the requirements of section
VI. 26
PDF page 27
2. Enabling PJM review of DR/DER BYONC after registrations have been
completed in a Delivery Year
As PJM verification of BYONC occurs prior to registration and the provision of site level information, Voltus is suggesting including an ability for PJM to review DR/DER BYONC after registrations have been completed. This enables a practical check of ensuring capacity brought for the purposes of IRAS is ‘new’, while also allowing for the sequence of BYONC verification prior to load forecast.
3. Clarification that deficiency charges will apply under VIII(d), in the event that the review finds the BYONC arrangement does not meet the
requirements of VI(b)
Mirroring the existing consequence if a resource supporting a BYONC is unavailable, Voltus is suggesting that, should PJM find through their review, or at any time after verification, that BYONC does not meet the requirements of section VI, the deficiency charges process under Tariff, Attachment DD will apply. This clarifies the outcome generally and links into the specific process created by the amendments for certification and review suggested in Sections IV.B.1-2, supra. Redlines for all three amendments discussed in this subsection IV.B are provided in Attachment A.
V.
CONCLUSION
These comments have highlighted first and foremost the need for non-discriminatory treatment of DR and DER resources: it is unjust and unreasonable to determine whole categories of BTM resources, and gigawatts of potential capacity, ineligible to alleviate the growing resource adequacy shortfall through the BYONC construct given that “new” DR/DER can be defined just as effectively as “new” utility-scale generation and storage. The remedy is a definition of BYONC resource eligibility that includes site reactivations and new BTM asset capacity. These comments have also suggested minor modifications to rationalize BYONC 27
PDF page 28
reporting and verification processes in order to ease administrative burden and provide commercial clarity. Reflecting Voltus’s several suggested changes to the Tariff as proposed, a redlined copy of Tariff, Attachment DD-4 is appended to these comments (Attachment A). Voltus respectfully recommends that the Commission direct PJM to adopt the suggested or similar amendments.
Voltus deeply appreciates PJM’s and PJM stakeholders’ significant and ongoing efforts to design an effective and workable solution, and thanks FERC for this opportunity to comment.
Respectfully submitted,
/s/ Kimaya Abreu
Kimaya Abreu
Sr. Manager, Regulatory Affairs
Voltus, Inc.
2443 Fillmore St.
San Francisco, CA 94115
609.994.7686
kabreu@voltus.co
Dated: September 3, 2026
28
PDF page 29
ATTACHMENT A
SUGGESTED REDLINES TO PROPOSED TARIFF, ATTACHMENT DD-4: INTERIM RESOURCE ADEQUACY SERVICE
PDF page 30
I.
INTRODUCTION
This Attachment DD-4 sets forth the terms and conditions governing the provision of Interim Resource Adequacy Service. As more fully set forth in this Attachment and the PJM Manuals, and in conjunction with the Reliability Assurance Agreement:
(a)
Interim Resource Adequacy Service is a load reduction service, effective starting with the 2027/2028 Delivery Year, through which Eligible New Large Loads may be compensated for providing load reductions requested by the Office of the Interconnection to maintain system reliability for the purpose of supporting the integration of New Large Loads to the PJM Region that are not in arrangements with new capacity additions to the PJM Region;
(b)
Starting with the 2027/2028 Delivery Year, the Office of the Interconnection may, in accordance with the Manuals, instruct the implementation of an Interim Resource Adequacy Service Action prior to calling on Pre-Emergency Load Management Reductions Actions after determining that available economic real-time supply may not be sufficient to maintain reserves to meet applicable Reserve Requirements and/or Interconnection Reliability Operating Limits within prescribed limits and prevent cascading outages;
(c)
The Large Load Registry maintained by the Office of the Interconnection,
pursuant to the Reliability Assurance Agreement, shall inform which New Large Loads are eligible to be called on to provide Interim Resource Adequacy Service; and
(d)
The Office of the Interconnection shall coordinate with Electric Distributors, and other Members as appropriate, on the provision of Interim Resource Adequacy Service and the compensation for providing Interim Resource Adequacy Service.
