ER26-3515-000 · 2026-09-16 · Josh Shapiro, Governor of the Commonwealth of Pennsylvania

Motion for Leave to Answer and Answer of Josh Shapiro, Governor of the Commonwealth of Pennsylvania in Support of PJM Interconnection, LLC’s proposal to…

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
PJM Interconnection, LLC
)
Docket No. ER26-3515
)

MOTION FOR LEAVE TO ANSWER AND ANSWER OF PENNSYLVANIA
GOVERNOR JOSH SHAPIRO IN SUPPORT OF PJM’S PROPOSAL TO
ESTABLISH INTERIM RESOURCE ADEQUACY SERVICE AND A LARGE
LOAD REGISTRY

Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure,1 Pennsylvania Governor Josh Shapiro (Governor Shapiro) respectfully submits this motion for leave to answer and answer in support of PJM Interconnection, LLC’s (PJM) proposal pursuant to Federal Power Act (FPA) Section 205 to establish Interim Resource Adequacy Service (IRAS) and a Large Load Registry. The Commission should grant leave to answer to clarify certain issues and assist the Commission with its decision-making.

I. SUMMARY
PJM faces a crisis: large load growth has overwhelmed the region’s ability to serve that new demand in a reliable manner, driving skyrocketing costs and increasing the risk of reliability events, which may require manual load shed to protect the bulk power system.2 In that serious

1 18 C.F.R. §§ 385.211, 385.214.
2 PJM Transmittal at 13 (“Year-over-year, the shortfall of capacity supply needed to meet demand . . . has grown despite a net increase of 1,294.4 MW of Installed Capacity . . . the addition of new supply has not kept pace with rapid large load demand growth”); Opening remarks of Chair Swett, AD26-7 Transcript at 9 (July 23, 2026) (“PJM is the tip of the spear, it's the laboratory of national and economic security on which our country may rise or fall”); Opening remarks of Deputy Sec. of Energy Danly, AD26-7 Transcript at 32-34 (“PJM is a mess . . . Two auctions in a row that failed to meet the capacity requirement. That is not a functioning market.”); Opening remarks of Senior Director of White House National Energy Dominance

PDF page 2

2
context, IRAS is a critical measure to protect the region’s reliability and its ratepayers, consistent with the Governors’ and the Administration’s Statement of Principles3 and the Ratepayer Protection Pledge.4 The central thesis for those documents was that the data centers that are predominantly causing the present reliability crisis and spurring the need for new energy infrastructure should bear its costs. Pennsylvania is doing its part to meet the moment, advancing solutions to the current crisis within the Commonwealth—as described by the Pennsylvania Public Utility Commission in its filing in this docket—but no state can address the looming reliability emergency singlehandedly. PJM’s proposed mandatory, region-wide pre-emergency IRAS program is a necessary short-term fix to protect Pennsylvania residents and business—as well as PJM customers broadly—from the unjust and unreasonable harm of resource adequacy shortfall and related power outages.

Opponents raise three principal objections to PJM’s proposal, none of which warrant its rejection.5

First, protestors are wrong that PJM has veered beyond its jurisdiction. PJM is squarely in its lane to operate the bulk power system in order to maintain system reliability including, where

Council Lake, AD26-7 Transcript at 45-46 (“PJM is clearly broken, multiple failed capacity markets, capacity auctions, sky high price increases.”).

3 National Energy Dominance Council within the White House and Undersigned Governors, Statement of Principles Regarding PJM, https://www.energy.gov/documents/statement- principles-regarding-pjm.
4 The White House, President Trump’s Ratepayer Protection Pledge Secures American AI Dominance, Protects Consumers (July 23, 2026), https://www.whitehouse.gov/releases/2026/07/president-trumps-ratepayer-protection-pledge- secures-american-ai-dominance-protects-consumers/.
5 The Governor Shapiro focuses on challenges to the core design features of IRAS raised in the protests of the Data Coalition Center (DCC); Google; Vistra; Talen; Constellation; EPSA; and P3. Filers raise a host of other, less central, objections to IRAS. Because PJM has consented to modifications of its proposal consistent with NRG, if the Commission finds any validity to such objections, it may direct PJM to file tariff modifications sufficient to address them.

PDF page 3

3
necessary, directing the curtailment of load. Under its proposal, PJM properly leaves the task to the retail authority to determine which individual retail customers face disruption of service due to changes in system-level operation. PJM has also appropriately provided solicitude to the states by granting retail authorities a direct role in determining whether to provide wholesale compensation based on the curtailments directed under IRAS and, if so, how much compensation up to the cap proposed by PJM.

Second, opponents incorrectly argue that IRAS unduly discriminates against new large loads6 and/or existing generators.7 The new large computational loads that are causing the current strain on the region’s infrastructure are not similarly situated to other loads due to their unique features. Their addition is not organic load growth that might cause the need for rapid system expansion and new supply in the ordinary course. It is a new and distinct threat to reliability and affordability in the region. Treating these new loads as distinct matches reality. Likewise, it is not discriminatory to recognize the difference between a capacity resource that is already committed to serve system needs and a resource that has not yet assumed such a commitment. To the contrary, it is common sense to distinguish between new capacity that is available to serve new large loads, and existing capacity that is not. This is wholly consistent with designing a reliability construct that directs curtailment signals to zones/areas hosting new large loads that have not secured sufficient new capacity to meet their needs.

Third, protestors’ remaining arguments are largely contradictory, revealing the weakness of those objections. For example, some argue that IRAS will not be effective in incenting new large loads to bring their own capacity because only retail authorities, not PJM, decide which

6 DCC Protest at 26-30; Google Protest at 11-13; Constellation Protest at 30-37; Vistra Protest at
11. 7 Constellation Protest at 37-40; Vistra Protest at 12-14.

