ER26-3531-000 · 2026-09-08 · Microsoft Corporation
Protest of Microsoft Corporation re American Transmission Company LLC's 08/17/2026 tariff filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
American Transmission Company LLC;
Midcontinent Independent System
Operator, Inc.
)
)
)
Docket No. ER26-3531-000
PROTEST OF MICROSOFT CORPORATION
Pursuant to the Federal Energy Regulatory Commission’s (“Commission’s”)
Combined Notice of Filings #1,1 Microsoft Corporation (“Microsoft”) respectfully submits for the Commission’s consideration these comments on the August 17, 2026 filing of Midcontinent Independent System Operator, Inc. (“MISO”), on behalf of American Transmission Company LLC (“ATC”).2 ATC is one of two MISO utilities that retains local transmission planning responsibilities, with those planning procedures set out in Attachment FF-ATCLLC of MISO’s Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”).3 ATC intends the proposed reforms in this docket to comply with the local transmission planning obligations directed by the Commission in the MISO Show Cause Order4 and to complement MISO’s to-be-filed tariff reforms in compliance with that order.5 Microsoft supports transparent, durable, and nondiscriminatory local transmission planning processes necessary for interconnection and reliable service to transmission
1 Combined Notice of Filings #1, Docket No. ER26-3531-000 (Aug. 17, 2026).
2 Am. Trans. Co. LLC, Proposed Revisions to Attachment FF-ATCLLC of the MISO Tariff in Response to Show Cause Order, Docket No. ER26-3531-000 (Aug. 17, 2026) (“ATC Filing”).3 MISO performs local planning services for all but two of its transmission-owning members.4 Midcontinent Indep. Sys. Op., Inc., Order Instituting Proceeding under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).5 August 17 Filing at 1 (“ATC is proposing certain revisions . . . to fulfill obligations outlined in the Show Cause Order”).
PDF page 2
2
customers on behalf of their large retail loads. As Microsoft explained in a related ATC proceeding,6 as a signatory to the White House Ratepayer Protection Pledge, Microsoft is fully committed to “pay for all new power delivery infrastructure upgrades required to service [] data centers, including adequate network upgrade costs to ensure that these expenses are not passed on to the ordinary household.”7 In this case, however, Microsoft is concerned that ATC’s proposed local planning reforms do not align with the longstanding planning principles of Order No. 890 and fall short of reforms contemplated by the Commission in the Show Cause Order for three primary reasons:
1. ATC’s proposed local planning reforms do not give stakeholders like Microsoft a meaningful role, or even opportunity, to provide input into the planning process, even though this process will determine the facilities, schedule, and cost for which the applicable large retail customer is ultimately liable.
2. The proposed local planning reforms expand ATC’s unilateral exercise of discretion without guardrails and may produce inconsistent and unduly preferential or discriminatory outcomes that have consequences under the Federal Power Act.
3. The proposed local planning reforms require ATC to enter into two different contracts with its customers, but ATC has not filed these contracts as pro forma—nor has it explained why not.8
If ATC’s objective is to provide the same treatment to all transmission customers with large loads, ATC has not explained why it omitted pro forma contracts and will be instead negotiating those agreements separately for each of its transmission customer’s new large
6 Am. Trans. Co. LLC; Midcontinent Indep. Sys. Op., Inc., Protest and Motion for Hearing and Settlement Judge Procedures of Microsoft Corp. at 2, Docket No. ER26-3265-000 (filed Aug. 21, 2026).7 Ratepayer Protection Pledge at P 2, available at https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/8 The contracts are not part of the record in this docket. ATC has not provided them, even for informational purposes.
PDF page 3
3
loads. Moreover, ATC has not shown its reforms to comply fully with the longstanding planning principles of Order No. 890.9
Access to reliable electric service is essential to expand the capacity of cloud computing and artificial intelligence data center sectors, and observance of longstanding, proven utility regulatory principles like open access support the competitive, responsible growth that is necessary for U.S. leadership in the computing industry. If the Commission does not reject the ATC Filing, Microsoft requests that the Commission initiate unconsolidated hearing and settlement judge procedures in this proceeding and in the Docket No. ER26-3265-000 proceeding so that Microsoft and other interested stakeholders may work with ATC to resolve deficiencies in its local transmission planning processes.
I. PROTEST
A. ATC’s local planning reforms to address large load interconnection and service exclude participation by large retail customers like Microsoft.