PDF page 31
II.
RESPONSBILITIES OF THE OFFICE OF THE INTERCONNECTION
The Office of the Interconnection shall:
(a)
maintain the Large Load Registry, pursuant to Reliability Assurance Agreement, Schedule 11;
(b)
identify Eligible New Large Loads;
(c)
determine the megawatt quantity of New Large Loads eligible to provide Interim Resource Adequacy Service in each Electric Distributor zone/area for a given Delivery Year;
(d)
starting with the 2027/2028 Delivery Year, issue an Interim Resource Adequacy Service Action based on system conditions; and
(e)
request Electric Distributors to direct that a quantity of Eligible New Large Load Amounts in their respective zone(s)/area(s) be reduced in accordance with an Interim Resource Adequacy Service Action.
PDF page 32
III.
RESPONSBILITIES OF ELECTRIC DISTRIBUTORS
Electric Distributors shall:
(a)
execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in the Electric Distributor’s zone/area, which is an area within a Zone for which the relevant Electric Distributor specifies a separate Obligation Peak Load MW value and is a service area of an Electric Distributor that is a separately identifiable, geographic area bounded by wholesale metering;
(b)
coordinate with the Office of the Interconnection in developing and maintaining the Large Load Registry by providing the Office of the Interconnection any information or data the Electric Distributor believes appropriate to facilitate an accurate Large Load Registry, including applicable state or RERRA retail tariff or contractual obligations;
(c)
coordinate, as appropriate, with the relevant state(s) or RERRA(s), individual Load Serving Entities, and customers served by the Load Serving Entities in its zone/area to support transparent, effective, and orderly deployment of Interim Resource Adequacy Service; and
(d)
implement compensation program consistent with Tariff, Attachment DD-4, section X.
PDF page 33
IV.
DETERMINATION OF MAXIMUM INTERIM RESOURCE ADEQUACY
SERVICE EACH ELIGIBLE NEW LARGE LOAD MAY PROVIDE IN A
DELIVERY YEAR
(a)
All Eligible New Large Loads shall be available to be requested to provide Interim Resource Adequacy Service by the Office of the Interconnection.
(b)
The amount of Interim Resource Adequacy Service available to the Office of the Interconnection may change for each Delivery Year depending on the relationship of the amount of Capacity Resources committed, through Tariff, Attachment DD, for a given Delivery Year, and the Eligible New Large Load Amounts.
(i)
In the event ([the amount of Capacity Resources committed for a given Delivery Year (as determined after the Third Incremental Auction) is less than the PJM Region Reliability Requirement determined prior to the Third Incremental Auction] divided by the Pool-wide Accredited UCAP Factor) by an amount greater than the sum (in MW) of all Eligible New Large Load Amounts, then all Eligible New Large Load Amounts is needed by the Office of the Interconnection to be available to provide Interim Resource Adequacy Service for that Delivery Year;
(ii)
In the event ([the amount of Capacity Resources committed for a given Delivery Year (as determined after the Third Incremental Auction) is less than the PJM Region Reliability Requirement determined prior to the Third Incremental Auction] divided by the Pool-wide Accredited UCAP Factor) by an amount less than the sum (in MW) of all Eligible New Large Load Amounts, then the difference (in MW) shall be the cumulative amount (in MW) of Eligible New Large Load Amounts that the Office of the Interconnection needs to be available to provide Interim Resource Adequacy Service for that Delivery Year; and
(iii)
In the event ([the amount of Capacity Resources committed for a given Delivery Year (as determined after the Third Incremental Auction) equals or exceeds the PJM Region Reliability Requirement determined prior to the Third Incremental Auction] divided by the Pool-wide Accredited UCAP Factor), then the Office of the Interconnection does not need any Eligible New Large Loads to be available to provide Interim Resource Adequacy Service for that Delivery Year.
