ER26-3515-000 · 2026-09-08 · Virginia State Corporation Commission

Motion for Acceptance of Late-Filed Comments and Comments of the Virginia State Corporation Commission on the proposal of PJM Interconnection, L.L.C. to…

Text extracted from the eLibrary original (SHA-256 bfaf79d91cf324f0…). Download the original from the official source.

Contents · 3 sections
  1. I. MOTION FOR ACCEPTANCE OF LATE-FILED COMMENTS p. 2
  2. II. COMMENTS p. 2
  3. III. CONCLUSION p. 5

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Retail and wholesale authority · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

PJM also proposes that the NLLs be eligible for compensation when load is reduced.
Read this passage Filed comments: Reliability and curtailment

I. MOTION FOR ACCEPTANCE OF LATE-FILED COMMENTS

printed heading

MOTION FOR ACCEPTANCE OF LATE-FILED COMMENTS Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure, the VSCC respectfully requests that the Commission accept these late-filed Comments.
Read this passage

II. COMMENTS

printed heading · Topic match: Reliability and curtailment

In this proceeding PJM asks the Commission for authority to implement a curtailment regime that would interrupt retail service to retail NLLs that fail to comply with PJM’s IRAS requirements.
Read this passage Filed comments: Reliability and curtailment

III. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, the VSCC requests that the Commission act in this proceeding to empower state regulatory actions, rather than interfere with these efforts by approving PJM’s IRAS proposal.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Section 385.2010 upon each person designated on the official service list compiled by the Secretary in this proceeding. /s Frederick D.