Motion for Leave to Answer and Answer of PPL Electric Utilities Corporation to the 09/10/2026 Motion for Leave to Answer and Answer of PJM Interconnection,…
Text extracted from the eLibrary original (SHA-256 437882bcc71754e3…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in ER26-3380
Topics in the text: Credit and exit · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) ) ) Docket No.Read this passage
I. MOTION FOR LEAVE TO ANSWER
printed heading
Accordingly, PPL Electric respectfully requests that the Commission grant leave and accept this Answer.Read this passage
II. ANSWER
printed heading
II.Read this passage
A. PJM’s Characterization of PPL Electric’s Rate Schedule LP-6 is
printed heading · Topic match: Credit and exit
PJM’s Characterization of PPL Electric’s Rate Schedule LP-6 is Inaccurate and its use as Support for the Proposed LSE RBP Credit Requirement is Misplaced.Read this passage Filed comments: Credit and exit
III. CONCLUSION
printed heading
CONCLUSION In accordance with the foregoing, PPL Electric respectfully requests that the Commission grant leave and accept this Answer into the record of this proceeding.Read this passage
CERTIFICATE OF SERVICE
printed heading
Washington, DC 20006 Tel: 202.778.9064 stuart.robbins@klgates.com September 15, 2026Read this passage