As noted above, ATC is one of two transmission-owning members of MISO that retain authority over local transmission planning instead of delegating that responsibility to the grid operator. Accordingly, ATC performs local transmission planning pursuant to Attachment FF-ATCLLC of the MISO Tariff.10 As described in Attachment FF-ATCLLC, ATC administers the process for distribution-transmission interconnection planning, which involves planning for interconnection and service to distribution utilities, among other local
9 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 118 FERC ¶ 61,119 (Feb. 16, 2007) (“Order No. 890”); see also Midcontinent Indep. Sys. Op., Inc. and Am. Trans. Co. LLC., Revisions to Attachment FF-ATCLLC of the Midwest ISO Open Access Transmission and Energy Markets Tariff, Docket No. OA08-42-000 (filed Dec. 7, 2007).
10 ATC is not permitted by state law to delegate its local transmission planning authority to MISO or any other entity. See ATC Filing at 2, nn.7, 9.
PDF page 4
4
planning responsibilities. The proposed large load-related changes include adding to Attachment FF-ATCLLC newly defined terms like ATCLLC Large Load, Large Load Interconnection Criteria Confirmation Form, Load Interconnection Request Form, and ATCLLC Local Planning Criteria.11 The changes specifically address interconnection and service to distribution utilities for loads that are equal to or exceed 100 MW, and by extension are intended to capture the new loads of large retail customers like Microsoft. Microsoft has been working collaboratively with ATC and Wisconsin Electric Power Company, dba We Energies (“WEPCo”) to interconnect and serve Microsoft’s large data center campus in Racine County, Wisconsin. Microsoft appreciates ATC’s efforts to support the reliable integration of large retail loads into the transmission system and recognizes that a large retail load like a data center may have a significant grid impact. As a retail customer, Microsoft also recognizes the degree of separation that exists between it and ATC; however, Microsoft respectfully submits that large retail customers are important stakeholders in ATC’s local transmission planning work. As the Commission recognized in the Show Cause Order, stakeholder engagement is part of the tariff revision process.12 The most significant consequence of ATC developing these reforms without broad stakeholder consultation is that the proposed local planning procedures appear to exclude the opportunity for participation by interested large retail customers like Microsoft. Microsoft respectfully submits that local transmission planning processes should give large retail customers the option to participate—for instance, to test and validate local transmission
11 The Large Load Interconnection Criteria Confirmation Form, Load Interconnection Request Form, and ATCLLC Local Planning Criteria are not part of Attachment FF-ATCLLC. Section I.C addresses Microsoft’s concerns that certain agreements referenced in the local planning procedures are not tariffed pro forma agreements.12 See, e.g., Show Cause Order at PP 37, 41, 53, 62, 71, 73-76, 84
PDF page 5
5
needs, to explore solutions to challenges, to support the utility’s consideration of grid- enhancing technologies, or to coordinate on load ramp and in-service timelines. Retail customers’ participation in federally regulated electric matters is not a new concept at all, as the Commission has previously found that end-use retail customers may participate in the formula rate protocol process.13
ATC’s proposed reforms to its local planning process, however, do not contemplate that approach. For example, ATC provides for an “annual process to re-evaluate the ATCLLC Local Planning Criteria and requirements established by ATCLLC’s Business Practices to ensure the ATCLLC Local Planning Criteria and requirements established by ATCLLC’s Business Practices appropriately meet all requirements described herein.”14 Changes coming out of that process would now become effective “immediately following” the posting of the revisions (instead of 30 days after posting as the currently effective Order No. 890-approved procedures provide).15 The tariff reforms do not contemplate the participation of large retail loads in the annual review process. In Microsoft’s view, ATC should provide interested stakeholders with notice of the annual review process (such as by
13 See, e.g., See Am. Elec. Power Serv. Corp., 153 FERC ¶ 61,167 at P 12 (2015) (“As explained below, the Commission concludes that: (1) retail ratepayers may file complaints and protest transmission rates and wholesale power sales rates before the Commission; and (2) allowing retail customers to challenge transmission and wholesale power sales rates does not violate principles of federalism.”). See also id. at P 19 (“As the Commission found in PATH, indirect customers (e.g., retail customers) have a right to intervene and protest rates when some portion of those rates will be flowed through to their retail bill. Ms. Peine has, in fact, intervened in this matter and protested the SWEPCO/AEP Annual Update filings and, therefore, we see no reason to treat her participation any differently than the retail customers in PATH who similarly protested the formula rate updates, but did not intervene.”).14 Attachment FF-ATCLLCA, § V.F. 15Id.