PDF page 4

4
specific retail customers are allocated a share of zonal load curtailment8 but at the same time insist IRAS is too stringent, will disrupt expectations, and new large loads need a longer transition period to be just and reasonable.9 Both allegations cannot be true. Rather, IRAS is just and reasonable because it will increase the incentive for new large loads to invest in new capacity in order to decrease the likelihood that they face curtailment of their operations. IRAS is also just and reasonable because a given zone only faces the planning horizon risk of pre-emergency curtailment proportionate to the share of new large loads that fail to meet their own need for supply, which the zone has allowed to interconnect. The aspect of curtailment that PJM controls, i.e., operation of the bulk power system and aggregate MW limitations on service imposed at the zonal transmission system-level, is appropriate and commensurate with the risks posed to the bulk power system. PJM is not responsible for, and IRAS cannot be deemed unjust and unreasonable due to, actions (i.e., allocation of zonal curtailment to individual customers) that later may occur through the independent decision of a state retail authority.

Protestors also object to removal of new large loads that do not Bring Your Own New Capacity (BYONC) from the VRR Curve10; but that treatment is precisely the actual result of implementing IRAS. In periods of capacity shortage when IRAS is in effect, new large loads will not be served by system resources during periods of system strain. It is just and reasonable to isolate demand that is not being served by system capacity from being reflected in the demand curve. Exclusion of such load is necessary to accurately reflect the needs that are expected to be

8 Google Protest at 3 (“IRAS will not incentivize new large loads to bring their own capacity”).
9 DCC Protest at 35 (requesting, if it does not reject IRAS, that the Commission direct PJM to include a “meaningful transition” that limits application of IRAS). 10 Google Protest at 23-24.

PDF page 5

5
served by system resources, and to protect existing customers from costs that they did not contribute to. Likewise, objections to PJM’s proposed order of curtailment are policy judgments that do not render the design unjust and unreasonable. Rather, PJM’s design of IRAS to curtail zones/areas with large load growth not matched by new supply before calling on demand response products is an appropriate choice to protect existing customers because flipping that order would reduce available capacity to meet regional needs by deterring demand response registration.

In addition to their legal flaws, many of these protests fly in the face of commitments the same protestors already made in the Ratepayer Protection Pledge, and are essentially an argument that the new capacity needed to serve data centers must be paid for by all PJM customers through higher capacity market prices rather than by the actual cost-causers. IRAS is both just and reasonable and critical to vindicate the shared commitment in the Governors’ and the Administration’s Statement of Principles to “allocate costs to data centers . . . to load serving entities with new data centers that have not self-procured new capacity or agreed to be curtailable.”

PJM’s proposal of IRAS is necessary and appropriate in response to the severe challenges facing the region. Protestors’ intimations that PJM ignored better alternatives such as a state-led curtailment regime is legally irrelevant, but also incorrect.11 PJM’s decision to implement a mandatory, pre-emergency, region-wide solution is necessary leadership and serves to protect customers in response to requests from many state entities for such a uniform regional approach. States can, of course, independently implement actions within their jurisdictional authority to mitigate the challenges of large load growth, but they face the risk that such actions are not

11 DCC Protest at 2-4; Google Protest at 23-25.

PDF page 6

6
compatible with or recognized under PJM’s tariff, or that other states fail to take commensurate action.12 Failure to implement a consistent approach throughout the region could lead to a patchwork strategy that could frustrate PJM’s real-time operations and fail to achieve the goals of the implementing states.13 Given the urgency of this situation, only coordinated, region-wide action like IRAS can mitigate the severe cost and reliability challenges caused by large load growth imminently exceeding available supply. Governor Shapiro therefore urges the Commission to approve IRAS without delay, as timely implementation is critical to have IRAS in effect in time to avoid disruption of service for existing customers and to ensure its rate- protective effects are in place before the next Base Residual Auction in December.

12 For example, in a recent Virginia State Corporation Commission proceeding to establish large load connection queue process standards Dominion asserted that it could not consider the impacts of load flexibility to reduce impacts on the transmission system or resource adequacy in load interconnection studies because of PJM system planning requirements. Dominion asserted that “PJM must first establish governing rules and analytical frameworks necessary to evaluate non-firm or flexible load in both planning studies and system operations.” Similarly, Dominion asserted that “implementation of any fast-track or accelerated connection mechanism” for flexible loads “requires PJM rulemaking and FERC guidance.” Dominion, Rebuttal Testimony of Jacqueline R. Vitiello, Exhibit No. 25, VA SCC Case No. PUR-2026-00011, at 15-17 (filed Apr. 30, 2026), https://www.scc.virginia.gov/docketsearch/DOCS/8c2n01!.PDF; see also Dominion, Rebuttal Testimony of R. Matthew Gardner, Exhibit No. 21, VA SCC Case No. PUR-2026- 00011, at 7-8 (filed Apr. 30, 2026), https://www.scc.virginia.gov/docketsearch/DOCS/8c2j01!.PDF (“the Company needs FERC and PJM to take action on developing a formal framework for non-firm or flexible load planning and establish rules around a customer bringing its own new generation before the Company can begin to implement that framework.”). Dominion thus articulated the case for a coherent federal regulatory approach as proposed by PJM in IRAS. State regulators face barriers to know when the potential for inconsistency with a federal jurisdictional scheme genuinely warrant delay, or when such concerns lack merit and are raised to delay costly or burdensome reforms.
13 For example, PJM’s capacity shortage emergency procedures in Manual 13 for manual load dumps after EEA3 generally assign load shed requests to deficient zones. However, if the PJM Mid-Atlantic Region (MAAC) is deficient, the load shed is further allocated by the load shed allocation table in Attachment E. As such, a state within MAAC could implement a voluntary state IRAS program, and zones within that state could still face emergency EEA3 curtailments based on actions of other states and zones within MAAC.

