EL25-49-000 · 2026-09-08 · Constellation Energy Generation, LLC
Limited Protest and Comments of Constellation Energy Generation, LLC in response to PJM Interconnection, L.L.C.'s 08/17/2026 Compliance Filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-002
EL25-49-000
Docket No. AD24-11-001
Docket No. EL25-20-001
(consolidated)
Docket No. ER26-1479-000
ER26-1479-002
LIMITED PROTEST AND COMMENTS OF
CONSTELLATION ENERGY GENERATION, LLC
Constellation1 submits this limited protest and comments in response to the PJM
Compliance Filing.2 Two aspects of the PJM Compliance Filing are non-compliant with the June 2026 Co-Location Order.3 First, PJM has not shown that its proposal to delay the availability of Interim Network Integration Transmission Service (“Interim NITS”) until July 1, 2028, is just
1 Constellation Energy Generation, LLC (“Constellation”) files this limited protest and comments pursuant to Rule 211 of the Commission’s Rules of Practice and Procedure. 18 C.F.R. § 385.211 (2026).2 Compliance Filing of PJM Interconnection, L.L.C. in Response to Order on Rehearing, Clarification, Compliance Filing and Paper Hearing in Docket No. EL25-49-002, et al. (Aug. 17, 2026) (“PJM Compliance Filing”).3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 2026 Co-Location Order”).
PDF page 2
2
and reasonable.4 PJM has not explained with any specificity why it will take nearly two more years to implement the service the Commission ordered in December 2025. Second, PJM has not adequately explained the Necessary Study process for Interconnection Customers with existing or ongoing Necessary Studies, as the Commission directed.5 PJM should be required to confirm that customers can rely on the results of prior Necessary Studies where the scope has not changed. Three areas of the PJM Compliance Filing require clarification or further Commission direction. First, PJM should clarify the meaning of “partial NITS” and its ability to immediately provide that service. Second, PJM has added as a prerequisite for Interim NITS the “satisfaction of any technical requirements identified by the applicable Transmission Owner(s).”6 This condition requires reasonable limitations to prevent further Transmission Owner-driven delays in providing service. Finally, the Commission should clarify that Interim NITS service cannot be conditioned on resource adequacy considerations outside of real-time operational necessities.7 PROTEST
I. PJM’s Proposal to Delay the Availability of Interim NITS to July 1, 2028, Is Not Just and Reasonable
The Commission should reject PJM’s proposal to delay Interim NITS Service until July 1, 2028, as PJM has not established that such a prolonged implementation period is just and reasonable. First, PJM fails to “provide[] sufficient information” for the Commission to find such
4 Id. P 597.5 Id. P 283.6 PJM Compliance Filing, Att. A, at Part XI, Subpart A, § 702.4.7 See, e.g., June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 597 (“[W]hile PJM will procure generation capacity in forward capacity auctions to serve Eligible Customers taking FCD transmission service based on the contract demand level, PJM will not consider Interim NITS or NFCD transmission service in its resource adequacy planning.”).
PDF page 3
3
a delay to be just and reasonable.8 The Commission directed that PJM give “serious consideration” to the proposed effective date given the “urgent” nature of large load interconnections.9 Yet PJM justifies its July 1, 2028 implementation date in one conclusory sentence: “PJM Operations personnel will need to implement additional tools and processes before they will be able to monitor and curtail, as needed, the new non-firm Interim NITS product proposed in Tariff, Part XI.”10 That is wholly inadequate. PJM still has not adequately considered “whether Interim NITS … can be made effective at an earlier date,” as the Commission ordered it to do.11 As the June 2026 Co- Location Order explains, the Commission “requires more support for the timeliness of a proposed effective date.”12
Second, PJM’s vague claim that its Operations personnel will need until July 1, 2028, to “implement additional tools and processes” for Interim NITS is hard to square with PJM’s assertion that it can implement Interim Resource Adequacy Service (“IRAS”) by June 1, 2027, less than 10 months after being proposed.13 PJM fails to show that implementing Interim NITS would be any more challenging than implementing IRAS. To implement IRAS, PJM must establish a Large Load Registry, a new “database of information pertaining to Large Loads that will be established and maintained by PJM.”14 PJM will use the Large Load Registry to “identify,
8 Id.9 Id.10 PJM Compliance Filing at 23.11 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 597.12 Id.; see also id. (“[W]e agree with Vistra and Joint Co-Location Developers that PJM’s proposal lacks specificity. In particular, we find that the implementation details for the software updates necessary for PJM’s economic dispatch software and dispatch tools lack specificity.”) (emphasis added).13 Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515-000 (Aug. 13, 2026) (“IRAS Filing”).14 Id. at 5.