PDF page 6
6
posting on OASIS) and the tariff should provide a meaningful opportunity for large retail customers and other stakeholders to engage with ATC and stress-test proposed changes. With regard to ATC’s process for requesting transmission-distribution
interconnection to serve the large load of a distribution utility, such as WEPCo’s service to Microsoft’s Racine County data center campus, the tariff procedures should permit the large retail customer to participate in Distribution Interconnection Planning Meetings and to access transmission data and planning models. ATC holds distribution interconnection planning meetings only with “individual owners of Distribution Facilities”; it does not include the retail customers even though the purpose of these meetings is to
provide an opportunity for [ATC] to obtain such other information, or to validate previously received information, and to discuss with such
Distribution Facility owners whether the studies or assessments then being performed or which are to be performed, are appropriate to meet their
respective needs, and to determine whether the study models or assessment tools are appropriate for the particular Distribution Interconnection or Distribution Facilities owner’s requirements.16
A large retail customer could contribute meaningfully to these planning discussions. At the bare minimum, the large retail customer should be provided with the “results of [ATC’s] study or assessment” and ATC should have the opportunity to receive the large retail customer’s comments on the study.17
If ATC’s local planning procedures were reformed to provide a large retail customer with the opportunity to participate, it would be reasonable to provide a large retail load access to the same dispute resolution process available to ATC and its distribution utility. ATC’s local planning procedures direct that any dispute in connection with a distribution
16 Id. § VI.A.7. 17Id. § VI.A.8.
PDF page 7
7
interconnection request “shall be handled” in accordance with the process specified in a Distribution-Transmission Interconnection Agreement between ATC and the distribution utility.18 Although a large retail customer is ultimately responsible for the costs of facilities developed during the local planning process,19 even with the large load reforms proposed by ATC in this docket there is not yet an opportunity for that customer to resolve concerns quickly and efficiently through a tariffed alternative dispute resolution process such as the process directed under Order No. 890’s dispute resolution planning principle.20 Instead, the only option available to a large retail customer is to file a section 206 complaint with the Commission. To the extent the Commission intended its Show Cause Order reforms to provide large retail customers with the opportunity for direct engagement, the local planning reforms proposed in this docket do not achieve that objective.
B. ATC’s local planning reforms provide ATC with substantial discretion
and creates risk of undue discrimination and preferential treatment to
similarly situated transmission customers.
Order No. 890 required transmission providers to adopt transmission planning
processes that are coordinated, open, transparent, and comparable because planning decisions can materially affect access to transmission service, project timing, facility requirements, and
18 Id. § VII.C (disputes arising in connection with distribution interconnection requests).19 E.g., Am. Trans. Co. LLC, Comments of the Public Service Commission of Wisconsin at 5, Docket No. ER26-3265-000 (Aug. 14, 2026).20 Nothing in Order No. 890 suggests that the alternative dispute resolution process may foreclose participation of a large retail customer. To the contrary, FERC “encourage[d] transmission providers, customers, and other stakeholders” to utilize Commission resources in developing a tariffed dispute resolution processes. Order No. 890 at P 503; see id. at PP 496-503. See also Order No. 890-A, 121 FERC ¶ 61,297 at PP 217-21 (Dec. 28, 2007); see id. at P 220 (“Any stakeholder that has concerns regarding the dispute resolution mechanism proposed by a transmission provider, or any other aspect of the compliance filing, may bring them to the Commission’s attention on review of the proposal.”).
PDF page 8
8
cost.21 The Commission further recognized in that rulemaking that transmission customers and other stakeholders must have a meaningful opportunity to participate in the planning process and that planning standards must be sufficiently transparent to permit customers to understand and evaluate planning outcomes.
Since its Order No. 890 compliance docket more than two decades ago, ATC’s local planning procedures have remained largely unchanged.22 Here, however, ATC wants to loosen practices with new grants of discretion, undefined readiness requirements, extra-tariff criteria and business practices, discretionary access to its planning models, and to determine what studies, facilities, and upgrades are “necessary” or “appropriate.”23 Nowhere in Attachment FF-ATCLLC are readiness requirements actually specified, even though a distribution customer’s ability to “meet” or “complete” “all applicable readiness requirements” is required to proceed through the local planning process.24 These deficiencies weaken the coordinated, open and transparent transmission planning framework developed under Order No. 890 and increase the likelihood of unduly preferential and discriminatory treatment of transmission customers and, as follows, their large retail customers. For instance:
• Any interested party may request, in writing, copies of the models developed using the assessment tools employed by ATCLLC in performing any planning function or associated analysis or assessment, and ATCLLC may, in its discretion provide copies
21 See, e.g., Order No. 890 at PP 451-54, 460, 471-79; see also id. at P 488 (“The transmission planning required by this Final Rule is intended to provide transmission customers and other stakeholders a meaningful opportunity to engage in planning along with their transmission providers.”).22 See generally Docket No. OA08-42-000 et al.23 E.g., Attachment FF-ATCLLC, §§ III, V.E─V.G., VI.A.2, VI.A.6─VI.A.7, VI.A.10─VI.A.12, VI.B.3─VI.B.4, VI.B.7, VI.C.2, VI.C.4─VI.V.5. 24Id. § VI.A.4.