PDF page 7

7
II. ANSWER IN SUPPORT OF IRAS
A. IRAS properly targets wholesale sales and reliable operation of the bulk
power system.
Protestors variously characterize IRAS as “aim[ing] to interrupt retail service”; “compel[ing] states . . . to conform their retail curtailment frameworks to PJM tariff requirements”;14 “target[ing] retail customers . . . by mak[ing] the characteristics of the retail customer . . . the basis for a curtailment obligation”15; and failing to “directly affect wholesale rates.”16 None of these descriptions match the basic facts of PJM’s proposal. As PJM explains IRAS is a “supplemental capacity product” that may be called upon during “an Interim Resource Adequacy Service Action,” an action PJM anticipates will occur when it “is no longer able to maintain reserves within the RTO or zone” or “there are insufficient resources to keep [Interconnection Reliability Operating Limits] within defined operating limits in order to prevent instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the interconnection.”17 PJM’s proposal is manifestly aimed at provision of a wholesale product or service, and at ensuring reliable operation of the bulk power system; each is clearly within its jurisdiction. Indeed, actions that would be possible under IRAS are no different from other actions (or “Operating Instructions,” as defined by NERC) that PJM has long been authorized to take as the region’s Reliability Coordinator, Transmission Operator, and Balancing Authority.18 The Operating Agreement already expressly grants PJM the authority to coordinate curtailment

14 DCC Protest at 3.
15 Google Protest at 8-9.
16 Constellation Protest at 26-27.
17 PJM Transmittal at 75.
18 Id. at 81 (“Under the terms of the Operating Agreement and as the Reliability Coordinator, Transmission Operator, and Balancing Authority, PJM has the authority and flexibility to initiate Emergency Procedures as it sees fit to maintain the reliability of the PJM Region”).

PDF page 8

8
of load19; where PJM determines the aggregate amount of MW load reduction required to be curtailed in a zone or area and the Transmission Owner or Electric Distributor determines the end-use entities that are ultimately curtailed. IRAS differs in only two ways, each of which is just and reasonable and neither of which matters for PJM’s jurisdiction: (1) the implementation of curtailment signals prior to an EEA 1, and (2) the means by which PJM will determine the aggregate MW of load reduction directed within a zone or area. Implementing IRAS on a pre- emergency basis prior to a NERC EEA 1 will avoid escalating emergency procedures that include but are not limited to shortage pricing and public calls for conservation, which would represent socialization of costs, both financial and reliability related, being imposed by non- capacity backed new large loads upon all customers. For target MW reductions, PJM proposes to limit the total MWs of load reduction in a zone or area based on the share of new large loads (which PJM terms “Eligible New Large Loads”) that have failed to meet their capacity needs through BYONC or capacity procured pursuant to Reliability Backstop Procurement (RBP) rules.20 However, PJM does not direct the curtailment of these loads, rather it uses these criteria to set the aggregate MW reduction amount. It remains up to the retail authority to work with entities within their jurisdiction to implement the retail end-user curtailment priority. PJM’s focus on non-capacity backed new large loads to determine the MW reduction target in each zone or area is appropriate, since these entities are precipitating the reliability emergency. Duly targeting load reductions in zones or areas with non-capacity backed new large loads as a means to potentially avoid emergency procedures is a just and reasonable method for avoiding unjust

19 PJM, OA Schedule 1 Sec 1.6, OA Schedule 1 Sec 1.6 Office of the Interconnection (3.1.0), § 1.6.2 (v) and (vii) (“The Office of the Interconnection shall . . . Determine and declare than an Emergency is expected to exist . . . . Coordinate the curtailment of shedding of load. . . .”).

20 PJM Transmittal at 86-87.

PDF page 9

9
and unreasonable outcomes of shortage pricing and potential curtailment for existing PJM customers who have paid for the embedded costs of the existing system and have not contributed to the resource adequacy shortfall. Furthermore, the focus on zones or areas projected to have capacity shortfalls in real-time—through the existence of non-capacity backed large loads in the planning horizon—is consistent with PJM’s Operating Agreement Schedule 1, Section 1.7.11 which states that in an emergency “the Office of the Interconnection may not order a manual load dump in a Control Zone solely to address capacity deficiencies in another Control Zone.”21 In other words, PJM is appropriately aligning IRAS with existing practices that generally limit curtailment signals to zones with real-time capacity shortfalls.

In short, PJM is asserting no new novel authority in proposing IRAS, but rather is enhancing its deployment of existing tools to better ensure bulk system reliability (directing loadshed to areas with concentrations of non-capacity backed new large loads) and equitable wholesale market rates (more fairly allocating the risk of curtailment to zones or areas of the grid that have most contributed to the problem).