(c)
For each Delivery Year that meets the requirements of Tariff, Attachment DD-4, sections IV(b)(i) or IV(b)(ii), the Office of the Interconnection shall determine:
(i)
the total amount of Interim Resource Adequacy Service (in MW) needed to be available on a daily basis across the PJM Region for the Delivery Year; and
(ii)
the total amount of Interim Resource Adequacy Service (in MW) needed to be available on a daily basis in each Electric Distributor zone/area for the Delivery Year, which shall be equal to the product of the sum of all Eligible New Large Load Amounts needed in the PJM Region pursuant to Attachment DD-4, section IV(b) multiplied by the quotient of [(the sum of all Eligible New Large Load Amounts in the Electric Distributor’s zone/area) divided by (the sum of all Eligible New Large Load Amounts in the PJM Region)].
PDF page 34
V.
DETERMINATION OF NEW LARGE LOADS ELIGIBILITY TO PROVIDE
INTERIM RESOURCE ADEQUACY SERVICE
(a)
All New Large Loads shall be Eligible New Large Loads to the extent that the sum of a New Large Load’s Eligible New Large Load Amount is lessgreater than the New Large Load’s registered peak load (in MW)zero, as provided in the Large Load Registry. New Large Loads with a cumulative installed capacity equivalent of their BYONC arrangements and assigned Allocated RBP UCAP MW that equals or exceeds the New Large Load’s registered peak load, as provided in the Large Load Registry, shall not be Eligible New Large Loads. New Large Loads that are located within an FRR Service Area cannot be Eligible New Large Loads.
(b)
A New Large Load’s Eligible New Large Load Amount shall be determined as follows:
(New Large Load’s registered peak load (in MW), as provided in the Large Load Registry) minus (the sum of all BYONC arrangements with the New Large Load in accordance with Tariff, Attachment DD-4, section VII divided by the Forecast Pool Requirement for the first Delivery Year in which the BYONC cleared an RPM Auction, plus Allocated RBP UCAP MW assigned to the New Large Load, in accordance with Tariff, Attachment DD-4, section IX divided by the Forecast Pool Requirement for the first Delivery Year in which the Allocated RBP UCAP MW cleared an RPM Auction, plus the value of any Peak Shaving Adjustment attributed to the Large Load in the Large Load Registry).
(c)
For purposes of removing its eligibility to provide Interim Resource Adequacy Service, a New Large Load may enter into arrangements with BYONC supported by one or more resources.
PDF page 35
VI.
BRING YOUR OWN NEW CAPACITY CRITERIA
(a)
(i) Capacity Resources that cleared an RPM Auction for the first time in the Base Residual Auction for the 2027/2028, or 2028/2029, and 2029/2030 Delivery Years or the Third Incremental Auction for the 2027/2028 Delivery Year may qualify as BYONC to the extent the underlying resource meets the criteria in subsection (b) below.
(ii)
Megawatts of Unforced Capacity that have not cleared an RPM Auction, other than those specified in subsection (a)(i) above, may qualify as BYONC to the extent the underlying resource meets the criteria in subsection (b) below. To the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then megawatts of Unforced Capacity may qualify as BYONC to the extent the underlying resource meets the criteria in subsection (b) below and such megawatts (1) have not cleared in an RPM Auction conducted for a Delivery Year prior to the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met and (2) meet the eligibility criteria set forth in Tariff, Attachment DD-4, section VI.
(iii)
With the exception of the RPM Auctions listed in subsection (a)(i) above, to the extent megawatts of Unforced Capacity that have cleared an RPM Auction before any arrangement with a New Large Load based on such megawatts was reported to the Office of the Interconnection, then such megawatts of Unforced Capacity cannot qualify as BYONC even if the underlying resource meets the criteria in subsection (b) below.
