ER26-3380-000 · 2026-09-15 · PPL Electric Utilities Corporation
Motion for Leave to Answer and Answer of PPL Electric Utilities Corporation to the 09/10/2026 Motion for Leave to Answer and Answer of PJM Interconnection,…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
Docket No. ER26-3380-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
PPL ELECTRIC UTILITIES CORPORATION
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s
(“Commission”) Rules of Practice and Procedure,1 PPL Electric Utilities Corporation (“PPL Electric”) submits this answer (“Answer”) to the September 10, 2026 Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. (“PJM”) in the above-captioned
proceeding.2 PPL Electric files this Answer for the sole purpose of correcting a factual mischaracterization of its Rate Schedule LP-6 that appears on page 92 of PJM’s Answer.
I. MOTION FOR LEAVE TO ANSWER
While an answer to an answer or protest is not a matter of right under the Commission’s regulations,3 the Commission routinely permits such answers when the answer provides useful and relevant information that will assist the Commission in its decision-making process,41 18 C.F.R. §§ 385.212, 385.213.2 PJM Interconnection, L.L.C., Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-3380-000 (Sept. 10, 2026) (“PJM’s Answer”).3 18 C.F.R. § 385.213(a)(2).4 See, e.g., Pioneer Transmission, LLC v. N. Ind. Pub. Serv. Co. and Midwest Indep. Transmission Sys. Op., Inc., 140 FERC ¶ 61,057, at P 94 (2012); Sw. Power Pool, Inc., 131 FERC ¶ 61,252, at P 19 (2010), reh’g denied, 137 FERC ¶ 61,075 (2011) (accepting answers that “provided information that assisted us in our decision-making process”); Duke Energy Ky., Inc., 122 FERC ¶ 61,182, at P 25 (2008) (accepting answers to a
PDF page 2
2
corrects factual inaccuracies and clarifies the issues,5 provides information helpful to the disposition of an issue,6 or permits the issues to be narrowed.7 This Answer will assist the Commission in its decision-making process, corrects factual inaccuracies and clarifies the issues, and provides information helpful to the disposition of an issue. Accordingly, PPL Electric respectfully requests that the Commission grant leave and accept this Answer.
II. ANSWER
A. PJM’s Characterization of PPL Electric’s Rate Schedule LP-6 is
Inaccurate and its use as Support for the Proposed LSE RBP Credit
Requirement is Misplaced.
PJM’s Answer cites to the Pennsylvania Public Utility Commission’s approval of PPL Electric’s Rate Schedule LP-6 as support for PJM’s position that its proposed Load Serving Entity (“LSE”) Reliability Backstop Procurement (“RBP”) credit requirements are reasonable, and as evidence that LSEs in PJM are already requiring security from large loads to cover the costs to serve those large loads.8 While PPL Electric understands PJM’s intent in citing examples of large load security practices, Rate Schedule LP-6 is not an appropriate comparison, or an accurate example of such requirements being applied in this context. To clarify, Rate Schedule LP-6 governs infrastructure investment and minimum load commitments associated with the delivery of retail electric service that PPL Electric provides
protest that “provided information that assisted us in our decision-making process”); Tallgrass Transmission, LLC, 125 FERC ¶ 61,248, at P 26 (2008), reh’g denied, 150 FERC ¶ 61,224 (2015); PJM Interconnection, L.L.C., 120 FERC ¶ 61,083, at P 23 (2007) (answer to protests permitted when it provides information to assist the Commission in its decision-making process); Entergy Servs. Inc., 126 FERC ¶ 61,227, at P. 76 (2009).
5 See, e.g., PJM Interconnection, L.L.C., 84 FERC ¶ 61,224, at 62,078 (1998).6 See, e.g., CNG Transmission Corp., 89 FERC ¶ 61,100, at 61,287, n.11 (1999).7 See, e.g., New Energy Ventures, Inc. v. S. Cal. Edison Co., 82 FERC ¶ 61,335, at 62,323, n.1 (1998).8 See PJM’s Answer at 92.
PDF page 3
3
in its capacity as an Electric Distribution Company (“EDC”) in Pennsylvania, not in its role as an LSE in Pennsylvania (a restructured state). Accordingly, Rate Schedule LP-6 does not contain provisions that govern wholesale capacity procurement and generation supply to large loads, nor does it relate to the buyer-side credit obligations that PJM’s RBP proposal would impose on LSEs to cover the cost of capacity secured through the RBP.
While it is true that PPL Electric is a designated LSE within PJM as a signatory to the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”),9 and that PPL Electric is a provider of last resort under Pennsylvania’s Electricity Generation Customer Choice and Competition Act, 66 Pa.C.S.A. § 2801, et seq, PPL Electric does not currently serve as the LSE of record for any large load customers taking retail service pursuant to Rate Schedule LP-6, nor does it anticipate that large load customers will seek to use provider of last resort service to meet their capacity needs. Rate Schedule LP-6 does not relate to PPL Electric’s role or obligations as an LSE and does not address the security or collateral that may be required to be posted to satisfy RBP credit obligations that could be assigned to PPL Electric in its distinct capacity as an LSE within PJM. Accordingly, PJM’s specific reliance on Rate Schedule LP-6 for this proposition is misplaced and inaccurate and requires correction in the record of this proceeding.
9 The RAA is currently located under PJM’s “Intra-PJM Tariffs” eTariff title, available here: https://etariff.ferc.gov/TariffBrowser.aspx?tid=1731.
PDF page 4
4
III. CONCLUSION
In accordance with the foregoing, PPL Electric respectfully requests that the Commission grant leave and accept this Answer into the record of this proceeding.
Respectfully submitted,
Steven Nadel
Senior Counsel
PPL Services Corporation
645 Hamilton Street, Suite 601
Allentown, PA 18101
Tel: 610.774.4102
SMNadel@pplweb.com
/s/ Thomas DeVita
Kimberly B. Frank
Thomas S. DeVita
Stuart B. Robbins
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202.778.9064
kimberly.frank@klgates.com
thomas.devita@klgates.com
stuart.robbins@klgates.com
September 15, 2026
PDF page 5
CERTIFICATE OF SERVICE
I hereby certify that I have this day of September 15, 2026 served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Respectfully submitted,
/s/ Stuart Robbins
Stuart B. Robbins
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202.778.9064
stuart.robbins@klgates.com
September 15, 2026