Protestors acknowledge that PJM does not propose to direct the curtailment of any specific retail customer.22 In fact, PJM’s inability (and its disavowal of any attempt to do so) to control the curtailment priority among individual retail customers is simultaneously a point of contention for protestors.23 But protestors cannot logically claim both that PJM’s proposal

21 PJM, OA, OA Schedule 1 Sec 1.7, OA Schedule 1 Sec 1.7 General. (21.1.0), § 1.7.11.
22 DCC Protest at 11 (“it will not curtail specific end-use customers directly, but will direct Electric Distributors to curtail these customers’ demand”); Constellation Protest at 20 (PJM “leav[es] to the state regulatory sphere the choice of which particular identifiable retail customers will be subject to curtailment under IRAS”).
23 See Google Protest at 1-2 (calling PJM’s inability to direct curtailment of individual retail customers the “fundamental flaw”, “basic misalignment”, and “regulatory disconnect” of the IRAS proposal); Vistra Protest at 4 (calling IRAS an “illusory construct” because “there is no

PDF page 10

10
unlawfully “targets retail customers” and that PJM’s proposal is fatally flawed because it cannot guarantee which individual retail customers are curtailed. Both cannot be true. Stripped of embellishment, the facts are straightforward: under IRAS, PJM can only direct “a MW quantity of load reduction to the relevant Electric Distributer zone(s)/area(s)”24—it neither targets nor directs specific retail customers to be subject to curtailment, nor compels or restricts the authority of the retail authority to prioritize among the retail customers that must be curtailed in order to meet the required MW quantity of bulk load reduction and safeguard the reliability of the grid. This is what PJM and other balancing authorities have long existed to do. Protestors also make much of the fact that PJM’s determination of the MW quantity of bulk load reduction is based upon the characteristics of retail customers in the relevant Electric Distributer’s zone or area—i.e., that PJM proposes to base its curtailment of wholesale customers on whether the load growth in that zone or area is comprised of new Large Loads (i.e., a large and concentrated addition of 50 MW or more at the same electrical location) and whether such new Large Load additions have been matched by addition of commensurate new supply (new capacity in the form of BYONC or allocated RBP resources).

Protestors’ position appears to be that PJM must blind itself—that it is legally barred from acting on information about the characteristics of load growth in a zone or area, even if that information is directly relevant to reliable operation of the bulk power system and enables PJM to provide a just and reasonable wholesale product or service. There is no merit to this position.

assurance that new large loads will receive the purported benefit of BYONC because it is up to states and EDCs to decide curtailment orders and priorities”).

24 PJM Transmittal at 86.

PDF page 11

11
The caselaw on jurisdiction under the FPA has never drawn such rigid and restrictive boundaries on the information that is plainly relevant to setting a wholesale rate.25 The characteristics of retail loads and generation, both matters that reflect state regulation, are highly relevant and essential to inform a wholesale rate. Taking this information into account in designing the wholesale rate does not constitute regulation of those matters. It rather merely constitutes prudent regulation of wholesale rates in light of the “fact . . . that the wholesale and retail markets in electricity, as in every other known product, are not hermetically sealed from each other.”26

If adopted by the Commission, the protestors’ position would bar PJM from taking into consideration information about generating facilities—ramp rates, minimum run times, outage rates, and so on—because neither the Commission nor PJM have authority to directly regulate generation. This jurisdictional rule would be absurd and unworkable if applied to generating facilities in the context of running a wholesale energy or capacity market, and it is equally so if applied to retail loads. PJM is not barred from seeking information about the nature of the load growth in a zone, even if those matters are subject to retail jurisdiction, and using that information to shape wholesale market rates.

25 FERC v. EPSA, 577 U.S. 260, 281-282 (2016) (“When FERC regulates what takes place on the wholesale market, as part of carrying out its charge to improve how that market runs, then no matter the effect on retail rates, § 824(b) imposes no bar.” (emphasis added)); see also Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 387–88 (2015) (rejecting the “Platonic ideal” that there should be a clear division between areas of state and federal authority).
26 FERC v. EPSA, 577 U.S. 260, 281 (2016).

PDF page 12

12
B. PJM’s proposed compensation framework provides appropriate solicitude to
the states and is jurisdictionally sound.
Protestors separately challenge PJM’s provision of an opportunity for wholesale compensation for loads that provide IRAS as prescribing a retail rate.27 A number of state regulators who have not otherwise challenged IRAS raise questions and concerns about the proposed compensation structure, and some request that PJM or the Commission clarify that the wholesale compensation proposal is not aimed at or a limitation on state authority to regulate the retail rate.28 While Governor Shapiro is sympathetic to states’ requests to clarify these provisions, so clarified, the proposal is jurisdictionally sound. Rather than target or set retail rates, PJM’s proposal appropriately recognizes the states’ interests and affords states a unique, but not unprecedented, role in implementing the wholesale market rate. Under established Commission precedent upheld by the Supreme Court, availability of a wholesale rate may depend on retail conditions, as PJM proposes here.

Governor Shapiro understands the confusion that has resulted from PJM’s provision of wholesale compensation for a wholesale service because it envisions making that wholesale compensation level subject to change by the relevant retail authority. Providing such solicitude to the state regulatory authority to exert circumscribed authority over aspects of a wholesale rate has precedent, in the context of matters like wholesale demand response and wholesale participation of distributed energy resources where both federal jurisdiction and state jurisdiction exist over the same nexus of activities (e.g., a demand reduction can be sold as part of a

27 DCC Protest at 12 (“PJM’s tariff revisions seek to prescribe the amount paid to retail customers through their retail rates for service interruptions implemented at PJM’s direction”).
28 See e.g., Comments, Request for Clarification, and, in the alternative, Request to Sever of OPSI (“OPSI Comment”) at 8 (generally supporting key design elements of IRAS but requesting clarification that “retail regulators can set the IRAS rate itself at retail” and whether it is New Large Loads that determine the compensation level or retail regulators).

PDF page 13

13
wholesale demand response product or contribute to a retail demand response program). Indeed, in Order No. 719, in solicitude to the states’ retail authority over retail customers, the Commission granted the relevant electric retail regulatory authority (RERRA) a veto over that existence of the wholesale transaction entirely. 29 Accordingly, the Commission required RTO/ISOs to amend their market rules to permit demand response aggregators to bid in demand response into wholesale markets, unless the RERRA’s laws or regulations do not permit such participation.30 To this day, Order No. 719’s provision for a state opt-out limits demand response participation in wholesale markets.

