Limited Protest and Comments of Constellation Energy Generation, LLC in response to PJM Interconnection, L.L.C.'s 08/17/2026 Compliance Filing
Text extracted from the eLibrary original (SHA-256 7e427e4752eb0f83…). Download the original from the official source.
Contents · 6 sections
- I. PJM’s Proposal to Delay the Availability of Interim NITS to July 1, 2028, Is Not Just
- II. PJM Fails to Specify the Process for Interconnection Customers with Existing or
- I. PJM’s Comment That It Can Provide “Partial NITS” Requires Further Explanation
- II. Transmission Owner Technical Requirements Should Be Subject to Reasonable
- III. PJM May Not Condition the Availability of Interim NITS on Resource Adequacy
- CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Reliability and curtailment · Connecting load and generation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Finally, the Commission should clarify that Interim NITS service cannot be conditioned on resource adequacy considerations outside of real-time operational necessities.7 PROTESTRead this passage Filed comments: Reliability and curtailment
I. PJM’s Proposal to Delay the Availability of Interim NITS to July 1, 2028, Is Not Just
printed heading · Topic match: Registry access
To implement IRAS, PJM must establish a Large Load Registry, a new “database of information pertaining to Large Loads that will be established and maintained by PJM.”14 PJM will use the Large Load Registry to “identify, 8 Id. 9 Id. 10 PJM Compliance Filing at 23. 11 June 2026 Co-Location Order, 195…Read this passage Filed comments: Registry access
II. PJM Fails to Specify the Process for Interconnection Customers with Existing or
printed heading · Topic match: Connecting load and generation
See Limited Request for Rehearing and Clarification of Constellation Energy Generation, LLC, Docket No.Read this passage Filed comments: Connecting load and generation
I. PJM’s Comment That It Can Provide “Partial NITS” Requires Further Explanation
printed heading · Topic match: Connecting load and generation
PJM’s Comment That It Can Provide “Partial NITS” Requires Further Explanation On compliance, PJM states that “[a]t present, PJM can provide partial NITS, i.e., NITS in an amount less than requested and/or for a term shorter than requested, to Co-Located Load through the Necessary Study process and…Read this passage Filed comments: Connecting load and generation
II. Transmission Owner Technical Requirements Should Be Subject to Reasonable
printed heading
A, at Part VIII, Subpart A, § 401.H.3.c (“Transmission Provider shall assess the impact of the reduction in Capacity Interconnection Rights associated with the planned Eligible Load and Eligible Generating Facility ….”). 26 Tariff, Part IX, Subpart G, § 15 (Form of Necessary Studies Agreement)…Read this passage
III. PJM May Not Condition the Availability of Interim NITS on Resource Adequacy
printed heading · Topic match: Reliability and curtailment
PJM May Not Condition the Availability of Interim NITS on Resource Adequacy Considerations Constellation is concerned that PJM’s proposed tariff revisions will allow for anticipated resource adequacy concerns to form a basis for denying or limiting Interim NITS requests.Read this passage Filed comments: Reliability and curtailment
CONCLUSION
printed heading · Topic match: Reliability and curtailment
CONCLUSION For the foregoing reasons, Constellation requests that the Commission require PJM to: (1) make Interim NITS available by June 1, 2027, or explain why it cannot and propose the earliest Located Load are needed with respect to capacity market rules, reliability, and resource adequacy to…Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Clarkin DLA Piper LLP (US) 500 Eighth Street NW Washington, D.C. 20004 202-799-4538 carolyn.clarkin@us.dlapiper.comRead this passage