(b)
To qualify as Bring Your Own New Capacity, resources must meet the following eligibility requirements:
(i)
For generation and storage resources, the resource must be supported by one of the following:
(1)
a new-build generation resource including new resources that obtain
Capacity Interconnection Rights transferred from deactivated resources or resources that have announced deactivation as of April 10, 2026;
(2)
the incremental capacity created by an uprate of Existing Generation Capacity Resources, but only to the extent such incremental capacity is created through an increase in such Generation Capacity Resource’s
installed capacity and increase in Capacity Interconnection Rights
associated with that Generation Capacity Resource;
(3)
the incremental capacity created by the utilization of Surplus
Interconnection Service;
(4)
repowering of a deactivated generation resource that deactivated prior to April 10, 2026; or
PDF page 36
(5)
incremental capacity, whether due to greater Unforced Capacity or a higher level of Capacity Interconnection Rights, created by an Existing Generation Capacity Resource’s changing fuel type to a more efficient fuel type.
(ii)
For Demand Resources or DER Capacity Aggregation Resources, the resource must qualify as a Planned Demand Resource or DER Capacity Aggregation Resource, as described in the RAA, Schedule 6 and Schedule 6.2 and must be supported by any combination of the following:
(1)sites never previously registered nor otherwise previously supporting a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand;
(2)new-build behind-the-meter generation or storage assets;
(3)reactivations of locations previously registered or otherwise supporting a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand that deactivated prior to, and were not registered in or since, the 2025/2026 Delivery Year.
(1) be composed of, or reliant on, any location not registered in or prior to the 2026/2027 Delivery Year at which an incremental amount at that location is the result of the registration of new generation or storage assets at the location. However, to the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then will be composed of, or reliant on, any location registered in the Delivery Year prior to the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met; and/or
(2) be composed of, or reliant on, locations that were not previously supported a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand for or prior to the 2026/2027 Delivery Year. However, to the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then will be composed of, or reliant on, locations that were not previously supported a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand for the Delivery Year prior to the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met.
PDF page 37
VII.
BRING YOUR OWN NEW CAPACITY ARRANGEMENTS WITH NEW LARGE
LOADS
(a)
For any BYONC to be in an arrangement with a New Large Load,
(i)
the Load Serving Entity serving the New Large Load or the applicable Electric Distributor shall report the BYONC in an arrangement with the New Large Load, in accordance with the PJM Manuals. The Office of the Interconnection may also accept information to the extent interconnection customers, Large Loads, Transmission Owners, or other entities voluntarily report any BYONC that may be in an arrangement with a New Large Load; and
(ii)
the resource owner or entity with contractual authority to enter into a BYONC arrangement must certify to the Office of Interconnection, in accordance with the PJM Manuals, attesting to the arrangement with the New Large Load and that the BYONC will follow the requirements of Tariff, Attachment DD-4, sections VI and VIII.
(b)
For an arrangement between a New Large Load and BYONC to be effective for the 2027/2028 or 2028/2029 Delivery Years, for any BYONC arrangement to be considered, the requirements of Tariff, Attachment DD-4, section VII(a) must be met by April 1 for the first Delivery Year such arrangement is to result in a reduction in the New Large Load’s Eligible New Large Load Amount. By April 15, the Office of the Interconnection shall update the Large Load Registry to reflect any verified arrangements between New Large Loads and BYONC.
(c)
For an arrangement between a New Large Load and BYONC to be effective for the 2029/2030 Delivery Year, for any BYONC arrangement to be considered, the requirements of Tariff, Attachment DD-4, section VII(a) must be reported to the Office of the Interconnection no later than by 50 days prior to the commencement of the 2029/2030 Base Residual Auction or by 30 days prior to the posting of the planning parameters for the Incremental Auctions arrangement for the 2029/2030 Delivery Year. The Office of the Interconnection shall update the Large Load Registry to reflect any verified arrangements between New Large Loads and BYONC after the relevant RPM Auction.
(d)
For an arrangement between a New Large Load and BYONC to be effective for the 2030/2031 Delivery Year and subsequent Delivery Years, the requirements of Tariff, Attachment DD-4, section VII(a) must be reported to the Office of the Interconnection no later than by 30 days prior to the posting of the planning parameters for the relevant RPM Auction for the initial Delivery Year the BYONC enters into an arrangement with the New Large Load. The Office of the Interconnection shall update the Large Load Registry to reflect any verified arrangements between New Large Loads and BYONC after the relevant RPM Auction.