Here, PJM has proposed an even more circumscribed role for the retail regulatory authority over the wholesale rate than that provided by the Commission under Order No. 719. Whereas under Order No. 719, a retail authority has a dispositive role in determining whether the wholesale transaction may occur at all, PJM proposes in IRAS only to allow retail authority to determine, from a range of just and reasonable compensation levels, which just and reasonable compensation level to select. Specifically, by proposing a wholesale market compensation rate from zero dollars up to a cap of 50% of the Non-Performance Charge Rate, PJM is setting a default wholesale rate of 50% of the Non-Performance Charge Rate that will, absent other action by the retail authority, pass through to retail rates. Only if the retail authority acts to change that default rate to another just and reasonable compensation level, including potentially to zero, would that alternative wholesale compensation level apply and flow through to retail rates.31 As in Order No. 719, providing such a role for the retail authority does not render the wholesale rate

29 See Order No. 719, 125 FERC ¶ 61,071, at P 154 (2008).
30 Id.; see also PJM Transmittal at 108 (citing Orders No. 719 125 FERC ¶ 61,071, at P 154 (2008) & Order No. 719-B, 129 FERC ¶ 61,252 at P 5).
31 PJM Transmittal at 102 (“the wholesale IRAS rate is flexible and can be further reduced”).

PDF page 14

14
actually a retail rate, nor does it violate the FPA’s jurisdictional provision because the service remains at the wholesale level and the state role would be authorized and defined in a federal tariff. To be more precise, the retail authority does not set the wholesale rate, rather the wholesale rate is setting conditions under which that rate applies (i.e., absent state action, rate x applies; under conditions of state action y, rate z applies).

PJM’s transmittal and proposed tariff revision arguably could be clearer in describing the respective jurisdictional roles of PJM, as the public utility subject to federal jurisdiction that has power to propose a change to wholesale rates, and the retail authority, which has no authority to change that wholesale rate once it is established, but has authority pursuant to state law to determine how to allocate that charge among retail customers. At times, PJM confusingly appears to be speaking about compensation that would be provided to individual retail customers, which can only be provided via retail, not wholesale bills.32 But PJM is also clear that curtailment during an IRAS event is directed only as a MW quantity of load curtailment, i.e., bulk load, to a particular Electric Distributer’s zone or area,33 and wholesale compensation will therefore accrue (presumably as a credit) on a wholesale bill to the wholesale customers based on that total MW quantity of load curtailment. PJM acknowledges repeatedly in its filing that which individual retail customers receive that compensation is beyond its control.34 Cleaning up PJM’s

32 See PJM Transmittal at 104 (“The net result is a reduced capacity charge for Eligible New Large Loads, and thus a ‘practice . . . in which operators of wholesale markets pay electricity consumers for commitments not to use power at certain times’ and thus ‘directly’ affects wholesale capacity rates assessed.”) (emphasis added).
33 PJM Transmittal at 86 (PJM identifies for each zone/area the Eligible New Large Load Amounts—i.e., the MW quantity to be called upon to reduce load under IRAS. “Directing an Electric Distributor, rather than a specific end-use customer, to reduce a quantity of load is in keeping with PJM’s longstanding practice and reflects and respects the allocation of jurisdiction between the federal and state levels”).
34 PJM Transmittal at 104 (“the entities to be paid the rate and the loads to be charged to support such compensation must be determined at the state level”).

PDF page 15

15
proposed tariff provision pertaining to IRAS compensation35 to remove all references to “Eligible New Large Loads,” entities that PJM will not directly interface with in implementing the wholesale rate, would helpfully clarify that PJM is setting a wholesale rate (in which retail authority is permitted a role in implementation) rather than dictating terms of compensation to specific retail customers. Similarly, PJM’s proposed tariff would benefit from clarification to specify that provision of particular levels of compensation depend on certain conditions at retail. In other words, just as eligibility to participate as wholesale demand response depends on permission under the relevant state laws and regulations, wholesale compensation for IRAS at a reduced level depends on RERRA action specifying such an alternate compensation level within the acceptable, just and reasonable range. Such a reformulation would clarify that the retail authority is not setting the wholesale rate, but rather that conditions in the retail context inform the implementation of and are an input into the wholesale rate. Given PJM’s agreement to alterations of its proposal consistent with NRG, we understand such clarifications of PJM’s compensation structure to be permissible as they leave intact PJM’s core rate design (the wholesale curtailments remain subject to wholesale compensation within the same just and reasonable range as the initial proposal).

C. IRAS is not unduly discriminatory.
Protestors contend that IRAS is unduly discriminatory in its treatment of new large loads, existing capacity resources, or both.36 But it is not unduly discriminatory to distinguish between

35 See PJM Transmittal Attachment A, Redlined Proposed Tariff Provisions, Attachment DD-4 Section X (“Compensation for Providing Interim Resource Adequacy Service”).
36 DCC Protest at 27-30 (arguing PJM treatment under IRAS is arbitrary based on timing of when the load is placed in service); Google Protest at 11-12 (undue discrimination because “the only differences between EDs that receive curtailment orders and those that do not are the characteristics of their retail customers”); Constellation Protest at 29 (PJM’s proposal unduly discriminates against “certain load, based on load size and in-service date” and “against certain