PDF page 4
4
for each zone/area, the Eligible New Large Load Amounts, i.e., MW quantities that are eligible to be called upon to reduce load.”15 During emergency conditions, “PJM will instruct Electric Distributors to reduce load by a MW quantity equal to or less than the Electric Distributor’s Eligible New Large Load Amount.”16 In addition, the Electric Distributors must “coordinate, as appropriate, with the relevant state(s) or RERRA(s), individual Load Serving Entities, and customers ... to support transparent, effective, and orderly deployment of [IRAS].”17 PJM does not explain how long that coordination process will take or what it will entail. Nonetheless, PJM proposes to implement IRAS by June 1, 2027, so that “coordination” process must be completed in a matter of months.
These IRAS requirements appear comparable to, if not more complicated (given the involvement of numerous entities other than PJM) than what PJM claims is necessary for Interim NITS: establishing additional tools and processes to monitor and curtail the service. For IRAS, those tools and processes include the Large Load Registry and determination of each Electric Distributor’s Eligible New Large Load Amount. And IRAS may in fact be more complicated because it also requires the coordination process between the Electric Distributors, thirteen states and others to determine “under their own laws, policies, and definition of what constitutes ‘large load’—which resources will be called on to reduce load.”18
In the interest of efficiency, the Commission should exercise its authority under Section 206 of the Federal Power Act to fix a replacement rate and direct PJM to (i) adopt June 1,
15 Id. at 86.16 Id. 17 Id. at 27.18 Id. at 87.
PDF page 5
5
2027, as the date for implementing Interim NITS or (ii) demonstrate that it cannot meet that date and propose the earliest possible date that it can meet. Implementing Interim NITS by June 1, 2027, is just and reasonable as it would remedy an unlawful rate within approximately 18 months of the Commission’s finding. If PJM elects the latter, PJM should provide specific and detailed comments explaining why June 1, 2027, is not feasible and identify all work streams PJM is advancing before the availability of Interim NITS.
II. PJM Fails to Specify the Process for Interconnection Customers with Existing or Ongoing Necessary Studies
PJM fails to address the Commission’s finding that “PJM’s proposed revisions lack clarity with respect to how they apply to Interconnection Customers that have already executed Necessary Study Agreements.”19 As the June 2026 Co-Location Order found, the “scope” of the Necessary Studies “has not changed.”20 And PJM has not “otherwise demonstrate[d]” why “Interconnection Customers seeking to serve Co-Located Load cannot rely on the results of Necessary Studies that have already been performed if the scope of the study has not changed.”21
The Commission should specifically order PJM to clarify that Necessary Studies need not be repeated where their scope is the same as previously conducted Necessary Studies. The Necessary Studies process can take years.22 Requiring duplicative studies without justification would unnecessarily delay the interconnection of large loads and cannot be just and reasonable.
19 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 283.20 Id.21 Id.22 Under ideal conditions, PJM identifies a Necessary Study process of 270 days, but the process can take much longer. See Limited Request for Rehearing and Clarification of Constellation Energy Generation, LLC, Docket No. EL25- 49-000, et al., at 7 (“Constellation has been waiting years for Necessary Studies for multiple projects ….”).
