Motion for Leave to File Comments Out-of-Time and Comments of CyrusOne, LP on the proposal of PJM Interconnection, L.L.C. to Establish Interim Resource…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C. )
Docket No. ER26-3515-000
MOTION FOR LEAVE TO FILE COMMENTS OUT-OF-TIME AND
COMMENTS OF CYRUSONE, LP
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”)1, CyrusOne, LP (“CyrusOne”) respectfully submits this motion for leave to file its comments out-of-time (the “Motion”), together with its accompanying comments, on the filing by PJM Interconnection, L.L.C. (“PJM”) to establish an Interim Resource Adequacy Service and a Large Load Registry, submitted on August 13, 2026 (the “IRAS Filing”). As grounds for the Motion, and in support of the Comments, CyrusOne states as follows.
I. MOTION FOR LEAVE TO FILE COMMENTS OUT-OF-TIME
Rule 214 authorizes the Commission to grant a late-filed motion to intervene, and the Commission has broad discretion under Rule 101(e) to waive or extend its procedural rules for good cause where doing so serves the public interest and does not prejudice other parties.2 The Commission routinely accepts late-filed comments and protests in section 205 proceedings where acceptance would not disrupt the proceeding, would not prejudice other parties, and would assist the Commission in developing a complete and well-informed record.3
1 18 C.F.R. §§ 385.212, 385.213.
2 18 C.F.R. §§ 385.214, 385.101(e).3 See, e.g., Southwest Power Pool, Inc., 193 FERC ¶ 61,244 at P 68 (2025) (accepting out-of-time comments); PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 at P 13 (2025) (accepting out-of-time comments and out-of-time protest); PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 at P 83 (2024) (accepting out-of-time comments).
PDF page 2
2
Granting this Motion will not delay this proceeding or disrupt the Commission’s consideration of the IRAS Filing. The Motion and the accompanying Comments are being filed only a short time after the September 3, 2026 deadline due to administrative oversight, well in advance of any Commission action on the IRAS Filing. Granting this Motion to submit comments out of time will not disrupt these proceedings, prejudice existing parties, or create additional burdens for existing parties. Acceptance of CyrusOne’s Comments will benefit the Commission by ensuring a more complete record. CyrusOne is a significant developer and operator of data center facilities within the PJM Region and, as such, brings a direct, practical perspective on the operational and commercial consequences of the IRAS Filing for New Large Loads, including with respect to the treatment of multi-phase data center campuses and the interaction between the IRAS Filing’s proposed Large Load definitions and existing, previously negotiated retail service arrangements.
For these reasons, CyrusOne respectfully submits that good cause exists for the Commission to exercise its discretion under Rule 214 and Rule 101(e) to accept CyrusOne’s Comments out-of-time.
II. BACKGROUND
CyrusOne has been developing data centers for over 25 years as a global developer, owner, and operator, including several multi-year, multi-phase campuses that may be subject to PJM’s Reliability Backstop Procurement (“RBP”) and IRAS proposals. CyrusOne is a leading global data center developer and operator, providing mission-critical infrastructure for cloud providers, enterprises, and hyperscale customers. CyrusOne’s leading global platform of hybrid- cloud and multi-cloud deployments offers customers colocation, hyperscale and build-to-suit environments, which help enhance the strategic connections of their essential data infrastructure
PDF page 3
3
and support the achievement of sustainability goals. CyrusOne’s operations rely on dependable, robust, and economical electricity to support high-density computing environments that enable digital transformation across industries. CyrusOne is a signatory to the Ratepayer Protection Pledge.