PDF page 16

16
novel forms of load (very fast paced, very large peak demand additions that are concentrated in a single electrical location) that threaten the reliability of the grid and traditional forms of load that do not (load growth that is demonstrably slower-paced, occurring over many years, that is comprised of smaller and more distributed retail loads). As discussed herein, the Commission itself recognized the need for distinct treatment of large computational loads in recent orders. And likewise, it is common sense that existing capacity that has already been committed to provide services to the transmission system, and where existing consumers have contributed to embedded costs, is not similarly situated to newly available capacity (including new capacity that is not associated with a wholly new build generating facility, such as uprates of existing generating facilities) that does not face such commitments and is therefore available to serve the particular capacity needs of new large loads. Moreover, distinguishing between such differently situated resources is inherently needed to prevent cross-subsidization. Existing capacity has been committed—through wholesale markets and rates—to serving existing loads, where these existing loads have contributed to embedded costs in the form of capacity market payments. Allowing existing capacity to now contract with new large loads (e.g., as BYONC) would allow these new large loads to benefit from existing consumer embedded cost contributions, and more importantly, would worsen the reliability shortfall by shifting existing capacity to new loads, leaving existing consumers with reliability shortfalls. This is a form of unwilling consumer cross-subsidization of new large loads—both in terms of rates and reliability—that can only be addressed by providing for reasonable distinct treatment.

generation, based on resource vintage”); Vistra Protest at 3 (objecting that inability for new large loads to contract with existing capacity resources is “textbook undue discrimination”).

PDF page 17

17
1. It is not undue discrimination to determine IRAS exposure based on
the kind of load growth in a zone that is causing the region’s reliability and affordability impacts.

PJM aptly points out that the Commission has already determined that large loads may constitute a “separate category of load” that require distinct treatment to ensure just and reasonable and not unduly discriminatory rates.37 The Commission explained that, “integrating large loads poses specific challenges to transmission system operation given their size, operational behavior, and unique potential to impact the transmission system.”38 The Commission also recently credited the position of the North American Electric Reliability Corporation (NERC) that large loads are “substantially larger and constructed more quickly than prior loads using the [Bulk-Power System]” and pose unique challenges, in an Order directing NERC to take “urgent” action to establish Reliability Standards that will “assure that computational loads are reliably integrated into the operation of the Bulk-Power System.”39 The Commission has thus already recognized that the characteristics of retail customer loads may directly affect the provision of transmission service to Eligible Customers on behalf of large loads and reliable operation of the bulk power system, such that these features are relevant to Commission-jurisdictional rates. The same “unique operational challenges” and “unique operational impacts on the transmission system” of providing transmission service to Eligible Customers on behalf of large loads recognized by the Commission support PJM’s proposed distinct treatment of Electric Distributers who seek transmission service on behalf of such large loads.40

37 PJM Transmittal at 96 (citing the June 2026 Order to Show Cause, 195 FERC ¶ 61,211 (2026)).
38 June 2026 Order to Show Cause, 195 FERC ¶ 61,211 at P 58.
39 Reliability Standard(s) Pertaining to Computational Load Integration, 196 FERC ¶ 61,031, at PP 9-10 (July 16, 2026).
40 June 2026 Order to Show Cause, 195 FERC ¶ 61,211 at PP 50-58.

PDF page 18

18
PJM’s proposal is not unduly discriminatory because it focuses on distinctions among customers that are relevant to ensuring just and reasonable rates and reliable operation of the bulk power system. Large load customers that today drive completely novel degrees of load growth pose unique operational challenges to the transmission system.

Protestors’ effort to characterize IRAS as undue discrimination because it will apply only on a forward-looking basis to new large loads after its acceptance also fails.41 The Commission regularly accepts that new rules apply only to new entrants, and when needed grandfathers existing entities under prior rules without such treatment constituting undue discrimination.42 The Commission could not conduct its statutorily mandated task of ensuring just and reasonable and not unduly discriminatory rates if approving new rates on a prospective basis constituted undue discrimination. Rather than treating the imposition of new requirements as prohibited undue discrimination, the Commission considers instead whether the disruption of settled expectations due to the new rules is significant enough to warrant a transition period to mitigate the harm to settled expectations.43

41 See e.g., DCC Protest at 29 (arguing PJM has not demonstrated that “the timing on when load comes online” is a legitimate basis for discrimination).
42 See e.g., MISO, 150 FERC ¶ 61,180 at P 21 (2015) (rejecting arguments that differing treatment between interconnection customers constitutes undue preference, where that difference is due to the fact that certain interconnection customers are subject to generator interconnection procedures and agreements that pre-date new reforms); ISO-NE, 162 FERC ¶ 61,205 at P 47 (2018) (rejecting protestors’ arguments that ISO-NE’s inclusion of a cut-off date in the definition of resource types to which a particular capacity market rule would apply constitutes undue discrimination); PJM, 193 FERC ¶ 61,217 at P 224 (2025) (“To the extent an entity is a party to an existing contract for such a purpose, we find that it is appropriate to grandfather such entity so that it may continue using BTMG for the current term remaining under the existing contract”).
43 See e.g., Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements, 184 FERC ¶ 61,054 at P 856 (2023) (“We further find that the transition process, as adopted herein, appropriately balances the need to move expeditiously to the new cluster study process with the need to respect the investments and expectations of interconnection customers at an advanced stage in the existing interconnection process”).

PDF page 19

19
2. It is not undue discrimination to treat capacity resources that are
already committed to serve system needs in a different manner from
resources that have not yet assumed any such commitment.
Protestors’ argument that PJM’s proposal unduly discriminates against existing capacity resources is also meritless. IRAS seeks to mitigate unique impacts to the grid from rapid additions of very large quantities of load in a single electrical location without commensurate addition of capacity. For that purpose, existing capacity resources, which cannot serve those new large loads because they are already committed to provide capacity to the system, and new capacity (including new capacity that is created at existing generating facilities or at deactivated generating facilities), which is capable of serving the needs of new large loads and therefore can reduce the transmission system impacts of such additions, must be distinguished. The question is not whether resources that qualify new large loads to avoid curtailment under the IRAS scheme (as BYONC or via allocated RBP UCAP) and existing capacity resources are capable of providing the same “capacity, energy, and ancillary services products” in PJM’s wholesale markets.44 Rather the question is whether existing capacity resources can solve the specific and unique operational challenges caused by large load additions that PJM aims to solve with IRAS. The unqualified and commonsense answer is no. Resources that are already being counted upon to meet existing system needs do not have the same ability to address new large loads’ incremental capacity needs.