PDF page 6
6
CLARIFICATION
I. PJM’s Comment That It Can Provide “Partial NITS” Requires Further Explanation On compliance, PJM states that “[a]t present, PJM can provide partial NITS, i.e., NITS in an amount less than requested and/or for a term shorter than requested, to Co-Located Load through the Necessary Study process and therefore is proposing an October 17, 2026 effective date for the bulk of the revisions proposed in this filing.”23 The Commission should require PJM to clarify several aspects of this proposal.
First, PJM should clarify what “partial NITS” is, whether it is a new or existing transmission service, and which revisions are included in “the bulk.”
Second, PJM should clarify its reference to the Necessary Study process, as it is unclear how that process applies to PJM’s provision of “partial NITS” or Interim NITS. As the Commission explained, “the studies applicable to a transmission service request … are distinct from the Necessary Study process, which studies the modification of a generator interconnection.”24 In addition to explaining what it means, PJM also should clarify that the Necessary Study process can proceed at the same time as the study process for NITS and Interim NITS conducted by PJM. This is particularly appropriate when the co-location arrangement subject to the Necessary Study is one that will use NITS and Interim NITS services, which will not require delisting of the generator. This in turn will make it much less likely that the results would identify additions, modifications, or replacements to the Transmission System necessary
23 PJM Compliance Filing at 23.24 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 286.
PDF page 7
7
to maintain system reliability.25 Interim NITS is an entirely front-of-the-meter service where PJM will ultimately serve the entire load when standard NITS can be provided.
Constellation emphasizes that even under ideal conditions, PJM’s Necessary Study
process takes 270 days,26 and in practice, the process often takes much longer.27 Conditioning the provision of Interim NITS on the Necessary Studies could cause significant delay, making it even more important that the implementation date be June 1, 2027.
II. Transmission Owner Technical Requirements Should Be Subject to Reasonable
Limitations
PJM’s proposed Section 702.4 adds “satisfaction of any technical requirements identified by the applicable Transmission Owner(s)” as a “Technical Requirement[] Prior to Commencement of Service.”28 This requirement was not included in PJM’s Initial Brief,29 nor did the June 2026 Co-Location Order require PJM to add it.30
While Transmission Owners have a role in determining whether Interim NITS can be
reliably provided, reasonable processes and limitations on Transmission Owner-imposed technical requirements are necessary to ensure that Eligible Customers taking Interim NITS are not subject
25 PJM Compliance Filing, Att. A, at Part VIII, Subpart A, § 401.H.3.c (“Transmission Provider shall assess the impact of the reduction in Capacity Interconnection Rights associated with the planned Eligible Load and Eligible Generating Facility ….”).26 Tariff, Part IX, Subpart G, § 15 (Form of Necessary Studies Agreement) (“Transmission Provider’s good faith estimate for the time of completion of the Necessary Studies is within 270 days of the date Transmission Provider approves the dynamic model and data submitted by Project Developer ….”).27 Supra note 22.28 PJM Compliance Filing, Att. A, at Part XI, Subpart A, § 702.4.29 See PJM Initial Brief, Att. A, at Part XI, Subpart A, § 702.4 (listing six technical requirements, not including the requirement for “satisfaction of any technical requirements identified by the applicable Transmission Owner(s)”).30 See generally June 2026 Co-Location Order, 195 FERC ¶ 61,209 at PP 571-578 (discussing the Commission’s determination on the terms and conditions of Interim NITS).