CyrusOne frequently develops multiple, separately contracted facilities in phases over a period of years, at times including facilities located within close proximity to one another but built for different customers, on different timelines, and under separate service arrangements. CyrusOne would be a “New Large Load” within the meaning of the IRAS Filing with respect to qualifying load, and its facilities and expansion plans would be directly affected by the proposed Large Load and New Large Load definitions, the Large Load Registry, and the resulting IRAS curtailment framework. CyrusOne has made significant investment and construction decisions in several states within PJM. Our existing sites should not be seen or classified as “new” and have undergone years of studies, development, long lead equipment purchases, and include tenant contracts for capacity for years extending beyond 2026. Implementation of IRAS poses uncertainty and risk to projects that have been under development for several years.
I. COMMENTS OF CYRUSONE
CyrusOne submits these Comments to identify and recommend specific, targeted changes to the IRAS Filing’s proposed tariff language that, as written, creates unnecessary uncertainty for New Large Loads seeking to procure new capacity and comply with the proposed framework in good faith. For example, while CyrusOne often develops our sites to include backup emergency generation, the intention is to use that resource for testing and emergency purposes only. It is CyrusOne’s position that these resources should be utilized in a manner consistent with state and
PDF page 4
4
federal laws. If the Commission accepts the IRAS Filing, CyrusOne respectfully requests that the Commission direct PJM to clarify or modify the provisions identified below.
A. The Definition of “Large Load” Should be Revised to Eliminate the One Mile Radius Requirement, or in the Alternative be Revised to Make a Rebuttable
Presumption that Projects within a One-Mile Radius are Independent.
The IRAS Filing defines “Large Load” to mean end-use customer load with a cumulative peak load of 50 MW or greater at a single electrical site, and provides that, for configurations involving multiple affiliated load facilities or points of interconnection, all affiliated load facilities within a one-mile radius will be considered a single electrical site.4 PJM states that this one-mile radius rule is adapted from the Commission’s Qualifying Facility siting rules under Order No. 872.5
CyrusOne is concerned that this rule, as proposed, does not account for the way data center campuses are actually developed and financed. CyrusOne, like other data center developers, frequently constructs multiple, separately contracted facilities within a one-mile radius of one another and of existing operating facilities, on different timelines, for different customers, and under separate service and financing arrangements. Aggregating such facilities into a single electrical site based on proximity alone, without regard to whether they are commercially, contractually, or electrically independent, risks two specific consequences that CyrusOne believes the Commission did not intend. First, it could potentially cause an existing, already-operational facility to become newly subject to IRAS curtailment risk solely because a later, unrelated facility happens to be developed nearby, even though the existing facility’s capacity needs were accounted for and arranged years earlier. Second, it could cause multiple
4 IRAS Filing, Proposed Reliability Assurance Agreement, Definitions – Large Load. 5 IRAS Filing at 33 & n.95 (citing Qualifying Facility Rates and Requirements Implementation Issues Under the Public Utility Regulatory Policies Act of 1978, Order No. 872, 172 FERC ¶ 61,041, order on reh’g, Order No. 872- A, 173 FERC ¶ 61,158 (2020)).
PDF page 5
5
facilities that individually fall below the 50 MW Large Load threshold to be aggregated and thereby newly subjected to IRAS, based solely on their geographic proximity rather than any shared electrical or commercial relationship.
CyrusOne’s concerns in this respect are consistent with, and reinforced by, the comments filed by Equinix Inc. in this docket. Equinix has documented, through concrete examples from its own facilities in Northern Virginia’s Data Center Alley, that the same 100 megawatts of incremental load can be treated as 0 megawatts, 60 megawatts, or 100 megawatts of IRAS- eligible load depending solely on how that load happens to be geographically distributed among affiliated facilities, with no relationship to the actual resource adequacy risk presented.6 Equinix has requested that the Commission either eliminate the one-mile aggregation rule or, in the alternative, direct PJM to treat it as a rebuttable presumption, allowing an affected customer to demonstrate that affiliated facilities are properly treated as separate electrical sites based on factors such as separate service arrangements, separate points of interconnection, separate ownership and control, development history, and electrical and operational independence.7 CyrusOne agrees that the one-mile aggregation rule should be eliminated. With respect to an alternative to elimination, CyrusOne believes that the presumption should be that the facilities within a one-mile radius are independent and not aggregated for purposes applying the Large Load definition. Placing the burden on PJM, rather than on the affected customer, is the more just and reasonable allocation because PJM, not the customer, is the party proposing to depart from the ordinary rule that each electrical site is evaluated on its own. The one-mile radius rule was not developed through the stakeholder process but was instead imported from the
6 Protest, Request for Clarification and Comments of Equinix Inc., Docket No. ER26-3515-000 at 13-14 (Sept. 3, 2026) (“Equinix Comments”).7 Equinix Comments at 3, 14.