Allowing existing resources to meet the needs of new large loads—as BYONC or RBP— would only be allowing for a rent-seeking shell game, as new large loads would seek out available capacity resources made cheaper by years of ratepayer compensation, and existing capacity resources would seek to lock-in long-term contracts with new large loads. This would

44 Constellation Protest at 37.

PDF page 20

20
leave existing ratepayers as suddenly second-class customers in the system they have long paid to maintain, leaving them particularly vulnerable to reliability events from resource adequacy shortfalls and higher bills to support development of costly and slow new capacity.

D. IRAS is just and reasonable because it will encourage investment in new
capacity while protecting other customers from reliability and affordability impacts caused by large load growth.

Finally, protestors’ remaining objections to IRAS have no merit.45 Governor Shapiro focuses on claims that target the core design of IRAS, none of which warrant rejection of IRAS. To the extent that the Commission determines that modifications of IRAS are necessary to resolve other, less central concerns about its design, PJM has granted its consent to the Commission to modify its proposal consistent with NRG and the Commission can accordingly direct changes to PJM’s tariff proposal to address such concerns.46 Given the pressing need for timely solutions to PJM’s supply shortage, Governor Shapiro urges the Commission to accept IRAS by the statutory deadline to enable PJM to rapidly turn to more detailed implementation of the construct, with any necessary modifications.

First, protestors are wrong that IRAS cannot achieve its core objective and is unjust and unreasonable because PJM does not have jurisdiction over retail customers, and therefore cannot guarantee that the right retail customers will be curtailed and, to the extent that the wholesale compensation is set above zero, compensated for such curtailment. IRAS is just and reasonable

45 See, e.g., DCC Protest at 6, 35; Google Protest at 2, 14; Vistra Protest at 1.
46 For example, Governor Shapiro takes no position on concerns that IRAS should provide for a longer transition period before it becomes effective; or that modifications to the transmission services or capacity charges to new large loads subject to IRAS are necessary to be consistent with cost causation. To the extent the Commission finds merit in concerns about the details of implementation of IRAS, it should approve the proposal and direct modification of the proposal to address those concerns on further compliance, in order to move the PJM region forward with the only real solution it has to timely address the near-term reliability and affordability impacts of large load additions.

PDF page 21

21
because it appropriately places the potential risk of being subject to curtailment on the transmission zone or area serving a new non-capacity backed large load, and on the planning horizon that potential risk is proportionate to the quantity of new large load additions that are not matched with new capacity supply and therefore which pose unique risks to the transmission system in that operational horizon. PJM, and the Commission via oversight of jurisdictional rates, have no responsibility to ensure that that risk of curtailment falls incident to particular retail customers; that is beyond the scope of ensuring that the wholesale rate is just and reasonable and is a matter for retail ratemaking. Likewise, wholesale compensation need only be provided to the appropriate wholesale customer (in this case, the transmission customer providing service on behalf of the large loads) to be just and reasonable under the FPA; PJM need not and cannot address the subsequent allocation of such wholesale compensation among retail customers. But the jurisdictional division of labor does not require PJM or the Commission to sit idly by while large load additions not backed by new capacity erode reliability and affordability. PJM’s proposal reasonably aims to address the real challenges that large load growth presents while respecting the jurisdictional divide established by Congress. Moreover, protestors’ arguments that IRAS will fail to incentivize new large loads to invest in new capacity in order to reduce the likelihood that they are subject to curtailment is unconvincing,47 and is contradicted by arguments that IRAS is too harsh and must be mitigated by a more generous transition period.48 PJM proposes to identify the total MW quantity of load subject to IRAS in a zone or area based on new large loads that have not addressed their capacity needs within that zone/area, and to leave the actual curtailment directions being made to end-use

47 Google Protest at 2 (arguing IRAS would result in “less investment in capacity in PJM”).
48 DCC Protest at 35 (arguing that if the Commission is inclined to accept IRAS, at minimum it must adopt a meaningful transition mechanism).

PDF page 22

22
retail load to the Electric Distributer. As a result, individual large loads materially decrease their likelihood of being subject to curtailment by investing in new capacity. Such individual retail customers that invest in new capacity consistent with IRAS will also have, because of the federal tariff, a good argument to retail authorities that they should not be subject to curtailment, or should receive priority above other large loads in allocation of curtailment quantities during IRAS events. The Large Load Registry that PJM proposes to establish will provide information to enable retail regulators and retail load customers to understand the basis for PJM’s determination of the MW quantity of load subject to curtailment in a zone or area during an IRAS event. Ultimately, PJM’s proposal sufficiently aligns incentives to constitute a just and reasonable rate that must be accepted by the Commission.49

Second, protestors are wrong that it is not just and reasonable to remove new large loads that are subject to IRAS from the VRR Curve.50 PJM is not ignoring demand fundamentals; it is respecting supply realities. Specifically, due to supply project development constraints51

