ER26-3531-000 · 2026-09-08 · Microsoft Corporation

Protest of Microsoft Corporation re American Transmission Company LLC's 08/17/2026 tariff filing

Text extracted from the eLibrary original (SHA-256 3fc2c3cd0ae41f8e…). Download the original from the official source.

Contents · 5 sections
  1. I. PROTEST p. 3
  2. A. ATC’s local planning reforms to address large load interconnection and p. 3
  3. B. ATC’s local planning reforms provide ATC with substantial discretion p. 7
  4. C. ATC’s local planning reforms exclude pro forma agreements although p. 10
  5. II. CONCLUSION p. 13

Read topic-matched comments in ER26-3531

Topics in the text: Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

If the Commission does not reject the ATC Filing, Microsoft requests that the Commission initiate unconsolidated hearing and settlement judge procedures in this proceeding and in the Docket No.
Read this passage Filed comments: Cost allocation

I. PROTEST

printed heading

I.
Read this passage

A. ATC’s local planning reforms to address large load interconnection and

printed heading · Topic match: Cost allocation

Corp., 153 FERC ¶ 61,167 at P 12 (2015) (“As explained below, the Commission concludes that: (1) retail ratepayers may file complaints and protest transmission rates and wholesale power sales rates before the Commission; and (2) allowing retail customers to challenge transmission and wholesale…
Read this passage Filed comments: Cost allocation

B. ATC’s local planning reforms provide ATC with substantial discretion

printed heading · Topic match: Cost allocation

Order No. 890 required transmission providers to adopt transmission planning processes that are coordinated, open, transparent, and comparable because planning decisions can materially affect access to transmission service, project timing, facility requirements, and 18 Id. § VII.C (disputes arising…
Read this passage Filed comments: Cost allocation

C. ATC’s local planning reforms exclude pro forma agreements although

printed heading

ATC’s local planning reforms exclude pro forma agreements although ATC requires the parties to execute these contracts, further exacerbating the risk of undue discrimination and preferential treatment.
Read this passage

II. CONCLUSION

printed heading

CONCLUSION Microsoft respectfully requests that the Commission initiate hearing and settlement judge procedures in this proceeding to allow Microsoft and other interested stakeholders to work with ATC to develop robust local planning procures.