(e)
BYONC that is in an arrangement with a New Large Load must remain in such
arrangement with that New Large Load unless and until the New Large Load is permanently out-of-service.
(f)
A physical resource may support multiple BYONC, each of which may be in an
PDF page 38
arrangement with different New Large Loads, as long as no BYONC is in an arrangement with more than one New Large Load.
(g)
A New Large Load may enter into an arrangement with discrete BYONC supported by different physical resources.
(h)
A New Large Load may enter into an arrangement with BYONC in excess of its current Eligible Large Load Amount, e.g., to allow for expected growth in the New Large Load, and the full megawatt quantity of such BYONC shall be offered in the first RPM Auction for which the New Large Load is included in the Variable Resource Requirement Curve.
(i)
(i) For any generation or storage resource, the Accredited UCAP of any BYONC shall be the Accredited UCAP for the RPM Auction in which the BYONC cleared for the initial Delivery Year the BYONC is in an arrangement with the New Large Load.
(ii) For Demand Resources or DER Capacity Aggregation Resources, the Accredited UCAP shall be the Accredited UCAP for the RPM Auction in which the BYONC cleared for the initial Delivery Year the BYONC is in an arrangement with the New Large Load and must be demonstrated each year for a 10-year period using the Demand Response or DER Capacity Aggregation Resources installed capacity for the first Delivery Year after the BYONC is in an arrangement with the New Large Load. For Demand Resources or DER Capacity Aggregation Resources that are also the actual New Large Load, there is no demonstration required for the initial Delivery Year only to not be an Eligible New Large Load.
PDF page 39
VIII. BRING YOUR OWN NEW CAPACITY PARTICIPATION IN THE
RELIABILITY PRICING MODEL
(a)
All BYONC in an arrangement with a New Large Load must meet the requirements in Tariff, Attachment DD, section 5.5A and become Capacity Resources eligible to participate in RPM Auctions.
(b)
All BYONC in an arrangement with a New Large Load must be offered into the RPM Auctions as Capacity Resources consistent with and pursuant to the capacity must-offer requirements and exceptions set forth in Tariff, Attachment DD, sections 6.6 and 6.6A. BYONC may not seek an exception to the capacity must-offer requirement to provide an external sale, as available under Tariff, Attachment DD, section 6.6(g) for a 10-year period starting with the first Delivery Year which the BYONC is in an arrangement with the New Large Load.
(c)
All BYONC in an arrangement with a New Large Load and committed through RPM Auctions will be subject to all capacity market rules, as set forth in Tariff, Attachments DD and DD-1.
(d)
To the extent the resource supporting a BYONC arrangement:
(i) is reviewed by PJM immediately prior to the start of a Delivery Year, or at any other time, and does not meet the requirements of Tariff, Attachment DD-4, section VI(b); or
(ii) is otherwise unavailable in a given Delivery Year,
the seller of such resource will be subject to all relevant deficiency charges under Tariff, Attachment DD.
(e)
All BYONC in an arrangement with a New Large Load and not qualifying for an exception pursuant to Tariff, Attachment DD, section 6.6(g), must be offered into the applicable RPM Auctions as price takers, i.e., $0/MW-day UCAP for a 10-year period starting with the first Delivery Year which the BYONC is in an arrangement with the New Large Load. To the extent the resource is a Demand Resource or DER Capacity Aggregation Resource, the BYONC shall participate in RPM Auctions for ten (10) consecutive Delivery Years as an Annual Demand Resource or DER Capacity Aggregation Resource, as applicable; provided, however, the seller of such Demand Resource or DER Capacity Aggregation Resource may, in accordance with Tariff, Attachment DD-4, section VII(a)(i) report to the Office of the Interconnection BYONC that replaces such BYONC, where such replacement shall be for the remainder of the replaced BYONC’s ten-year RPM Auction participation commitment and the replaced BYONC (and its supporting registrations) may no longer provide BYONC. In such event, the replacement BYONC would need to be supported by the certification required by Tariff, Attachment DD-4, section VII(a)(ii), and such replacement arrangement must be effective coincident with the initial BYONC releasing its arrangement.