49 Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1017 (D.C. Cir. 2022) (“The statutory requirement that rates be ‘just and reasonable’ is obviously incapable of precise judicial definition, affording the Commission leeway in its ratemaking decisions”) (internal quotation and citation omitted); Long Island Power Auth. v. FERC, 27 F.4th 705, 714 (D.C. Cir. 2022) (Commission is not held to the standard of “exacting precision” in ratemaking) (internal quotation and citation omitted).
50 DCC Protest at 6 (“PJM proposes to undermine the ability of the capacity market to send price signals for the development of new capacity by excluding Eligible New Large Loads from the calculation of the Variable Resource Requirement curve”); Google Protest at 14 (arguing PJM’s proposal “break[s] supply and demand fundamentals by ignoring the demand that PJM itself expects to materialize”); Constellation Protest at 46 (arguing aspect of the proposal will “harm long-term resource adequacy, the capacity market, and customers’ pocketbooks by muting the price signals that are necessary to encourage new entry and retain existing resources.); Vistra Protest at 16 (this aspect of the proposal “meddle[s] with capacity market fundamentals”).
51 PJM, “2027/2028 Base Residual Auction Reserve Target Shortfall Report” at 5-9 (Feb. 2026), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-2028/2027- 2028-bra-reserve-target-shortfall-report.pdf (“Even if every viable project were to clear the interconnection process today, developers face a rigid physical barrier that prevents immediate construction. As detailed in PJM’s recent Periodic Review of Variable Resource Requirement

PDF page 23

23
sufficient new capacity is not and perhaps cannot come online as fast as new large load demand, at any price. In the face of this reality, PJM is crafting a deliberate market design during resource adequacy shortfall crisis in which the capacity market is not aiming to procure supply for certain new large loads because they will be subject to curtailment and not served by system resources during times of system strain. PJM’s proposal thus ensures the capacity market is accurately seeking to procure capacity sufficient to serve the transmission system needs during the periods when IRAS applies. Market design that recognizes IRAS new large loads are not capacity backed is appropriate and beneficially prevents distorted price signals that are incapable of materializing new supply. Lastly, the exclusion of this demand from the VRR Curve is not permanent, such treatment only lasts while IRAS is active, and Eligible New Large Loads are subject to potential curtailment during IRAS actions. Once PJM achieves capacity sufficiency for the requisite three- year period and IRAS goes dormant, the load that was previously subject to IRAS no longer falls under the definition of Eligible New Large Loads and would be incorporated back into the demand curve. Again, this matches both demand and supply fundamentals because when IRAS is not in effect—meaning when demand and supply are balanced—the capacity market is expected to procure sufficient resources to serve all loads.

Protestors appear to recognize that PJM’s decision to exclude demand from large loads that is not matched with commensurate new supply from the VRR Curve is necessary to ensure

(VRR) Parameters, the industry has hit a supply chain wall that has a project schedule timeline of the Reference Resource technology longer than the three-year-forward market.”); see also Synapse Energy Economics et al., “Assessing Electricity Resource Adequacy in Pennsylvania and PJM”, prepared on behalf of the Pennsylvania Public Utility Commission (Sept 14, 2026), https://www.puc.pa.gov/media/4044/2026_assessing_electricity_resource_adequacy_in_pa_and_ pjm.pdf (finding PJM’s Loss of Load Expectation planning criterion is not met by 2027, and is worse than that criterion by a factor of six by 2030, under the Reference Case that factors in PJM’s interconnection queue reforms, including the Reliability Resource Initiative and Expedited Interconnection Track, and PJM’s RBP).

PDF page 24

24
that residential and existing commercial customers’ capacity rates do not increase as large loads connecting to the grid continue to accelerate.52 But Protestors reveal their paper-thin adherence to the Ratepayer Protection Pledge, as they nevertheless argue that PJM’s only option is to procure supply for all new large loads through the capacity market, driving capacity market prices in PJM even higher and worsening the affordability crisis in the region. Fortunately for the region, PJM’s hands are not tied as the Protestors insist. PJM has proposed a just and reasonable wholesale market scheme that, on an interim basis during times of sustained capacity shortage, provides for more limited service in return for the potential for wholesale compensation to the types of new large load additions that would otherwise pose unique and serious operational challenges to the transmission system. PJM’s proposal is a just and reasonable approach to addressing the severe challenges faced by the region.

PJM’s proposal to curtail Eligible New Large Loads prior to calling on Pre-Emergency Load Management is likewise critical to mitigate existing customers’ exposure to curtailment risk and increased capacity costs caused by large loads that do not bring their own capacity, and is a just and reasonable rate. If demand response were called prior to curtailment of Eligible New Large Loads, demand response would be called upon more frequently due to the growing capacity shortage in PJM and the need to serve non-capacity backed new large loads. This in turn would result in existing customers sharing the increased cost of calling on the demand response that is due to large load growth, diluting the incentive for new large loads to procure their own capacity. Moreover, if called upon too frequently, demand response resources will be less likely to register over time, reducing the capacity available to serve the region at a time when every resource that can be quickly brought online is needed. Again, PJM’s proposal to expose the new

52 Google Protest at 14.

PDF page 25

25
large loads that are causing the operational risks to the system to bear those risks directly, where the hypothetical alternative of driving capacity prices ever higher could not actually produce new supply fast enough to avoid operational risks, is a just and reasonable choice.

III. CONCLUSION
For the foregoing reasons, Governor Shapiro respectfully requests the Commission to accept PJM’s proposal, subject to modification consistent with NRG as necessary to ensure its implementation as soon as possible.

Respectfully submitted,
/s/ Kim Smaczniak
Kim Smaczniak
Miles Farmer
Avi Zevin
Nathan Lobel
Roselle LLP
300 New Jersey Ave. NW, Suite 300
Washington, DC 20001
kim.smaczniak@rosellellp.com
miles.farmer@rosellellp.com
avi.zevin@rosellellp.com
nathan.lobel@rosellellp.com

PDF page 26

26
CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.

Dated: September 16, 2026
/s/ Nathan Lobel
Nathan Lobel
Roselle LLP
300 New Jersey Ave. NW, Suite 300
Washington, DC 20001
nathan.lobel@rosellellp.com