PDF page 6
6
Commission’s Qualifying Facility siting rules, which govern generation siting for an entirely different purpose, and applied to data center campuses without any reasoned account of why data centers, which cluster for latency, interconnection, and other commercial reasons entirely unrelated to energy, should be treated the same as generating facilities for aggregation purposes.
Requiring PJM to identify and prove those same facts as a threshold matter, before aggregating facilities that would otherwise be treated as independent, ensures the rule is applied only where PJM can affirmatively demonstrate that the facilities function as a single integrated site, rather than sweeping in longstanding, independently developed campuses by default. Such a demonstration could include, for example, confirming the presence of a contract or utility agreement showing that the facilities share a common point of interconnection, common ownership or control, or another arrangement establishing that the facilities are electrically or contractually connected, rather than merely located near one another. For these reasons, CyrusOne’s preferred outcome is elimination of the one-mile aggregation rule altogether. Should the Commission nonetheless decline to eliminate the rule, CyrusOne requests that the Commission direct PJM to adopt a rebuttable presumption that affiliated facilities within a one- mile radius are separate electrical sites, with PJM bearing the burden of demonstrating that specific facilities are sufficiently integrated to warrant aggregation.
B. IRAS Should Not Apply to Incremental Load Added Before June 1, 2027 or Load Served Under Pre-Existing Binding Retail Service Agreements.
The IRAS Filing defines “New Large Load” to include, among other things, incremental load in service after June 1, 2027 that increases existing end-use customer load at a site that did not previously meet the Large Load definition.8 PJM’s transmittal letter indicates that the Large
8 IRAS Filing, Proposed Reliability Assurance Agreement, Definitions – Large Load.
PDF page 7
7
Load Registry is intended to track the in-service date of each increment of load, together with a facility’s peak load and ramp schedule, in order to determine which increments are properly treated as New Large Load. CyrusOne notes that this June 1, 2027 cutoff does not operate in isolation from one-mile radius aggregation rule discussed above. Because the one-mile aggregation rule can cause otherwise independent, previously developed facilities to be combined into a single electrical site, that aggregation can in turn cause a facility to newly cross the Large Load threshold and subject unrelated, previously arranged load to New Large Load treatment based on its in-service date. These two provisions are therefore problematic in combination, and CyrusOne requests that the Commission consider and address their interaction together, not solely as separate issues.9
The proposed tariff language does not clearly implement PJM’s stated intent for the Large Load Registry to track in-service dates and ramp schedules to determine which increments are New Large Load. The New Large Load definition appears to capture only the specific increment that causes a previously smaller site to first cross the 50 megawatt Large Load threshold. It does not clearly address subsequent increments at a site that already qualifies as a Large Load. It also does not state whether the resulting New Large Load designation applies only to the qualifying increment or to the entire registered peak load of the site.10 This ambiguity is directly relevant to CyrusOne’s facilities, many of which will be coming into service over a multi-year ramp that will continue after June 1, 2027, and are or will be energized in phases. To the extent the Commission determines that multi-year, multi-phase existing projects such as CyrusOne's should nonetheless be included within the New Large Load definition, CyrusOne
9 IRAS Filing at 36-45.10 IRAS Filing, Proposed Reliability Assurance Agreement, Definitions – Large Load; see also Equinix Comments at 8.