(f)
To the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then any existing BYONC are relieved of the obligations under this Tariff, Attachment DD-4, section VIII.
PDF page 40
IX.
ALLOCATION OF RBP UCAP MW
(a)
Each Electric Distributor zone/area allocated RBP Charges pursuant to Tariff, Attachment DD, section 18.3(a) shall be allocated RBP UCAP MW on a pro-rata basis using the Electric Distributor zone/area’s assigned share of the total Final RBP Target MW across all zone/areas.
(b)
Each New Large Load’s Allocated RBP UCAP MW shall be determined as follows:
(i)
Each Electric Distributor allocated RBP UCAP MW shall inform the Office of the Interconnection how such RBP UCAP MW should be further allocated among the New Large Loads located in the Electric Distributor’s zone/area; or
(ii)
In the event the Electric Distributor has not informed the Office of the Interconnection how its RBP UCAP MW should be further allocated by April 1 before a given Delivery Year, the Office of the Interconnection shall allocate such RBP UCAP MW to the Electric Distributor’s zone/area pro-rata among all New Large Loads located in the zone/area.
(c)
The Office of the Interconnection shall list in the Large Load Registry each New Large Load’s Allocated RBP UCAP MW.
PDF page 41
X.
COMPENSATION FOR PROVIDING INTERIM RESOURCE ADEQUACY
SERVICE
(a)
The rate for the provision of Interim Resource Adequacy Service shall be 50% of the Non-Performance Charge Rate specified in Tariff, Attachment DD, section 10A(e), unless any Eligible New Large Load elects to (i) accept in its retail rates a sum less than 50% of the Non-Performance Charge Rate as compensation for the provision of wholesale Interim Resource Adequacy Service, or (ii) waive receipt in its retail rates any compensation for the provision of wholesale Interim Resource Adequacy Service as contemplated by Tariff, Attachment DD-4, section X(c). If any Eligible New Large Load so elects to accept less than 50% of the Non-Performance Charge Rate or waives in its entirety receipt of compensation for the provision of wholesale Interim Resource Adequacy Service, the wholesale rate for the provision of Interim Resource Adequacy Service shall reflect the accepted sum less than 50% of the Non-Performance Charge Rate or if compensation is waived entirely, the rate shall be zero dollars.
(b)
(i) Following an Interim Resource Adequacy Event, unless the Electric Distributor informs the Office of the Interconnection otherwise in accordance with Tariff, Attachment DD-4, section X(b)(ii), the Electric Distributor shall be responsible for compensating all Eligible New Large Loads that provided Interim Resource Adequacy Service for up to the amount of such service provided. The Electric Distributor shall be responsible for charging customers in its zone/area to fund any such compensation.
(ii)
The Electric Distributor may request the Office of the Interconnection to compensate certain Members for the provision of Interim Resource Adequacy Service and to assess charges on certain Load Serving Entities within the Electric Distributor’s zone/area to fund such compensation. In support of such request, as further set forth in the PJM Manuals, the Electric Distributor shall (1) identify each Member to be compensated and provide the level of compensation and (2) identify each Load Serving Entity to be charged and the level of charge.
(iii)
The Office of the Interconnection, PJMSettlement, and the Members will not assume financial responsibility for the failure of a party to pay any amounts owed to another party under this section. In the event the Electric Distributor requests the Office of the Interconnection facilitate the billing associated with an Interim Resource Adequacy Event, such billing shall be considered a bilateral transaction between the Electric Distributor and the identified Members and PJMSettlement shall not be a contracting party to the settlement.
(c)
Nothing in this Tariff, Attachment DD-4, section X shall interfere with any Eligible New Large Load’s election to (i) accept in its retail rates a sum less than 50% of the Non-Performance Charge Rate as compensation for the provision of wholesale Interim Resource Adequacy Service, or (ii) waive receipt in its retail rates any compensation for the provision of wholesale Interim Resource Adequacy Service.