Comments of Voltus, Inc. on PJM Interconnection LLC’s Federal Power Act Section 205 filing requesting the approval of tariff amendments to establish an…
Text extracted from the eLibrary original (SHA-256 a4c3d375116dbcd4…). Download the original from the official source.
Contents · 18 sections
- II. CLARIFYING THE BYONC CRITERIA FOR DEMAND-SIDE RESOURCES IS
- A. For DR/DER Resources, New Assets and Reactivations May Be Ineligible to Support
- B. New BTM Assets and Site Reactivations Are a Genuine and Substantial Potential Source
- D. In a Context in Which the Private Market Has Been Asked to Proceed Expeditiously with
- E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and
- F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable Resulting in a
- G. The Proposed Test Provides a Concrete Delineation of Potential Reactivations and Is
- H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations Eligible to
- III. PJM’S INCLUSION OF PEAK SHAVING ADJUSTMENTS IN THE LARGE LOAD
- IV. VOLTUS SUGGESTS MINOR REDLINES TO ALIGN BYONC REPORTING
- INTRODUCTION
- E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and
- F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable
- G. The Proposed Test Provides a Concrete Delineation of Potential Reactivations
- H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations
- CONCLUSION
- ATTACHMENT A
- INTRODUCTION
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
To Establish Interim Resource Adequacy Service And A Large Load Registry To Address System Reliability Docket No.Read this passage Filed comments: Registry access
TABLE OF CONTENTS
printed heading
TABLE OF CONTENTS I.Read this passage
II. CLARIFYING THE BYONC CRITERIA FOR DEMAND-SIDE RESOURCES IS
printed heading
II.Read this passage
A. For DR/DER Resources, New Assets and Reactivations May Be Ineligible to Support
printed heading
A.Read this passage
B. New BTM Assets and Site Reactivations Are a Genuine and Substantial Potential Source
printed heading
B.Read this passage
D. In a Context in Which the Private Market Has Been Asked to Proceed Expeditiously with
printed heading
D.Read this passage
E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and
printed heading
E.Read this passage
F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable Resulting in a
printed heading
F.Read this passage
G. The Proposed Test Provides a Concrete Delineation of Potential Reactivations and Is
printed heading
G.Read this passage
H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations Eligible to
printed heading
H.Read this passage
III. PJM’S INCLUSION OF PEAK SHAVING ADJUSTMENTS IN THE LARGE LOAD
printed heading · Topic match: Registry access
III.Read this passage Filed comments: Registry access
IV. VOLTUS SUGGESTS MINOR REDLINES TO ALIGN BYONC REPORTING
printed heading
Adjusting RPM Auctions that Capacity Can Have Cleared Prior to Becoming BYONC..24 B.Read this passage
INTRODUCTION
printed heading · Topic match: Reliability and curtailment
Voltus contends that both categories must be added back to the final tariff and provides a redline to effectuate this change in Section II.E. 3 FERC precedent strongly supports the non-discriminatory treatment of demand-side resources.Read this passage Filed comments: Reliability and curtailment
E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and
printed heading
Doing so creates potential ambiguity as to whether new assets at new or reactivated sites may support BYONC. 3. Line item (3) employs the language and logic of the reactivation definition for FTM generation in VI(b)(i)(4) On the generation/storage side, PJM proposes that the “repowering of a…Read this passage
F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable
printed heading · Topic match: Reliability and curtailment
Thus the appropriate definition of DR/DER reactivations must assess whether a site now out of market would stay out in the normal course of business; in other words, whether it should be considered actually deactivated rather than temporarily unavailable.Read this passage Filed comments: Reliability and curtailment
G. The Proposed Test Provides a Concrete Delineation of Potential Reactivations
printed heading · Topic match: Reliability and curtailment
On the customer/aggregator side, there may be insufficient information available to check eligibility against a longer lookback: a site’s residents, owners, and/or operators may have no recollection or knowledge of long-past DR participation, or may confuse participation in a utility DR program…Read this passage Filed comments: Reliability and curtailment
H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations
printed heading · Topic match: Registry access
IV. VOLTUS SUGGESTS MINOR REDLINES TO ALIGN BYONC REPORTING TIMELINES AS TARIFFED WITH UNDERLYING INTENT A. Adjusting RPM Auctions that Capacity Can Have Cleared Prior to Becoming BYONC Voltus notes a minor inconsistency with the reporting timelines that must be met for BYONC to qualify and…Read this passage Filed comments: Registry access
CONCLUSION
printed heading · Topic match: Reliability and curtailment
CONCLUSION These comments have highlighted first and foremost the need for non-discriminatory treatment of DR and DER resources: it is unjust and unreasonable to determine whole categories of BTM resources, and gigawatts of potential capacity, ineligible to alleviate the growing resource adequacy…Read this passage Filed comments: Reliability and curtailment
ATTACHMENT A
printed heading · Topic match: Reliability and curtailment
ATTACHMENT A SUGGESTED REDLINES TO PROPOSED TARIFF, ATTACHMENT DD-4: INTERIM RESOURCE ADEQUACY SERVICE I.Read this passage Filed comments: Reliability and curtailment
INTRODUCTION
printed heading · Topic match: Reliability and curtailment
IV. DETERMINATION OF MAXIMUM INTERIM RESOURCE ADEQUACY SERVICE EACH ELIGIBLE NEW LARGE LOAD MAY PROVIDE IN A DELIVERY YEAR (a) All Eligible New Large Loads shall be available to be requested to provide Interim Resource Adequacy Service by the Office of the Interconnection. (b) The amount of…Read this passage Filed comments: Reliability and curtailment