PDF page 9
9
of such models under appropriate confidentiality agreements, subject to the rules and regulations of the FERC.”25
• “Distribution –Transmission Interconnection Requests are studied or assessed by ATCLLC primarily upon a first come, first served basis upon completion of any applicable readiness requirements.”26 “Each request is studied in the order in which such request meets applicable readiness requirements, unless in ATCLLC’s judgment and determination, require that a later received request should be studied prior to earlier received requests.”27
• “The terms and conditions of the Distribution – Transmission Interconnection Agreement published on ATCLLC’s website may be changed, modified or revised by ATCLLC in its judgment and determination….”28
• “The ATCLLC Local Planning Criteria and requirements established by ATCLLC’s Business Practices may be revised from time to time in response to changes in industry standards, new system conditions, new technologies and new operating procedures, as appropriate and subject to change at any time at ATC’s discretion.”29
• “Change, modification, supplement, or revision to the ATCLLC Local Planning Criteria and/or requirements established by ATCLLC’s Business Practices shall become applicable immediately following the posting by ATCLLC of such revised criteria to the ATCLLC website.”30
• “ATCLLC shall reflect such modifications to existing Distribution Interconnections or proposed new Distribution Interconnections . . . and the Transmission Facilities that are determined to be necessary as a result of such study or studies or other assessment shall be incorporated into such other planning functions . . . to the extent necessary or appropriate to reflect the effect of such request or the Transmission Facilities determined necessary”31
• “To the extent necessary and appropriate, ATCLLC shall incorporate the results of the studies or assessments performed for any and all Distribution – Transmission Interconnection Requests in its network assessment.”3225 Attachment FF-ATCLLCA, § V.G.26 Id. § VI.A.2. 27Id. 28 Id. § IV (definition of Distribution – Transmission Interconnection Agreement).29 Id. § V.F.30 Id.31 Id. § VI.A.11.32 Id.
PDF page 10
10
Microsoft recognizes that transmission providers and transmission owners must confront challenges today that are very different from those that existed when Order No. 890 was issued nearly two decades ago. Microsoft also appreciates ATC’s work to reform its local transmission planning process to address the growing demand associated with large retail loads while maintaining system reliability and preventing inappropriate cost shifts to other customers. As the Commission evaluates ATC’s proposed revisions to Attachment FF- ATCLLC, however, Microsoft respectfully requests that it consider not only whether the proposal addresses the operational challenges posed by large-load interconnections, but also whether the proposal preserves the fundamental structural safeguards of open access transmission service.
C. ATC’s local planning reforms exclude pro forma agreements although
ATC requires the parties to execute these contracts, further
exacerbating the risk of undue discrimination and preferential
treatment.
ATC’s proposal contemplates that transmission customers requesting transmission service for an ATCLLC Large Load will be required to enter into a Minimum Transmission Charge Agreement (“MTCA”) and one or more Large Load Project Commitment Agreements (“LLPCAs”). Microsoft protested these agreements for its Racine County data center campus submitted by ATC in currently pending Docket No. ER26-3265 because as- filed, those agreements contained blatant errors and deficiencies, and raised cost-of-service and open access red flags. As in this proceeding, the agreements at issue in Docket No. ER26-3265 were negotiated without any input or participation from Microsoft, and the consequences of this fact are axiomatic in their structural shortcomings. Microsoft understands that ATC’s preference is that its transmission customers remain subject to the same terms and conditions. Yet Microsoft cannot reconcile this stated
PDF page 11
11
preference with ATC’s decision to omit the MTCA and the LLPCA as pro forma contracts in Attachment FF-ATCLLC. These agreements establish the substantive rights and obligations that will govern the planning, construction, financing, and operation of facilities necessary to serve large loads, and ultimately their terms will flow through to the large load retail customer. Their absence from the Tariff is significant. By requiring customers to enter into agreements that are not part of a generally applicable Tariff in order to receive electric service, ATC introduces a level of discretion that creates a substantial risk that similarly situated customers may be offered materially different terms and conditions. The danger is particularly acute when the agreements are negotiated exclusively between ATC and its affiliates (like WEPCo) without any input from the applicable large load customer, as is the case for the agreements currently pending in Docket No. ER26-3265. The Commission recognizes that pro forma contracts have a role in ensuring that transmission providers administer jurisdictional services on a transparent, consistent, and non-discriminatory basis. Recently, in PJM Interconnection, L.L.C., the Commission explained that where specific contractual provisions provide benefits to interconnection customers, those benefits should be made available through a pro forma agreement “to ensure that all similarly situated interconnection customers are treated on a consistent and fair basis.”33 Likewise, in Southwest Power Pool, Inc., the Commission reminded the grid operator that if it elects to offer a particular form of service, the applicable terms and benefits should be memorialized in a pro forma agreement “to ensure that all similarly-situated interconnection customers are treated on a consistent and fair basis.”34 These precedents recognize the concerns here—
33 PJM Interconnection, L.L.C., 191 FERC ¶ 61,025, at P25 (2025).34 Sw. Power Pool Inc., 128 FERC ¶ 61,191, at P 21 (2009).
