Motion for Leave to File Comments Out-of-Time and Comments of CyrusOne, LP on the proposal of PJM Interconnection, L.L.C. to Establish Interim Resource…
Text extracted from the eLibrary original (SHA-256 d497a424eb9092cd…). Download the original from the official source.
Contents · 7 sections
- I. MOTION FOR LEAVE TO FILE COMMENTS OUT-OF-TIME
- II. BACKGROUND
- I. COMMENTS OF CYRUSONE
- A. The Definition of “Large Load” Should be Revised to Eliminate the One Mile
- B. IRAS Should Not Apply to Incremental Load Added Before June 1, 2027 or Load
- C. PJM Should Further Explain the Basis for Excluding New Large Loads from
- II. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Registry access · Reliability and curtailment · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
ER26-3515-000 MOTION FOR LEAVE TO FILE COMMENTS OUT-OF-TIME AND COMMENTS OF CYRUSONE, LP Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”)1, CyrusOne, LP (“CyrusOne”) respectfully submits this motion for…Read this passage Filed comments: Registry access
I. MOTION FOR LEAVE TO FILE COMMENTS OUT-OF-TIME
printed heading · Topic match: Retail and wholesale authority
CyrusOne is a significant developer and operator of data center facilities within the PJM Region and, as such, brings a direct, practical perspective on the operational and commercial consequences of the IRAS Filing for New Large Loads, including with respect to the treatment of multi-phase data…Read this passage Filed comments: Retail and wholesale authority
II. BACKGROUND
printed heading · Topic match: Cost allocation
CyrusOne is a signatory to the Ratepayer Protection Pledge.Read this passage Filed comments: Cost allocation
I. COMMENTS OF CYRUSONE
printed heading
If the Commission accepts the IRAS Filing, CyrusOne respectfully requests that the Commission direct PJM to clarify or modify the provisions identified below.Read this passage
A. The Definition of “Large Load” Should be Revised to Eliminate the One Mile
printed heading · Topic match: Reliability and curtailment
Should the Commission nonetheless decline to eliminate the rule, CyrusOne requests that the Commission direct PJM to adopt a rebuttable presumption that affiliated facilities within a one- mile radius are separate electrical sites, with PJM bearing the burden of demonstrating that specific…Read this passage Filed comments: Reliability and curtailment
B. IRAS Should Not Apply to Incremental Load Added Before June 1, 2027 or Load
printed heading · Topic match: Registry access
These two provisions are therefore problematic in combination, and CyrusOne requests that the Commission consider and address their interaction together, not solely as separate issues.9 The proposed tariff language does not clearly implement PJM’s stated intent for the Large Load Registry to track…Read this passage Filed comments: Registry access
C. PJM Should Further Explain the Basis for Excluding New Large Loads from
printed heading · Topic match: Cost allocation
The IRAS Filing proposes, beginning with the 2029/2030 Delivery Year, to exclude New Large Loads that lack sufficient BYONC or Allocated RBP Unforced Capacity (“UCAP”) megawatts from the Variable Resource Requirement (“VRR”) Curve used in the Reliability Pricing Model auctions, in order to protect…Read this passage Filed comments: Cost allocation
II. CONCLUSION
printed heading · Topic match: Retail and wholesale authority
CONCLUSION For the foregoing reasons, CyrusOne respectfully requests that the Commission (1) grant the Motion and accept these Comments for consideration in this proceeding, and (2) if the Commission accepts the IRAS Filing, direct PJM to: (a) adopt a rebuttable presumption for the one-mile…Read this passage Filed comments: Retail and wholesale authority
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 11th day of September 2026. /s/ Emily Starobin Emily Starobin Husch Blackwell LLP 1801 Pennsylvania Ave.Read this passage