PDF page 8
8
requests that the Commission direct PJM to provide a reasonable transition mechanism for such projects, such as a phase-in period or grandfathering of load increments tied to service arrangements or construction commitments made before the IRAS Filing, to avoid disrupting projects that have been under development for years in reliance on the pre-existing regulatory framework.
CyrusOne accordingly requests that the Commission direct PJM to: (1) clarify that only the incremental load added after June 1, 2027 that itself causes a site to newly cross the Large Load threshold, or that is added at a site already so qualified, is treated as New Large Load, rather than the entirety of an existing facility’s registered peak load; and (2) exclude from the New Large Load definition any load, including its contractual ramp, that is already covered by a binding retail service agreement executed before the date of the IRAS Filing.11 Absent such clarification, New Large Loads like CyrusOne cannot determine with confidence the amount of Bring Your Own New Capacity (“BYONC”) they would need to procure to avoid IRAS exposure, which undermines the very objective the IRAS Filing is intended to serve.
C. PJM Should Further Explain the Basis for Excluding New Large Loads from
the VRR Curve Beginning with the 2029/2030 Delivery Year.
The IRAS Filing proposes, beginning with the 2029/2030 Delivery Year, to exclude New Large Loads that lack sufficient BYONC or Allocated RBP Unforced Capacity (“UCAP”) megawatts from the Variable Resource Requirement (“VRR”) Curve used in the Reliability Pricing Model auctions, in order to protect existing customers from capacity price increases attributable to those loads.12 CyrusOne understands and does not dispute PJM’s stated ratepayer- protection rationale for this exclusion. CyrusOne notes, however, that other commenters have
11 This request is consistent with the relief requested by Equinix. See Equinix Comments at 3, 17.12 IRAS Filing at 5-6.
PDF page 9
9
raised a related question that CyrusOne believes warrants further explanation: because the exclusion removes certain New Large Load demand from the auction, it may also reduce the price signal that would otherwise encourage new generation investment to serve that same load.13 CyrusOne respectfully requests that PJM clarify how the VRR Curve exclusion is intended to interact with, rather than undermine, the incentive for New Large Loads and capacity suppliers to bring new supply to the PJM Region.
II. CONCLUSION
For the foregoing reasons, CyrusOne respectfully requests that the Commission (1) grant the Motion and accept these Comments for consideration in this proceeding, and (2) if the Commission accepts the IRAS Filing, direct PJM to: (a) adopt a rebuttable presumption for the one-mile aggregation rule as applied to independently developed facilities, with PJM bearing the burden of demonstrating sufficient affiliation to trigger the New Large Load designation; (b) clarify the treatment of incremental load and ramp schedules under the New Large Load definition, exclude load under pre-existing binding retail service agreements, and address the compounding interaction between the one-mile aggregation rule and the June 1, 2027 cutoff; (c) provide a reasonable transition mechanism for multi-year, multi-phase existing projects if such projects are included within the New Large Load definition; and (d) further explain the basis for, and intended interaction of, the proposed VRR Curve exclusion with incentives for new generation investment.
13 See, e.g., Comments of Microsoft Corporation, Docket No. ER26-3515-000 at 9 (Sept. 3, 2026).
PDF page 10
10
/s/ Michael Blackwell_____
Kevin Marquardt
Michael Blackwell
CyrusOne, LP
Linda Walsh
2850 N Harwood Street, Suite 2200
Husch Blackwell LLP
Dallas, TX 75201
1801 Pennsylvania Ave., NW, Suite 1000
kmarquardt@cyrusone.com
Washington, DC 20006
Tel: (202) 378-2300
michael.blackwell@huschblackwell.com
linda.walsh@huschblackwell.com
Counsel to CyrusOne LP
Dated: September 11, 2026
PDF page 11
11
CERTIFICATE OF SERVICE
Pursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C. this 11th day of September 2026.
/s/ Emily Starobin
Emily Starobin