PDF page 12
12
transparency and comparability are undermined when contracts for a tariff service are negotiated outside of a generally applicable tariff framework. Because ATC intends the MTCA and the LLPCA to become a standard feature of local transmission planning and service, the terms governing those arrangements should be set in Commission-approved pro forma agreements rather than through individualized negotiations or website-posted contracts that may change over time.
The Commission reached a similar conclusion in MidAmerican Energy Co., where it rejected non-conforming provisions in an interconnection agreement, explaining that the insurance requirements the transmission provider wished to adopt for one interconnection customer should instead be incorporated into the pro forma Large Generator Interconnection Agreement.35 The Commission emphasized there that pro forma agreements are necessary to ensure that all similarly situated customers are “treated on a consistent and fair basis.”36 That safeguard is particularly relevant here because the agreements contemplated by ATC will govern matters that may ultimately determine a large retail customer’s financial exposure, project development obligations, termination rights, security requirements, and long-term service costs. Without Commission-approved pro forma agreements, large retail customers have no assurance that these provisions will be applied consistently from one large project to the next.
35 MidAmerican Energy Co., 116 FERC ¶ 61,018, at P 12 (2006) (“Indeed, MidAmerican’s proposed insurance requirements are tailored to more closely match the need for insurance with the exposure to liabilities by not requiring the full insurance coverage until construction commences. However, these benefits should be made available to all interconnection customers in a transparent, non-discriminatory manner so that MidAmerican cannot favor Pomeroy Wind over the rest of MidAmerican’s customers.”).36 Id.; See also Sw. Power Pool, Inc., 129 FERC ¶ 61,121, at P 13 (2009) (stating that “[t]he use of pro forma documents ensures that interconnection customers receive non-discriminatory service and that all interconnection customers are treated on a consistent and fair basis.”).
PDF page 13
13
ATC has not explained why it did not propose a pro forma MTCA and LLPCA to comply with the Show Cause Order, when pro forma contracts are consistent with longstanding Commission policy and precedent. Permitting ATC to require execution of non- tariffed agreements while reserving discretion over their contents only exacerbates concerns regarding transparency, comparability, and the potential for inconsistent treatment by ATC among its customers.
II. CONCLUSION
Microsoft respectfully requests that the Commission initiate hearing and settlement judge procedures in this proceeding to allow Microsoft and other interested stakeholders to work with ATC to develop robust local planning procures. In the alternative, Microsoft respectfully requests that the Commission reject the proposed tariff changes without prejudice to be refiled.
Respectfully submitted,
Jeffery Riles
Sr. Director of Energy Markets, America
Jordan Weiszhaar
Sr. Manager of Energy Regulatory Strategy,
Americas
Microsoft Corporation
One Microsoft Way
Redmond, WA 98052
Tel: 425.882.8080
jeffriles@microsoft.com
jordanw@microsoft.com
/s/ Kimberly Frank
Kimberly B. Frank
Thomas S. DeVita
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202.778.9064
kimberly.frank@klgates.com
thomas.devita@klgates.com
Coleman Wheeler
K&L Gates LLP
17 North Second Street, 18th Floor
Harrisburg, PA 17101
Tel: 717.231.4820
coleman.wheeler@klgates.com
September 8, 2026
PDF page 14
CERTIFICATE OF SERVICE
I hereby certify that I have this day of September 8, 2026 served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Respectfully submitted,
/s/ Kimberly Frank
Kimberly B. Frank
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202.778.9064
kimberly.frank@klgates.com
September 8, 2026