PDF page 8
8
to undue delay or burden. Absent such limitations, a Transmission Owner could raise a technical requirement late in the process, further delaying the availability of Interim NITS. Reasonable limitations should include requiring Transmission Owners to identify applicable technical
requirements at the time they provide feedback on transmission studies, requiring all Transmission Owner technical requirements to be on file with the Commission,31 and prohibiting Transmission Owners from imposing technical requirements that are duplicative of PJM’s technical
requirements where redundancy is not justified.32
III. PJM May Not Condition the Availability of Interim NITS on Resource Adequacy
Considerations
Constellation is concerned that PJM’s proposed tariff revisions will allow for anticipated resource adequacy concerns to form a basis for denying or limiting Interim NITS requests. That would be contrary to the Commission’s intent. As the Commission explained, “PJM will not
consider Interim NITS … in its resource adequacy planning.”33 The Commission recognized that “increasing amounts of new Co-Located Load seeking to be served by an Eligible Customer faster than equivalent generation can come online may create resource adequacy problems,”34 but found
31 See also Response Brief of Constellation Energy Generation, LLC at 12 (Apr. 24, 2026) (“[T]he Commission should require PJM’s and Transmission Owners’ standards, requirements, guidance, and practices on Co-Location Arrangements to be on file with the Commission on a standalone basis or reflected in PJM’s Tariff. Rules for Co- Location Arrangements must be clearly stated and available as they ‘significantly affect rates, terms and conditions’ of service and can be ‘readily susceptible to specification.’”) (citation omitted).32 See, e.g., id. at 13-18 (explaining requiring double protection schemes by default is “unsupported” and “unduly discriminatory”).33 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 597. 34 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 236 (2025); id. P 201 (“Regarding broader resource adequacy and reliability concerns associated with maintaining sufficient generation to serve Co-Located Load, we reiterate that load growth generally involves resource adequacy and reliability considerations, regardless of whether the new load is Co-Located Load.”); see also id. P 243 (finding “there is not sufficient evidence to conclude that additional Tariff changes regarding Interconnection Customers electing to use their generation facilities to serve Co-
PDF page 9
9
that Eligible Customers should be able to take service on behalf of Co-Located Loads that are “willing and able to limit their energy withdrawals from the transmission system under certain conditions.”35 The solution was not to bar Co-Located Loads from being timely served but to allow Interim NITS and other interruptible services and curtail when circumstances required. Nevertheless, two tariff provisions raise this concern that PJM may attempt to condition Interim NITS on anticipated resource adequacy shortfalls. Section 702.3 provides that PJM will determine the amount of Interim NITS that “can be provided reliably … while maintaining the reliability of the Transmission System” based on study procedures in “Tariff, Part XI, Subpart A, Section 704”36—yet that section in turn states only that PJM will determine whether “additional studies are needed” and if so, PJM will inform the “Eligible Customer of those studies as soon as practicable.”37 Section 705.1 provides that PJM may “curtail Interim NITS for capacity or reserve shortages as further set forth in the PJM Manuals”38 but does not identify the particular Manual or specify that it is referring to real-time capacity or reserve shortages. The Commission should confirm that a projection of resource adequacy is not a prerequisite for finding that PJM can reliably provide Interim NITS.
CONCLUSION
For the foregoing reasons, Constellation requests that the Commission require PJM to:
(1) make Interim NITS available by June 1, 2027, or explain why it cannot and propose the earliest
Located Load are needed with respect to capacity market rules, reliability, and resource adequacy to ensure that the PJM Tariff remains just and reasonable”).
35 Id. P 160. 36 PJM Compliance Filing, Att. A, at Part XI, Subpart A, § 702.3.37 Id. § 704.1.38 Id. § 705.1.
PDF page 10
10
feasible date; (2) clarify that Necessary Studies need not be repeated where existing or ongoing Necessary Studies sufficiently cover the circumstance; (3) clarify the meaning of “partial NITS” and its proposal to provide that service immediately; (4) impose reasonable limitations on Transmission Owner technical requirements; and (5) implement its proposed tariff in a manner that does not use resource adequacy as a basis for denying or limiting Interim NITS requests.
Respectfully submitted,
/s/ Seth T. Lucia
September 8, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
Christopher A. Wilson
Vice President, Federal Regulatory Affairs
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Seth T. Lucia
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
seth.lucia@constellation.com
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
202-799-4538
carolyn.clarkin@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC
PDF page 11
CERTIFICATE OF SERVICE
I hereby certify that I have on this 8th day of September, 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026).